Jointless Post Tensioned Slab on Grade. The Future for Industrial Concrete Flooring?

Size: px
Start display at page:

Download "Jointless Post Tensioned Slab on Grade. The Future for Industrial Concrete Flooring?"

Transcription

1 Jointless Post Tensioned Slab on Grade The Future for Industrial Concrete Flooring?

2 Floor Slab Function (ref N.I.M. Williamson, Concrete floors for warehousing and distribution facilities: fit for purpose?. ICE 1996) To distribute, without deformation or cracking, the loads applied to it to the weaker sub-grade below, and to provide a suitable wearing surface upon which the operations in the facility may be carried out efficiently and safely.

3 Concrete The Shop Floor for Industry... the floor is the most important part of the building. All activities occur on or near the floor and the remainder of the structure is simply a means of protecting the floor and workforce from the environment. B.C. Crisp B.E., M.I.P.E.N.Z., M.I.E. (Aust).

4 The demands on floors have increased over the last few years and in any event floors have not performed too well. The C&CA in Australia reports there are more complaints about floor slabs than all other concrete put together. It would seem we need to do the job better.

5 The floor is becoming increasingly important as we use higher racking and faster forklifts. We want our floors to be flatter and last longer. We can no longer accept opening cracks, failed joints or potholes.

6 A USA study of 200 Large Industrial floors showed joints as the biggest cause for concern. This all adds up to the need to ensure that the floor is designed properly. Its not satisfactory just to use the same design as before.

7 What defines a Good Floor? Optimum Joint Detailing - Most floors fail at the joints

8 Flatness - Forklifts travel faster on flatter floors - improved productivity Hardness - resistance to abrasive wear Low Maintenance Costs and Few Repairs

9 Main Elements Of A Concrete Floor Levelling sand Slip Membrane Slab t 1 = Subbase t 2 = Imported Fill (if used) t 3 >t 1 +t 2 Subgrade

10 Uneven Ground Causes Restraint

11 Restrained shrinkage causes multi directional cracking of the floor, curling and rapid disintegration of structural integrity

12 A unreinforced floor is really a number of smaller floors joined together = JOINTS

13 Formed Construction Joints Sawed Contraction Joints

14 What Has Changed in the last 30 Years? Fast Moving Consumer Goods

15 Bigger Warehouses & Higher Racking

16 Efficient Distribution

17 Higher Stacking

18 Faster Forklifts

19 24 Hour Operations

20 Lets get the good stuff out FAST

21 Impact Point Aggregat e looses cont act and slab fault s when joint opens Joints open due to Drying Shrinkage and Curling Sawed Cont ract ion Joint Sect ion

22

23 A facility managers worst problem FAILED JOINTS!!!!!

24 Industrial Concrete Floors Following are examples of jointed floors that were easy to construct and would NEVER BE A PROBLEM

25 Rocking Slabs

26 Curled Edges

27 Joints cut too late

28 Joints too far apart

29 Inadequate Sub - base

30 Overloading

31 Curling of Joints

32 Why we need to reduce Joints

33 Damaged Wheels = $$$$$$$$$

34 Load Tippage

35 Forklift Maintenance

36 Floor Repairs

37 joints unfilled 6-12mm wide joints unfilled over 12mm wide cracks over 6mm wide joints where slabs rock joints repaired but failed joints where filler became brittle cracks with spalled edges joints filler too soft to support cracks with islands joints opening 2-5mm joints with one side higher surface worn away joints with a metal screed key 54% 47% 45% 44% 44% 42% 39% 34% 32% 28% 27% 23% 16% Results from the survey of over 200 USA Distribution facilities Joints are a big problem.

38 Joint Requirements Increasing Loads have increased Wheels have got smaller Wheels are harder Modern floors need to eliminate JOINTS

39 Jointless Floors the way to go Traditional 2000m 2, 860m saw cut joints PT JOINTLESS 2000m 2, NO saw cut joints

40 Hidden Cost wheel replacement operator fatigue and moral increased housekeeping load tipping and breakage reduced building value

41 OUR INDUSTRY MISSION... To provide the owner with a world class surface facility offering long life and low maintenance....this is not possible using unreinforced jointed concrete

42 Our Team was approached by BMW South Africa to design, supply and construct a 9,000m 2 Jointless Surface Bed for their new parts Distribution Facility.

43 OUR INDUSTRY MISSION BMW had identified Joint Failure in many of their existing floors as a problem for their handling operations and consequently wanted a Jointless Floor.

44 OUR INDUSTRY MISSION Criteria that had to be met : No Joints No Cracking CAT 2 Floor Tolerances No Curling Wire Guidance

45 OUR INDUSTRY MISSION Could not use unreinforced concrete option as this would exhibit saw cut joints, construction joints, shrinakge opening of joints, curling of joints and would need to be in excess of 200mm thick.

46 WHY WE CHOSE PT : No Joints No Curling It was the greenest option using the least concrete It is an engineered solution It is a robust, durable system proven worldwide It had best capital cost and life cycle values

47 PT GROUND SLABS Francois Le Roux Nyeleti Consulting

48 What are Post-Tensioned industrial slabs? Slabs on ground reinforced with Post-Tensioned tendons consisting of steel cables Jacks tension cables at slab edges Permanent 2-way compression placed on slab

49 Two Main Functions of the PT Counteract initial shrinkage cracking Pre-Compress concrete to counter cracking due to: Ongoing Shrinkage Flexural Tensile Stresses due to external loads Temperature gradients in slab

50 BASICS Bonded Flat Slab system used Tendons comprise of bare steel cables (Strands) inside galvanised steel duct 12.9 and 15.7 dia. strand Tendons un-profiled in one layer Placed centrally in slab Equal or close to equal tendons in both directions

