CONSTRUCTION METHOD STATEMENT FOR DEMOLITION AND NEW BUILD OF 13 NO. HOUSES AT LIME GROVE SCHOOL SITE BATH
|
|
- Miles Richard Cooper
- 7 years ago
- Views:
Transcription
1 CONSTRUCTION METHOD STATEMENT FOR DEMOLITION AND NEW BUILD OF 13 NO. HOUSES AT LIME GROVE SCHOOL SITE BATH
2 2
3 Construction Method Statement INTRODUCTION The site is currently a disused school with various derelict boarded up buildings on it. Initial demolition of the school building will need to take place and once planning consents are in place a demolition contractor has been appointed. The demolition contractor will also be the Principal Contractor while demotion works are carried out. In the interests of being environmentally friendly, all existing concrete and brick rubble will be crushed and reused on site. SITE SET UP The extent of the site compound will be as shown in Appendix 1 In the interest of protection for the general public, it will be our intention to have full protective hoarding and screens around the site. ACCESS AND EGRESS The existing gate to the school will be kept in place for access and egress purposes. With regard to members of the public using the adjacent footpath to the south boundary a banksman will be in place to control traffic accessing and leaving the site TREE PROTECTION All tree protection measures will be in place to approved drawings prior to any operations taking on site. 3
4 Construction Method Statement DELIVERIES It is our intention to bring all deliveries along the A36 Pulteney Road turning into Pulteney Grove then left into Lime Grove Gardens avoiding Lime Grove due to the narrowness of the road, as shown in Appendix 2. All deliveries to site will take place on rigid axle lorries only due to residents parking on the road in Lime Grove Gardens. It is also our intention to avoid deliveries during rush hour to alleviate congestion for the local residents. CONTRACTORS PARKING All contractors parking will be on-site or in the pay and display car park outside of Bath Cricket Club. Absolutely no parking will be allowed by sub-contactors on any the adjacent roads. PILING None 4
5 Construction Method Statement GROUNDWORKS Groundworks will be carried out by supply and fix contractors, to be appointed, once planning for the development has been received. The above conditions will be set out in the Terms of Engagement. It is also envisaged that while the groundworkers are on site the groundworker will be the Principal Contractor and Bloor Homes will be the client. Once development has reached oversite stage and on-site road and footpaths completed, Bloor Homes will take over as Principal Contractor and our own employed manager will be on site on a permanent basis. All contractors and sub-contractors will be expected to have passed Bloor Homes standard competency checks and where necessary references will be taken and checked. COMMUNICATION AND LIAISING Throughout the project Bloor Homes and all their staff and contractors will maintain a high level of liaison and communication with all relevant parties to ensure the programme can be carried out with least amount of disruption to our neighbours, their property and the general public. The proposed site manager for this development will be Mr John Mumford who has worked in Bath previously on similar projects. WHEEL WASHING If required, a wheel wash may be put in place at the entrance to the site. 5
6 Construction Method Statement WASTE MANAGEMENT A full waste management plan will be put in place once planning is granted. DISC CUTTING All contractors and sub-contractors are made fully aware of their responsibilities and where necessary, dampening down measures will be put in place. PROPOSED ORDER OF BUILD Plots 1, 2, 5, 12, 13, 11, 10, 9, 8, 7, 6, 4 and 3. ESTIMATE OF CONTRACTORS ON SITE We estimate no more than 25 contractors on site any one time including: 4 Groundworkers 1 Forklift driver 1 Labourer 3 Carpenters 2 Plumbers 8 Bricklayers 2 Electricians 6
7 Construction Method Statement PROGRAMME OF WORKS It is estimated that the whole project would take no longer than 14 months. HOURS OF WORKING Hours of working will be: 8am to 5pm Monday to Friday 8am to 1pm Saturday No Sunday or Bank Holiday work. The site will be a Considerate Contractor Site Construction Director Mr John Gibbons Contracts Manager Mr Phil Lloyd Head Office Telephone Number
8 Appendix 1 8
