1 Performance and Resources Board, 22 September 2015 Agenda item: 19 Report title: Report by: Action: Project Management Methodology John McDermott, Head of Corporate Business Planning To note Executive summary An organisation-wide project management methodology has been developed and Corporate Business Planning has developed into a central Project Management Office. The chosen project and portfolio management system is currently being configured, with an expected completion in September Interaction with the business on the methodology is continuing, with workshops taking place across the business ahead of formal communications in September-December 2015, and formal training for users during November and December Recommendations The Performance and Resources Board is asked to note the current position in relation to: a Methodology and Project Management Office. b System configuration. c Interaction with the business.
2 Performance and Resources Board, 22 September 2015 Agenda item 19 Project Management Methodology Methodology and Project Management Office (O) 1 Corporate Business Planning (CBP) has developed an organisation-wide project management methodology based on industry best-practice, feedback from across the organisation and guidance from the chosen project and portfolio management (P) software system supplier (Planview). The latest version of the methodology is shown at Annexes A D (minor adjustments ongoing): a O approach Annex A. b Project management overview Annex B. c Project management stages Annex C. d Project management roles and responsibilities Annex D. 2 CBP has now been developed into a central O function providing support and governance with regard to this methodology (and system). System configuration 3 CBP and Information Systems (IS) are currently configuring the chosen P system to the corporate methodology and it is anticipated that this work will be concluded during September The basis for the system configuration is a detailed taxonomy (or classification) that expresses each piece of data required, the associated values and how it will inform reporting. This taxonomy is available on request. 5 Once the system is approved, CBP will fulfil the role of system owner (aligned to ownership of the methodology) and IS the role of system administrator. Interaction with the business 6 Timelines for this work remain unchanged and are at Annex E, with limited use of the system for business planning during September October 2015 and then full use from January CBP has already interacted with the business through a number of formal and informal workshops (details available on request), and a formal communications campaign is being planned for September December Whilst the methodology will be available across the organisation, the initial intention is for the system to be used by those managing projects on a day to day basis. Formal training will be provided to the user community (identified by the business) during November December
3 Performance and Resources Board, 22 September 2015 Agenda item 19 Project Management Methodology 9 CBP will establish a community of practice approach to the methodology and associated system, bringing together all those involved in projects on a regular basis to help shape future developments. 3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19 19 - Annex D - Project Management Roles & Responsibilities This document provides details of the roles and responsibilities within the organisation wide Project Management Methodology
20 0. Pre-Project Activity Documentation (template) Explanation (where necessary) Accountable (reviewing) Responsible (undertaking) Project manager assigned Project Manager assigned to undertake stages 1. to 2. of this methodology Assistant Director (AD) Head of Section (HoS) Concept raised Basic information AD Project Manager () Concept captured Pre-project framework AD Concept classified as BAU / project, and if project as formal / informal Automatic calculation based on score Classification of project and automatic calculation informally reviewed by the Project Management Office (O) Head of Corporate Business Planning (HoCBP) O Analyst Lessons learned relevant for this concept reviewed (including adjustments for Optimum Bias ) Lessons learned collated [auto] AD O Analyst 1. Ideas Activity Documentation (template) Explanation (where necessary) Accountable (reviewing) Responsible (undertaking) Concept investigated Business case Key attributes defined O Analyst O reporting starts Analytic reports TBC [auto] In future may include all informal projects and BAU data to give more accurate results The O will use information from the P system to produce analytic reports for the Senior Management Team (SMT), the Performance and Resources Board (PRB) and Council Expectation; weekly system updates by users O Analyst Corporate Business Planning Officer (CBPO) Gated review of stage In future may develop export of outputs to stakeholders Gated review Quantitative and qualitative review HoCBP O Analyst
21 2. Research Activity Documentation (template) Explanation (where necessary) Accountable (reviewing) Responsible (undertaking) Requirements defined Requirements specification Including requirements / scope / objectives / potential product areas / sections involved / standard roles O Analyst Costs defined Financial plan Non-staff and staff O Analyst O reporting continues Analytic reports TBC [auto] In future may include all informal projects and BAU data to give more accurate results The O will use information from the P system to produce analytic reports for the SMT, PRB and Council Expectation; weekly system updates by users O Analyst CBPO Gated review of stage In future may develop export of outputs to stakeholders Gated review Quantitative and qualitative review HoCBP O Analyst Project prioritised / considered by the SMT Analytics reports TBC [auto] In future may include all informal projects and BAU data to give more accurate results Investment planning undertaken on the basis of data from 0. Pre-Project / 1. Ideas / 2. Research stages Potential scenarios modelled Project prioritised / approved / rejected by the SMT SMT HoCBP Project Sponsor advised of outcome HoCBP O Analyst Project Manager (re)assigned Project Manager assigned to undertake stages 3. to 6. of this methodology AD / HoS O Analyst
