1 19-27 Young Street Development Kensington Construction Management Plan Resident Update Draft 2nd October 2013 υ
2 Introduction An initial construction management meeting took place on Tuesday 10 th September between Grainger, Grainger s consultants and 4 local residents. At the beginning of the meeting Grainger outlined its intended process of consultation with residents and achieving a satisfactory construction management plan for the delivery of the Young Street development proposals, which is summarised as follows; Grainger is committed to working with residents to minimise where possible the adverse impact of the construction process. As part of the current planning application package a construction management plan was submitted Whilst typically a developer would not consider the construction management process until after planning is achieved, Grainger is keen to agree the principles of the construction management process as soon as possible with local residents As part of this process Grainger proposes a Construction Management Panel (CMP) is established, consisting of the developer and a number (circa 6) of local residents, who are selected and chosen by local residents. Once a contractor is selected, the contractor would also join the CMP. It is proposed that the CMP meet on a monthly, bi-weekly or weekly basis as Pre Construction Management Meetings to take place between planning and construction start (anticipated autumn 2014). The purpose of the Pre Construction Management Meetings (PCMM) will be to agree the final detailed construction management plan to be incorporated in the contract tender documentation. It is proposed that the CMP meet on a monthly or bi-weekly basis as Construction Management Meetings to take place during construction The purpose of Construction Management Meetings (CMM) will be to update the panel on construction progress, identify any issues and ensure resolutions are being implemented. Outline Timetable Planning Detailed Design Construction Completion 2013 Jan 14 Autumn 14 Autumn 14 to Autumn 16 Summer 2016 CMP Pre-Construction Management Construction Management As required Established Meetings (CMMP s) Meetings (CMM s) Over the course of the meeting on 10 th September a number of areas were discussed and detail provided. The residents agreed to consider who would wish to sit on the Construction Management Panel. Grainger agreed to provide a separate note to cover specific queries raised at the meeting regarding; Community Engagement Process, Traffic Management, Noise, Dust and Vibration.
3 Construction Management Plan Update After the initial residents meeting, the following has been produced as a draft addendum/appendix to the current construction management plan submitted to the Royal Borough of Kensington and Chelsea; 1) Community Engagement Grainger will ensure that liaison and consultation with residents continues through-out the project. This will be achieved by the Construction Management Panel (CMP), Pre-construction Management Meetings (PCMM) and Construction Management Meetings (PCM). Representatives from Grainger, the professional team and the main contractor will be introduced and will attend all such meetings, as appropriate. Grainger will ensure a clear point of contact is made available throughout the project and establish a clear escalation process should issues not be addressed. The contractor will develop a site logistic and traffic management plan that will be shared and agreed with local residents prior to commencing on site. 2) Traffic Control No construction traffic will enter Kensington square. All major vehicle movements will take place outside peak times i.e. after 10am and before 16.30pm Monday to Friday. The main contractor will be obliged to coordinate deliveries with Barkers department store, including Whole Foods and PC World. Full time project gateman and banksman will be employed to manage construction traffic on Young Street. These people are key as they will be the first point of contact and can deal with issues before they become problems. They will be selected for their experience and ability to liaise with local residents and the general public. During substructure operations vehicles will load and unload within the confines of the site. We will endeavour to do the same during superstructure operations, but this may not be practical. During periods of more intense vehicular activity, eg concrete pours, a vehicle holding area will be established outside the local vicinity. 3) Control of Potential Impacts on the Local Community (Noise, Dust and Vibration) No works will be permitted on Saturdays, Sundays or Bank holidays unless there are unavoidable and specific reasons and local residents have been advised in advanced. A managed approach will be adopted for the deconstruction of the Car Park structure using hydraulic crushing techniques whenever possible to "nibble" away the structure and work top
4 down, maintaining the existing structure to maximise the shielding effects for as long as possible. Limits for noise, dust and vibration together with monitoring regime will be established. The contractor will be contractually obliged to select methods of working and plant to minimise emission of noise, dust and vibration. With respect to noise a pre-construction background noise assessment will be completed in order to set a maximum noise level. An action level of 70 dba will be targeted with compulsory quiet periods at sensitive times, for example over lunchtime 12noon to 1.30pm. There would be occasions when the limit would inevitably be exceeded. Windows of operation for these noisy operations would be considered and mitigation measures fully explored before the works proceed. Trigger points will also be pre-determined for dust and vibration. The action level for vibration will be 5mm per sec, where it is recognised that a vibration level of 10mm/sec could risk the start of structural implications. With respect to dust an action level of 250 mirco-grams per cubic meter over a 15 minute period is proposed. In addition daily and weekly aggregate levels will also be recorded to monitor the overall performance of the contractor. The contractor will be obliged to deploy "real-time" monitoring equipment for: noise; vibration and dust at the perimeter of the site and other strategic points in the local vicinity and on sensitive buildings. Should a trigger point be reached then the contractor's resident site manager (or he deputy) and the client s representative will be notified instantaneously by so the problem can be address and any corrective action can be instigated. The Client s structural engineer will advise the scope and range for condition surveys of adjoining properties based on the geotechnical information obtained during the recent site investigations and the anticipated risks to neighbouring property. A fully height (2.4m) hoarding will be erected incorporating acoustic deadening material and, together with a "cocoon" of scaffold with monoflex sheeting to the height of the existing structure, will maximise noise screening during the noisiest operations. The Contractor will be obliged to keep the site well ordered, tidy and satisfactorily maintained at all times. Construction welfare facilities and smoking area will be located on site. Operatives will be encouraged to stay on site at break times. Safe pedestrian access will be maintained along Young Street at all times with clear segregation from construction traffic.