51 Advantages of post tensioning Eliminate JOINTS PT Compression force counter shrinkage forces that cause cracking Eliminate need for joints Extensive joint-free areas ~ 2500 sq.m Savings on joint cost, repair costs & downtime for facility

52 Advantages of post tensioning Increased Strength and load capacity Thinner slabs achieve same strength ~ 20 to 30% saving on slab thickness Overcomes poor ground conditions easier Less sub-grade preparation required i.e. It usually requires less supporting layer-works Therefore, savings on capital cost usually achieved

53 Advantages of post tensioning Increased robustness If cracked by overload, crack held closed by permanent compression force in slab Rapid deterioration & breakup avoided Ongoing repairs minimised

54 Typical applications Distribution Centres & Warehouses

55 Typical applications Refrigerated stores

56 Typical applications Bulk solid storage

57 Typical applications Heavy equipment maintenance facilities

58 Typical applications Freight forwarding centres

59 Typical applications Container-handling facilities

60 Typical applications Base Slabs for Water Retaining Structures

61 applications Typical applications Raft Slabs

62 Materials

63 High Tensile Strand 15.7 or 12.9mm dia, 7 wire cable Modulus c. 195 kn/mm² Approx 3 tonne coils

64 Duct (Void Former) Galvanised metal 70 or 90mm wide x 20mm high. 3 Strand also available Joints Tape Sealed

65 ANCHORAGES Grout Tube Anchor Block Ducting Steel Strand (Cable) Anchor Casting Corrosion-protective Grout LIVE END (For Stressing/Tensioning)

66 ANCHORAGES Corrosion-protective Grout Grout Tube Ducting Steel Strand (Cable) Bulbed Strand Ends DEAD END Protruding cables cast into concrete to anchor cables at the one end to allow tensioning at the other

67 Analysis and Design

68 Analysis stage Analysis & Design of PT ground slabs is carried out in a rigorous manner based on engineering principles Finite Element modelling of slab & subgrade

69 Analysis stage ALL Service loads considered Racking, vehicles, materials, containers Edge & internal load cases Environmental influences considered Temperature Subgrade movements Creep & shrinkage Base Friction etc.

70 Analysis stage Stress ratios for repeated loads Vehicles ~ unlimited Racking ~ daily-weekly cycle (full bay) Containers ~ daily cycle (full stack) Materials ~ weekly cycle

71 Design stage Final design expectations Thickness ~ 70 to 80% of equivalent RC slab Pre-Stress ~ 1-2 Mpa (long-term)

72 Construction

73 Construction Key to success is attention to detail

74 Installation stage Key items Subgrade preparation is key i.e. Compaction & levels Isolate Columns etc 100% sand/poly cover Dowel sleeving

75 Installation stage External Slabs Prior to pour

76 Concrete Placement Key items : Proper planning Correct equipment Adequate Manpower

77 Post-Concreting Key items : Early formwork stripping for stressing vital Unlock blocking and joint systems Initial stress to control initial shrinkage cracking - 9Mpa concrete strength required Final stress - 25Mpa concrete strength required

78 Stressing Hydraulic Pump and Stressing jack to tension strands/cables Certificate of Calibration essential for each Jack & Gauge

79 Grouting

80 Post-Grouting

81 Post-concreting stage The finished Product (Coca Cola Melbourne)

82 CONCLUSION Sophisticated design process followed which, models all significant forces & actions on & in slab It is a properly ENGINEERED slab Joint free areas ~ 2500 sq.m Greatly reduces joint const n costs Greatly reduces joint maint costs & downtime Potential savings in capital cost

83 CONCLUSION Durable & robust Proven & reliable technology SSL have designed and installed in excess of 1,4mill SQ-m of PT SOG between 1994 and 2009 SSL have completed approx. 500,000 Sq-m of external heavy duty PT SOG Adopted widely for major facilities

84 BONDED POST TENSIONED SOLUTION AT BMW Case study

85 Client: Consultant: Contractor: TEAM BMW SA Nyeleti Consulting (NC) Concrete laser flooring (CLF) PT Supplier and design assistance: Structural Systems Africa (SSA)

86 BACKGROUND Clients requirements Rehabilitated facility floor Full production during rehabilitation CAT 2 regularity suitable for VNA Phased construction Lower life cycle cost

87 BACKGROUND Analysis Approach Load transfer testing Floor visual survey

88 BACKGROUND Load transfer testing LWD testing done 143 tests Poor transfer 72%

89 BACKGROUND Visual survey High percentage floor defects Shattered slabs, cracking, joint failure etc. Poor surface regularity

90 Vertical floor level (m) BACKGROUND Long Section of Row K-J mm level difference Row K-J Row K-J Distance (m)

91 Height in m from datum BACKGROUND Transverse regularity of aisle BB Meters from datum line Joint 1 Between J1 and J2 Max limit Min Limit Joint 2 Joint 4 Betwee J4 and J5 J 5

92 OPTIONS OFFERED Conventional Rehabilitation Bonded post tension slab (150mm thick) on slip membrane Continuously reinforced slab (175mm thick) on slip membrane 200mm SFRC on slip membrane

93 Other Problems 1. Building constraints a. Saw tooth roof with 4.5m height beams at low end b. Cable trays at 4.5m height c. CANNOT OPEN A BOOM PUMP d. Columns at 10m grid (MOVEMENT RESTRICTIONS) e. 4 Phases with 8 weeks wait period between pours

94 WHY PT Eliminating all control joints Max floor 150mm thick Jointless pour up to 5000m2 No transverse joints Eliminate slab curl

