OUTLINE TENDER STAGE METHOD STATEMENT Removal of Asbestos Cement Roof & demolition of Building At Highbury Roundhouse. Ronald Road. London.
|
|
- Shon Sparks
- 7 years ago
- Views:
Transcription
1 OUTLINE TENDER STAGE METHOD STATEMENT Removal of Asbestos Cement Roof & demolition of Building At Highbury Roundhouse. Ronald Road. London. N5 1XB Document Control Revision No. Date Approved Signature 1
2 Table of Contents PROJECT SPECIFIC DETAILS / ARRANGEMENTS SECTION 1 SECTION 2 SECTION 3 Project Team Scope of Works Method of Works SECTION 4 Training SECTION 5 Emergency Arrangements 2
3 Section 1. Project Team Client: TBC Independent Safety Solutions Address: Address: Uplands House. Warren Road, Rettendon Common, Essex. CM3 8DF Contact: Name: Tel: Mobile: Name: Tel: Fax: Mobile: Name: Chris Webber Tel: Fax: Mobile:
4 Section 2 Scope of Works This is an outline tender stage method statement which will be developed to construction phase upon award of the works. It should be noted that this Method Statement is INDICATIVE only. The works generally consist of the following elements: Attendance during the construction of the reinforced concrete wall to support the existing distressed party boundary wall. Removal of the asbestos cement roof covering and mansard panels. Erection of a scaffold platform and dust screen to rear elevation. Removal of internal M&E services. Demolition of the building to ground slab level. 4
5 SECTION 3 Method of Works. Plant Assigned to the project: 1 x 360 Excavator with pulveriser 1 x 25 Tonne Dump Truck 1 x Mobile Elevated Working Platform 1 x Crushing Station 1 x Hygiene Unit 1. Upon arrival on site operatives will receive a site specific induction detailing the arrangements in the site specific RAMS. Operatives will be required to sign the site induction register to confirm that the induction has been received and understood. 2. Site access will be via the main entrance gates off Ronald road. 5. Operatives will don the following PPE before entering the building: Hard Hat High Visibility Tabard Safety Footwear Gloves Safety Goggles Ear Protection Ori-nasal Half masks rated at FFP3. Attendance during the construction of the RC retaining wall. i) Operatives will carefully clear overgrown vegetation around the disused steel store by means of handheld tools to reduce likelihood of further structural distress. 5
6 ii) The steel store will be accessed and the contents emptied into a waste skip. The exact contents are not known at this stage as access has not been possible. Any items that can be recycled will be segregated and placed in an appropriate skip. iii) The empty steel store will be lifted onto a flatbed lorry by means of a hiab and carted from site for recycling. iv) The structural engineer will be invited to inspect the exposed section of the boundary wall. v) The principle contractor will commence construction of a secondary reinforced concrete wall to provide support to the existing distressed brickwork wall. Removal of Internal M&E i) The PC will arrange for the disconnection of all electrical, gas and water services. ii) The PC will issue a permit to work confirming the extent of service isolations. iii) Operatives will enter the building and remove all high level air conditioning units, water storage tanks, electrical fittings and the mezzanine floor. Access to high level will be via a suitable MEWP. Where a MEWP is not practicable due to space restraints, a scaffold tower will be utilised. Ladders will only be used for inspection and short duration works. 6
7 Scaffold Access Platform/Dust & Debris Screen. i) The PC will arrange via the client for residents to remove all garden items a minimum of three metres away from the boundary wall. ii) A specialist scaffold contractor will be appointed to erect a screen and single lift scaffold to the rear of the property within the residents gardens. The working platform will be used by our operatives to remove the asbestos cement panels to the mansard. iii) Scaffold operatives will be required to have received basic asbestos awareness training as part of their competencies. iv) The screen will be erected to ensure that the top extends at least one metre beyond the building ridge. v) Monoflex will be secured to the fan from ground level to the top secured with toggles. vi) Upon completion the scaffold contractor will invite the PC to inspect the structure and provide a completion certificate and scafftag. vii) The scaffold will be inspected prior to each use and by a competent person on a frequency not exceeding seven days. Note/ Design drawings will be required for this scaffold due to the potential imposed loading due to weather conditions. Asbestos Removal. The existing roof is constructed from corrugated asbestos cement sheets. Although this material is non-licensable we will be complying with best practice as detailed in the following documents: Control of Asbestos Regulations 2006 Asbestos Essentials HS (G) 210. i) Operatives will set up suitable water jets to suppress the asbestos cement sfairp. ii) Operatives will don disposable coveralls rated at class 3 (5/6 particulate tight) and ori-nasal half masks for which they have a current face-fit certificate fitted with P3 filters. iii) By means of a MEWP, operatives will access the internal straw board lining and lower to the ground for disposal as contaminated waste. 7
