1 PROJECT MANAGEMENT Planning: time and cost Anna Ilmer ( ) Manuel Leupold ( ) Anna Ilmer & Manuel Leupold Planning: Time and cost 1

2 Roberts, Paul (2007): Guide to project management. Achieving lasting benefit through effective change. London: Profile Books Ltd, p Anna Ilmer & Manuel Leupold Planning: Time and cost 2

3 Agenda 1. Overview 2. Estimating Techniques 3. Development of a resource plan 4. Flexibility of resource plans and the consequences Anna Ilmer & Manuel Leupold Planning: Time and cost 3

4 1. Overview: Products and tasks Products are results of sequences of tasks Product Lifecycle: Draft Review Amend Approve Anna Ilmer & Manuel Leupold Planning: Time and cost 4

5 Estimate An estimate is a probability assessment based on skill and experience of the time and resources required for the delivery of a specified product that has been considered at length during product-based planning. (Roberts 2007: 112) Anna Ilmer & Manuel Leupold Planning: Time and cost 5

6 2. Estimating techniques Without any references to any stored data or prior experience top down & bottom up Delphi technique analogy Require estimation data from previous projects work distribution standard project / product Anna Ilmer & Manuel Leupold Planning: Time and cost 6

7 Top down and bottom up Top down: Created at the beginning of the project takes the whole project and applies an overall timescale and cost. (Roberts 2007: 112) No possibility for detail planning High level nature May contain risky assumptions Focus on TIME / COST / QUALITY Anna Ilmer & Manuel Leupold Planning: Time and cost 7

8 Top down and bottom up Bottom-up: more detailed than Top-down Breaks a product into a set of smaller product Anna Ilmer & Manuel Leupold Planning: Time and cost 8

9 Top down and bottom up TIME Stage 1 8 weeks Stage 2 8 weeks Stage 3 10 weeks Stage 4 15 weeks Stage 5 15 weeks COST $ $ $ $ $ QUALITY Feasibility study report Need analysis report Design report Developed solution Tested,implememnted solution QUALITY Gathered data Drafted report Reviewed report Amended report Approved report Presented report COST $ $ $ $ $ $ TIME 1 week 2 weeks 2 weeks 1 week 1 week 1 week Anna Ilmer & Manuel Leupold Planning: Time and cost 9

10 The Delphi technique Named after the greek oracle, wich was consulted before all major undertakings Experts estimate the effort (or budget) for products other experts review the estimation and give an anonymously feedback the first experts are encouraged to revise t their earlier estimates in the light of these o other views Anna Ilmer & Manuel Leupold Planning: Time and cost 10

11 Analogy Comparing the project, or aspects of it, with something similar is one way in which estimates can be developed. (Roberts 2007: 114) Anna Ilmer & Manuel Leupold Planning: Time and cost 11

12 Workdistribution May be used only for similar projects Use of experience and reliable data from former projects Show the distribution of effort or budget across the standard project lifecycle or across different types of resource Anna Ilmer & Manuel Leupold Planning: Time and cost 12

13 Workdistribution Project total 100% Project Management initiation 5% 5% Need Sales Analysis 25% 35% Solution Operations Design 15% 25% Solution Third parties Dev % Solution IT implementati 35% on 10% Anna Ilmer & Manuel Leupold Planning: Time and cost 13

14 Standard project/product Matrix for working out effort for future project Based on data from repeatedly carried out projects For repeatable work, which varies in size and complexity For accurate estimation, size and complexity should be measurable Anna Ilmer & Manuel Leupold Planning: Time and cost 14

15 Standard project/ product COMPLEXITY LOW MEDIUM HIGH SIZE SMALL MEDIUM LARGE Anna Ilmer & Manuel Leupold Planning: Time and cost 15

16 3.Development of a resource plan Resource management Timescale identification Product flow diagram / PERT diagram Gantt Chart Cost estimate Resource plan Resource plan with financial information Anna Ilmer & Manuel Leupold Planning: Time and cost 16

17 Resource management Capital Office Equipment, computer hardware Non-human ressources Travels, advanced education, expenses Human resources Skills, experience, effort, productivity Anna Ilmer & Manuel Leupold Planning: Time and cost 17