95 WAREHOUSE LAYOUT

96 Warehouse layout 4446m² 2556m²

97 POST TENSIONING LAYOUT

98 POST TENSIONING LAYOUT 1. Edge reinforcement

99

100

101

102

103 POST TENSIONING LAYOUT

104 POST TENSIONING LAYOUT 1.Movement joints a.movement was estimated as 0.5mm / m to free edge. b.main movement joint estimated as 18mm c.measured on site as 12mm to date (after 60days)

105

106

107 Tensioning direction

108 Tensioning direction

109 Construction sequence 1. Installation of a. Polyterm Sub base b. Formwork and slip sheets c. PT system d. Concrete and finishing

110 CONSTRUCTION SEQUENCE 1. INSTALLATION OF LEVELLING COURSE

111 CONSTRUCTION SEQUENCE 2. INSTALLATION OF SLIP SHEETS/FORM WORK

112 3. POUR OF CONCRETE CONSTRUCTION SEQUENCE

113 CONSTRUCTION SEQUENCE

114 CONSTRUCTION SEQUENCE 4. Post Tensioning

115 CONSTRUCTION SEQUENCE Post tensioning Initial tensioning at 9MPa Final at 25MPa

116 CONSTRUCTION SEQUENCE WHAT IF THINGS GO WRONG?

117 Construction sequence Finish product.

118 End

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS FUTURE SLAB PENETRATIONS and DEMOLITION of POST-TENSIONED FLOORS 1.0 INTRODUCTION Post-tensioned floor slabs in Australia and South East Asia are now universally regarded as the most cost effective form

More information

Chapter 2 Basis of design and materials

Chapter 2 Basis of design and materials Chapter 2 Basis of design and materials 2.1 Structural action It is necessary to start a design by deciding on the type and layout of structure to be used. Tentative sizes must be allocated to each structural

More information

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION General 7 www.meadowburke.com 877-518-7665 MB1109 CONCRETE FLOOR SLAB AND CASTING BED CONSTRUCTION Quality Construction Begins at Ground Level Everything

More information

9.3 Two-way Slabs (Part I)

9.3 Two-way Slabs (Part I) 9.3 Two-way Slabs (Part I) This section covers the following topics. Introduction Analysis and Design Features in Modeling and Analysis Distribution of Moments to Strips 9.3.1 Introduction The slabs are

More information

1.2 Advantages and Types of Prestressing

1.2 Advantages and Types of Prestressing 1.2 Advantages and Types of Prestressing This section covers the following topics. Definitions Advantages of Prestressing Limitations of Prestressing Types of Prestressing 1.2.1 Definitions The terms commonly

More information

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE By H P Gupta & D K Gupta DIFFERENT TYPES OF DAMAGES 1.Minor cracks 0.5 to 5 mm wide in load or non-load bearing walls 2.Major

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI 318-14

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI 318-14 Draft Table of Contents Building Code Requirements for Structural Concrete and Commentary ACI 318-14 BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE (ACI 318 14) Chapter 1 General 1.1 Scope of ACI 318

More information

Chapter 5 Bridge Deck Slabs. Bridge Engineering 1

Chapter 5 Bridge Deck Slabs. Bridge Engineering 1 Chapter 5 Bridge Deck Slabs Bridge Engineering 1 Basic types of bridge decks In-situ reinforced concrete deck- (most common type) Pre-cast concrete deck (minimize the use of local labor) Open steel grid

More information

METHOD OF STATEMENT FOR STATIC LOADING TEST

METHOD OF STATEMENT FOR STATIC LOADING TEST Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents

More information

How To Build A Luxury Apartment Complex In London

How To Build A Luxury Apartment Complex In London Post Tensioning Awards 2009 Project Summary Type of structure Location Architects Structural Engineer Residential with leisure suites including Swimming pool, Cinema, Virtual Golf, Wine Cellars, and Parking

More information

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE A.Rito Proponte, Lda, Lisbon, Portugal J. Appleton A2P Consult, Lda, Lisbon, Portugal ABSTRACT: The Figueira da Foz Bridge includes a 405 m long cable stayed

More information

DESIGN OF SLABS. Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia

DESIGN OF SLABS. Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia DESIGN OF SLABS Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia Introduction Types of Slab Slabs are plate elements

More information

The Value of a Warehouse Floor Raising Flooring Standards around the Globe

The Value of a Warehouse Floor Raising Flooring Standards around the Globe The Value of a Warehouse Floor Raising Flooring Standards around the Globe An IKEA warehouse floor in Dortmund, Germany placed with the Somero SXP Laser Screed Referencing Technical Report No. 34, Third

More information

How to build a Pizza Oven in 4 days

How to build a Pizza Oven in 4 days How to build a Pizza Oven in 4 days Preparation day (slab) 1. Foundation 1500 deep x 1300 wide x 75mm deep Required 20 bags cement pre mix. If you already have a concrete base, you save this prep day DAY

More information

Hardened Concrete. Lecture No. 14

Hardened Concrete. Lecture No. 14 Hardened Concrete Lecture No. 14 Strength of Concrete Strength of concrete is commonly considered its most valuable property, although in many practical cases, other characteristics, such as durability

More information

SPECIFICATIONS. INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP)

SPECIFICATIONS. INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP) SPECIFICATIONS INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP) Part 1 General 1.1 CONFORMITY Conforms to the requirements of the general conditions of the contract.

More information

BRIDGE REHABILITATION TECHNIQUES

BRIDGE REHABILITATION TECHNIQUES BRIDGE REHABILITATION TECHNIQUES Yogesh Chhabra, General Manager, The D S Brown Company, 57 Pioneer Road, Singapore 628508 Web www.dsbrown.com E-Mail ychhabra@dsbrown.com.sg Ph. +6598444104, +6565588111

More information

INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE.

INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE. INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE. M.Sc. Gediminas Viršilas Head of Bridge Division, Lithuanian Road Administration Working group 2 of PIARC Technical Committee

More information

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab, DESIGN OF SLABS Dr. G. P. Chandradhara Professor of Civil Engineering S. J. College of Engineering Mysore 1. GENERAL A slab is a flat two dimensional planar structural element having thickness small compared

More information

The following sketches show the plans of the two cases of one-way slabs. The spanning direction in each case is shown by the double headed arrow.

The following sketches show the plans of the two cases of one-way slabs. The spanning direction in each case is shown by the double headed arrow. 9.2 One-way Slabs This section covers the following topics. Introduction Analysis and Design 9.2.1 Introduction Slabs are an important structural component where prestressing is applied. With increase

More information

September 1, 2003 CONCRETE MANUAL 5-694.900 CONCRETE PAVEMENT REHABILITATION 5-694.900

September 1, 2003 CONCRETE MANUAL 5-694.900 CONCRETE PAVEMENT REHABILITATION 5-694.900 September 1, 2003 CONCRETE MANUAL 5-694.900 5-694.901 GENERAL CONCRETE PAVEMENT REHABILITATION 5-694.900 Concrete Pavement Rehabilitation is an extremely valuable tool of the Minnesota Department of Transportation

More information

Guidelines for the Design of Post-Tensioned Floors

Guidelines for the Design of Post-Tensioned Floors Guidelines for the Design of Post-Tensioned Floors BY BIJAN O. AALAMI AND JENNIFER D. JURGENS his article presents a set of guidelines intended to T assist designers in routine post-tensioning design,

More information

INTRODUCTION TO CONCRETE PAVEMENTS

INTRODUCTION TO CONCRETE PAVEMENTS INTRODUCTION TO CONCRETE PAVEMENTS Abstract Arvo Tinni Tinni Management Consulting February 2013 This paper describes the experiences and design methodologies for concrete pavements in Australia. It is

More information

Technical Notes 3B - Brick Masonry Section Properties May 1993

Technical Notes 3B - Brick Masonry Section Properties May 1993 Technical Notes 3B - Brick Masonry Section Properties May 1993 Abstract: This Technical Notes is a design aid for the Building Code Requirements for Masonry Structures (ACI 530/ASCE 5/TMS 402-92) and Specifications

More information

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General

More information

Design and Construction of Cantilevered Reinforced Concrete Structures

Design and Construction of Cantilevered Reinforced Concrete Structures Buildings Department Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-68 Design and Construction of Cantilevered Reinforced Concrete Structures

More information

HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS

HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS BSW HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS BSW is a fully reinforced Pre-Applied system membrane designed for horizontal and vertical external blind-side

More information

SECTION 3 DESIGN OF POST TENSIONED COMPONENTS FOR FLEXURE

SECTION 3 DESIGN OF POST TENSIONED COMPONENTS FOR FLEXURE SECTION 3 DESIGN OF POST TENSIONED COMPONENTS FOR FLEXURE DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE LEAD AUTHOR: TREY HAMILTON, UNIVERSITY OF FLORIDA NOTE: MOMENT DIAGRAM CONVENTION In PT design,

More information

Prestressed Storage Tanks

Prestressed Storage Tanks Prestressed Storage Tanks Mike Harper Regional Manager mike.harper@dntanks.com / 714 767 1313 Kevin Peacock Regional Manager kevin.peacock@dntanks.com / 949 698 2740 DN Tanks overview Construction Procedures

More information

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements University of Pittsburgh Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements Authors: J. M Vandenbossche S. Sachs August 2013 1. Introduction Bonded concrete overlays of asphalt

More information

University of Missouri Hospitals and Clinics. Structural Repair and Protection of Post-tensioned Parking Garage

University of Missouri Hospitals and Clinics. Structural Repair and Protection of Post-tensioned Parking Garage University of Missouri Hospitals and Clinics Structural Repair and Protection of Post-tensioned Parking Garage 1 University of Missouri Project The University of Missouri Health Care Patient and Visitor

More information

COMPETENCY ANALYSIS PROFILE. Rodworker 452A. (All unshaded skill sets must be demonstrated/ completed) Lift equipment and materials

COMPETENCY ANALYSIS PROFILE. Rodworker 452A. (All unshaded skill sets must be demonstrated/ completed) Lift equipment and materials COMPETENCY ANALYSIS PROFILE Rodworker 452A (All unshaded skill sets must be demonstrated/ completed) PROTECT SELF AND OTHERS Wear personal protective (PPE) Lift and Apply housekeeping rules Interpret warning

More information

PRESTRESSED CONCRETE. Introduction REINFORCED CONCRETE CHAPTER SPRING 2004. Reinforced Concrete Design. Fifth Edition. By Dr. Ibrahim.

PRESTRESSED CONCRETE. Introduction REINFORCED CONCRETE CHAPTER SPRING 2004. Reinforced Concrete Design. Fifth Edition. By Dr. Ibrahim. CHAPTER REINFORCED CONCRETE Reinforced Concrete Design A Fundamental Approach - Fifth Edition Fifth Edition PRESTRESSED CONCRETE A. J. Clark School of Engineering Department of Civil and Environmental

More information

If stepping is required, step at 180mm as seen in this picture.