9 ACCOMMODATION SCHEDULE TYPE A (1622 Sq Ft) 4 TYPE B (1960 Sq Ft) 2 TYPE C (1490 Sq Ft) 5 TYPE D (754 Sq Ft) 2 TOTAL 13 Notes: EXISTING TREES- TO BE RETAINED 1. Plot 5 will be used for an office, canteen and toilets. 2. Below plot 5 the garages of plots 1, 2, 3 and 4 will be used as storage. 3. Sub-contract parking to the rear garden of plot 3 and in front of garden Turning area for lorries in front of gardens 6, 7 and Banksman with be in attendance at all time to direct lorry movement Legend: P11 P10 P10 P12 P12 P13 P13 P11 P12 P13 Lorry Turning Area Sub-Contract Parking Compound and Welfare Storage Turning Area with Banksman Pedestrian Access Traffic Route Cross Over Point EXISTING RETAINING WALL 6 P6 P7 P9 P8 4 3 P5 P3 P4 P2 P1 2 TYPE D 5 EXISTING RETAINING WALL 1 Job. Former Lime Grove School Bath (13 units) Title. Traffic Management Plan Scale. Date. 1:500@A Drawn. Checked. TDO THIS DRAWING AND THE BUILDING WORKS DEPICTED ARE THE COPYRIGHT OF BLOOR HOMES LIMITED AND MAY NOT BE REPRODUCED OR AMENDED EXCEPT BY WRITTEN PERMISSION. NO LIABILITY WILL BE ACCEPTED FOR AMENDMENTS MADE BY OTHER PERSONS DO NOT SCALE THIS DRAWING, USE FIGURED DIMENSIONS ONLY, IF IN DOUBT ASK. R BLOOR HOMES LIMITED 3 STANTON COURT, SOUTH MARSTON PARK SWINDON, SN3 4YH TELEPHONE FACSIMILE LIME GROVE SCHOOL, BATH Drawing No. BHS91.TM01
10 Appendix 2 9
11
12
Construction Management Statement. Introduction. Contents
Construction Management Statement Project Name Dee Point Primary School Introduction On all Morgan Sindall projects, the safety and welfare of all is of paramount importance. This document concentrates
More informationSite Layout & Traffic Plan
Location Site address: Norbury Manor Business Enterprise College, Kensington Avenue, Thornton Heath, Croydon CR7 8BT. The new block will be constructed on the existing hard play area. The construction
More informationConstruction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot
Construction Management Statement Residential development at Bywell House, St Mary s Hill, Ascot Parking of Vehicles of Site Personnel, Operatives and Visitors Site staff, visitors to the development and
More informationConstruction Traffic Management Plan
Construction Traffic Management Plan Proposed Additional Accommodation for SWDPLS Shinners Bridge Dartington Produced for and on behalf of Built Environments Team Devon County Council NPS South West Ltd
More informationCONSTRUCTION MANAGEMENT PLAN
CONSTRUCTION MANAGEMENT PLAN for CHILDRENS CENTRE, PRIMARY CLASSROOM & REPLACEMENT PRESCHOOL AT CLYST ST MARY PRIMARY SCHOOL EXETER, DEVON EX5 1BG REVISION A 7 May 2010 1 P a g e Mansell have been appointed
More informationNorth Camden Town Neighbourhood Forum. 1. The meeting was organised as a drop-in session to accommodate all attendees on different schedules.
Camden Road Construction Liaison Meeting Tuesday 12 th May 2015, 5pm - 7pm The Irish Centre, Camden Square Attendees: Local representatives (LR) Anne Holt (AH) Polly Holt (PH) Gill Scott (GS) James Demos
More informationConstruction Traffic Management Plan
Construction Traffic Management Plan Proposed Additional Classroom Accommodation for Woolacombe Primary School Produced for and on behalf of Built Environments Team Devon County Council NPS South West
More informationCONSTRUCTION TRAFFIC MANAGEMENT PLAN Issue 2, V5, 11/11/13
Note: Please refer to the end of this document for guidance notes about completing this form Q1. What is the full postal address of the site? Your response Q2. Planning reference and revision number (if
More informationDemolition & Construction Management Plan
Demolition & Construction Management Plan 72 76 Cadogan lane SW1 Demolition & Construction Management Plan Issue Date: March 2013 Contents: 1.0 Introduction 1.1 Objectives of the Plan 1.2 Project Overview
More informationUniversity Arms Hotel, Cambridge
Traffic Management Plan For University Arms Hotel, Cambridge Prepared By: James Batterbee Number: M1342 / Rev B Date: 29 th August 2014 CONTENTS: (1) INTRODUCTION (2) VEHICLE ACCESS & EGRESS AND PEDESTRIAN
More informationCONSTRUCTION TRAFFIC MANAGEMENT PLAN V11, 26/09/12
If the project you are constructing was subject to planning permission and a condition requiring a Construction Traffic Management Plan (CTMP) was applied to the planning consent, this condition will need
More information5. Specific Use Regulations
5. Specific Use Regulations 5.1 Application 5.1.1 The specific use regulations shall apply to all development unless otherwise exempted in this section. 5.1.2 Where these regulations may be in conflict
More informationConstruction Management Plan (CMP) Application
About this form Principal Contractor (Applicant) Applicant Details (Person lodging application and main contact for CMP) DA and Site Details Development Consent for Works you are carrying out Construction
More informationTHIS PAGE INTENTIONALLY LEFT BLANK
THIS PAGE INTENTIONALLY LEFT BLANK Construction Traffic Management Plan 2 Contents 1. Introduction... 4 1.1 Conditions of Consent... 4 2. Goals of the CTMP... 6 2.1 Objectives... 6 2.2 Predicted Construction
More information1.1 The application property is an extended two-storey semi-detached house fronting Bedale Road. The side garden adjoins a link road to Wydale Road.