18 Human resources - Productivity People will not be 100% productive. Productivity does not always increase when more people are allocated to a task. People have different productivity rates. Productivity increases are usually temporary. Anna Ilmer & Manuel Leupold Planning: Time and cost 18

19 Dependable productivity estimates Let people estimate their own work. Make planning assumptions clear. Agree product descriptions. Look at metrics from previous work. Negotiate penalty/reward clauses. Anna Ilmer & Manuel Leupold Planning: Time and cost 19

20 Timescale identification Anna Ilmer & Manuel Leupold Planning: Time and cost 20

21 Timescale identification Anna Ilmer & Manuel Leupold Planning: Time and cost 21

22 Cost estimate Anna Ilmer & Manuel Leupold Planning: Time and cost 22

23 4.Flexibility of resource plans and the consequences Anna Ilmer & Manuel Leupold Planning: Time and cost 23

24 Anna Ilmer & Manuel Leupold Planning: Time and cost 24

Pearson Education Limited 2003

Pearson Education Limited 2003 156 Activities Activity 9.1 (PP. 357 358) [Project planning exercise] You are required to construct a project plan for the following information system development project. Your objective is to schedule

More information

Introduction to Project Management. What is the Project Management Life Cycle? Common Life Cycle Characteristics

Introduction to Project Management. What is the Project Management Life Cycle? Common Life Cycle Characteristics Introduction to Project Management Chapter 2 The Project Management Life Cycle Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 2-1 What

More information

Introduction to the ITS Project Management Methodology

Introduction to the ITS Project Management Methodology Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer

More information

Project Integration Management

Project Integration Management Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform

More information

Certificate In Project Management (CIPM)

Certificate In Project Management (CIPM) Conceptualize Plan Plan & Deliver Organize Implement Control Change if Required Integrate Deliver & Closeout Knowledge Leverage Certificate In Project Management (CIPM) Course Overview The Certificate

More information

PLANNING FOR YOUR PROJECT

PLANNING FOR YOUR PROJECT PLANNING FOR YOUR PROJECT This tool kit has been designed to provide an introduction to planning. It will help you to think about the reasons behind why you should plan, what to plan and the variations

More information

OCR LEVEL 3 CAMBRIDGE TECHNICAL

OCR LEVEL 3 CAMBRIDGE TECHNICAL Cambridge TECHNICALS OCR LEVEL 3 CAMBRIDGE TECHNICAL CERTIFICATE/DIPLOMA IN IT PROJECT PLANNING WITH IT Y/601/7321 LEVEL 3 UNIT 9 GUIDED LEARNING HOURS: 60 UNIT CREDIT VALUE: 10 PROJECT PLANNING WITH IT

More information

Making project management indispensable for business results. Project Management 101

Making project management indispensable for business results. Project Management 101 Making project management indispensable for business results. Project Management 101 Donald E. Moore, MBA, PMP, President of PMI NB Kelly Barter, Chapter Manager of PMI NB AGM April 28, 2011 Topics of

More information

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter 1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process

More information

Project Management Process

Project Management Process Project Management Process Description... 1 STAGE/STEP/TASK SUMMARY LIST... 2 Project Initiation 2 Project Control 4 Project Closure 5 Project Initiation... 7 Step 01: Project Kick Off 10 Step 02: Project

More information

Policy statement: Assessment, recording and reporting achievement.

Policy statement: Assessment, recording and reporting achievement. Policy statement: Assessment, recording and reporting achievement. In partnership with the home and the local community, the school has a responsibility to fulfil the demands of the national curriculum

More information

MSc Project Planning

MSc Project Planning MSc Project Planning Dr Paul Brunn 4 th February 2009 Project Planning and Control Intro to General Methods Some simple examples How to plan and complete an MSc Dissertation project EPS Graduate Education

More information

The contact workshop is a mix of instructor lead and self paced learning, designed as per the PMBOK Fifth edition of Project Management Institute.