22 3. Initiation Activity Documentation (template) Explanation (where necessary) Accountable (reviewing) Responsible (undertaking) Project Board / Team established Project Board () Project Sponsor (PS) Requirements reviewed / refined Requirements specification Conduct workshops and engage with users as appropriate to analyse requirements Stakeholder mapping undertaken Stakeholder strategy Mapping and communication method captured Detailed planning undertaken Project plan In future may develop individual Product descriptions and standardisation of products to allow greater reporting functionality Including milestones (prepopulated) / products (including certain standard items for all projects) / product milestones / tasks / resource / decisions Recording risks / issues starts Risk log Issues log In future may develop Change control log and individual Change requests Benefits case clarified Benefits realisation plan In future may develop individual Benefit profiles and standardisation of quantification fields to allow greater reporting functionality Including benefit type / quantification baseline / qualification target / value (if applicable) / when realised / how realised / resource / comment / status Cost tracking starts Financial plan Project costs tracked by Project Manager and Management Accountant on a monthly basis Lessons logging starts Lessons learned log
23 3. Initiation (cont.) Activity Documentation (template) Explanation (where necessary) Accountable (reviewing) Responsible (undertaking) Project status reporting starts Highlight report [auto] Automatic report collating key data from 3. Initiation stage O reporting continues Analytic reports TBC [auto] In future may include all informal projects and BAU data to give more accurate results The O will use information from the P system to produce analytic reports for the SMT, PRB and Council Expectation; weekly system updates by users O Analyst CBPO All project information collated Project initiation document (PID) [auto] In future may develop as is / to be Process maps Automatic report collating key data from 0. Pre-Project / 1. Ideas / 2. Research / 3. Initiation stages Gated review of stage In future may develop export of outputs to stakeholders Gated review Quantitative and qualitative review HoCBP O Analyst
24 4. Delivery Activity Documentation (template) Explanation (where necessary) Accountable (reviewing) Responsible (undertaking) All project information reviewed / refined PID [auto] In future may develop as is / to be Process maps Automatic report collating key data from 0. Pre-Project / 1. Ideas / 2. Research / 3. Initiation stages Delivery activities undertaken / detailed planning and tracking continues Project plan In future may develop individual Product descriptions, standardisation of products to allow greater reporting functionality, and Work packages Including milestones (prepopulated) / products (including certain standard items for all projects) / product milestones / tasks / resource / decisions Recording risks / issues continues Risk log Issues log In future may develop Change control log and individual Change requests Benefits tracking starts Benefits realisation plan In future may develop individual Benefit profiles and standardisation of quantification fields to allow greater reporting functionality Including benefit type / quantification baseline / qualification target / value (if applicable) / when realised / how realised / resource / comment / status Cost tracking continues Financial plan Project costs tracked by Project Manager and Management Accountant on a monthly basis Lessons logging continues Lessons learned log Project status reporting continues Highlight report [auto] Automatic report collating key data from 4. Delivery stage
25 4. Delivery (cont.) Activity Documentation (template) Explanation (where necessary) Accountable (reviewing) Responsible (undertaking) O reporting continues Analytic reports TBC [auto] In future may include all informal projects and BAU data to give more accurate results The O will use information from the P system to produce analytic reports for the SMT, PRB and Council Expectation; weekly system updates by users O Analyst CBPO Gated review of stage In future may develop export of outputs to stakeholders Gated review Quantitative and qualitative review HoCBP O Analyst
26 5. Go live Activity Documentation (template) Explanation (where necessary) Accountable (reviewing) Responsible (undertaking) Go live activities undertaken / detailed planning and tracking concludes Project plan In future may develop individual Product descriptions, standardisation of products to allow greater reporting functionality, and Work packages Including milestones (prepopulated) / products (including certain standard items for all projects) / product milestones / tasks / resource / decisions Recording risks / issues / actions concludes Risk log Issues log In future may develop Change control log and individual Change requests Benefits tracking continues Benefits realisation plan In future may develop individual Benefit profiles and standardisation of quantification fields to allow greater reporting functionality Including benefit type / quantification baseline / qualification target / value (if applicable) / when realised / how realised / resource / comment / status Cost tracking concludes Financial plan Project costs tracked by Project Manager and Management Accountant on a monthly basis Lessons logging continues Lessons learned log Project status reporting concludes Highlight report [auto] Automatic report collating key data from 5. Go live stage
27 5. Go live (cont.) Activity Documentation (template) Explanation (where necessary) Accountable (reviewing) Responsible (undertaking) O reporting continues Analytic reports TBC [auto] In future may include all informal projects and BAU data to give more accurate results The O will use information from the P system to produce analytic reports for the SMT, the Performance and Resources Board (PRB) and Council Expectation; weekly system updates by users O Analyst CBPO Project close undertaken Close report [auto] In future may develop Stakeholder satisfaction survey Automatic report collating key data from 3. Initiation / 4. Delivery / 5. Go live stages Gated review of stage In future may develop export of outputs to stakeholders Gated review Quantitative and qualitative review HoCBP O Analyst Project considered by the SMT Analytic reports TBC [auto] In future may include all informal projects and BAU data to give more accurate results Project close approved / rejected HoCBP O Analyst