5 Please feel free to contact a member of the Grainger team; David Walters MRICS Development Director dwalters@graingerplc.co.uk Nick Kybert Project Manager nkybert@graingerplc.co.uk Richard Luffingham MRICS Development Manager rluffingham@graingerplc.co.uk Grainger plc 161 Brompton Road Knightsbridge London SW3 1QP United Kingdom
Demolition & Construction Management Plan
Demolition & Construction Management Plan 72 76 Cadogan lane SW1 Demolition & Construction Management Plan Issue Date: March 2013 Contents: 1.0 Introduction 1.1 Objectives of the Plan 1.2 Project Overview
More informationConstruction Management Statement. Introduction. Contents
Construction Management Statement Project Name Dee Point Primary School Introduction On all Morgan Sindall projects, the safety and welfare of all is of paramount importance. This document concentrates
More informationPROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON. Construction Management Plan
PROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON Construction Management Plan May 2013 CONTENTS Page No: 1.0 INTRODUCTION 1 2.0 PROJECT ORGANISATION AND RESPONSIBILITIES 2 2.1 Client
More informationApproval Services Unit
Approval Services Construction Management Plan Pro-Forma Commercial Properties Please complete the enclosed form and return to:- By Mail: Approval Services Unit City of Perth Council House 27 St Georges
More informationConstruction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot
Construction Management Statement Residential development at Bywell House, St Mary s Hill, Ascot Parking of Vehicles of Site Personnel, Operatives and Visitors Site staff, visitors to the development and
More informationHoward Primary School Construction Management Plan
2.1 Introduction Howard Primary School Construction Management Plan The Howard Primary school project covers the construction of a new three storey block next to a live school and includes alterations
More informationPollution & Noise from Demolition & Construction Sites
CONTROL OF Pollution & Noise from Demolition & Construction Sites N oi se Co ns tru ct io n MAY 2008 THE LONDON BOROUGH 3 CONTENTS Part 1 Introduction Page 1. Background 4 2. Purpose of the code 5 3.
More informationDepartment of Markets and Consumer Protection. Code of Practice for Deconstruction and Construction Sites. Seventh Edition May 2013
Department of Markets and Consumer Protection Code of Practice for Deconstruction and Construction Sites Seventh Edition May 2013 Department of Markets and Consumer Protection City of London PO Box 270
More informationUniversity Arms Hotel, Cambridge
Traffic Management Plan For University Arms Hotel, Cambridge Prepared By: James Batterbee Number: M1342 / Rev B Date: 29 th August 2014 CONTENTS: (1) INTRODUCTION (2) VEHICLE ACCESS & EGRESS AND PEDESTRIAN
More informationRotherham Metropolitan Borough Council
Rotherham Metropolitan Borough Council Town and Country Planning Act 1990 Self Architects The White House 24A St Andrews Road Sheffield S11 9AL Reference RB2014/1110 Decision Date 20 October 2014 Description
More informationCITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES
CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES INTRODUCTION What is a Construction Management Plan? The City of Vincent requires careful management of construction involving excavation and retention
More informationNorth Camden Town Neighbourhood Forum. 1. The meeting was organised as a drop-in session to accommodate all attendees on different schedules.