If stepping is required, step at 180mm as seen in this picture. Cast Foundations to standard building regulations requirements. Foundations must be cast completely level, 600mm wide by 230mm deep for single storey, double storey is not allowed by NHBRC. If stepping

More information

8 EXTRA LIGHT GRC SANDWICH ELEMENTS FOR ROOFING IN INDUSTRIAL BUILDINGS

8 EXTRA LIGHT GRC SANDWICH ELEMENTS FOR ROOFING IN INDUSTRIAL BUILDINGS 8 EXTRA LIGHT GRC SANDWICH ELEMENTS FOR ROOFING IN INDUSTRIAL BUILDINGS MARICA DELLA BELLA and DIEGO CIAN Precompressi Centro Nord S.p.A., Italy SUMMARY: Secondary roofing elements, complementary to the

More information

Resurfacing Concrete. Page 1 of 5

Resurfacing Concrete. Page 1 of 5 Resurfacing Concrete Materials List QUIKRETE Concrete Resurfacer (No. 1131) (see calculator on page 5 for quantity needed) QUIKRETE Concrete and Stucco Wash (No. 8601) QUIKRETE Concrete Sealer (No. 8800)

More information

SECTION 3 DESIGN OF POST- TENSIONED COMPONENTS FOR FLEXURE

SECTION 3 DESIGN OF POST- TENSIONED COMPONENTS FOR FLEXURE SECTION 3 DESIGN OF POST- TENSIONED COMPONENTS FOR FLEXURE DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE LEAD AUTHOR: TREY HAMILTON, UNIVERSITY OF FLORIDA NOTE: MOMENT DIAGRAM CONVENTION In PT design,

More information

Basics of Reinforced Concrete Design

Basics of Reinforced Concrete Design Basics of Reinforced Concrete Design Presented by: Ronald Thornton, P.E. Define several terms related to reinforced concrete design Learn the basic theory behind structural analysis and reinforced concrete

More information

Construction. 3-part thixotropic epoxy patching mortar. Product Description. Tests

Construction. 3-part thixotropic epoxy patching mortar. Product Description. Tests Product Data Sheet Edition 05/12/2014 Identification no: 020204030010000044 Sikadur -41 CF Rapid 3-part thixotropic epoxy patching mortar Construction Product Description Uses Characteristics / Advantages

More information

Hanson Building Products. precast basement solutions

Hanson Building Products. precast basement solutions Hanson Building Products precast basement solutions Hanson Building Products Basement Systems Add an extra dimension and combine the inherent flexible, structural and waterproof properties of concrete

More information

Analysis and Repair of an Earthquake-Damaged High-rise Building in Santiago, Chile

Analysis and Repair of an Earthquake-Damaged High-rise Building in Santiago, Chile Analysis and Repair of an Earthquake-Damaged High-rise Building in Santiago, Chile J. Sherstobitoff Ausenco Sandwell, Vancouver, Canada P. Cajiao AMEC, Vancouver, Canada P. Adebar University of British

More information

SikaProof A Technology

SikaProof A Technology SikaProof A Technology The fully bonded waterproofing system Keep your basements durably and securely watertight What is SikaProof A? How does it work? Where can it be used? What are the advantages of

More information

SECTION 5 ANALYSIS OF CONTINUOUS SPANS DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE LEAD AUTHOR: BRYAN ALLRED

SECTION 5 ANALYSIS OF CONTINUOUS SPANS DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE LEAD AUTHOR: BRYAN ALLRED SECTION 5 ANALYSIS OF CONTINUOUS SPANS DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE LEAD AUTHOR: BRYAN ALLRED NOTE: MOMENT DIAGRAM CONVENTION In PT design, it is preferable to draw moment diagrams

More information

Precast Concrete Parking Structures

Precast Concrete Parking Structures Precast Concrete Parking Structures Durability starts at the joints BY DAVID C. MONROE AND JOSEPH L. WHITE Parking structures comprise the largest market segment for the structural precast, prestressed

More information

Installation PowerPoint for Grasscrete Formers

Installation PowerPoint for Grasscrete Formers Installation PowerPoint for Grasscrete Formers 1 This document describes the two single-use tools utilized to create the Grasscrete product. The original Former is a vacuum formed light gauge plastic mold

More information

CURRENT PRACTICE SHEET

CURRENT PRACTICE SHEET CURRENT PRACTICE SHEET INTRODUCTION An expansion joint can be defined as a device to support the surfacing, or to provide a running surface, across the expansion gap, ie the area between adjacent spans

More information

SAFE HANDLING OF PRECAST CONCRETE PRODUCTS

SAFE HANDLING OF PRECAST CONCRETE PRODUCTS SAFE HANDLING OF PRECAST CONCRETE PRODUCTS Safety Handling of Precast Concrete Products The lifting of any precast product requires the use of special equipment and substantial planning and knowledge.

More information

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003) NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:

More information

Chapter. Restoration of Damaged Structures

Chapter. Restoration of Damaged Structures 5 Chapter Restoration of Damaged Structures Bringing back a damaged structure to its pre-earthquake state and original strength is called restoration. This is the first step of building rehabilitation.

More information

The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma

The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma Bart B. Barrett, B.S., P.E.1 Kerry S. Lee, M.B.A., P.E., M. ASCE2 Erik L. Nelson, Ph.D., P.E., M. ASCE3

More information

PROPERTIES AND MIX DESIGNATIONS 5-694.200

PROPERTIES AND MIX DESIGNATIONS 5-694.200 September 1, 2003 CONCRETE MANUAL 5-694.200 5-694.210 PROPERTIES OF CONCRETE PROPERTIES AND MIX DESIGNATIONS 5-694.200 Inspectors should familiarize themselves with the most important properties of concrete:

More information

Structural Foundation System

Structural Foundation System Structural Foundation System SLABTEK, a technological advancement in foundation designs for residential and lightweight commercial structures SlabTek is a patent allowed process for concrete foundations

More information

Saint Gobain Gyproc India Ltd. (Formerly India Gypsum Ltd.)