28 6. Review Activity Documentation (template) Explanation (where necessary) Accountable (reviewing) Responsible (undertaking) Benefits tracking concludes Benefits realisation plan In future may develop individual Benefit profiles and standardisation of quantification fields to allow greater reporting functionality Including benefit type / quantification baseline / qualification target / value (if applicable) / when realised / how realised / resource / comment / status Lessons logging concludes Lessons learned log O reporting concludes Analytic reports TBC [auto] In future may include all informal projects and BAU data to give more accurate results The O will use information from the P system to produce analytic reports for the SMT, the Performance and Resources Board (PRB) and Council Expectation; weekly system updates by users O Analyst CBPO Post project analysis undertaken Post implementation review [auto] Automatic report collating key data from 6. Review stage Gated review of stage In future may develop export of outputs to stakeholders Gated review Quantitative and qualitative review HoCBP O Analyst Project considered by the SMT Analytic reports TBC [auto] In future may include all informal projects and BAU data to give more accurate results Project review approved / rejected HoCBP O Analyst 7. Complete Formal completion of project
29 Performance and Resources Board meeting, 22 September 2015 Agenda item 19 Project management methdology Annex E Planview and 2016 Business Planning Timeline Date Planview dates 2016 Business Planning dates Notes Friday 28 August Phase 1 deadline - operational plan templates (stages 0 and 1) Tuesday 1 September - Wednesday 2 September Solution Review Workshop Monday 7 September Monday 7 September - Friday 25 September Collation of all directorate templates from Phase 1 (CBPO) Phase 2 - Manual data collection for stage 2 (requirements specification and financial plan) in template Information to be captured by nominated leads in each directorate - with support from CBs Monday 21 September Monday 21 September - Friday 25 September Planview goes LIVE (date TBC) Input stages 0 and 1 to Planview (CBs) Friday 25 September Phase 2 deadline - operational plan templates (stage 2) Monday 28 September - Tuesday 6 October Input stage 2 to the Planview (nominated leads in each directorate) * Allow time for training on using the system Wednesday 7 October Wednesday 7 October - Tuesday 13 October Wednesday 14 October Thursday 5 November Wednesday 11 November Thursday 10 December November/December January 2016 PlanView training for all users All information on the Planview system Reviewing Planview input - ready for prioritisation exercise with COO and directors (CBs, John and Dan) Meeting with COO and Directors to discuss Planview input Performance and Resources Board Draft business plan and budget 2016 Council Draft Business Plan and Budget 2016 Council 2016 Business Plan and Budget Follow up actions from the meeting Go live with Project Management Methodology and Planview system
Project Management Methodology
18 June 2015 Performance and Resources Board 4 To consider Project Management Methodology Issue 1 An update on progress with the implementation of an organisation-wide project management methodology and
More informationPublic Debt Management Capacity Building Program
Sub-Regional Workshop on Debt Relief and Sustainability Analysis Basseterre, St. Kitts and Nevis, from October 1 st to 10 th, 2014. Preliminary Agenda Day 1: Wednesday, October 1 st 09:00-09:30 Registration
More informationJob Description. Applications Analyst (BI) (BISRID_033)
Job Description Job Title: Reports to: Team: Location: Applications Analyst (BI) (BISRID_033) SAP Applications Leader BIS Nelson Job Purpose Responsible for the provision of the overall management of BI
More informationFuture Council Programme Evaluation Framework
Future Council Programme Evaluation Framework Overview of the Evaluation Framework for the Future Council Programme DRAFT v0.7 August 2015 Contents 1. Evaluation Framework Overview 2. Evaluation Framework
More informationOutline Brief for Development of Strategic Estates Plan for Bristol, South Gloucester, North Somerset and Somerset Clinical Commissioning Groups
Item 13 Strategic Estates Planning Outline Brief for Development of Strategic Estates Plan for Bristol, South Gloucester, North Somerset and Somerset Clinical Commissioning Groups Phase 1: Priorities and
More informationNSW Government ICT Benefits Realisation and Project Management Guidance
NSW Government ICT Benefits Realisation and Project Management Guidance November 2014 CONTENTS 1. Introduction 1 2. Document purpose 1 3. Benefits realisation 1 4. Project management 4 5. Document control
More informationLevel: 3 Credit value: 5 GLH: 28 Relationship to NOS:
Unit 341 Implement UAN: Level: 3 Credit value: 5 GLH: 28 Relationship to NOS: Assessment requirements specified by a sector or regulatory body: Aim: T/506/1929 Management & Leadership (2012) National Occupational
More informationAPMP. The APM Project Management Qualification. Syllabus, learning outcomes and assessment criteria aligned to the APM Body of Knowledge 6 th edition
The syllabus provides a summary of the coverage of the qualification, the details are then found in the learning outcomes and assessment criteria. Both the syllabus and the learning outcomes and assessment
More informationStrategy Deployment Through Collaborative Planning. Linking the Strategy to Practical Activity
Strategy Deployment Through Collaborative Planning Linking the Strategy to Practical Activity Establish the Strategic Goal. After the Collaborative Planning activity Collaborative Planning iterative and
More informationSAP Product Stewardship Network Supplier Enablement Service Description (English)
SAP PRODUCT STEWARDSHIP NETWORK - SUPPLIER ENABLEMENT - SERVICE DESCRIPTION SAP Product Stewardship Network Supplier Enablement Service Description (English) Table of Content 1 Definitions... 3 2 Introduction...
More informationPORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3)
PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) 1st February 2006 Version 1.0 1 P3M3 Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value
More informationInformation and Communications Technology (ICT) Steering Committee - Information Sheet
Information and Communications Technology (ICT) Steering Committee - Information Sheet Version 2.2 Thursday, June 30, 2011 Document Ownership Information Document Owner M Livesley Document Preparation
More informationGovernment Communication Professional Competency Framework
Government Communication Professional Competency Framework April 2013 Introduction Every day, government communicators deliver great work which supports communities and helps citizens understand their
More informationEffective objective setting provides structure and direction to the University/Faculties/Schools/Departments and teams as well as people development.
Effective objective setting provides structure and direction to the University/Faculties/Schools/Departments and teams as well as people development. The main purpose of setting objectives is to reflect
More informationGUIDELINES FOR PILOT INTERVENTIONS. www.ewaproject.eu ewa@gencat.cat
GUIDELINES FOR PILOT INTERVENTIONS www.ewaproject.eu ewa@gencat.cat Project Lead: GENCAT CONTENTS A Introduction 2 1 Purpose of the Document 2 2 Background and Context 2 3 Overview of the Pilot Interventions
More informationThe Gateway Review Process
The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible
More informationUoD IT Job Description
UoD IT Job Description Role: Projects Portfolio Manager HERA Grade: 8 Responsible to: Director of IT Accountable for: Day to day leadership of team members and assigned workload Key Relationships: Management
More informationDouglas Robertson, Investment Framework Manager Dougal List, Organisation Improvement Manager
AGENDA NO. 2.3 BOARD PAPER Paper no: 14/02/0800 Meeting date: 27 February Prepared by: Douglas Robertson, Investment Framework Manager Dougal List, Organisation Improvement Manager Recommended by: Dave
More informationSTRATEGIC REVIEW OF HUMAN RESOURCE MANAGEMENT IN UNICEF. Terms of Reference July 20 2005
1. Background STRATEGIC REVIEW OF HUMAN RESOURCE MANAGEMENT IN UNICEF Terms of Reference July 20 2005 UNICEF has decided to undertake a Strategic Review of its approach to and performance in Human Resource
More informationProject Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee
Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Page 1 2 Contents 1. Introduction... 3 1.1 Definition of a... 3 1.2 Why have
More informationProject Management Framework
Information Services Project Management Framework October 2003 Document ID No. Page 1 of 1 Contents 1. Introduction Page 3 2. Use of Framework Page 3 3. Project Register and Monitoring Page 4 4. Project
More informationQuality Impact Assessment. Executive summary
Report to Public Trust Board 28 th February 2013 Title Sponsoring Executive Director Author(s) Purpose Previously considered by Quality Impact Assessment Director of Quality and Safety/ Chief Nurse Director
More informationProject Management Assessment Overview
Project Management Assessment Overview Goals The goals of the assessment are to: Provide a self assessment of your company skills in nine areas of project management (e.g. Risk Management, Scope Management,
More informationKey Accountabilities and Tasks:
Job Title: Key relationships Location: Job Purpose: Digital Marketing Executive Reports to: Marketing and Business Development Manager Responsible for: N/A Works with: Marketing team, PR, Design, external
More informationPosition Description
Position Description Job title Group Section Responsible to Responsibility for staff Project Coordinator Natural Resource Operations Rotorua Lakes Protection & Restoration Programme Rotorua Lakes Business
More informationDPC - Strategy and Project Delivery Unit Project Management Methodology. Updated April 2010
DPC - Strategy and Project Delivery Unit Project Management Methodology Updated April 2010 This project management methodology is designed to help SPDU staff to plan, manage and measure a successful project
More informationPROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
More informationQualification details
Outcome Statement Qualification details Title New Zealand Certificate in Organisational Risk and Compliance (Level 4) Version 1 Qualification type Certificate Level 4 Credits 60 NZSCED 080317 Quality Management
More informationGeneral Dental Council Website Review: Dental Professionals Survey Invitation to Tender
General Dental Council Website Review: Dental Professionals Survey Invitation to Tender Summary 1. The General Dental Council (GDC) invites tender proposals for a research project on the usability of the
More informationDo not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.