Camden Road Construction Liaison Meeting Tuesday 12 th May 2015, 5pm - 7pm The Irish Centre, Camden Square Attendees: Local representatives (LR) Anne Holt (AH) Polly Holt (PH) Gill Scott (GS) James Demos
More informationCONTROL OF POLLUTION ACT 1974, SECTION 61 PRIOR CONSENT APPLICATION CONSTRUCTION AND DEMOLITION SITE NOISE
CONTROL OF POLLUTION ACT 1974, SECTION 61 PRIOR CONSENT APPLICATION CONSTRUCTION AND DEMOLITION SITE NOISE I/WE HEREBY MAKE APPLICATION to the London Borough of Merton Council for Prior Consent under Section
More informationCONSTRUCTION TRAFFIC MANAGEMENT PLAN Issue 2, V5, 11/11/13
Note: Please refer to the end of this document for guidance notes about completing this form Q1. What is the full postal address of the site? Your response Q2. Planning reference and revision number (if
More informationSite Layout & Traffic Plan
Location Site address: Norbury Manor Business Enterprise College, Kensington Avenue, Thornton Heath, Croydon CR7 8BT. The new block will be constructed on the existing hard play area. The construction
More informationJOB DESCRIPTION. To provide administrative support for all assessment related processes for which Registry are responsible.
JOB DESCRIPTION 1. JOB TITLE: Administrative Officer (Assessment) 2: HRMS REFERENCE NUMBER: HRMS/13090 3. ROLE CODE: AORS 4. DEPARTMENT: Registry Services 5. ORGANISATION CHART: Reporting to the Senior
More informationGalloper Wind Farm Project. Traffic Management Plan May 2013 Draft v1 Document Reference GWF/TMP/100513. Galloper Wind Farm Limited
Galloper Wind Farm Project Traffic Management Plan May 2013 Draft v1 Document Reference GWF/TMP/100513 Galloper Wind Farm Limited Document title Galloper Wind Farm Project Traffic Management Plan Status
More informationLogo here. TRAFFIC MANAGEMENT PLAN Ref : xxxx Dated xxxxxx. Enter details. Delivery Address: Enter details
Logo here Ref : xxxx Dated xxxxxx Mandatory H&S 905 Rev 1: xxxxx Page 1 of 1 Project: Project No: Date: Prepared by: Enter details Enter details Enter details Enter details Delivery Address: Enter details
More informationCONSTRUCTION TRAFFIC MANAGEMENT PLAN V11, 26/09/12
If the project you are constructing was subject to planning permission and a condition requiring a Construction Traffic Management Plan (CTMP) was applied to the planning consent, this condition will need
More informationConstruction Site Set Up Requirements
Process Code Number Revision COP A 035 B Document Title Construction Site Set Up Requirements B 1/11/10 SRC SAT DH Final A 1/10/10 SRC MI Draft comment Rev. Date Prepared Reviewed Approved Detail/Comment
More informationDevonport EfW CHP Facility. CEMP Proposal for Non Destructive Testing Activities. 1. Introduction
Devonport EfW CHP Facility CEMP Proposal for Non Destructive Testing Activities. 1. Introduction This application is issued in compliance with the principles of the approved Construction Environmental
More informationCONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP)
CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP) [Colston Budd Hunt & Kafes Pty Ltd AS AMENDED BY City of Sydney] 23 March 2010 1. PREAMBLE 1.1 This document constitutes the Demolition and Traffic Management
More informationFor the Provision of animal collection and impound services.
RFT PART B SPECIFICATION Darebin City Council Request for Tender (RFT) CT 201332 For the Provision of animal collection and impound services. RFT PART B - SPECIFICATION 1. INTRODUCTION AND BACKGROUND 1.1.