COMMITTEE REPORT Date: 13 October 2011 Ward: Osbaldwick Team: Major and Parish: Osbaldwick Parish Commercial Team Council Reference: 11/02264/FUL Application at: 27 Bedale Avenue Osbaldwick York YO10 3NG
More informationApproval Services Unit
Approval Services Construction Management Plan Pro-Forma Commercial Properties Please complete the enclosed form and return to:- By Mail: Approval Services Unit City of Perth Council House 27 St Georges
More informationLogo here. TRAFFIC MANAGEMENT PLAN Ref : xxxx Dated xxxxxx. Enter details. Delivery Address: Enter details
Logo here Ref : xxxx Dated xxxxxx Mandatory H&S 905 Rev 1: xxxxx Page 1 of 1 Project: Project No: Date: Prepared by: Enter details Enter details Enter details Enter details Delivery Address: Enter details
More informationCONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP)
CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP) [Colston Budd Hunt & Kafes Pty Ltd AS AMENDED BY City of Sydney] 23 March 2010 1. PREAMBLE 1.1 This document constitutes the Demolition and Traffic Management
More informationCITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES
CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES INTRODUCTION What is a Construction Management Plan? The City of Vincent requires careful management of construction involving excavation and retention
More informationConstruction Traffic Management Plan
Introduction This (CTMP) has been prepared in order to discharge Condition 20 of planning permission ref 07/02879/EFUL for the enabling site works associated with the wider Bath Western Riverside development.
More informationHoward Primary School Construction Management Plan
2.1 Introduction Howard Primary School Construction Management Plan The Howard Primary school project covers the construction of a new three storey block next to a live school and includes alterations
More information19-27 Young Street Development Kensington
19-27 Young Street Development Kensington Construction Management Plan Resident Update Draft 2nd October 2013 υ Introduction An initial construction management meeting took place on Tuesday 10 th September
More informationRAEBURN GARAGE, 118 RAEBURN AVENUE, SURBITON
RAEBURN GARAGE, 118 RAEBURN AVENUE, SURBITON DELIVERY AND SERVICING PLAN August 2015 Introduction This Delivery and Servicing Plan (DSP) has been prepared in relation to the proposed redevelopment of Raeburn
More informationConstruction Site Set Up Requirements
Process Code Number Revision COP A 035 B Document Title Construction Site Set Up Requirements B 1/11/10 SRC SAT DH Final A 1/10/10 SRC MI Draft comment Rev. Date Prepared Reviewed Approved Detail/Comment
More information5. Builder/Contractor Guidelines/Work Rules
Architectural Standards Committee 5. Builder/Contractor Guidelines/Work Rules 5.1 Builder/Contractor Responsibilities 5.2 Work Time and Days 5.3 Posting of Permits The builder/contractor is responsible
More informationThis document must be read in conjunction with the Permit to Work and Service Interruption Notice policy.