APM Introductory Certificate in Project Management Exam paper Candidate Reference Number Date of Exam Location of the Exam General Notes Time allowed 1 hour Answer all 60 multiple choice questions Use
More informationOperations Manager Job Description March 2012
Operations Manager Job Description March 2012 Thermaflo is seeking an experienced Operations Manager with a technical background in process engineering. At Thermaflo we strongly believe that the success
More informationUCISA ITIL Case Study on Nottingham Trent University
UCISA ITIL Case Study on Nottingham Trent University 1. Introduction Nottingham Trent University is a large, diverse and vibrant modern university with approximately 24,000 students. Its mission is to
More informationStandard 1. Governance for Safety and Quality in Health Service Organisations. Safety and Quality Improvement Guide
Standard 1 Governance for Safety and Quality in Health Service Organisations Safety and Quality Improvement Guide 1 1 1October 1 2012 ISBN: Print: 978-1-921983-27-6 Electronic: 978-1-921983-28-3 Suggested
More informationProject Communication Plan Template
by: Michael B. Bender Contact Information: Michael B. Bender Ally Business Developers 23W236 Kimberwick Lane Naperville, IL 60540 Phone: 630/548-0399 e-mail: MBender@AllyBusiness.com (c) 2005 Allibus Corp.
More informationJOB DESCRIPTION. 1. JOB TITLE: Assistant Procurement Officer. 4. DEPARTMENT: Chief Financial Officer/Bursar s Office
JOB DESCRIPTION 1. JOB TITLE: Assistant Procurement Officer 2. REFERENCE NUMBER: HR13297a 3. ROLE CODE: APOBO 4. DEPARTMENT: Chief Financial Officer/Bursar s Office 5. ORGANISATION CHART: Chief Financial
More informationIntroductory Certificate The APM Project Fundamentals Qualification
Introductory Certificate The APM Project Fundamentals Qualification Syllabus, learning outcomes and assessment criteria aligned to the APM Body of Knowledge 6th edition The syllabus provides a summary
More informationSound Transit Internal Audit Report - No. 2014-3
Sound Transit Internal Audit Report - No. 2014-3 IT Project Management Report Date: Dec. 26, 2014 Table of Contents Page Background 2 Audit Approach and Methodology 2 Summary of Results 4 Findings & Management
More informationAdoption of a PPM Solution Using An Agile Approach. Andy Robinson
Adoption of a PPM Solution Using An Agile Approach Andy Robinson 1 Agenda Drivers for using a Portfolio and Project Management system Organisational maturity Where to start Planning, delivery, realisation
More informationTOOL D14 Monitoring and evaluation: a framework
TOOL D14 Monitoring and evaluation: a framework 159 TOOL D14 Monitoring and evaluation: a framework TOOL D14 For: About: Purpose: Use: Resource: Commissioners in primary care trusts (PCTs) and local authorities
More informationObjectives. Project Management Overview. Successful Project Fundamentals. Additional Training Resources
Project Management for Small Business Moderator: Maria Mancha Frontline Systems, Inc. Objectives Project Management Overview Successful Project Fundamentals Additional Training Resources Project Management
More informationGeneral Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided.
Introductory Certificate The APM Project Fundamentals Qualification. Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60
More informationHuman Performance & the Role of Human Resources
DEFENSE LOGISTICS AGENCY AMERICA S COMBAT LOGISTICS SUPPORT AGENCY Human Performance & the Role of Human Resources Ms. Cheryl Steptoe-Simon July 20, 2016 Human Performance Functions Human Performance Components
More informationDirector of Development and External Affairs (DDEA)
JOB DESCRIPTION Post Digital Development Manager Job Family Specialist, Professional and Administrative Grade 6 Role code DDM001 Status Full-time Contract Type Permanent Reporting to Director of Development
More informationJob Description. Industry business analyst. Salary Band: Purpose of Job
Job Description Job Title: Industry business analyst Division/Company: Industry Policy/Payments UK Reporting To: Director of Industry Policy Salary and: C Purpose of Job To provide thought leadership and
More informationLESSONS LEARNED REPORT
Demystifying Quality in a Project Environment Best Practice User Group Workshop LESSONS LEARNED REPORT Purpose This document summarises the results of a workshop looking at Quality in a Project Environment,
More informationOperations. Group Standard. Business Operations process forms the core of all our business activities
Standard Operations Business Operations process forms the core of all our business activities SMS-GS-O1 Operations December 2014 v1.1 Serco Public Document Details Document Details erence SMS GS-O1: Operations
More informationPeer Reviews on Pre-application of Internal Models for NSAs and Colleges Final Report
EIOPA-RP-13-096a 18 July 2013 Peer Reviews on Pre-application of Internal Models for NSAs and Colleges Final Report 1/17 Table of Contents 1. Introduction... 3 1.1 Reasons for the peer reviews... 3 1.2
More informationTerms of Reference for LEAP II Final Evaluation Consultant
UNESCO Office Kabul, Afghanistan November 2015 Terms of Reference for LEAP II Final Evaluation Consultant Post Title: Final Evaluation Specialist Organization: UNESCO Office Kabul Location: Kabul, Afghanistan
More informationAction Plan Template. [Community Name] Climate Change Action Plan. Province of Manitoba Climate Change Planning Resources.