More information1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY
1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY Dumfries Timber Co. Ltd. is committed to comply with our legal duties in order to provide a safe and healthy working environment
More informationGuideline for preparing an Environmental and Social Management Plan
Guideline for preparing an Environmental and Social Management Plan NZ Transport Agency www.nzta.govt.nz Version 1: April 2014 ISBN 978-0-478-41934-4 (online) Copyright information This publication is
More informationWELCOME TO OUR EXHIBITION
WELCOME TO OUR EXHIBITION The purpose of the exhibition is to provide you with the opportunity to view our proposals and give feedback prior to the submission of a planning application to the London Borough
More informationHome Office, Home Occupation and Home Business
, Home Occupation and Home Business Introduction This fact sheet provides summary information on requirements for, Home Occupation and Home Business proposals. It is not a definitive document but provides
More informationSTANDARD ELEMENTS OF A CONSTRUCTION MANAGEMENT PLAN
STANDARD ELEMENTS OF A CONSTRUCTION MANAGEMENT PLAN JULY 2015 Standard Elements of a Construction Management Plan (CMP) This guidance tool was developed through partnership between the Department of Planning
More informationJOB DESCRIPTION. 5. ORGANISATION CHART: Reports to the Premises Manager (Thornton)
JOB DESCRIPTION 1. JOB TITLE: Mechanical & Electrical (M&E) Services Co-ordinator 2. HMRS REFERENCE NUMBER: HRMS/13270a 3. ROLE CODE: MESCF 4. DEPARTMENT: Facilities Management 5. ORGANISATION CHART: Reports
More informationConstruction Management Plan (CMP) Application
About this form Principal Contractor (Applicant) Applicant Details (Person lodging application and main contact for CMP) DA and Site Details Development Consent for Works you are carrying out Construction
More informationCONSTRUCTION MANAGEMENT PLAN
CONSTRUCTION MANAGEMENT PLAN for CHILDRENS CENTRE, PRIMARY CLASSROOM & REPLACEMENT PRESCHOOL AT CLYST ST MARY PRIMARY SCHOOL EXETER, DEVON EX5 1BG REVISION A 7 May 2010 1 P a g e Mansell have been appointed
More informationReference: 05/00928/FUL Officer: Mr David Jeanes
DEVELOPMENT CONTROL BOARD 5 January 2006 Reference: 05/00928/FUL Officer: Mr David Jeanes Location: Proposal: Applicant: Whiffens Farm Clement Street Sutton-At-Hone Kent BR8 7PQ Retrospective application
More informationInformation Sheet. What is a Workplace Transport Risk Assessment?
Workplace Transport Safety Risk Assessment Information Sheet This information sheet provides basic information on conducting a workplace transport risk assessment. The information is aimed at employers,
More informationAppendix 8 Providing Pre-construction information and check list (Regulations 10)
Appendix 8 Providing Pre-construction information and check list (Regulations 10) Project specific health and safety information STFC will have procedures in place to ensure that there is timely release
More informationConstruction Management Plan pro forma v2.0
Construction Management Plan pro forma v2.0 Regents Park Estate By; Lovell Partnership Limited 4th Draft issued on 23 Dec 2015 following comments from Camden Officers Contents Internal review sheet 3 Introduction
More informationJOB DESCRIPTION. Five: Operations Managers, Staging Manager, Assistant to Head of Shows Operations.
JOB DESCRIPTION Job Title: Department: Location: Reports to: Staff reports: Other reports: Job Purpose: Head of Shows Operations Shows Department Vincent Square, London Head of RHS Shows Five: Operations
More informationWhistler Village Construction Management Strategy
Whistler Village Construction Management Strategy Purpose: To mitigate the impacts of construction activity on the Whistler Village resort experience and on Village businesses and property owners. Objectives:
More informationConstruction Management Plan Template
Plan Template Planning Permit Number:... Date Planning Permit Issued:... Approval Stamp (Office Use only): Standard Plan Template Project details Company Operational Details.. Directors Name Company Name
More informationRAEBURN GARAGE, 118 RAEBURN AVENUE, SURBITON
RAEBURN GARAGE, 118 RAEBURN AVENUE, SURBITON DELIVERY AND SERVICING PLAN August 2015 Introduction This Delivery and Servicing Plan (DSP) has been prepared in relation to the proposed redevelopment of Raeburn
More informationConstruction Traffic Management Plan
Construction Traffic Management Plan Proposed Additional Classroom Accommodation for Woolacombe Primary School Produced for and on behalf of Built Environments Team Devon County Council NPS South West
More informationTriton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan
Triton Knoll Offshore Wind Farm Limited Electrical System Outline Traffic Management Plan October 2014 RWE Innogy UK Triton Knoll TMP Copyright 2014 RWE Innogy UK Ltd All pre-existing rights reserved.