The contact workshop is a mix of instructor lead and self paced learning, designed as per the PMBOK Fifth edition of Project Management Institute. PMP Bootcamp workshop Duration: 4 Days - 35 PDUs GRT Consulting LLP brings you their eminent PMP Boot camp workshop to address the requirements of delegates preparing for the Project Professional (PMP

More information

WHITE PAPER IT SERVICE MANAGEMENT IT SERVICE DESIGN 101

WHITE PAPER IT SERVICE MANAGEMENT IT SERVICE DESIGN 101 WHITE PAPER IT SERVICE MANAGEMENT IT SERVICE DESIGN 101 Prepared by: Phillip Bailey, Service Management Consultant Steve Ingall, Head of Service Management Consultancy 60 Lombard Street London EC3V 9EA

More information

BUSINESS OCR LEVEL 3 CAMBRIDGE TECHNICAL. Cambridge TECHNICALS BUSINESS PROJECT MANAGEMENT CERTIFICATE/DIPLOMA IN K/502/5459 LEVEL 3 UNIT 18

BUSINESS OCR LEVEL 3 CAMBRIDGE TECHNICAL. Cambridge TECHNICALS BUSINESS PROJECT MANAGEMENT CERTIFICATE/DIPLOMA IN K/502/5459 LEVEL 3 UNIT 18 Cambridge TECHNICALS OCR LEVEL 3 CAMBRIDGE TECHNICAL CERTIFICATE/DIPLOMA IN BUSINESS BUSINESS PROJECT MANAGEMENT K/502/5459 LEVEL 3 UNIT 18 GUIDED LEARNING HOURS: 60 UNIT CREDIT VALUE: 10 BUSINESS PROJECT

More information

Quality Manual ISO 9001:2015 Quality Management System

Quality Manual ISO 9001:2015 Quality Management System Quality management input comprises the standard requirements from ISO 9001:2015 which are deployed by our organization to achieve customer satisfaction through process control. Quality Manual ISO 9001:2015

More information

Software Engineering CSCI 4490. Lesson 9 Project Management Part 1- Planning & Estimating. February 23, 2015

Software Engineering CSCI 4490. Lesson 9 Project Management Part 1- Planning & Estimating. February 23, 2015 Lesson 9 Project Management Part 1- Planning & Estimating February 23, 2015 Projects and Project Managers Project a [temporary] sequence of unique, complex, and connected activities having one goal or

More information

www.aryanengineering.com Email: info@aryanengineering.com

www.aryanengineering.com Email: info@aryanengineering.com What is PMP Certification exam? www.aryanengineering.com PMP stands for Project Management Professional certification exam. PMP, is one of the most respected and globally recognized certification is offered

More information

HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7?

HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7? HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7? This document contains introduction to P2ware Project Manager 7 views (P2ware Project Manager 7 walkthrough) and shows how to create high quality plans

More information

Certification Exam Objectives: PK0-003

Certification Exam Objectives: PK0-003 Certification Exam Objectives: PK0-003 INTRODUCTION The CompTIA Project + examination is designed for business professionals involved with projects. This exam will certify that the successful candidate

More information

Quick Reference Guide Interactive PDF Project Management Processes for a Project

Quick Reference Guide Interactive PDF Project Management Processes for a Project Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process

More information

Critical Path Analysis & PERT Charts (taken from www.business.com.

Critical Path Analysis & PERT Charts (taken from www.business.com. Critical Path Analysis & PERT Charts (taken from www.business.com. - Planning and scheduling more complex projects Critical Path Analysis and PERT are powerful tools that help you to schedule and manage

More information

URGENCY: A CRITICAL FACTOR IN PROJECT PLANNING

URGENCY: A CRITICAL FACTOR IN PROJECT PLANNING URGENCY: A CRITICAL FACTOR IN PROJECT PLANNING Ricardo Viana Vargas, MSc, IPMA-B, PMP Professor Fundação Getúlio Vargas (FGV) Brasil Professor Fundação Instituto de Administração (FIA USP) - Brasil CEO

More information

Input, Output and Tools of all Processes

Input, Output and Tools of all Processes 1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) Marc.Conrad@luton.ac.uk 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /

More information

PMP Exam Preparation Answer Key

PMP Exam Preparation Answer Key Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.