[Community Name] Climate Change Action Plan Prepared By: Acknowledgements: Ex. council/board, staff, committee Date: When submitted to council/board Executive Summary A short summary outlining the main
More information2.1 We continue to focus on five areas of development in this report:
MEETING: Agenda item and Paper Number Agenda Title Sponsor Author PUBLIC BOARD MEETING 18 November 2015 5 CM/11/15/05 2015/16 Quarter 2 Corporate Performance and Finance report Mark Edmonds, Director of
More informationManchester City Council Role Profile. Service Desk Analyst, Grade 6. ICT Service, Corporate Core Directorate Reports to: Team Lead (Service Support)
Key Role Descriptors: Manchester City Council Role Profile Service Desk Analyst, Grade 6 ICT Service, Corporate Core Directorate Reports to: Team Lead (Service Support) Job Family: Technical The role holder
More informationLessons learned from creating a change management framework
Lessons learned from creating a change management framework Author Melanie Franklin Director Agile Change Management Limited Contents Introduction 3 What is a Change Management Framework? 3 Why is it called
More informationE N T R E P R E N E U R I A L S K I L L S P A S S P R O J E C T Q U A L I T Y A S S U R A N C E P L A N
E N T R E P R E N E U R I A L S K I L L S P A S S P R O J E C T Q U A L I T Y A S S U R A N C E P L A N Version 6.0 24/05/2014 Entrepreneurial Skills Pass V E R S I O N H I S T O R Y Version # Date Author
More informationProcedure ODRQ06-1 Strategic Planning
APPROVAL SIGNATURES DATE Delia Mozer (original signature on file) Director 04/01/02 REVISION HISTORY Rev No. Description of Change Author Effective Date Basic Initial Release Delia Mozer 10/01/02 A B C
More informationManaging Successful Programmes
Managing Successful Programmes Syllabus 2011 (Version 2.0 - July 2012) 1. Introduction The Managing Successful Programmes (MSP) guidance explains the programme management principles, governance themes
More informationRetained Fire Fighters Union. Introduction to PRINCE2 Project Management
Retained Fire Fighters Union Introduction to PRINCE2 Project Management PRINCE2 PRINCE stands for: PRojects IN Controlled Environments and is a structured method which can be applied to any size or type
More informationGuide to: Successful Customer Onboarding
Guide to: Successful Customer Onboarding Getting Started The first 90 days will decide the fate of most implementations. While the complexity of your product could shift the timeline, if a customer feels
More informationDIGITAL MARKETPLACE (G CLOUD 7) OFFERING. Sopra Steria Integration Platform Support as a Service. Service Overview. Sopra Steria in the public sector
DIGITAL MARKETPLACE (G CLOUD 7) OFFERING Sopra Steria Integration Platform Support as a Service Sopra Steria in the public sector Organisations across the public sector choose Sopra Steria to deliver transformation
More informationSingle Sourcing as Enabler for SAP Clients
Single Sourcing as Enabler for SAP Clients Gert Keuschnigg IBM Business Consulting Services Vienna, April 2005 Table Of Contents Initial Situations at Clients and Goals of Single Sourcing Approaches of
More informationNCBS DATA ANALYST EXPERT COACH TERMS OF REFERENCE. National Capacity Building Secretariat
NCBS DATA ANALYST EXPERT COACH TERMS OF REFERENCE Position Type Organization Partner organization Duration Type of contract Data Analyst Expert Coach Consultancy contract National Capacity Building Secretariat
More informationHow To Monitor A Project
Module 4: Monitoring and Reporting 4-1 Module 4: Monitoring and Reporting 4-2 Module 4: Monitoring and Reporting TABLE OF CONTENTS 1. MONITORING... 3 1.1. WHY MONITOR?... 3 1.2. OPERATIONAL MONITORING...
More informationProject Charter and Scope Statement
Prepared by: Mike Schmidt Version: 1.0 Last Revision Date: April 14, 2010 Create Date: May 6, 2010 EXECUTIVE SUMMARY... 3 1 INTRODUCTION... 4 2 PROJECT OBJECTIVES... 4 2.1 MISSION... 4 2.2 OBJECTIVES...