More informationPLANNING SUPPORT STATEMENT. 29 Fernshaw Road, London SW10 0TG MRS. GAIL TAYLOR & MRS. KAREN HOWES. Prepared For TR/6570
PLANNING SUPPORT STATEMENT 29 Fernshaw Road, London SW10 0TG Prepared For MRS. GAIL TAYLOR & MRS. KAREN HOWES November 2012 Contents 1 INTRODUCTION 1 THE APPLICATION PROPERTY AND SURROUNDING AREA 1 RELEVANT
More informationAppendix D CONSTRUCTION MANAGEMENT PLAN
Appendix D CONSTRUCTION MANAGEMENT PLAN Contents Introduction... 2 Construction Work in Environmental Zones... 3 Construction Schedule... 6 Construction Work Hours... 7 Site Management... 7 Pre-construction
More informationThis document must be read in conjunction with the Permit to Work and Service Interruption Notice policy.
UNIVERSITY OF HERTFORDSHIRE HIGHER EDUCATION CORPORATION SITE RULES FOR CONTRACTORS The University s Site Rules for Contractors are issued on the authority of the Director of Estates, Hospitality and Contract
More informationEnvironment Committee 11 January 2016
Environment Committee 11 January 2016 Title Whole Life Costing of Footway Maintenance Treatments and Scheme Prioritisation Report of Wards Status Urgent Key Enclosures Commissioning Director, Environment
More informationPLANNING POLICY 3.3.5
PLANNING POLICY 3.3.5 CHILD CARE PREMISES 1. Introduction A Child Care Premises is used to provide a child care service within the meaning of the Child Care Services Act 2007, but does not include a Family
More informationStrategy Deployment Through Collaborative Planning. Linking the Strategy to Practical Activity
Strategy Deployment Through Collaborative Planning Linking the Strategy to Practical Activity Establish the Strategic Goal. After the Collaborative Planning activity Collaborative Planning iterative and
More informationConsiderate Constructors Scheme Site Manager s Guide
Considerate Constructors Scheme Site Manager s Guide Started in 1997, the Considerate Constructors Scheme was set up by the UK construction industry to improve its image. The Scheme is a non-profit-making,
More informationWork Type Definition and Submittal Requirements Work Type: Construction Contract Administration & Management
The first section, Work Type Definition, provides a detailed explanation of the work type. The second section, Work Type Submittal Requirements, identifies the requirements a firm must meet to become pre-qualified
More informationConsiderate Constructors Scheme Site Manager s Guide
J5478 Site manager guide aw_layout 1 04/10/2013 09:03 Page 1 Considerate Constructors Scheme Site Manager s Guide Started in 1997, the Considerate Constructors Scheme was set up by the UK construction
More informationSite Induction Presentation
ABC Contracting Site Induction Presentation This presentation provides a mock site induction and serves to help those people in the process of preparing and delivering site inductions It is essential that
More informationCirque du Soleil 2015
The Adelaide City Council invites engagement from the community about Cirque du Soleil 2015 Project Summary The Adelaide City Council has received an application from Cirque du Soleil for the use of The
More informationNZDF Temporary Military Training Activities. Palmerston North City Council
NZDF Temporary Military Training Activities for Palmerston North City Council File No. N1447TMT Version 22 nd June 2014 Nigel Lloyd Director of Acoustic Services E-mail: nigel@acousafe.co.nz 98 NZDF Temporary
More informationMONITORING PEDESTRIAN TRAFFIC CONTRACT TERM
COUNCIL REPORT MONITORING PEDESTRIAN TRAFFIC CONTRACT TERM Agenda Item 5.8 24 April 2007 Committee Finance and Governance Presenter Cr Shanahan Purpose 1. To seek approval to enter into a three year contract
More informationData Centres A complete solution to noise control and acoustic packages
Data Centres A complete solution to noise control and acoustic packages Introduction World class noise control. Expertise you can trust. IAC Acoustics is world-renowned for providing cost effective solutions
More informationSITE MANAGEMENT PLAN 2013
1 SITE MANAGEMENT PLAN 2013 GROUNDS OF THE ROYAL HOSPITAL CHELSEA, LONDON SW3 RHS CHELSEA FLOWER SHOW January, 2013 2 1. RHS CHELSEA FLOWER SHOW: PROJECT & KEY FACTS Overview The RHS Chelsea Flower Show
More informationLocal Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations
Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations Cambridge City Council - East Cambridgeshire District Council - Fenland District Council, Huntingdonshire
More informationHealth & Safety Policy For Locations Hosting Film Production Companies
Health & Safety Policy For Locations Hosting Film Production Companies Throughout this document, the location will be referred to as The Venue and the film production company as The Contractor. The following
More informationConstruction Noise Management Guideline for Major Transport Infrastructure Projects
th Proceedings of 20 International Congress on Acoustics, ICA 2010 23-27 August 2010, Sydney, Australia Construction Noise Management Guideline for Major Transport Infrastructure Projects Cedric Roberts,
More informationOUTLINE TENDER STAGE METHOD STATEMENT Removal of Asbestos Cement Roof & demolition of Building At Highbury Roundhouse. Ronald Road. London.