Saint Gobain Gyproc India Ltd. (Formerly India Gypsum Ltd.) Saint Gobain Gyproc India Ltd. (Formerly India Gypsum Ltd.) Gyproc Plasters The cracks in cement sand plaster are an inherent feature which cannot be completely prevented but can only be controlled and

More information

Chaudière Crossing Bridge Rehabilitation

Chaudière Crossing Bridge Rehabilitation Chaudière Crossing Bridge Rehabilitation Douglas K. Lowry P. Eng., Armtec Infrastructure Incorporated David Delicate, P.Eng. Public Works and Government Services Canada (Retired) Prepared for presentation

More information

REPAIR AND STRENGTHENING OF HISTORICAL CONCRETE BRIDGE OVER VENTA RIVER IN LATVIA

REPAIR AND STRENGTHENING OF HISTORICAL CONCRETE BRIDGE OVER VENTA RIVER IN LATVIA 1 REPAIR AND STRENGTHENING OF HISTORICAL CONCRETE BRIDGE OVER VENTA RIVER IN LATVIA Verners Straupe, M.sc.eng., Rudolfs Gruberts, dipl. eng. JS Celuprojekts, Murjanu St. 7a, Riga, LV 1024, Latvia e-mail:

More information

SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE

SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE Community Development Permit Services SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE PROJECT NAME PROJECT ADDRESS PERMIT NUMBER CITY RECEIVED STAMP AND INITIALS Instructions: BEFORE

More information

DESIGN OF PRESTRESSED BARRIER CABLE SYSTEMS

DESIGN OF PRESTRESSED BARRIER CABLE SYSTEMS 8601 North Black Canyon Highway Suite 103 Phoenix, AZ 8501 For Professionals Engaged in Post-Tensioning Design Issue 14 December 004 DESIGN OF PRESTRESSED BARRIER CABLE SYSTEMS by James D. Rogers 1 1.0

More information

Joint Rehabilitation. Driving Forces for Concrete Pavement Joint Repairs

Joint Rehabilitation. Driving Forces for Concrete Pavement Joint Repairs Long Life Concrete Pavement Joint Performance Joint Rehabilitation Gary Fick, Trinity Construction Management Services, Inc. Representing the National CP Tech Center Driving Forces for Concrete Pavement

More information

1.5 Concrete (Part I)

1.5 Concrete (Part I) 1.5 Concrete (Part I) This section covers the following topics. Constituents of Concrete Properties of Hardened Concrete (Part I) 1.5.1 Constituents of Concrete Introduction Concrete is a composite material

More information

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection

More information

Section 500 Rigid Pavement

Section 500 Rigid Pavement Table of Contents 1. Reinforced or Plain Cement Concrete Pavements, Reinforced or Plain Cement Concrete Pavement (RPS), and Protective Coating for Cement Concrete Pavement... 500-1 2. Pavement Relief Joint...

More information

The First Commandment for floor slabs:

The First Commandment for floor slabs: The First Commandment for floor slabs: P for the Practitioner Thou Shalt Not Curl Nor Crack...(hopefully) by Wayne W. Walker and Jerry A. Holland LL FLOOR SLABS CURL, except Aunder unusual conditions or

More information

Introduction. Eurocodes. Specification. Cost

Introduction. Eurocodes. Specification. Cost Introduction Eurocodes Specification Cost Structural Eurocodes BS EN 1990 (EC0): BS EN 1991 (EC1): Basis of structural design Actions on Structures BS EN 1992 (EC2): BS EN 1993 (EC3): BS EN 1994 (EC4):

More information

CONCRETE REPAIR GUIDELINES. Concrete repairs can be broken down into four basic types, plus special repairs and planing.

CONCRETE REPAIR GUIDELINES. Concrete repairs can be broken down into four basic types, plus special repairs and planing. CONCRETE REPAIR GUIDELINES Concrete repairs can be broken down into four basic types, plus special repairs and planing. Note: It is recommended that investigation into soundness of pavement be performed

More information

DESIGNING STRUCTURES IN EXPANSIVE CLAY

DESIGNING STRUCTURES IN EXPANSIVE CLAY DESIGNING STRUCTURES IN EXPANSIVE CLAY A GUIDE FOR A RCHITECTS AND E NGINEERS Table of Contents 1. Introduction Page 1 2. Common Foundation Systems Page 2 3. Drilled Piers Page 3 a. Skin Friction Piers

More information

The Concrete Life Cycle: Maintain to Sustain. Fred Goodwin BASF Construction Chemicals (EB-N) Beachwood OH

The Concrete Life Cycle: Maintain to Sustain. Fred Goodwin BASF Construction Chemicals (EB-N) Beachwood OH The Concrete Life Cycle: Maintain to Sustain Fred Goodwin BASF Construction Chemicals (EB-N) Beachwood OH What is Concrete? Concrete: Instant rock -just add water to make a hard wet sponge. A composite

More information

Dowel-Bar Retrofit Using Polyester Polymer Concrete

Dowel-Bar Retrofit Using Polyester Polymer Concrete PPETG May 3-4, 2011, Oklahoma City Dowel-Bar Retrofit Using Polyester Polymer Concrete Shakir Shatnawi, Ph.D., P.E. President, SHATEC ENGINEERING CONSULTANTS, LLC sshatnawi@sbcglobal.net 916-990-6488 2

More information

Welded Fabric. The CARES Guide to Reinforcing Steels Part 5. Installation of welded fabric on a major contract. 1.0 Introduction