8 iv) Operatives will spray the straw board with a water /surfactant solution during removal to reduce the likelihood of fibre release. v) An initial high level asbestos cement roof sheet will be carefully broken out, (sacrificial sheet) whilst suppressing to gain access to the ridge tile/capping from inside. vi) Retaining bolts will be carefully cropped and passed through the asbestos cement sheets. vii) The asbestos cement sheets will be carefully lowered inwards and lowered to the ground. viii) Asbestos cement sheets will be placed on the forklift truck and placed in the asbestos skip. ix) The mansard asbestos cement sheets will be accessed via the scaffold to the rear of the property. All sheets will be removed in the same way as the roof sheets, However a sacrificial sheet will not be necessary. x) AC sheets will be passed into the building and placed on the FLT for disposal in the asbestos skip. xi) Upon completion of each shift, operatives will decontaminate in the Hygiene unit provided. Left: Asbestos Cement roof to be removed by hand under suppression. Right: Asbestos Cement sheet to mansard as viewed from within the building. 8
9 Demolition of Masonry Walls. i) Prior to commencement of works the client s structural engineer is to confirm the structural integrity of the wall. ii) The client and the appointed demolition contractor will agree any temporary shoring that may be required prior to disturbance. iii) Water jets will be utilised for the duration of the demolition works to reduce the likelihood of noise nuisance to the neighbouring residents. iv) Due to the structural distress of the building a 360 degree excavator fitted with a long reach pulveriser will be utilised to demolish the structure. v)the excavator will cause the walls to fall inward within its own footprint to reduce the need for operatives to work on an unstable structure. vi) Arisings will be loaded onto the dumper truck and conveyed to the crushing station. vii) Arisings will be crushed to the clients specification and/or removed from site for recycling. viii) Plant will be secured and immobilised whenever not in use. ix) Upon completion of the demolition works the site will be swept and handed back to the client. Site Clearance. Upon completion of the works all plant and equipment will be removed from site. 9
10 SECTION 5 Emergency Arrangements 1. The muster point will be located at the entrance gate located off Ronald Road. 2. Upon notification of imminent danger operatives will stop works immediately and make their way to the muster point. 3. The site manager or his deputy will check that all operatives are present by means of the site signing in book. 4. There will be a minimum of two first aiders on the site at all times. 5. Emergency services will be summonsed via the mobile phone network by dialling 999 or
SAFE REMOVAL AND DISPOSAL OF ASBESTOS CEMENT BUILDING PRODUCTS
SAFE REMOVAL AND DISPOSAL OF ASBESTOS CEMENT BUILDING PRODUCTS Within the City of Mandurah many dwellings exist with asbestos cement building products. When removing the asbestos, concerns may be raised
More informationASBESTOS IN THE HOME
J:\Public Protection Division\Food and Occupational Safety\Leaflets\A S B E S T O S.docJ:\Public Protection Division\Food and Occupational Safety\Leaflets\A S B E S T O S.doc ASBESTOS IN THE HOME What
More informationProcedures for Cutting and Handling of Asbestos Cement Pipe. City of Richmond Public Works Operations
Procedures for Cutting and Handling of Asbestos Cement Pipe City of Richmond Public Works Operations Version 2.0 Updates to: November 1995 Procedures Prepared by: AMEC Earth & Environmental a division
More informationDemolition & Construction Management Plan
Demolition & Construction Management Plan 72 76 Cadogan lane SW1 Demolition & Construction Management Plan Issue Date: March 2013 Contents: 1.0 Introduction 1.1 Objectives of the Plan 1.2 Project Overview
More informationScaffold Standard (Standard to Managing and Appointing Scaffolding Contractors on University College London (UCL) Projects) Management Standard
Scaffold Standard (Standard to Managing and Appointing Scaffolding Contractors on University College London (UCL) Projects) Management Standard UNIVERSITY COLLEGE LONDON Engineering, Maintenance & Infrastructure
More informationJob safety analysis Installing wall frames and roof trusses on-site
Job safety analysis Installing wall frames and roof trusses on-site 1. Taking delivery: - unloading the truck - moving materials manually to the work area Body sprains and strains from lifting materials
More informationPollution & Noise from Demolition & Construction Sites
CONTROL OF Pollution & Noise from Demolition & Construction Sites N oi se Co ns tru ct io n MAY 2008 THE LONDON BOROUGH 3 CONTENTS Part 1 Introduction Page 1. Background 4 2. Purpose of the code 5 3.