More information

Software Development Standard Deliverables

Software Development Standard Deliverables Software Development Standard Deliverables Lifecycle Methodology Created By Rafael Soultanov Version 1.1 September 19, 20044 Development Lifecycle Methodology Document Control Change Record Date Author

More information

ISO 9001:2000 - A Quality Manual for the Transition Period and Beyond

ISO 9001:2000 - A Quality Manual for the Transition Period and Beyond ISO 9001:2000 - A Quality Manual for the Transition Period and Beyond By Mark Kaganov Abstract This article shows a practical approach to converting an ISO 9001:1994 quality manual into the new ISO 9001:2000

More information

PRINCE2:2009 Glossary of Terms (English)

PRINCE2:2009 Glossary of Terms (English) accept (risk response) acceptance acceptance criteria activity agile methods approval approver assumption assurance A risk response to a threat where a conscious and deliberate decision is taken to retain

More information

Implementing the Project Management Balanced Scorecard

Implementing the Project Management Balanced Scorecard Implementing the Project Management Balanced Scorecard Jessica Keyes CRC Press Taylor & Francis Group Boca Raton London New York CRC Press is an imprint of the Taylor & Francis Croup, an informa business

More information

(Refer Slide Time: 01:52)

(Refer Slide Time: 01:52) Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This

More information

Scotland Your project business plan

Scotland Your project business plan Scotland Your project business plan Scotland Your project business plan Further copies available from: Email enquiries.scotland@biglotteryfund.org.uk Phone 0870 240 2391 Textphone 0141 242 1500 Our website

More information

WHAT IS PRINCE2? Benefits There are many benefits of using PRINCE2 but primarily it:

WHAT IS PRINCE2? Benefits There are many benefits of using PRINCE2 but primarily it: WHAT IS PRINCE2? Introduction PRINCE2 (Projects in a Controlled Environment) is a structured project management method that can be applied regardless of project scale, type, organisation, geography or

More information

Systems Analysis and Design

Systems Analysis and Design Systems Analysis and Design Slides adapted from Jeffrey A. Hoffer, University of Dayton Joey F. George, Florida State University Joseph S. Valacich, Washington State University Modern Systems Analysis

More information

Investigate Requirements for Software Solutions

Investigate Requirements for Software Solutions Unit 29: Investigate Requirements for Software Solutions Learning Outcomes A candidate following a programme of learning leading to this unit will be able to: Gather and analyse appropriate and relevant

More information

The Elective Part of the NSS ICT Curriculum D. Software Development

The Elective Part of the NSS ICT Curriculum D. Software Development of the NSS ICT Curriculum D. Software Development Mr. CHEUNG Wah-sang / Mr. WONG Wing-hong, Robert Member of CDC HKEAA Committee on ICT (Senior Secondary) 1 D. Software Development The concepts / skills

More information

Setting SMART Objectives

Setting SMART Objectives Setting SMART Objectives Whilst line managers are responsible for ensuring that objectives are set it is important that, wherever possible, objectives are jointly agreed, between staff and line manager,

More information

The management of the projects with MS Project

The management of the projects with MS Project The management of the projects with MS Project Author: AgimDerguti 1 What is Microsoft Project? Microsoft Project is a project management software program developed and sold by Microsoft Designed to assist

More information

Minnesota Health Insurance Exchange (MNHIX)

Minnesota Health Insurance Exchange (MNHIX) Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration

More information

ITS Change Management Guidelines

ITS Change Management Guidelines ITS Change Management Guidelines Revision 3.0 Original drafted March 5, 2002 Revision 3.1 Version Update November 28, 2011 Revision 3.2 Version Updated February 24, 2012 Revision 3.3 Current Version Updated

More information

Chapter 3 Managing the Information Systems (IS) Project

Chapter 3 Managing the Information Systems (IS) Project Content Chapter 3 Managing the Information Systems (IS) Project Process of managing IS projects Skills required to be an effective project manager Skills and activities of a project manager during project

More information

AUDITOR GUIDELINES. Responsibilities Supporting Inputs. Receive AAA, Sign and return to IMS with audit report. Document Review required?

