Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.
|
|
- Alexis Boyd
- 8 years ago
- Views:
Transcription
1 Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir Presented By: Doug Stachler, P.E.
2 Project Organization Owner Delaware County Engineers Office Design Consultant CH2M HILL Contractor Double Z Construction Geotechnical Subconsultant BBC&M Survey Subconsultant Canter Surveying
3 Project Background Bridge carries local traffic over Hoover Reservoir Recreational boat waterway Drinking water source for the City of Columbus Popular Bicycle Route
4 Project Background Existing Bridge Built in 1954 Total Bridge Length = 182 Bridge Width = 26-0 (f/f barrier) 3-Span Steel Rolled Beam Bridge Standard Jointed Type Abutments Located within limits of 1200-foot sag vertical curve
5 Purpose of Project Deterioration of Bridge Deck & Steel Beams
6 Purpose of Project Deterioration of Concrete Curbs & Steel Railing
7 Purpose of Project Steel Railing Anchored into Concrete Curb Anchorage for the Bridge Railing is IMPORTANT
8 Purpose of Project Deterioration of Abutment Backwalls
9 Factors Attributed to Bridge Deterioration 55 Years of Ohio Winters Low Point of Sag Vertical Curve Located on Bridge Over-the-deck Drainage
10 Project Goals Replace existing bridge deck and rolled beams Convert existing jointed type abutment to semiintegral type Remove abutment backwall but patch and reuse existing abutment pile cap
11 Project Goals Provide a new bridge deck with increased width Meet current roadway design standards Provide additional safety for bicyclists
12 Project Goals Reuse as much of existing piers as possible
13 Project Goals Modify roadway profile to shift low point of sag vertical curve off of the bridge Location of Low Point on Existing Profile
14 Project Goals Keep all proposed work above the Ordinary High Water Mark (OHWM) to avoid necessary permits with the Army Corps of Engineers
15 Project Approach Traditional Bridge Design Process Red Bank Bridge Design Process Design Superstructure Design Superstructure Design Substructure NO Is Existing Substructure Design Sufficient? YES Design Foundation NO Is Existing Foundation Design Sufficient? YES Design Complete Design Complete
16 Superstructure Replacement Original Bridge New Bridge Steel Rolled Beams Size Fy Spacing W33x ksi 7-4 W33x ksi 8-8 Bridge Deck F/F Curb or Barrier Overhang Total Superstructure Depth ½ ¾ Over-the-deck drainage system with steel tube railing allows the total out-to-out deck dimension to match the face-to-face barrier dimension Use Steel Drip Strip rather than Concrete Curb and Gutter Increase design live load to HS-25 & design for 60 psf FWS New superstructure is composite design
17 Modified Twin Steel Tube Railing
18 Pier Design Increased bridge deck width required the existing pier caps to be replaced and widened Pier cap cantilever increased by 21 Pier cap depth increased by approximately 6
19 Pier Design Developed a structural model of existing pier columns and existing pier footing Structural properties of existing pier members was based on original construction plans Geotechnical investigations performed to verify existing footing elevations and soil bearing capacity for existing footings Finite element analysis confirmed capacity of existing spread footings
20 Abutment Design Existing deteriorated backwalls were removed and replaced with semi-integral integral abutment diaphragm Top portion of existing abutment beam seats, and existing wingwalls were removed and replaced
21 Abutment Design Abutment pile cap was widened and 4 new piles were added to accommodate the widened superstructure
22 Roadway Profile Adjustment New pier caps and new abutment seats easily allowed for adjustments to roadway profile. Sag vertical curve was slightly adjusted to relocate the low point of the sag to just beyond the forward approach slab Allowed for runoff to be collected into a catch basin rather than over the side of the structure Although over-the-side runoff still exists
23 Manage Runoff Water Quality Worked with City of Columbus Watershed Department and recommended ODOT approved BMP s Low cost exfiltration trenches used on curbed bridge approaches to minimize contaminant- laden runoff to protect the water quality in the reservoir
24 Challenges During Construction Special care had to be taken to keep all construction debris, stormwater runoff, and hazardous chemicals out of the reservoir Demolished the existing deck by sawing deck into small slabs that could be removed with hydraulic excavators Beams were also cut into short sections and then removed Existing overlay was left on the deck surface to prevent the slab from breaking up under the weight of the demo equipment Pier false-work was designed to accommodate both the removal of the pier caps and for supporting the new pier caps
25 Project Cost Federal Funding Secured = $1,426,440 Final Engineer Cost Estimate = $965,000 Contract Award = $914,357 6 bids received Competitive and tightly clustered bids Throughout construction there were no design-related change orders and the overall project was under the contract amount
26 Project Complete
27 Summary Improved the safety for travelling public Repaired existing deterioration while at the same time, provided remedies to help mitigate future deterioration to new bridge Reused as much of existing bridge as possible to make project cost-effective All done while being conscientious about maintaining water quality in the reservoir