OUTLINE TENDER STAGE METHOD STATEMENT Removal of Asbestos Cement Roof & demolition of Building At Highbury Roundhouse. Ronald Road. London. N5 1XB Document Control Revision No. Date Approved Signature
More informationTRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS. LEC (Company Audit) Guidance Notes
TRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS LEC (Company Audit) Guidance Notes Glossary of Terms Transport for London (TfL) London Low Emission
More informationTRANSPORT ASSESSMENT GUIDANCE
TRANSPORT ASSESSMENT GUIDANCE Contents 1 INTRODUCTION...1 Purpose of the Guidance...1 Policy Context...1 Who Should Read This Document?...2 Structure of Guidance...3 2 ASSESSMENT PRINCIPLES AND PROCESS...4
More information********* Shorter notice periods will be considered, however this will be at the discretion of the University.
Filming Guidelines The University of Strathclyde welcomes production companies and filmmakers to use its estate as locations. From the beauty of Ross Priory on the shores of Loch Lomond to the city centre
More information1.1 The application property is an extended two-storey semi-detached house fronting Bedale Road. The side garden adjoins a link road to Wydale Road.
COMMITTEE REPORT Date: 13 October 2011 Ward: Osbaldwick Team: Major and Parish: Osbaldwick Parish Commercial Team Council Reference: 11/02264/FUL Application at: 27 Bedale Avenue Osbaldwick York YO10 3NG
More informationBSH Exhibition Sample Risk Assessment for exhibitors / contractors
BSH Exhibition Sample Risk Assessment for exhibitors / BSH Conferences Ltd have produced this risk assessment for its exhibitors to use as a template if they have not undertaken risk assessment before.
More informationJOB DESCRIPTION. 5. ORGANISATION CHART: Reports directly to the Maintenance Team Leader
JOB DESCRIPTION 1. JOB TITLE: Multi Skilled Maintenance Technician (Plumbing) 2. HMRS REFERENCE NUMBER: HR14109 3. ROLE CODE: MSMTEST 4. DEPARTMENT: Maintenance (Chester Campus), Facilities 5. ORGANISATION
More informationWEST OF WATERLOOVILLE FORUM. 10 April 2006. Councillors: Winchester City Council. Councillor Clohosey (Standing Deputy for Councillor Chamberlain)
1 WEST OF WATERLOOVILLE FORUM 10 April 2006 Attendance: Chamberlain Cooper Hiscock (P) Deputy Members: Councillors: Winchester City Council Collin (Chairman) (P) Rees Stallard (P) Councillor Clohosey (Standing
More informationTHE ROYAL BOROUGH OF KENSINGTON AND CHELSEA PLANNING APPLICATIONS COMMITTEE 16/06/2015
THE ROYAL BOROUGH OF KENSINGTON AND CHELSEA PLANNING APPLICATIONS COMMITTEE 16/06/2015 REPORT BY THE EXECUTIVE DIRECTOR, PLANNING AND BOROUGH DEVELOPMENT Application: /PP/15/02000 Agenda Item: N34 Address:
More informationFramework Servicing Management Plan
Framework Servicing Management Plan 66-74 Notting Hill Gate Stranton Properties Ltd September 2014 DOCUMENT CONTROL Project Centre has prepared this report in accordance with the instructions from Stranton
More informationHow To Build A Luxury Apartment Complex In London
Post Tensioning Awards 2009 Project Summary Type of structure Location Architects Structural Engineer Residential with leisure suites including Swimming pool, Cinema, Virtual Golf, Wine Cellars, and Parking
More informationHealth and safety policy
1. General statement of intent The Company recognises and accepts its responsibilities as an employer to ensure, so far as is reasonably practicable, the health, safety and welfare of its employees and
More informationConstruction Traffic Management Plan
Introduction This (CTMP) has been prepared in order to discharge Condition 20 of planning permission ref 07/02879/EFUL for the enabling site works associated with the wider Bath Western Riverside development.