UNIVERSITY OF HERTFORDSHIRE HIGHER EDUCATION CORPORATION SITE RULES FOR CONTRACTORS The University s Site Rules for Contractors are issued on the authority of the Director of Estates, Hospitality and Contract
More informationAppendix 8 Providing Pre-construction information and check list (Regulations 10)
Appendix 8 Providing Pre-construction information and check list (Regulations 10) Project specific health and safety information STFC will have procedures in place to ensure that there is timely release
More informationFoulford Primary School Site Traffic Management Plan. December 2012 (Review date October 2013)
Foulford Primary School Leuchatsbeath Drive Cowdenbeath Fife KY4 9SN Foulford Primary School Site Traffic Management Plan December 2012 (Review date October 2013) Site Traffic Management Plan Foulford
More informationGalloper Wind Farm Project. Traffic Management Plan May 2013 Draft v1 Document Reference GWF/TMP/100513. Galloper Wind Farm Limited
Galloper Wind Farm Project Traffic Management Plan May 2013 Draft v1 Document Reference GWF/TMP/100513 Galloper Wind Farm Limited Document title Galloper Wind Farm Project Traffic Management Plan Status
More informationRepton Primary School. Traffic Management Plan
Repton Primary School Traffic Management Plan Headteacher: Mrs H Wallis Signature: H Wallis Date: 26 th June 2015 Chair of Governors: Mrs L Eaton Signature: L Eaton Date: 26 th June 2015 8 th June 2015
More informationPay Guide - Hospitality Industry (General) Award 2010 [MA000009]
Pay Guide - Hospitality Industry (General) Award 2010 [MA000009] Published 28 June 2016 Pay rates change from 1 July each year, the rates in this guide apply from 01 July 2016. Information about the definition
More informationWhen: Wednesday - January 16th @ 2:00 P.M. Auction Location: Santa Clara County Roads and Airports Department 101 Skyport Drive, San Jose, CA 95110
Sealed Bid Auction 2 Homes, 1 Residential Lot & 1 Commercial Unit When: Wednesday - January 16th @ 2:00 P.M. Auction Location:, s for All Residential Properties Saturday December 15, 2012 Saturday January
More informationRawdon Investments Limited & Aldi Stores Limited Former Barkers Nursery, Clitheroe Servicing Management Plan
Rawdon Investments Limited & Aldi Stores Limited Former Barkers Nursery, Clitheroe Servicing Management Plan Technical Note No. 6 Project: Former Barkers Nursery, Clitheroe Planning Application 3/2014/0890
More informationDELIVERY & SERVICING PLAN. REDWOOD PARTNERSHIP Consulting Engineers Transportation Planners
Redwood Partnership Transportation Limited Maritime House Basin Road North Portslade Brighton BN41 1WR T: 01273 414515 F: 01273 376824 E: consult@redwoodpartnership.co.uk www.redwoodpartnership.co.uk REDWOOD
More informationReference: 05/00928/FUL Officer: Mr David Jeanes
DEVELOPMENT CONTROL BOARD 5 January 2006 Reference: 05/00928/FUL Officer: Mr David Jeanes Location: Proposal: Applicant: Whiffens Farm Clement Street Sutton-At-Hone Kent BR8 7PQ Retrospective application
More informationAPPLICATION FOR PLANNING PERMISSION FOR A SOIL TREATMENT FACILITY AT KINGS CLIFFE LANDFILL SITE, STAMFORD, NORTHAMPTONSHIRE
APPLICATION FOR PLANNING PERMISSION FOR A SOIL TREATMENT FACILITY AT KINGS CLIFFE LANDFILL SITE, STAMFORD, NORTHAMPTONSHIRE DESIGN AND ACCESS STATEMENT Report Reference: AU/KC/SPH/1449/01/D&A/FIN Baddesley
More informationReplacing lead and common supply pipes
Replacing lead and common supply pipes How do I know if I have lead pipes? If your home was built before 1970, there s a chance that your water supply pipe is made from lead. This is the pipe that brings
More informationVEHICLE CROSSOVER INFORMATION PACK
VEHICLE CROSSOVER INFORMATION PACK CONTENTS Introduction Section A Section B Section C Section D Section E Criteria for approving a vehicle crossover application (Diagrams to demonstrate measurement criteria)