AUDITOR GUIDELINES. Responsibilities Supporting Inputs. Receive AAA, Sign and return to IMS with audit report. Document Review required? 1 Overview of Audit Process The flow chart below shows the overall process for auditors carrying out audits for IMS International. Stages within this process are detailed further in this document. Scheme

More information

Effective & Practical. Management of Projects

Effective & Practical. Management of Projects Effective & Practical Concepts, Methods & Techniques Project Planning & Delivery Management of Project Risks High Quality Training Courses presented by Internationally Recognised Expert Speakers The Diamond

More information

Project Scheduling & Tracking

Project Scheduling & Tracking Project Scheduling & Tracking Traditional Techniques: Work Breakdown Structure (WBS) Gantt Charts Precedence Diagrams Earned Value Planning It is the mark of an instructed mind to rest satisfied with the

More information

ISO 9001 for Small Projects

ISO 9001 for Small Projects Chapter 8 ISO 9001 for Small Projects INTRODUCTION TO ISO 9001 FOR SMALL PROJECTS Many organizations are intimidated by the amount of documentation associated with ISO 9001 conformance requirements. The

More information

TECHNICALS LEVEL 2016 3 BUSINESS

TECHNICALS LEVEL 2016 3 BUSINESS 2016 Suite Cambridge TECHNICALS LEVEL 3 BUSINESS Unit 16 Principles of project management M/507/8163 Guided learning hours: 60 Version 2 - Revised content - March 2016 ocr.org.uk/business LEVEL 3 UNIT

More information

NFSA Project Management Guidelines

NFSA Project Management Guidelines NFSA Project Management Guidelines Project Management Guide Purpose of this Guide This Guide outlines the NFSA Project Management Guidelines, and includes: NFSA Project Life Cycle Governance Roles and

More information

WBS, Estimation and Scheduling. Adapted from slides by John Musser

WBS, Estimation and Scheduling. Adapted from slides by John Musser WBS, Estimation and Scheduling Adapted from slides by John Musser 1 Today Work Breakdown Structures (WBS) Estimation Network Fundamentals PERT & CPM Techniques Gantt Charts 2 Estimation Predictions are

More information

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes

More information

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name

More information

IT2404 Systems Analysis and Design (Compulsory)

IT2404 Systems Analysis and Design (Compulsory) Systems Analysis and Design (Compulsory) BIT 1 st YEAR SEMESTER 2 INTRODUCTION This is one of the 4 courses designed for Semester 1 of Bachelor of Information Technology Degree program. CREDITS: 04 LEARNING

More information

The 10 Knowledge Areas & ITTOs

The 10 Knowledge Areas & ITTOs This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading

More information

Project Management Certificate (IT Professionals)

Project Management Certificate (IT Professionals) Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.

More information

Visual design and UX services for cloud based applications, services and sites

Visual design and UX services for cloud based applications, services and sites G- Cloud service Visual design and UX services for cloud based applications, services and sites 2013 Page 1 Table of contents 1. About us... 3 2. Overview of G- Cloud Service... 3 If it looks good, you

More information

Retained Fire Fighters Union. Introduction to PRINCE2 Project Management

Retained Fire Fighters Union. Introduction to PRINCE2 Project Management Retained Fire Fighters Union Introduction to PRINCE2 Project Management PRINCE2 PRINCE stands for: PRojects IN Controlled Environments and is a structured method which can be applied to any size or type

More information

Software Project Management

Software Project Management Software Project Management Week 5: Work Breakdown Structures and a Case Study COMP3711 Software Project Management 1 Project Planning: A 12 Step Program 1) Set goal and scope 2) Select lifecycle 3) Set

More information

Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs

Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs HUMAN RESOURCE MANAGEMENT Organizational planning Staff Acquisition Project interfaces such as organizational interfaces, technical interfaces and interpersonal interfaces. Staffing requirements Staffing

More information

MNLARS Project Audit Checklist

MNLARS Project Audit Checklist Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?

More information

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain * TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited

More information

[14:37 2007/2/22 Ch03-H8325.tex] ISBN: 0750683252 YULL: BTEC First ICT Practitioners Curriculum Support Pack Page: 42 41 58

[14:37 2007/2/22 Ch03-H8325.tex] ISBN: 0750683252 YULL: BTEC First ICT Practitioners Curriculum Support Pack Page: 42 41 58 Unit 3 ICT project The activities provided to support this unit have been designed to give students an insight into some of the tools and techniques required to embark on effective project management.