More informationCompliance Noise Monitoring
Monitoring Byron Centre The Manse Road Myocum HEALTH SCIENCE ENVIROMENTAL EDUCATION ENVIRONMENTAL AUDITOR Monitoring Byron Centre The Manse Road Myocum Prepared for: Byron Shire Council Version 1.0 Date:
More informationConstruction Traffic Management Plan
Construction Traffic Management Plan Proposed Additional Accommodation for SWDPLS Shinners Bridge Dartington Produced for and on behalf of Built Environments Team Devon County Council NPS South West Ltd
More informationCONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL
CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL This manual applies to all development projects within Pitkin County. A Construction Management Plan (CMP) shall be submitted for all projects in Pitkin
More informationConstruction Logistics Handbook LOGISTICS
Construction Logistics Handbook LOGISTICS August 2015 Contents Section 1 Introduction Section 2 Site Access Section 3 Supply Chain Management Tools Section 4 Standards and Tools Section 5 Site Specific
More informationMajor Improvement Schemes in Basingstoke
Major Improvement Schemes in Basingstoke 1. Welcome Welcome to this exhibition, which provides information about the planned highway improvements being delivered in Basingstoke from 2015 2018. A30 Winchester
More informationManchester City Council Item 6 Planning and Highways Committee 8 May 2014
Application Number 104843/FO/2014/N1 Date of Appln 28th Feb 2014 Committee Date 8th May 2014 Ward Moston Ward Proposal Location Applicant Agent Change of use of ground floor to a hot food takeaway (Fish
More informationScaffold Standard (Standard to Managing and Appointing Scaffolding Contractors on University College London (UCL) Projects) Management Standard
Scaffold Standard (Standard to Managing and Appointing Scaffolding Contractors on University College London (UCL) Projects) Management Standard UNIVERSITY COLLEGE LONDON Engineering, Maintenance & Infrastructure
More informationCONSTRUCTION SEQUENCE & PROGRAMME
CONSTRUCTION SEQUENCE & PROGRAMME 2 CONTENTS 1.0 Introduction 7 2.0 Key activities 8 2.1 Airport related activities 2.2 Construction of new roads and accesses 2.3 Earthworks zone a 2.4 Earthworks zone
More informationLT McGuinness Site 10 Development, Wellington Waterfront. Construction Traffic Management Plan. 7 October 2014
LT McGuinness Site 10 Development, Wellington Waterfront Construction Traffic Management Plan 7 October 2014 TDG Ref: 12950 141007 ltm ctmp final report.docx LT McGuinness Site 10 Development, Wellington
More informationREPORT FOR: Traffic and Road Safety Advisory Panel
REPORT FOR: Traffic and Road Safety Advisory Panel Date of Meeting: 3 October 2012 Subject: INFORMATION REPORT - NETWORK MANAGEMENT DUTY 2011/12 Responsible Officer: John Edwards - Interim Corporate Director,
More informationContractor Performance Report Scoring Guide
Report Main Roads Western Australia Table of Contents CONTRACTOR PERFORMANCE REPORT SCORING GUIDE... 3 1. APPLICATION... 3 2. REPORTING... 3 2.1 Objectives... 3 2.2 Frequency... 3 2.3 Responsibility...