More informationProposed Sports Hall at. Oldfield School. Kelston Road. Bath BA1 9AB. Construction Management Plan June 2011 Rev A
Proposed Sports Hall at Oldfield School Kelston Road Bath BA1 9AB Construction Management Plan June 2011 Rev A CONTENTS 1.0 Introduction 2.0 Site Location 3.0 Proposed Development 4.0 Construction Management
More informationDRIVER LICENCE ENDORSEMENTS Demonstrate knowledge and skills for driving a forklift on a road for endorsement F (forklifts)
1 of 6 level: 3 credit: 2 planned review date: July 2006 sub-field: Driving replacement information: This unit standard replaced the components relating to endorsement F requirements of unit standard 16670
More information10.1 WILL HEY FARM WATFORD LANE NEW MILLS RETENSION OF NEW STABLE BLOCK, SAND PADDOCK AND ASSOCIATED EARTHWORKS AND LANDSCAPING (FULL - MINOR)
HPK/2012/0207 03/04/2012 WILL HEY FARM WATFORD LANE NEW MILLS MR & MRS M WILSON KIRSTY WILSON EQUINE AND WILL HEY FARM BED & BREAKFAST RETENSION OF NEW STABLE BLOCK, SAND PADDOCK AND ASSOCIATED EARTHWORKS
More informationSITE MANAGEMENT PLAN 2013
1 SITE MANAGEMENT PLAN 2013 GROUNDS OF THE ROYAL HOSPITAL CHELSEA, LONDON SW3 RHS CHELSEA FLOWER SHOW January, 2013 2 1. RHS CHELSEA FLOWER SHOW: PROJECT & KEY FACTS Overview The RHS Chelsea Flower Show
More informationUNIVERSITY PRE-SCHOOL & CHILDCARE CENTRE
FACILITIES AND SERVICES SERVICE LEVEL AGREEMENT - ONGOING SERVICES UNIVERSITY PRE-SCHOOL & CHILDCARE CENTRE PART ONE CONDITIONS 1. Introduction The purpose of the Agreement is to define the service responsibilities
More informationWORK RULES AND CONTRACTOR REQUIREMENTS FOR ALL UNIT OWNERS & UNIT OWNER CONTRACTORS PERFORMING WORK ON THE PREMISES AT HAWTHORNE PLACE CONDOMINIUMS
WORK RULES AND CONTRACTOR REQUIREMENTS FOR ALL UNIT OWNERS & UNIT OWNER CONTRACTORS PERFORMING WORK ON THE PREMISES AT HAWTHORNE PLACE CONDOMINIUMS 1) GENERAL GUIDELINES a) The following rules, regulations,
More informationLT McGuinness Site 10 Development, Wellington Waterfront. Construction Traffic Management Plan. 7 October 2014
LT McGuinness Site 10 Development, Wellington Waterfront Construction Traffic Management Plan 7 October 2014 TDG Ref: 12950 141007 ltm ctmp final report.docx LT McGuinness Site 10 Development, Wellington
More informationrepairing leaks to your service pipe increasing water efficiency
repairing leaks to your service pipe increasing water efficiency nobody loves a leak A water leak on your property is a waste of a precious resource. If left running it may cause damage to your property
More informationManchester City Council Item 6 Planning and Highways Committee 8 May 2014
Application Number 104843/FO/2014/N1 Date of Appln 28th Feb 2014 Committee Date 8th May 2014 Ward Moston Ward Proposal Location Applicant Agent Change of use of ground floor to a hot food takeaway (Fish
More informationGosport Borough Council Waste and Recycling Collection Policy
Gosport Borough Council Waste and Recycling Collection Policy WASTE AND RECYCLING COLLECTION POLICY The Council is under a duty to arrange the collection of household waste from properties in its area.
More informationConstruction Management Plan. Springfield Hospital
Springfield Hospital Page No: 1 of 22 Document Control Job Title : Springfield Job No. 532 Document Title : Revision Date Description Prepared by Checked by Approved by 17/05/10 First Draft JR Page No:
More informationapproval of matters specified in conditions; and The Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013
Application for: planning permission; planning permission in principle; further applications; approval of matters specified in conditions; and mineral workings (if the planning authority do not have a
More informationProposed Sports Hall at. Oldfield School. Kelston Road. Bath BA1 9AB. Construction Management Plan June 2011
Proposed Sports Hall at Oldfield School Kelston Road Bath BA1 9AB Construction Management Plan June 2011 CONTENTS 1.0 Introduction 2.0 Site Location 3.0 Proposed Development 4.0 Construction Management
More informationAVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES
overhead 23/11/04 2:28 PM Page 1 AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES ESB Code 9803203 overhead 23/11/04 2:28 PM Page 2 overhead 23/11/04 2:28 PM Page 3 Page 1 of 20
More informationPenalty points and fixed charge offences
Appendix : points and fixed charge offences s that carry penalty points Payment Conviction 8 next 8 Speeding E0 Failure by Driver to comply with front seat belt requirements (for self and for passengers
More informationNSW Payroll Tax Information for Contractors and Employment Agents
NSW Payroll Tax Information for Contractors and Employment Agents Deemed employees If a relevant contract or employment agency contract is not exempt, the hiring business or employment agency is deemed
More informationConstruction Management Plan pro forma v2.0
Construction Management Plan pro forma v2.0 Regents Park Estate By; Lovell Partnership Limited 4th Draft issued on 23 Dec 2015 following comments from Camden Officers Contents Internal review sheet 3 Introduction
More informationNew Home Construction Packet
New Home Construction Packet Congratulations! You are building a new home in Meyerland. This packet of information was assembled to assist you with the process. It contains all the forms that you will
More informationGUIDANCE FOR FUTURE PLANNING PROPOSALS AND THEIR IMPACT ON WASTE VEHICLES SOUTH AND VALE
GUIDANCE FOR FUTURE PLANNING PROPOSALS AND THEIR IMPACT ON WASTE VEHICLES SOUTH AND VALE Policy DC7 New developments must make adequate provision for the sorting, storage and collection of waste arising
More information7 Temple Close Dorchester, Dorset
7 Temple Close Dorchester, Dorset 7 Temple Close, Dorchester, Dorset DT1 2QL A Modern Detached Four Bedroom House within the popular Castle Park residential part of Dorchester, close to Thomas Hardy School
More informationMinistry of the Environment Decree. on housing design
G1 THE NATIONAL BUILDING CODE OF FINLAND Housing Design Regulations and Guidelines 2005 Ministry of the Environment Decree on housing design adopted in Helsinki on the 1 st of October 2004 In accordance
More informationDrainage. Information for those with problem drains
Drainage Information for those with problem drains Contents 1 Purpose 2 Introduction 2 Explanations: what is a drain and what is a sewer 3 Explanation of the responsibilities for public and private sewers
More informationConstruction Management Plan Template
Plan Template Planning Permit Number:... Date Planning Permit Issued:... Approval Stamp (Office Use only): Standard Plan Template Project details Company Operational Details.. Directors Name Company Name
More informationCAMBERFORD LAW PLC. RECRUITMENT AGENCY and EMPLOYMENT BUSINESS INSURANCE PROPOSAL FORM
CAMBERFORD LAW PLC RECRUITMENT AGENCY and EMPLOYMENT BUSINESS INSURANCE PROPOSAL FORM Please note that 'You' or 'Your' in the context of this Enquiry Form means the persons named as Proposer and/or any
More informationElephant & Castle Regeneration TRADERS CHARTER
Elephant & Castle Regeneration TRADERS CHARTER June 2007 Elephant and Castle Shopping Centre Tenants Association 1 Elephant & Castle Regeneration TRADERS CHARTER June 2007 As small business traders at
More informationPage 19. Report of the Executive Head of Planning and Transportation. Ref: A2010/62734/FUL WARD: A03 / STONECOT Time Taken: 7 weeks, 0 days
Page 19 Agenda Item 3 DEVELOPMENT CONTROL COMMITTEE - Date: 23 June 2010 Report of the Executive Head of Planning and Transportation. Ref: A2010/62734/FUL WARD: A03 / STONECOT Time Taken: 7 weeks, 0 days
More informationRESIDENTIAL WINDOW REPLACEMENT
3S258 MANNING AVENUE WARRENVILLE, IL 60555 PH: 630.393.9050 FAX 630.393.1531 RESIDENTIAL WINDOW REPLACEMENT A building permit is required for the installation or replacement of windows in a residence.