Welded Fabric. The CARES Guide to Reinforcing Steels Part 5. Installation of welded fabric on a major contract. 1.0 Introduction Welded Fabric 1.0 Introduction Welded fabric, often referred to as mesh, is a machine welded grid arrangement of reinforcing bars or wires. It is covered by British Standard BS4483. This was revised in

More information

Connection Solutions

Connection Solutions Connection Solutions DESIGN BUILD SYSTEM Connection Solutions for Cold formed Steel Construction Complies with; AS/NZS 4600:2005 AISI S100:2007 AS/NZ 1397 ASTM A653 DESIGN & BUILD SYSTEM FRAMECAD Construction

More information

Guidelines for Durable Driveways, Carports Patios, Walks, Garage Floors

Guidelines for Durable Driveways, Carports Patios, Walks, Garage Floors Guidelines for Durable Driveways, Carports Patios, Walks, Garage Floors The Right Concrete Mix Placing and Finishing Joints Correctly Spaced Curing for Durability "Concrete durability is the ability to

More information

Investigation of Foundation Failure. Step 1 - Data Collection. Investigation Steps

Investigation of Foundation Failure. Step 1 - Data Collection. Investigation Steps Foundations on Expansive Clay Soil Part 3 - Investigation of Failed Foundations Presented by: Eric Green, P.E. Structural Engineer Slide 1 Copyright Eric Green 2005 Investigation of Foundation Failure

More information

SIKA AT WORK THE KAENG KRACHAN ELEPHANT HOUSE AT ZURICH ZOO

SIKA AT WORK THE KAENG KRACHAN ELEPHANT HOUSE AT ZURICH ZOO SIKA AT WORK THE KAENG KRACHAN ELEPHANT HOUSE AT ZURICH ZOO SIKA SYSTEMS FROM BASEMENT TO ROOF BASEMENT TO ROOF SOLUTIONS FOR ELEPHANT HOUSE AT ZURICH ZOO PROJECT DESCRIPTION The Kaeng Krachan Elephant

More information

SECTION 807 PUMP STATION REHABILITATION

SECTION 807 PUMP STATION REHABILITATION SECTION 807 PUMP STATION REHABILITATION 807-1 DESCRIPTION: Rehabilitation of pump stations shall be defined as the cleaning, removal, repair and/or replacement of any and/or all components including but

More information

LAYING BLOCK AND BRICK

LAYING BLOCK AND BRICK LAYING BLOCK AND BRICK Products highlighted in this section: SAKRETE Type N Mortar Mix SAKRETE Type S Mortar Mix Brick And Block Laying Basics The first step in building a brick or block wall is to construct

More information

(B) Reinforcing and Tie Bars shall conform to the requirements of Mn/DOT 3301 unless otherwise shown on the Contract Drawings.

(B) Reinforcing and Tie Bars shall conform to the requirements of Mn/DOT 3301 unless otherwise shown on the Contract Drawings. S-1 (2301) FABRICATION AND PLACEMENT OF PRECAST CONCRETE PAVEMENT PANELS This work consists of furnishing and installing reinforced precast concrete highway pavement slabs as shown on the Plans and in

More information

Presentation Goals and Outline. Introduction to Post-Tensioning. The Precast Show 2014 NPCA 1. Post-Tensioning Institute.

Presentation Goals and Outline. Introduction to Post-Tensioning. The Precast Show 2014 NPCA 1. Post-Tensioning Institute. Presentation Goals and Outline Develop understanding for: PT Basics: Prestressed concrete; advantages; modern PT systems; encapsulation and durability Application Concepts: Facts vs. myths; shortening

More information

Technical handbook Panel Anchoring System

Technical handbook Panel Anchoring System 1 Basic principles of sandwich panels 3 Design conditions 4 Basic placement of anchors and pins 9 Large elements (muliple rows) 10 Small elements (two rows) 10 Turned elements 10 Slender elements 10 Cantilevering

More information

Validation of Cable Bolt Support Design in Weak Rock Using SMART Instruments and Phase 2

Validation of Cable Bolt Support Design in Weak Rock Using SMART Instruments and Phase 2 Validation of Cable Bolt Support Design in Weak Rock Using SMART Instruments and Phase 2 W.F. Bawden, Chair Lassonde Mineral Engineering Program, U. of Toronto, Canada J.D. Tod, Senior Engineer, Mine Design

More information

Formwork for Concrete

Formwork for Concrete UNIVERSITY OF WASHINGTON DEPARTMENT OF CONSTRUCTION MANAGEMENT CM 420 TEMPORARY STRUCTURES Winter Quarter 2007 Professor Kamran M. Nemati Formwork for Concrete Horizontal Formwork Design and Formwork Design

More information

Properties of Fresh Concrete

Properties of Fresh Concrete Properties of Fresh Concrete Introduction The potential strength and durability of concrete of a given mix proportion is very dependent on the degree of its compaction. It is vital, therefore, that the

More information

Formwork Direct International Ltd Phone No +44 (0151) 532 0179 Fax no +44 (0151) 523 8330 E-Mail: sales@formworkdirect.co.