More informationIntroductory Certificate. The APM Project Fundamentals Qualification
The syllabus provides a summary of the coverage of the qualification, the details are then found in the learning outcomes and assessment criteria. Both the syllabus and the learning outcomes and assessment
More informationProject Management Manual
Project Management Manual PM01 Introduction to the Project Management Manual Ref: PM01 (V7.01) - Uncontrolled once Printed Issued on 20 th December 2006 Manual Owner: James Couper Head of Project Management
More informationJob description. Terms of reference. Date: August 2015. Job title: Vacancy reference: Team/business unit: Base location: Reporting line:
Job description August 2015 Terms of reference Date: August 2015 Job title: Vacancy reference: Team/business unit: Project Team Leader PS15116 Pensions Administration Base location: Reporting line: Responsible
More informationRole Reporting Information. Role Family Analyst (Why the family exists and how it adds value to EnergyAustralia)
Role Reporting Information Role Title Business Analyst Position Number Role Reports Directly To Practice Leader EnergyAustralia Group Executive Manager Chief Information Officer Date 10/08/2015 Role Family
More informationDECEMBER 2015 PTAB Public Hearing Schedule
IPR 2015-00021 Tuesday, December 01, 2015 9:00 AM A ALEXANDRIA, VA 2013-003491 12422863 Tuesday, December 01, 2015 9:00 AM (MST) 14-133 DENVER, CO 2013-003763 11839384 Tuesday, December 01, 2015 9:00 AM
More informationAnnual Business Plan 2016-2017 and Budget Process
94 AGENDA ITEM NO.: 19.2 TO: Council Meeting on 22 September 2015 DIRECTOR: REPORT AUTHOR: SUBJECT: Ginny Moon, Director Corporate Services Chris Birch, Manager Financial Services Annual Business Plan
More informationPLA WITH A PURPOSE Credit by Examination Working Group Structure, Outcomes, & Timeline
PLA with a Purpose Overview PLA WITH A PURPOSE Credit by Examination Working Group Structure, Outcomes, & Timeline Prior Learning Assessment (PLA) comprises a number of time-tested approaches that evaluate
More informationBenefits. MIRACLE Benefits. I have no idea! What is going on in here? Konferencja "Bezpieczny Projekt" WARSZAWA 11 maja 2010 r.
Programme Plan MIRACLE Benefits Benefits What is going on in here? I have no idea! 1 W A R S Z A W A R Z E S Z Ó W W R O C Ł A W 1 Fitting the pieces together How the APMG Product Set helps you manage
More informationAmbulance Victoria. Position Description
Position Title: IT Project Manager Team Leader Position Description Division: Information & Technology Department: Solution Delivery Reports To: Manager Solution Delivery Direct Reports: IT Project Managers
More informationPlease see the full job description at the end of this document for full details on the Qualifications and Experience required for this role.
Title of Post Research Manager Location Christchurch Square, Dublin 8. Employment Type Fulltime (37 hrs) and Permanent Salary 50,209-65,505 Contact Person Helena Nolan 01 4530355 To apply, email application
More informationIntegrating the Worldwide Project Management Method (WWPMM) into an IBM Global Services Method Project
IBM Global Services Integrating the Worldwide Project Management Method (WWPMM) into an IBM Global Services Method Project Technique Paper (TP) Copyright International Business Machines Corporation, 2000
More informationTECHNICALS LEVEL 2016 3 BUSINESS
2016 Suite Cambridge TECHNICALS LEVEL 3 BUSINESS Unit 16 Principles of project management M/507/8163 Guided learning hours: 60 Version 2 - Revised content - March 2016 ocr.org.uk/business LEVEL 3 UNIT
More informationPRE SHOW COMMUNICATIONS
PRE SHOW COMMUNICATIONS NEWSLETTERS AND EMAILS The following emails are sent f by the Marketing Team to promote the show to potential visitors and Hosted Buyers from July to November and encourage them
More informationPROJECT MANAGER. Grade: Salary:
PROJECT MANAGER Grade: Salary: Career Grade F/G* *see career grade structure 24,427 to 33,771 per annum Status: 12 months fixed term contract with potential for a further 12 months extension subject to
More informationHSA Bank s Group Online Contributions System Guide
HSA Bank s Group Online Contributions System Guide Overview Thank you for selecting HSA Bank as your health savings account (HSA) administrator. HSA Bank, one of the leading HSA administrators in the nation,
More informationM&E Officer. Location: [Africa] [Ghana] [Accra] Category: Field Operations. Job Type: Fixed term, Full-time
M&E Officer Location: [Africa] [Ghana] [Accra] Category: Field Operations Job Type: Fixed term, Full-time M&E Officer To be responsible for high quality design, monitoring and evaluation of Cocoa Life
More informationBLOOM AND WAKE (ELECTRICAL CONTRACTORS) LIMITED QUALITY ASSURANCE MANUAL
130 Wisbech Road Outwell Wisbech Cambridgeshire PE14 8PF Tel: (01945) 772578 Fax: (01945) 773135 Copyright 2003. This Manual and the information contained herein are the property Bloom & Wake (Electrical
More informationBusiness Administration Certificates
T1 Important Dates Semester 1 T9a Business Administration Certificates Faculty of Business and Information Technology Timetable 2014 Orientation: 14 February Start Date: 17 February End Date: 27 June Semester
More informationRisk Management Plan template <TEMPLATE> RISK MANAGEMENT PLAN FOR THE <PROJECT-NAME> PROJECT
RISK MANAGEMENT PLAN FOR THE PROJECT Prepared by: Approved by: Reference: Version: Date: INTRODUCTION This document is the Risk Management