More informationHousehold waste & recycling storage requirements
South Gloucestershire Council Guidance for Developers on Household waste & recycling storage requirements INTRODUCTION As part of the Council s aim to improve the quality of life for residents as well
More informationCONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL
CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL This manual applies to all development projects within Pitkin County. A Construction Management Plan (CMP) shall be submitted for all projects in Pitkin
More informationWe have consulted with internal and external. King Square Estate Newsletter. Regeneration Proposals
www.islington.gov.uk/housing Regeneration Proposals NOVEMBER 2014 Welcome to the third edition of the King Square newsletter, with the latest update on the King Square Estate regeneration project. This
More informationOWNER/TENANT LETTER OF AUTHORIZATION & INDEMNITY (This form is available online via www.sanctuarygreen.com.sg)
SANCTUARY GREEN CONDOMINIUM THE MANAGEMENT CORPORATION STRATA TITLE PLAN NO. 2916 189 TANJONG RHU ROAD, #01-02 SINGAPORE 436926 TEL: 6241 4818 FAX: 6241 8082 OWNER/TENANT LETTER OF AUTHORIZATION & INDEMNITY
More informationParking On-street parking Front garden parking Off-street parking
Nae place mair braw A guide to placemaking in Perth and Kinross Whan I haik't up to Craigie Hill And lookit east and west; "In a' the world," said I to mysel', "My ain shire is the best." Parking On-street
More informationBusinesses. Temporary and Long Term. Introduction to. in the City of Logan
Introduction to Temporary and Long Term Businesses in the City of Logan City of Logan Business Licensing a Division of the Community Development Department 435-716-9230 office 435-716-9001 fax Temporary
More informationThe Delivery Hub health, safety and environment Raising the bar 20 Transport and logistics management
Safe roads, reliable journeys, informed travellers The Delivery Hub health, safety and environment Raising the bar 20 Transport and logistics management Version I - November 2013 An executive agency of
More informationFederation of Piling Specialists
Federation of Piling Specialists COMPANY NAME CONTRACT NAME TENDER REF SCHEDULE OF ATTENDANCES AND FACILITIES TO BE PROVIDED BY THE CLIENT TO A STEEL SHEET PILING SPECIALIST For the purposes of this document
More informationGOODS LIFT BOOKING, LOADING DOCK PROCEDURES & MANAGEMENT SERVICES PARKING
GOODS LIFT BOOKING, LOADING DOCK PROCEDURES & MANAGEMENT SERVICES PARKING 2014 PREPARED BY: Jones Lang LaSalle (NSW) Pty Ltd A.B.N. 37 002 851 925 Chifley Tower, 2 Chifley Square, Sydney NSW 2000 Tel:
More informationDevelopment Variance Permit Application Package
When do I need a Development Variance Permit? Development Variance Permit Application Package If my proposed development does not meet the standards set out in the Zoning Regulation Bylaw on matters that
More informationConstruction Management Plan
Prepared by Expertise Building & (EBCPL) Construction Management Plan GAP BLUFF PRECINCT OFFICERS MESS THE ARMOURY GAP BLUFF COTTAGE CAMP COVE PRECINCT CONSTABLE S COTTAGE 33 CLIFF STREET GREEN POINT COTTAGE
More informationA Householder s Planning Guide for the Installation of Antennas, including Satellite Dishes
A Householder s Planning Guide for the Installation of Antennas, including Satellite Dishes Introduction This booklet is an outline of the planning regulations for antennas in England, and includes the
More informationElectricity Gas. Application for utility connections Business premises. Section E PME (Protective Multiple Earthing)
Electricity Gas Send your completed application form with supporting documentation to: Thank you for considering Energy Services as your utility provider. In the East and West Midlands, electricity connections
More informationApplication Package for License for Sidewalk Dining Adjacent to Eating Establishment
Application Package for License for Sidewalk Dining Adjacent to Eating Establishment Community & Economic Development Department Planning Division T :: 831.648.3190 F :: 831.648.3184 www.ci.pg.ca.us/cedd
More informationDevelopment Layout Design
Development Layout Design General Design Considerations for Adoptable Highways Version 1 June 2012 Transportation, Waste and Environment Service Issue and Revisions Record Revision Date Originator Purpose
More informationApplication for electricity connections Business premises. Electricity. Send your completed application form with supporting documentation to:
Electricity Thank you for considering for your electricity connections. We have put together these notes to help you fill out your and to ensure we receive all the correct information for your application
More informationPlease describe the proposal accurately and concisely. State the number of storeys proposed and the position of any extensions.
Householder Application for Planning Permission for Works or Extension to a Dwelling and for Relevant Demolition in a Conservation Area Town and Country Planning Act 1990 1. Applicant Name and Address
More informationSite Traffic Management Plan
Masterton Primary School Aberdour Road Dunfermline Fife KY11 8HY Telephone: 01383 602455 Email: masterton.enquiries@fife.gov.uk Head Teacher: Mr Stephen Humphries Site Traffic Management Plan Date December
More informationAppendix 6 Storage and Collection of Waste and Recycling
Appendix 6 Storage and Collection of Waste and Recycling Appendix 6 Storage and Collection of Waste and Recycling September 2008 (Version 2) 1 Appendix 6 Appendix 6 Design and Sustainability SPD Storage
More informationPLUMBERS ROW, LONDON, E1
PRESTIGE D1 (EDUCATION) & B1 ACCOMMODATION APPROX 10,664 SQ FT (990 M²) GROSS INTERNAL FLOOR AREA PLUMBERS ROW, LONDON, E1 *SELF-CONTAINED GROUND & LOWER GROUND FLOORS WITH PRIVATE ENTRANCES *READY FOR
More informationThe land is allocated within the Westbury on Trym Conservation Area and the land is protected by a blanket TPO 340.