More information13.4 REPORT TITLE: TRANSPORT MASTER PLAN PROPOSED PROCESS DATE OF MEETING: 15 DECEMBER 2008 TECHNICAL SERVICES INFRASTRUCTURE AND PROJECTS
13.4 REPORT TITLE: TRANSPORT MASTER PLAN PROPOSED PROCESS DATE OF MEETING: 15 DECEMBER 2008 AUTHOR: AUTHOR S TITLE: REPRESENTORS: ATIS BERZINS MANAGER ENGINEERING AND TECHNICAL SERVICES N/A FILE NUMBER:
More informationSOUND INSULATION FOR AIR CONDITIONERS AND OTHER EXTERNAL MECHANICAL PLANT. Installing and Maintaining Air Conditioning Units
SOUND INSULATION FOR AIR CONDITIONERS AND OTHER EXTERNAL MECHANICAL PLANT Excessive noise from the operation of machines and external mechanical plant can disturb neighbours, disrupt sleep, interfere with
More informationHEALTH AND SAFETY POLICY LEWIS & RABY ENGINEERS LTD
HEALTH AND SAFETY POLICY LEWIS & RABY ENGINEERS LTD Birchall Road Knowsley Industrial Estate Liverpool L33 7TG TABLE OF CONTENTS STATEMENT OF SAFETY POLICY... 3 STATEMENT OF INTENT... 4 HEALTH & SAFETY
More informationWork Breakdown Structure Element Dictionary Construction
Initiation CON 5.1 Initiation encompasses deliverables associated with the development, implementation and control of the project s schedule, budget and scope, including the solicitation for a contractor
More informationWelcome. Purpose of the exhibition
Welcome Welcome to our exhibition, setting out plans for a redevelopment of Ten Broadway. It is currently the headquarters of the Metropolitan Police, which has made a decision to rationalise and relocate
More informationThank you for coming today
Bessant Drive, Kew Welcome Thank you for coming today Today s event is about the construction delivery for our forthcoming development of high-quality homes and GP surgery off Bessant Drive, Kew. This
More informationDavid Watkins RIBA Part 3 Course 2014. Cost Control and Management
David Watkins RIBA Part 3 Course 2014 Cost Cost Management Control and and Management_dhw_2014 Control_dhw_2014 For which of you, desiring to put up a tower, For which does of not you, first desiring give
More informationJOB DESCRIPTION. 5. ORGANISATION CHART: Reports to the Institute of Medicine Administrator. Institute of Medicine Directors
JOB DESCRIPTION 1. JOB TITLE: Administrative Assistant 2. HRMS REFERENCE NUMBER: HR14132 3. ROLE CODE: FINADMIN01 4. DEPARTMENT: Institute of Medicine (IoM) 5. ORGANISATION CHART: Reports to the Institute
More informationContractors and Suppliers Code of Conduct. June 2013
Contractors and Suppliers Code of Conduct June 2013 Owner: Facilities, Maintenance and Property Manager Page 1 of 8 Table of Contents 1. Purpose of this Document... 3 1.1. Non Compliance with Code... 3
More informationArticle IV. Noise, Noise Pollution and Vibration
Article IV. Noise, Noise Pollution and Vibration Sec. 12-121. Definitions. Sec. 12-122. Source requirements. Sec. 12-123. Requirements for air circulation devices. Sec. 12-124. Hourly restrictions on certain
More informationVacancy information pack
Vacancy information pack Thank you for your interest in the role of Regional Fundraising Officer (London). Please email your CV along with a covering letter to Stef Parsons at recruitment@alzheimersresearchuk.org
More informationAbu Dhabi EHSMS Regulatory Framework (AD EHSMS RF)
Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF) EHS Regulatory Instrument Code of Practice EHS RI CoP 44.0 Traffic Management and Logistics Version 2.0 February 2012 ACKNOWLEDGEMENTS With gratitude
More informationSenior Project Manager
Senior Project Manager Applications are invited for the position of a Senior Project Manager for UCL Consultants Ltd. The following application information is enclosed: 1. Information on UCL Consultants
More informationRotherham Metropolitan Borough Council. Appendix A. Street Lighting. Sustainable Energy Action Plan
Rotherham Metropolitan Borough Council Appendix A Street Lighting Sustainable Energy Action Plan October 2010 Streetpride Service Summary Modern street lighting provides many benefits to the community
More informationWHS Contractor Management Procedure
Wudinna District Council 1. Overview Wudinna District Council as part of its commitment under its Policy recognises its obligation to: Ensure, so far as is reasonably practicable, the health and safety
More informationREPORT 4 FOR DECISION. This report will be considered in public
REPORT 4 Subject: Safety Readiness for the Summer 2013 Events Programme Agenda item: Public Item 7 Report No: 4 Meeting date: 28 May 2013 Report to: Board Report of: Mark Camley, Interim Executive Director
More informationAppointment of a Practice Manager. Firs House Surgery and Telegraph Street Surgery. Further information for applicants
Appointment of a Practice Manager Firs House Surgery and Telegraph Street Surgery FIRS HOUSE SURGERY Station Road, Histon Cambridge CB24 9NP Tel: (01223) 234286 TELEGRAPH STREET SURGERY 42 Telegraph Street,
More information