More informationUniversity Arms Hotel, Cambridge
Traffic Management Plan For University Arms Hotel, Cambridge Prepared By: James Batterbee Number: M1342 / Rev B Date: 29 th August 2014 CONTENTS: (1) INTRODUCTION (2) VEHICLE ACCESS & EGRESS AND PEDESTRIAN
More informationConstruction OS&H Working at height
Construction OS&H Working at height Summary Common hazards with working at height General OS&H requirements when working at height Scaffolding Structural frames Demolition of above ground structures Roof-work
More informationA: SIGNIFICANT RISKS Initial Risk Rating H/M/L B: KEY CONTROL MEASURES ACTION
ELECTRICAL CONTRACTOR RISK ASSESSMENT AND KEY CONTROL MEASURES CONTRACTOR NAME: AEC Automation Ltd. NAME OF CONTRACT: A: SIGNIFICANT RISKS Initial Risk Rating H/M/L Slips, trips and falls. Manual handling.
More informationSAFE WORK PROCEDURE SWP 015 WORKING AT HEIGHT SEPTEMBER 2013 DOC. NO. D13/248399
Operation Brief Description of Activity Limitations MORELAND CITY COUNCIL Operations Centre 7-9 Walter Street Hadfield Vic 3046 Tel: 8311 4300 Working at height Approved by the Walter Street OHS committee
More informationhave been provided with information on whether they do or do not contain asbestos before starting work;
Health Effects of Asbestos If your work involves possible exposure to asbestos, you should: be aware of the risks from asbestos exposure; understand the importance of keeping exposure as low as possible;
More informationSITE CONTRACTOR PROCEDURES
SITE CONTRACTOR PROCEDURES Asset Collection Type B Assets are considered High risk ; the site activities must be in accordance with Graysonline contractor procedures and are to be collected by appointment
More informationDescription of the Task/Activity: General door/window fitting/replacement. Start Date/Time: Site Address/ Location: Finish Date/Time:
Method Statement This method statement is to be read in conjunction with the attached risk assessments and the Wembley Windows (SC) Ltd Health and Safety Policy and Procedures Manual. Description of the
More informationTHE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY
THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY CONTENTS Page No 1 INTRODUCTION 2 2 LEGISLATION 2 3 HIERARCHY OF CONTROL 2 4 WORK AT HEIGHT POLICY 3 5 ROLES AND RESPONSIBILITIES 3 6 RISK ASSESSMENTS
More informationAsbestos Management Policy (Version 3)
Asbestos Management Policy (Version 3) Contents Page Introduction 3 College Policy Statement for Asbestos Management 3 Objectives (of this Policy and Procedure) 3 Application of Policy 4 Licensed Asbestos
More informationASBESTOS in state and local government
ASBESTOS in state and local government Inspection campaign In 2013/14, WorkSafe WA is conducting a proactive inspection campaign focusing on the management of asbestos in state and local government buildings.