Formwork Direct International Ltd Phone No +44 (0151) 532 0179 Fax no +44 (0151) 523 8330 E-Mail: sales@formworkdirect.co. Tie Rod & Formwork s well as containing our comprehensive range of Formwork Tie Sytems; this section also covers our market leading Rapidobat Column Former. Exclusive also to Formwork Direct are innovations

More information

The ACI 562 Repair Code

The ACI 562 Repair Code The ACI 562 Repair Code Code Requirements for Evaluation, Repair and Rehabilitation of Concrete Buildings by Keith Kesner 1 Chair ACI 562 Lawrence Kahn 2 Former Chair ACI 562 1. Associate WDP & Associates,

More information

Construction Specification for Concrete Curb and Concrete Curb and Gutter

Construction Specification for Concrete Curb and Concrete Curb and Gutter Engineering & Construction Services Division Standard Specifications for Road Works TS 3.50 April 2015 for Concrete Curb and Table of Contents TS 3.50.01 SCOPE... 3 TS 3.50.02 REFERENCES... 3 TS 3.50.03

More information

EAST LYME HIGH SCHOOL

EAST LYME HIGH SCHOOL Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed

More information

Odyssey of the Mind Technology Fair. Simple Electronics

Odyssey of the Mind Technology Fair. Simple Electronics Simple Electronics 1. Terms volts, amps, ohms, watts, positive, negative, AC, DC 2. Matching voltages a. Series vs. parallel 3. Battery capacity 4. Simple electronic circuit light bulb 5. Chose the right

More information

APPENDIX B. I. Background Information

APPENDIX B. I. Background Information APPENDIX B GUIDELINES FOR IDENTIFYING AND REPAIRING LOCALIZED AREAS OF DISTRESS IN AC PAVEMENTS PRIOR TO CAPITAL PREVENTIVE MAINTENANCE OR REHABILITATION REPAIRS I. Background Information A. AC Pavement

More information

MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS

MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS May 29, 2013 Revision B Structural Guideline for Design and Installation Holes in Composite Floor Slab Terminal 3, Departure Level

More information

Fall Protection Solutions

Fall Protection Solutions P R O V I D I N G S A F E T Y S O L U T I O N S W O R L D W I D E Fall Protection Solutions COLLECTIVE PROTECTION KEEGUARD FREE STANDING GUARD RAIL APPROVED BY CERAM AND APAVE KEE DOME SKYLIGHT FALL PROTECTION

More information

Wisconsin Building Products Evaluation

Wisconsin Building Products Evaluation Safety & Buildings Division 201 West Washington Avenue P.O. Box 2658 Madison, WI 53701-2658 Evaluation # 200813-O Wisconsin Building Products Evaluation Material Best Management Standards for Foundation

More information

Two-Way Post-Tensioned Design

Two-Way Post-Tensioned Design Page 1 of 9 The following example illustrates the design methods presented in ACI 318-05 and IBC 2003. Unless otherwise noted, all referenced table, figure, and equation numbers are from these books. The

More information

Reinforcement HUESKER. HaTelit. Engineering with geosynthetics

Reinforcement HUESKER. HaTelit. Engineering with geosynthetics HUESKER Engineering with geosynthetics rhuesker HUESKER HUESKER HUESKER HUESKER HUESKERr SKER HUESKER HUESKER Asphalt HUESKER HUESKER HUESKERHUES Reinforcement - the answer to reflective cracking in asphalt

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

Detailing of Reinforcment in Concrete Structures

Detailing of Reinforcment in Concrete Structures Chapter 8 Detailing of Reinforcment in Concrete Structures 8.1 Scope Provisions of Sec. 8.1 and 8.2 of Chapter 8 shall apply for detailing of reinforcement in reinforced concrete members, in general. For

More information

Pavement Design. Guest Lecturer Dr. Sirous Alavi, P.E. SIERRA TRANSPORTATION. 1005 Terminal Way, Suite 125 Reno, Nevada 89502

Pavement Design. Guest Lecturer Dr. Sirous Alavi, P.E. SIERRA TRANSPORTATION. 1005 Terminal Way, Suite 125 Reno, Nevada 89502 Pavement Design Guest Lecturer Dr. Sirous Alavi, P.E. SIERRA TRANSPORTATION ENGINEERS,, INC. I 1005 Terminal Way, Suite 125 Reno, Nevada 89502 Topics Introduction Design Factors Pavement Types Fundamentals

More information

Owner's Manual & Assembly Instructions

Owner's Manual & Assembly Instructions Owner's Manual & Assembly Instructions PM01 BASE KIT Model No. FDN1014 717090311 CAUTION: SOME PARTS HAVE SHARP EDGES. CARE MUST BE TAKEN WHEN HANDLING THE VARIOUS PIECES TO AVOID A MISHAP. FOR SAFETY

More information

Structural Failures Cost Lives and Time

Structural Failures Cost Lives and Time Structural Failures Cost Lives and Time Recent failures of storage bins, silos and other structures highlight the need to increase awareness of hazards associated with these structures. Since 2010, one

More information

SÖDERLEDSTUNNEL STOCKHOLM FIRE PROTECTION OF THE WESTERN TUBE A CASE STUDY

SÖDERLEDSTUNNEL STOCKHOLM FIRE PROTECTION OF THE WESTERN TUBE A CASE STUDY SÖDERLEDSTUNNEL STOCKHOLM FIRE PROTECTION OF THE WESTERN TUBE A CASE STUDY AGENDA INTRODUCTION / PROJECT OVERVIEW DESIGN / FIRE PROTECTION PROJECT DETAILS ABOUT TBT INTRODUCTION UNDERPASSING ISLAND SÖDERMALM

More information

Post-Tensioned Concrete in Buildings

Post-Tensioned Concrete in Buildings Post-Tensioned Concrete in Buildings A 40+ Year Overview By Ken Bondy ACI Fall Convention San Francisco, October 2004 41 Years Ago It was the fall of 1963 I was 23 years old I had completed my MSCE course

More information

Successful Approach to the Repair of Reinforced Concrete Support Structures in Delayed Coking Units

Successful Approach to the Repair of Reinforced Concrete Support Structures in Delayed Coking Units Successful Approach to the Repair of Reinforced Concrete Support Structures in Delayed Coking Units Thomas Kline Director- Concrete Repair Solutions STRUCTURAL TECHNOLOGIES, LLC Houston, Texas USA November

More information