More informationRole Description Metro Operations, Data Analyst
Role Description Metro Operations, Data Analyst Cluster Agency Division/Branch/Unit Location Transport Transport for NSW Infrastructure & Services / Service Delivery & Performance / Metro Service Delivery
More informationIS&T Project Management: Project Management 101. June, 2006
IS&T Project Management: Project Management 101 June, 2006 Session Objectives Review basics management Discuss obstacles to effective management Share practices that work for you Empower you to try some
More informationRelease: 1. BSBPMG510A Manage projects
Release: 1 BSBPMG510A Manage projects BSBPMG510A Manage projects Modification History Not applicable. Unit Descriptor Unit descriptor This unit describes the performance outcomes, skills and knowledge
More informationProject Management Fact Sheet:
Project Management Fact Sheet: Project Documentation Version: 2.2, November 2008 DISCLAIMER This material has been prepared for use by Tasmanian Government agencies and Instrumentalities. It follows that
More informationNational Disability Authority Resource Allocation Feasibility Study Final Report January 2013
National Disability Authority Resource Allocation Feasibility Study January 2013 The National Disability Authority (NDA) has commissioned and funded this evaluation. Responsibility for the evaluation (including
More informationResearch and information management strategy 2015-18. Using research and managing information to ensure delivery of the Commission s objectives
Research and information management strategy 2015-18 Using research and managing information to ensure delivery of the Commission s objectives 1 1. Introduction This strategy sets out a range of research
More informationRisk Management Strategy and Policy. The policy provides the framework for the management and control of risk within the GOC
Annex 1 TITLE VERSION Version 2 Risk Management Strategy and Policy SUMMARY The policy provides the framework for the management and control of risk within the GOC DATE CREATED January 2013 REVIEW DATE
More informationINTERNATIONAL LABOUR ORGANIZATION THE OFFICE OF THE ILO LIAISON OFFICER. Call for Expression of Interest ILO/YGN/15/10.
INTERNATIONAL LABOUR ORGANIZATION THE OFFICE OF THE ILO LIAISON OFFICER Call for Expression of Interest ILO/YGN/15/10 19 November 2015 Post Title: Organization: Duty Station: National Consultant for the
More informationJob Grade: Band 5. Job Reference Number:
Job Title: Business Analyst Job Grade: Band 5 Directorate: Job Reference Number: People and Transformation P01216 The Role: This is a challenging role working with and across all services to support the
More informationNOT PROTECTIVELY MARKED KATHIE CASHELL, STRATEGY AND PROJECTS MANAGER BUSINESS SERVICES DIRECTORATE
COMMISSION MEETING 8 JUNE KATHIE CASHELL, STRATEGY AND PROJECTS MANAGER BUSINESS SERVICES DIRECTORATE OUTLINE CORPORATE PLANNING PROCESS IN /12 1.0 Purpose of Report 1.1. To present to Commission an outline
More informationCustomer Experience Functional Lead - BaseCamp. Business Change Manager
Position Profile Position: Customer Experience Functional Lead - BaseCamp Position Incumbent: Company: Location: Reporting to: Meridian Energy Christchurch Business Change Manager Date: December 2008 This
More informationJohn Tighe ISO 9001 Lead Auditor & Scheme Champion. Alongside CD1, the ballot for 3 specific questions agreed in Sept 2013.
ISO 9001:2015 Draft. Fergal O Byrne, Head of Business Excellence Certification. John Tighe ISO 9001 Lead Auditor & Scheme Champion. NSAI 1 Alongside CD1, the ballot for 3 specific questions agreed in Sept
More informationPOSITION DESCRIPTION, PERFORMANCE MEASURES AND TARGETS
POSITION DESCRIPTION, PERFORMANCE MEASURES AND TARGETS Attachment 1 Position Title: Administration Assistant Responsible to: Office Manager Responsibility: Office Administration Current Incumbent: (Vacant)
More informationOPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT)
OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT) 3 DAY COURSE INTRODUCTION The principles of project management are generic and therefore can be applied to all projects regardless of business sector.
More informationCAPABILITY MATURITY MODEL & ASSESSMENT
ENTERPRISE DATA GOVERNANCE CAPABILITY MATURITY MODEL & ASSESSMENT www.datalynx.com.au Data Governance Data governance is a key mechanism for establishing control of corporate data assets and enhancing
More informationSolvency II. PwC. *connected thinking. Solvency II GAP-analysis: practical experience (life and non-life business)
Solvency II Solvency II GAP-analysis: practical experience (life and non-life business) *connected thinking PwC Decide ambition level for Solvency II Business use Standard model, Total eller partiel Optimizing
More informationReport to Trust Board 29.11.12. Executive summary
Report to Trust Board 29.11.12 Title Sponsoring Executive Director Author(s) Purpose Previously considered by Transforming our Booking and Scheduling Systems Steve Peak - Director of Transformation Steve
More informationSolihull Clinical Commissioning Group
Solihull Clinical Commissioning Group Business Continuity Policy Version v1 Ratified by SMT Date ratified 24 February 2014 Name of originator / author CSU Corporate Services Review date Annual Target audience
More informationPart B1: Business case developing the business case
Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project
More information