More informationLevel 1 Award in Health and Safety in a Construction Environment
Level 1 Award in Health and Safety in a Construction Environment Student notes (sample) www.britsafe.org Membership Training Qualifications Audit and Consultancy Audit and Policy Consultancy and Opinion
More informationConstruction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot
Construction Management Statement Residential development at Bywell House, St Mary s Hill, Ascot Parking of Vehicles of Site Personnel, Operatives and Visitors Site staff, visitors to the development and
More informationASBESTOS AND THE HOME RENOVATOR. A basic guide on what you need to know about asbestos
ASBESTOS AND THE HOME RENOVATOR A basic guide on what you need to know about asbestos DISCLAIMER This publication contains information regarding occupational health and safety. It includes some of your
More informationAsbestos in your home
Asbestos in your home How to dispose of Asbestos safely Telephone Number: 01372 732000 contactus@epsom-ewell.gov.uk www.epsom-ewell.gov.uk If you would like a copy of this document in large print, on tape
More informationIndependent Contractor Policy
Independent Contractor Policy This Policy has been implemented to prevent accidents and personal injuries. It is not intended to be entirely inclusive. It is the responsibility of the Independent Contractor
More informationSafety Training Needs Assessment
Safety Needs Assessment Form Instructions: Please review each question and either check YES or NO. If a question is checked YES you will be required to complete the training topic before initial assignment
More informationPolicy on the Management of Asbestos
WISHAW AND DISTRICT HOUSING ASSOCIATION Policy on the Management of Asbestos As with all the Association s policies and procedures, this document, where required, may be able to be translated into other
More informationCONTRACTOR INDUCTION HANDBOOK
CONTRACTOR INDUCTION HANDBOOK POLICY The health and safety of all school employees and contractor employees is a vital concern at the school. Contract personnel will be treated in a manner consistent with
More informationEnvironmental Protection Information Sheet: 2. Advice on Asbestos
Environmental Protection Information Sheet: 2 Advice on Asbestos A s b e s t o s Asbestos is a natural mineral, which has been widely used in construction materials and in articles within the home for
More informationTable of Contents Introduction How to Use This Manual How to Do a Facility Audit
Table of Contents Introduction How to Use This Manual How to Do a Facility Audit OSHA Plant Safety Audit Checklist: Self-Inspection Types of Hazards Addressing the Hazards in Your Work Area Safety and
More informationDocument ref: MG(M)201 Version no: 01 Page no: 1 / 12. Contractor rules
Page no: 1 / 12 Contractor rules Table of Contents Purpose... 2 Scope... 2 1. Responsibilities... 2 2. Planning Stage... 3 3. Site induction, emergency procedures and documentation... 3 4. Risk Assessment
More informationThe asbestos crisis. Why Britain needs an eradication Law. Background. Levels of mortality
The asbestos crisis. Why Britain needs an eradication Law. The All-Party Parliamentary Group on Occupational Safety and Health believes that the time has come to put in place regulations requiring the
More informationThe asbestos crisis Why Britain needs an eradication law
Why Britain needs an eradication law All-Party Parliamentary Group on Occupational Safety and Health The All-Party Parliamentary Group on Occupational Safety and Health believes that the time has come
More informationBILL WHYTE FLOORCOVERINGS LTD UNIT 5 KINGS COURT KING ST LEYLAND LANCS PR269RL. Tel: 01772 432120 METHOD STATEMENT
BILL WHYTE FLOORCOVERINGS LTD UNIT 5 KINGS COURT KING ST LEYLAND LANCS PR269RL Tel: 01772 432120 METHOD STATEMENT Prepared For The Main Activities / Operations Performed By The Employees Of Bill Whyte
More informationWOLVERHAMPTON WASTE SERVICES GUIDANCE FOR THE SAFE REMOVAL, COLLECTION AND DISPOSAL OF MATERIALS CONTAINING ASBESTOS OR ASBESTOS CEMENT
WOLVERHAMPTON WASTE SERVICES GUIDANCE FOR THE SAFE REMOVAL, COLLECTION AND DISPOSAL OF MATERIALS CONTAINING ASBESTOS OR ASBESTOS CEMENT IMPORTANT PLEASE ENSURE THAT YOU READ AND UNDERSTAND THE GUIDANCE
More informationPolicy for the Management of Asbestos in the Workplace
Southwark Council Management of Asbestos in the Workplace November 2011 Page 1 of 15 CONTENTS 1. INTRODUCTION... 3 2. POLICY STATEMENT... 3 3. ASBESTOS RISK CLASSIFICATION SCHEME... 5 4. SAMPLING OF ASBESTOS
More informationHATFIELD TOWNSHIP DEMOLITION PERMIT APPLICATION PROCEDURES
HATFIELD TOWNSHIP DEMOLITION PERMIT APPLICATION PROCEDURES A demolition permit is required for complete demolition of residential or non-residential structures. PART I Location of Property Complete address
More informationConstruction and Civil Work Management
STANDARD LME-12:001901 Uen Rev A Contents 1 Introduction... 3 2 Definitions... 3 3 Requirements... 4 3.1 General... 4 3.2 Responsibilities... 4 3.3 OHS Safety Plan... 5 3.4 Start of Construction Phase...
More informationSprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW
Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW August 2006 NSW Department of Commerce Parsons Brinckerhoff Australia Pty Limited ACN 078 004 798 and Parsons
More informationContractor s Safe Working Agreement
Contractor s Safe Working Agreement This statement provides details on how I/we, the Trade Contractor will manage the health and safety hazards associated with my/our work. ASSESSING WORKPLACE HEALTH AND
More informationHealth & Safety Policy For Locations Hosting Film Production Companies
Health & Safety Policy For Locations Hosting Film Production Companies Throughout this document, the location will be referred to as The Venue and the film production company as The Contractor. The following
More informationPolicy for the Management of Asbestos in Buildings
in Buildings Health and Safety Services 1 A1. Introduction If asbestos fibres enter the lungs they can cause cancer or incurable disease. Consequently the University is committed to ensure that all reasonably
More informationSafety and Environmental Information for External Companies Koehler Oberkirch
and al and at Work 1. Delivery, Notice, Signature After receiving the following information sheets, the team leader from every external company is required to read through them, explain them to their employees,
More informationMETHOD STATEMENT INSTALLATION OF INSULATING FLANGE KITS
METHOD STATEMENT INSTALLATION OF INSULATING FLANGE KITS Revision Date Prepared By Approved By Method Statement IF Kits BAC Corrosion Control Limited Stafford Park 11 Telford TF3 3AY Tel: 01952 290321 Fax:
More informationCRITERIA FOR REGISTRATION AS ASBESTOS CONTRACTOR
Published: March 2003 Department of Labour CRITERIA FOR REGISTRATION AS ASBESTOS CONTRACTOR Chief Directorate of Occupational Health and Safety NO: OHC 3 2 1. BACKGROUND In terms of the Asbestos Regulations,
More information1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY
1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY Dumfries Timber Co. Ltd. is committed to comply with our legal duties in order to provide a safe and healthy working environment
More informationWorking at height A brief guide
Working at height A brief guide Introduction This brief guide describes what you, as an employer, need to do to protect your employees from falls from height. It will also be useful to employees and their
More informationWHS CONTRACTOR MANAGEMENT PROCEDURE
1. Overview The Port Augusta City Council as part of its commitment under its WHS Contractor Management policy, recognises its obligation to: Ensure, so far as is reasonably practicable, the health and
More informationPollution Incident Response Management Plan
Pollution Incident Response Management Plan POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN 1. Introduction This Pollution Incident Response Management Plan (PIRMP) has been prepared to describe the processes
More informationUBC Plant Operations Asbestos Work Procedures April 2004
UBC Plant Operations Asbestos Work Procedures April 2004 These Procedures are for use by UBC Plant Operations, Utilities, Housing & Conferences, and IT Services only and are not intended for use by other
More informationAsbestos Management & Abatement
Asbestos Management & Abatement Latest revised date: October 29, 2012 Page 1 of 18 1.0 LEGAL & LEGISLATIVE REQUIREMENTS This standard provides guidance to meeting the minimum requirements of the Act &
More informationWHS Contractor Management Procedure
Wudinna District Council 1. Overview Wudinna District Council as part of its commitment under its Policy recognises its obligation to: Ensure, so far as is reasonably practicable, the health and safety
More informationWhich generic risk assessments are provided? Construction Risk. Assessments Plus. ervices
Which generic risk assessments are provided? Assessments Plus A01 Asbestos Containing Materials A02 Brick/Block Laying A03 Cable Pulling A04 Carpentry/Joinery A05 Concreting Operations A06 Confined Spaces
More informationDIVISION 248 ASBESTOS REQUIREMENTS. Asbestos Emission Standards and Procedural Requirements 340-248-0250. Asbestos Abatement Project Exemptions
DIVISION 248 ASBESTOS REQUIREMENTS Asbestos Emission Standards and Procedural Requirements 340-248-0250 Asbestos Abatement Project Exemptions (1) Any person who conducts or provides for the conduct of
More informationDischarging of Scrap
/ Health & Safety OPERATION STANDARD Ref.: Aperam Safety ST 006 A1 Issue: 15.05.2012 Vers.: v0 Rev.: AM Safety ST 006 -A1 - V0-10.05.2010 Discharging of Scrap Controlled Elaborated by: Checked by: Approved
More informationPart 2. Overview. Risk management. Workplace health and safety legislation. How should asbestos exposure be managed? Identifying asbestos hazards
Part 2. Overview Risk management Workplace health and safety legislation How should asbestos exposure be managed? identify hazards assess risk decide on control measures implement control measures monitor
More informationASBESTOS MANAGEMENT POLICY
ASBESTOS MANAGEMENT POLICY Published : 4th Revision December 2014 1 Table of Contents INTRODUCTION... 3 DUTY TO MANAGE ASBESTOS... 3 DUTIES OF CAMPUS SERVICES... 3 1.0 POLICY OBJECTIVES... 5 2.0 RESPONSIBILITIES...