More information

PBL: Project Management. Competency: Project Definition

PBL: Project Management. Competency: Project Definition Competency: Project Definition 1. Define project management and the context of modern project management. 2. Describe how to manage projects throughout the five major process groups. 3. Define the characteristics

More information

Introduction to Project Management. What is a Project? Project Management Institute (PMI) Chapter 1 Introduction

Introduction to Project Management. What is a Project? Project Management Institute (PMI) Chapter 1 Introduction Introduction to Project Management Chapter 1 Introduction Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 1-1 What is a Project? A planned

More information

Cost Estimation Strategies COST ESTIMATION GUIDELINES

Cost Estimation Strategies COST ESTIMATION GUIDELINES Cost Estimation Strategies Algorithmic models (Rayleigh curve Cost in week t = K a t exp(-a t 2 ) Expert judgment (9 step model presented later) Analogy (Use similar systems) Parkinson (Work expands to

More information

ESKIPM2(SQA Unit Code- F9CX 04) Project management software

ESKIPM2(SQA Unit Code- F9CX 04) Project management software Overview This is the ability to use a software application that plans, organises and monitors completion of the component tasks within a project in logical sequence, given constraints of people and resource

More information

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Planning and Managing Software Projects 2010-11 Session 6 Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 These

More information

Project Planning With IT

Project Planning With IT Unit 17: Project Planning With IT Unit code: QCF Level 3: Credit value: 10 Guided learning hours: 60 Aim and purpose Y/601/7321 BTEC National The aim of this unit is to ensure learners understand the processes

More information

SELF ASSESSMENT GUIDE FOR PLACEMENT SERVICE PROVIDERS 2009/2010

SELF ASSESSMENT GUIDE FOR PLACEMENT SERVICE PROVIDERS 2009/2010 SELF ASSESSMENT GUIDE FOR PLACEMENT SERVICE PROVIDERS 2009/2010 Electronic copies of this document are available by contacting the Manager Standards Monitoring Unit on 9222 2598 CONTENTS OVERVIEW...3 PURPOSE

More information

Dr. Tarek A. Tutunji Philadelphia University, Jordan. Engineering Skills, Philadelphia University

Dr. Tarek A. Tutunji Philadelphia University, Jordan. Engineering Skills, Philadelphia University Philadelphia University, Jordan Project Management In the previous section, Engineering Responsibility was presented. In this session, Project Management will be introduced. This session is divided into

More information

SOFTWARE PROJECT MANAGEMENT

SOFTWARE PROJECT MANAGEMENT SOFTWARE PROJECT MANAGEMENT http://www.tutorialspoint.com/software_engineering/software_project_management.htm Copyright tutorialspoint.com The job pattern of an IT company engaged in software development

More information

A checklist for project managers

A checklist for project managers A checklist for project managers The checklist presented below aims to help you decide what project documents are needed, approximately when you need to create them, and what other resources are available.

More information

ISO 14001:2004 EMS Internal Audit Guidance

ISO 14001:2004 EMS Internal Audit Guidance ISO 14001:2004 EMS Internal Audit Guidance Contents Introduction... 3 About the Internal Audit Solution... 3 Forms & Records... 3 Audit Procedure... 3 Document Reference Numbering... 4 Navigating the Documents...

More information

G Barnaby Electronics Ltd case Study - Comparison of Entity-Relationship and Normalisation Database Designs

G Barnaby Electronics Ltd case Study - Comparison of Entity-Relationship and Normalisation Database Designs G Barnaby Electronics Ltd case Study - Comparison of Entity-Relationship and Normalisation Database Designs G.1 Compare the two Database Designs created from the Entity-Relationship Model and Normalisation

More information

Project Audit & Review Checklist. The following provides a detailed checklist to assist the PPO with reviewing the health of a project:

Project Audit & Review Checklist. The following provides a detailed checklist to assist the PPO with reviewing the health of a project: Project Audit & Review Checklist The following provides a detailed checklist to assist the PPO with reviewing the health of a project: Relevance (at this time) Theory & Practice (How relevant is this attribute

More information

Technical Project Management

Technical Project Management Technical Project Management Patrick Stanard IBM z Systems Architect Manager-North Region Ellis Holman IBM Certified Infrastructure Architect - System z - All - IMT US East Great Lakes Agenda Why I hate

More information

Work Breakdown Structure (WBS) Emanuele Della Valle http://emanueledellavalle.org