SITE DESCRIPTION The site is occupied by a large single dwelling house which was built in 2007. The building is surrounded by large trees and has a substantial rear garden. The land is allocated within
More informationTemporary event application form Lake Karapiro
If you require assistance with your booking or forms, help can be obtained from the following: Mighty River Domain at 07 827 4178 info@lakekarapiro.co.nz www.lakekarapiro.co.nz Waikato Regional Council
More informationApplication for electricity connections Business premises
Electricity Thank you for considering Western Power Distribution for your electricity connections. We have put together these notes to help you fill out your and to ensure we receive all the correct information
More informationCity Code of ANN ARBOR, MICHIGAN Chapter 55 Zoning
ARTICLE II. USE REGULATIONS 5:10.2. R1A, R1B, R1C, R1D single family dwelling district (1) Intent. (a) These single family residential districts are designed to provide an environment of predominantly
More informationLeakage Code of Practice. Domestic Customers
Leakage Code of Practice Domestic Customers A Leakage Code of Practice Domestic Customers The advice in this Leakage Code of Practice is important and has been approved by the Water Services Regulation
More information21 Plumbers Row London E1 1EQ
bernardgordon.co.uk Ref: 1484 Ref: 1447 21 Plumbers Row London E1 1EQ Prestige D1 (education) & B1 accommodation Approx. 10,664 sq. ft. (990m²) gross internal floor area Self-contained, ground and lower
More informationAppendix G. Security management plan
Appendix G Security management plan Security Management Plan Prepared by: Kann Finch Group Project Energy Australia Belmore Park Zone 1- Sub-station component General Design Requirements The perimeter
More informationDimensional and Structural Data for Elliptical Pipes. PD 26 rev D 21/09/05
Dimensional and Structural Data for Elliptical Pipes 21/09/05 Page 1 of 15 1. Foreword This document details a method for the structural design of Stanton Bonna Elliptical pipes for the common conditions
More informationNoosa Jazz Festival Terms and Conditions Food and Market Stalls
Noosa Jazz Festival Terms and Conditions Food and Market Stalls Welcome to the Noosa Jazz Festival! As Noosa Shire s second longest-running event, the Noosa Jazz Festival has a proven track record of delivering
More informationCANNOCK CHASE COUNCIL MINUTES OF THE MEETING OF THE PLANNING CONTROL COMMITTEE WEDNESDAY, 30 JANUARY 2013 AT 3.00 P.M.
CANNOCK CHASE COUNCIL MINUTES OF THE MEETING OF THE PLANNING CONTROL COMMITTEE WEDNESDAY, 30 JANUARY 2013 AT 3.00 P.M. IN THE CIVIC CENTRE, BEECROFT ROAD, CANNOCK PART 1 PRESENT: Councillors Cartwright,
More informationMethod Statement Ground & Gardens Maintenance Service
CONFORMED COPY Method Statement Ground & Gardens Maintenance Service Revision History Revision Date Reviewer Status 23 March 2007 Project Co Final Version Table of Contents 1 Objectives... 3 2 Management
More informationINTERIM ADVICE NOTE 65/05 DESIGN OF VEHICLE RECOVERY OPERATIONS AT ROAD WORKS
INTERIM ADVICE NOTE 65/05 DESIGN OF VEHICLE RECOVERY OPERATIONS AT ROAD WORKS The Purpose of this document is to provide the Project Sponsor / Designer with comprehensive guidance on the range of issues
More informationMount Browne (Surrey Police Head Quarters), Sandy Lane, Guildford Vision Statement. November 2013. with
Mount Browne (Surrey Police Head Quarters), Sandy Lane, Guildford Vision Statement November 2013 with Tibbalds Planning & Urban Design 19 Maltings Place 169 Tower Bridge Road London SE1 3JB Telephone 020
More informationthe Ministry of Transport is attributed as the source of the material
Disclaimer All reasonable endeavours are made to ensure the accuracy of the information in this report. However, the information is provided without warranties of any kind including accuracy, completeness,
More informationCONSTRUCTION SEQUENCE & PROGRAMME
CONSTRUCTION SEQUENCE & PROGRAMME 2 CONTENTS 1.0 Introduction 7 2.0 Key activities 8 2.1 Airport related activities 2.2 Construction of new roads and accesses 2.3 Earthworks zone a 2.4 Earthworks zone
More information