More informationLIVING WITH FIBRO JUNE 1998 WORKCOVER NSW HEALTH AND SAFETY NOTES. WorkCover. Watching out for you.
LIVING WITH FIBRO JUNE 1998 WORKCOVER NSW HEALTH AND SAFETY NOTES WorkCover. Watching out for you. Disclaimer This publication contains information regarding occupational health, safety, injury management
More informationColorado Department of Public Health And Environment Hazardous Materials and Waste Management Division
Brian Long Solid Waste Compliance Assurance Unit brian.long@state.co.us Richard Mruz Hazardous Waste Corrective Action Unit richard.mruz@state.co.us Colorado Department of Public Health And Environment
More informationWhat is Asbestos Cement and how is it identified?
Regulatory Services Dealing with Asbestos Cement Every year the Council's Environmental Protection team receives a large number of enquiries about garden sheds, garages and house soffits made of asbestos.
More informationASBESTOS REGULATIONS 2001. Government Notice No 155 Gazette No 23108 dated 10 February 2002
ASBESTOS REGULATIONS 2001 Government Notice No 155 Gazette No 23108 dated 10 February 2002 SUMMARY OF THE NEW PROVISIONS: More detailed and streamlined Method of assessment changed (A) INTRODUCTION Exposure
More informationHow to Safely Remove Asbestos
How to Safely Remove Asbestos Code of Practice December 2012 CP113 Workplace Standards Department of Justice This code of practice has been approved by the Tasmanian Minister for Workplace Relations under
More informationSILICA DUST HAZARD ASSESSMENT & WORK PLAN
Part 1 Project Information 1 Prime contractor: 2 Superintendent: 2a Phone: 3 Project: 4 CSO/FA: 4a Phone: 5 Project Address: 6 Site Phone: 6a Site fax: 7 Company doing cement finishing: 8 Subcontractor
More informationManagement of asbestos in recycled construction and demolition waste
Management of asbestos in recycled construction and demolition waste Guide November 2010 Disclaimer This publication may contain occupational health and safety and workers compensation information. It
More informationRegulatory Services. Asbestos in the Home. What is asbestos?
Regulatory Services Asbestos in the Home What is asbestos? Asbestos is a natural silicate mineral consisting of fibres. The fibres are strong, durable, and resistant to heat, long, thin and flexible. There
More informationAUDIT OF DET ASBESTOS MANAGEMENT IN QUEENSLAND SCHOOLS
AUDIT OF DET ASBESTOS MANAGEMENT IN QUEENSLAND SCHOOLS Conducted By GASKIN CONSTRUCTION SERVICES PTY LTD TABLE OF CONTENTS SECTIONS Section 1 Section 2 Section 3 Section 4 Section 5 Section 6 Section 7
More informationConstruction Notification and Start-Up
The University of British Columbia Land and Building Services Prepared by: Frank Geyer Work Procedure Approved by: David Barnes Construction Notification and Start-Up Issue Date: 08 October 2002 Replaces:
More informationTremline Pty Ltd trading as The Hills Bark Blower
JSA No: Rev: 10011 Date: 10010 ABN 1 07 880 6 Website: wwwbarkblowercomau Job Number Start Time: Vehicle : Max Length Hose Date: Company Name: Product: Quantities Depth Job site address: Description of
More informationwww.suttonhousingpartnership.org.uk Asbestos
www.suttonhousingpartnership.org.uk Asbestos images courtesy of www.sxc.hu and/or www.morguefile.com Asbestos Asbestos was widely used until the 1980 s to improve the performance of materials and to provide
More informationAsbestos is found naturally in rock formations around the world. It is made up of lots of small fibres.
Your Guide to Asbestos March 2010 Many people worry about the health risks of asbestos, but as long as it is not damaged it is unlikely to cause problems. This booklet tells you what you need to know.