Work Breakdown Structure (WBS) Emanuele Della Valle http://emanueledellavalle.org Planning and Managing Software Projects 2011-12 Class 7 Work Breakdown Structure (WBS) Emanuele Della Valle http://emanueledellavalle.org Credits 2 This slides are largely based on Prof. John Musser class

More information

GCE APPLIED ICT A2 COURSEWORK TIPS

GCE APPLIED ICT A2 COURSEWORK TIPS GCE APPLIED ICT A2 COURSEWORK TIPS COURSEWORK TIPS A2 GCE APPLIED ICT If you are studying for the six-unit GCE Single Award or the twelve-unit Double Award, then you may study some of the following coursework

More information

DIRECTIVE NUMBER: 141.03.04.001 v2.0. SUBJECT: Correctional Integration Systems Change Management Plan

DIRECTIVE NUMBER: 141.03.04.001 v2.0. SUBJECT: Correctional Integration Systems Change Management Plan DEPARTMENT OF CORRECTION SUPPORT Management Services DIRECTIVE NUMBER: SUBJECT: Correctional Integration Systems Change PAGE NUMBER: 1 of 10 Adopted: 12-15-03 01.00.00. POLICY OF THE DEPARTMENT It is the

More information

PROJECT MANAGER. Grade: Salary:

PROJECT MANAGER. Grade: Salary: PROJECT MANAGER Grade: Salary: Career Grade F/G* *see career grade structure 24,427 to 33,771 per annum Status: 12 months fixed term contract with potential for a further 12 months extension subject to

More information

Appendix G: Organizational Change Management Plan. DRAFT (Pending approval) April 2007

Appendix G: Organizational Change Management Plan. DRAFT (Pending approval) April 2007 Appendix G: Organizational Change Management Plan DRAFT (Pending approval) April 2007 Table of Contents TABLE OF CONTENTS... 1 INTRODUCTION:... 2 ABT ORGANIZATIONAL CHANGE MANAGEMENT SCOPE... 2 PEOPLESOFT

More information

Software Testing and Software Development Lifecycles

Software Testing and Software Development Lifecycles Software Testing and Software Development Lifecycles Executive Summary This paper outlines a number of commonly used software development lifecycle models, with particular emphasis on the testing activities

More information

ESKIPM3 Project management software

ESKIPM3 Project management software Overview This is the ability to use a software application that plans, organises and monitors completion of the component tasks within a project in logical sequence, given constraints of people and resource

More information

FSDT Project Management Session. Worksheets and Planning Tools

FSDT Project Management Session. Worksheets and Planning Tools FSDT Project Management Session Worksheets and Planning Tools Table of contents What is a project?...3 The project life cycle...3 Project Phases...4 Initiation phase...4 Approval Phase...5 Project Launch...6

More information

Software Application: Information System Elements. Project Management in Information Technology (IT) Projects. Project Scheduling basics

Software Application: Information System Elements. Project Management in Information Technology (IT) Projects. Project Scheduling basics Software Application: Information System Elements Project Scheduling Basics Working With Resources Fine Tuning the Project Managing the Project Project Presentations Project Management in Information Technology

More information

INVESTING IN REFORM INVESTING IN STOCKPORT DRAFT BUSINESS CASE

INVESTING IN REFORM INVESTING IN STOCKPORT DRAFT BUSINESS CASE INVESTING IN STOCKPORT DRAFT BUSINESS CASE INVESTING IN REFORM IIS Programme/Project Name: Project Name: Portfolio: IIS Outcome: IIS Board SRO: IIS Project Lead: Public Realm and Solutions SK Communities

More information

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False Chapter 1.7 Project Management Part I: Objective type questions and answers 1. Project financing is one of the step of project management- State True or False 2. Proposed new technologies, process modifications,

More information

Overview of: A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition

Overview of: A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition Overview of A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition Overview of: A Guide to the Project Management Body of Knowledge (PMBOK Guide) Fourth Edition 1 Topics for Discussion

More information

MIS 460 Project Management

MIS 460 Project Management Ursuline College Accelerated Program CRITICAL INFORMATION! DO NOT SKIP THIS LINK BELOW... BEFORE PROCEEDING TO READ THE UCAP MODULE, YOU ARE EXPECTED TO READ AND ADHERE TO ALL UCAP POLICY INFORMATION CONTAINED

More information

Project Portfolio Management: James C. Brown Sr. Manager, Research PMO Pioneer Hi-Bred International

Project Portfolio Management: James C. Brown Sr. Manager, Research PMO Pioneer Hi-Bred International Project Portfolio Management: Metrics that Work James C. Brown Sr. Manager, Research PMO Pioneer Hi-Bred International Agenda PPM Interest What is Project Portfolio Management? Challenges Myths Benefits

More information

Custom Software Development Approach

Custom Software Development Approach Custom Software Development Approach Our approach to custom software development combines benefits from several standard development process models. We tend to have a well-defined, predictable and highly

More information

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART C CERTIFIED PRACTISING PROJECT MANAGER (CPPM)

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART C CERTIFIED PRACTISING PROJECT MANAGER (CPPM) AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART C CERTIFIED PRACTISING PROJECT MANAGER (CPPM) February 2010 Version 1.12 Copyright: Australian Institute of Project Management Document

More information

To be used in conjunction with the Invitation to Tender for Consultancy template.

To be used in conjunction with the Invitation to Tender for Consultancy template. GUIDANCE NOTE Tendering for, choosing and managing a consultant Using this guidance This information is not intended to be prescriptive, but for guidance only. Appointing consultants for relatively small

More information

Scheduling and Review of Project Activities

Scheduling and Review of Project Activities Project Implementation Manual Scheduling and Review of Project Activities 1. INTRODUCTION 2. UNDERSTANDING CONTRACTUAL OBBLIGATIONS 3. PLANNING, MONITORING & AUDITING 4. PROCUREMENT 5. REPORTING 1.1 Purpose

More information

Integrated talent management at Commerzbank: Tailored online solution for systematic succession planning

Integrated talent management at Commerzbank: Tailored online solution for systematic succession planning Integrated talent management at Commerzbank: Tailored online solution for systematic succession planning Cut-e Networking Event, Hamburg, 22nd March, 2012 Group Human Resources Talent Management Succession

More information

Comparing the Differences and Complementary features of PRINCE2 and the PMI PMBOK Guide

Comparing the Differences and Complementary features of PRINCE2 and the PMI PMBOK Guide Comparing the Differences and Complementary features of PRINCE2 and the Guide PRINCE2 is the UK Government s structured project management method. PMI stands for the Project Management Institute producing

More information

PROJECT MANAGEMENT PLAN CHECKLIST

PROJECT MANAGEMENT PLAN CHECKLIST PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,

More information

Managing Aviation Projects from Concept to Completion

Managing Aviation Projects from Concept to Completion Managing Aviation Projects from Concept to Completion TRIANT G. FLOURIS & DENNIS LOCK ASHGATE Contents List of Figures xiii Acknowledgments xix Foreword by William DeCota, ' xxi Foreword by Dr Yiannis

More information

INTRODUCTION TO PROJECT MANAGEMENT

INTRODUCTION TO PROJECT MANAGEMENT INTRODUCTION TO PROJECT MANAGEMENT OVERVIEW The purpose of presentation is to provide leaders and team members of projects, committees or task forces with advanced techniques and practical skills for initiating,

More information

Head of Lease Terms - Ten Steps to a Successful negotiation

Head of Lease Terms - Ten Steps to a Successful negotiation Imperial College ThinkSpace Leasing Terminology Head of lease terms The principal terms upon which the lease will be drafted are detailed within a single document, entitles the Heads of Lease Terms. These

More information

SOFTWARE ENGINEERING INTERVIEW QUESTIONS

SOFTWARE ENGINEERING INTERVIEW QUESTIONS SOFTWARE ENGINEERING INTERVIEW QUESTIONS http://www.tutorialspoint.com/software_engineering/software_engineering_interview_questions.htm Copyright tutorialspoint.com Dear readers, these Software Engineering

More information

Risk Profiling Toolkit DEVELOPING A CORPORATE RISK PROFILE FOR YOUR ORGANIZATION

Risk Profiling Toolkit DEVELOPING A CORPORATE RISK PROFILE FOR YOUR ORGANIZATION Risk Profiling Toolkit DEVELOPING A CORPORATE RISK PROFILE FOR YOUR ORGANIZATION I Background Under the TBS Risk Management Policy, departments and agencies must identify the potential perils, factors

More information