More informationSTANDARD OPERATING INSTRUCTION. Safe Handling and Removal of Asbestos Cement Pipes Procedure
STANDARD OPERATING INSTRUCTION Safe Handling and Removal of Asbestos Cement Pipes Procedure 1 July 2012 Title System Reference Number Approved By Safe Handling and Removal of Asbestos Cement Pipes People
More informationOccupational health and safety specification for construction works contracts
Occupational health and safety specification for construction works contracts 30 th November 2012 (Draft) Comment on this standard may be submitted by 08 February 2013 to: The Director-General National
More informationAsbestos in the home. Health and safety in the home. Asbestos in the home A
Asbestos in the home Health and safety in the home Asbestos in the home A Did you know? Asbestos is the name given to a group of fibrous silicate minerals that can potentially cause lung disease if inhaled.
More informationTemporary Batch Plants
Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category
More informationENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS
ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS PREPARED BY: DEPARTMENT OF ENVIRONMENT AND LANDS INDUSTRIAL ENVIRONMENTAL ENGINEERING DIVISION APRIL 16, 1992 - TABLE OF
More informationDEMOLITION PERMIT CHECKLIST* B.H.M.C. Section 10-3-4201
GEORGE CHAVEZ, City Building Official DAVID YELTON, Building Inspection Manager NESTOR OTAZU, Community Preservation Manager BUILDING & SAFETY DIVISION 455 North Rexford Drive, 1 st Floor Beverly Hills,
More informationSAFETY AND ENVIRONMENTAL INFORMATION FOR EXTERNAL COMPANIES. Koehler Kehl
1. Delivery, Notice, Signature After receiving the following information sheets, the team leader from every external company is required to read through them, explain them to their employees, and after
More informationRutgers Environmental Health and Safety
Rutgers Environmental Health and Safety PCB Self-Audit (TSCA Program) Facility Name: Rutgers University, Facility Address: Facility EPA Identification Number: Date of Self-Audit Inspection: Campus/Farm/Field
More informationASBESTOS MATERIALS IN SCHOOLS
CODE OF PRACTICE FOR MANAGEMENT OF ASBESTOS MATERIALS IN SCHOOLS CONTENTS 1. Introduction 1.1 Scope 1.2 The OPW Health and Safety Unit 2 Background 2.1 General Information 2.2 Main Risks 2.3 Main Risk
More informationHOW TO SAFELY REMOVE ASBESTOS
HOW TO SAFELY REMOVE ASBESTOS Code of Practice DECEMBER 2011 Safe Work Australia is an Australian Government statutory agency established in 2009. Safe Work Australia consists of representatives of the
More informationRSPH Level 3 Certificate in Asbestos Project Management. February 2013. 10 Guided Learning Hours 2 Prior Learning Hours
RSPH Level 3 Certificate in Asbestos Project Management February 2013 10 Guided Learning Hours 2 Prior Learning Hours Description The Control of Asbestos Regulations impose duties on every person who has,
More informationManaging the risk of falls while working on roofs in housing construction
Workplace Health and Safety Queensland Managing the risk of falls while working on roofs in housing construction Where the risk of falling is 3 metres or more (or roof slope over 26 ) Before you start
More informationPAINT REMOVAL SYSTEM PAINT REMOVAL SPECIFICATION SAFE WORK METHOD STATEMENT FOR LEAD PAINT REMOVAL
PAINT REMOVAL SYSTEM PAINT REMOVAL SPECIFICATION SAFE WORK METHOD STATEMENT FOR LEAD PAINT REMOVAL CONTENTS: 1.0 AWARENESS AND PRECAUTION 2.0 TEST SAMPLING & REMOVAL EVALUATION 3.0 SITE EVALUATION 4.0
More informationSchneps, Leila; Colmez, Coralie. Math on Trial : How Numbers Get Used and Abused in the Courtroom. New York, NY, USA: Basic Books, 2013. p i.
New York, NY, USA: Basic Books, 2013. p i. http://site.ebrary.com/lib/mcgill/doc?id=10665296&ppg=2 New York, NY, USA: Basic Books, 2013. p ii. http://site.ebrary.com/lib/mcgill/doc?id=10665296&ppg=3 New
More informationKAWERAU DISTRICT COUNCIL BUSINESS DISASTER RECOVERY PLAN 2011
KAWERAU DISTRICT COUNCIL BUSINESS DISASTER RECOVERY PLAN 2011 Kawerau District Council Private Bag 1004 Ranfurly Court KAWERAU 3169 Tel (07) 306 9009 Fax (07) 323 8072 Email kaweraudc@kaweraudc.govt.nz
More informationAsbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material
Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material Revised November 21, 2013 Application Code of Practice Where asbestos is present or believed to be present in a workplace
More informationConstruction Management Statement. Introduction. Contents
Construction Management Statement Project Name Dee Point Primary School Introduction On all Morgan Sindall projects, the safety and welfare of all is of paramount importance. This document concentrates
More informationOSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION
OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION Table of Contents Executive Summary... 1 Introduction... 1 Installing
More informationFor ease of reference the clauses are arranged in 12 sections as follows:-
NASC TERMS The general NASC terms under which members carry out their work are normally set out in their Standard Terms of Trading, often found on the reverse of their quotation form and referred to as
More informationTool Box Talk. Forklift Operations
Tool Box Talk Forklift Operations Treat them with respect 40k for H40, 62k for H70 Mercedes CL, Jaguar Daimler or XKR, Porsche Carrera 4S 40k, same price as H40 treat them the same! 62k, same price as
More informationAsbestos Disposal in the Northern Territory
Information on the requirements for the disposal of Asbestos in the Northern Territory Scope These guidance notes have been developed to assist industry, local government, consultants and other relevant
More informationKEEP ASBESTOS YOUR QUICK GUIDE DON T BE AN EASY TARGET THIS GUIDE
KEEP THIS GUIDE ASBESTOS YOUR QUICK GUIDE DON T BE AN EASY TARGET Asbestos could be in the house or building you are working on right now. Left alone, it isn t dangerous. However, once disturbed, tiny
More informationBritish Columbia Institute of Technology. BCIT Safety Manual ASBESTOS MANAGEMENT
BCIT Safety Manual Contents 1. Purpose... 3 2. Definitions... 3 2.1 Asbestos... 3 2.2 Asbestos Containing Material (ACM)... 3 2.3 Friable Material... 3 2.4 Low Risk Work Activity... 3 2.5 Moderate Risk
More informationControl Provisions under the Air Pollution Control Ordinance
ProPECC PN 2/97 ENVIRONMENTAL PROTECTION DEPARTMENT PRACTICE NOTE FOR PROFESSIONAL PERSONS Handlin of Asbestos Containin Materials in Buildins Introduction Asbestos is a generic name given to a group of
More informationCONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP)
CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP) [Colston Budd Hunt & Kafes Pty Ltd AS AMENDED BY City of Sydney] 23 March 2010 1. PREAMBLE 1.1 This document constitutes the Demolition and Traffic Management
More informationCHAPTER 10. FALL PROTECTION PROGRAM
CHAPTER 10. FALL PROTECTION PROGRAM 1000 GENERAL. This chapter establishes policy for developing fall protection programs to protect all Federal Aviation Administration (FAA) personnel working at elevated
More informationSafety Systems Review Facilities Management Guidance and specification Version 1 2014
Safety Systems Review Facilities Management Guidance and specification Version 1 2014 Membership Training Qualifications Audit and Consultancy Policy and Opinion Awards Contents Page Safety Systems Review
More informationPERSONAL PROTECTIVE EQUIPMENT HAZARD ASSESSMENT, EQUIPMENT SELECTION AND TRAINING DOCUMENTATION
DRAFT SAMPLE WRITTEN PERSONAL PROTECTIVE EQUIPMENT HAZARD ASSESSMENT, EQUIPMENT SELECTION AND TRAINING DOCUMENTATION For Compliance With 1910.132 Wyoming General Rules and Regulations Wyoming Department
More informationUNOFFICIAL. 1. Owner: Delaware Department of Transportation (DelDOT) WEBSITE
SECTION 01013 - SUMMARY OF THE WORK - ASBESTOS ABATEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationControl of Asbestos. Blue crocidolite Brown amosite White chrysotile
Control of Asbestos Asbestos has been the main cause of occupational ill health from about 1950 onwards and is still the greatest single work related cause of death from ill health. Past exposure is now
More informationTraffic Management Issue 1.0 Revision: v2 October 2014
Disclaimer IMPORTANT: The information in this guide is of a general nature, and should not be relied upon as individual professional advice. If necessary, legal advice should be obtained from a legal practitioner
More informationHow a client and contractor working together can benefit both partners, and ensure work is carried out with good standards of health and safety.
2.5 WORK AT HEIGHT - FALL PROTECTION DURING ROOF WORK A PARTNERSHIP APPROACH BETWEEN CLIENT AND CONTRACTOR Interbrew UK Ltd Samlesbury Brewery Cuerdale Lane Samlesbury Preston PR5 0XD United Kingdom Tel:
More information