2015 ODOT Bridge Design Conference May 12, 2014. DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement.
2015 ODOT Bridge Design Conference May 12, 2014 DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement Mary Ann Triska 2015 HDR, all rights reserved. Presentation Outline Project
More information3.1 Historical Considerations
3. Recommended Scope of Bridge improvements 3.1 Historical Considerations In the fall of 2000, an outside consultant, Fraser Design, suggested that the existing 4 th St. Bridge is potentially eligible
More informationPaving Capitalization Work Categories and Treatments
Statement of ODOT Infrastructure Capitalization Policy Government Accounting Standards Board (GASB) 34 requires public agencies to capitalize infrastructure assets on their financial statements for periods
More informationAPPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.
Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations
More informationIH-635 MANAGED LANES PROJECT, SEG. 3.2
IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,
More informationFEBRUARY 2014 LRFD BRIDGE DESIGN 4-1
FEBRUARY 2014 LRFD BRIDGE DESIGN 4-1 4. STRUCTURAL ANALYSIS AND EVALUATION The analysis of bridges and structures is a mixture of science and engineering judgment. In most cases, use simple models with
More informationNational Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination
Structural Effective Beginning with the April 2011 The structural engineering exam is a breadth and exam examination offered in two components on successive days. The 8-hour Vertical Forces (Gravity/Other)
More informationInformational Workshop Public Meeting Kanawha Falls Bridge Project
Informational Workshop Public Meeting Kanawha Falls Project WV Department of Transportation Division of Highways in Cooperation with the Federal Highway Administration State Project S310-13-0.02 00 Federal
More informationThe unit costs are based on the trend line of the 3 low bids for the average quantity.
Page 1 of 8 COST ESTIMATE GENERAL INSTRUCTIONS The unit costs are based on the trend line of the 3 low bids for the average quantity. Apply the Unit Costs to ordinary structures. Unit Costs should generally
More informationSafe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
More information~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway:
Texas Depadment of Transpo,tation Bridge Condition Survey Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway: Irving Street Facility Name: Lone Wolf Bridge Structure Number: B00315-031
More informationPublic Information & Public Scoping Meeting
Public Information & Public Scoping Meeting William F. Cribari Memorial Bridge Route 136 over the Saugatuck River Review of Rehabilitation Study Report Public Scoping for the gathering and analysis of
More informationPage & Turnbull imagining change in historic environments through design, research, and technology
DCI+SDE STRUCTURAL EVALUATIONS OFFICE BUILDING, TOOL SHED & WATER TANK, AND BLACKSMITH & MACHINE SHOP BUILDINGS SAN FRANCISCO, CALIFORNIA [14290] PRIMARY PROJECT CONTACT: H. Ruth Todd, FAIA, AICP, LEED
More informationDesign of Bridges. Introduction. 3 rd to 4 th July 2012. Lecture for SPIN Training at the University of Dar es Salaam
Design of Bridges Introduction 3 rd to 4 th July 2012 1 FUNCTION OF A BRIDGE To connect two communities which are separated by streams, river, valley, or gorge, etc. 2 EVOLUTION OF BRIDGES 1. Log Bridge
More informationCAPPELEN MEMORIAL BRIDGE REHABILITATION
CAPPELEN MEMORIAL BRIDGE REHABILITATION Owner: Hennepin County Engineering: HNTB with Olson-Nesvold Engineering (ONE) and others Section 106 Historical Committee: Hennepin County, MnDOT Cultural Resources
More informationStructures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS
Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS 1 Proposal & Plans Received? 2 Review Proposal, highlight important facts. Know proposal well to be able to find answers quickly.
More informationBRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM
BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM Swaminathan Srinivasan, P.E., M.ASCE H.C. Nutting/Terracon David Tomley, P.E., M.ASCE KZF Design Delivering Success for
More informationTable 4.9 Storm Drain Inlet Protetion Applicable for
BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection
More informationRed Wing Bridge Project. PAC #5/TAC #8 Meeting July 18, 2013
Red Wing Bridge Project PAC #5/TAC #8 Meeting July 18, 2013 Alternatives Analysis Agenda Overview of Past Progress Progress Since April PAC Bridge 9103 Rehabilitation Study Bridge 9040 Rehab vs. Replacement
More informationAlberta Transportation Bridge Inspection & Maintenance System (Web 2005) 00747-1 Bridge. Bridge Inspection. Assistant Name Assistant Class
Bridge File Number Year Built/Year Supstr 00747-1 Bridge 1964/1964 Bridge or Town Name SUNNYSLOPE Located Over Located On 582:04 C1 33.896 Water Body Cl./Year Navigabil. Cl./Year Legal Land Location KNEEHILLS
More informationChallenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26
2014 HDR Architecture, 2014 2014 HDR, HDR, Inc., all all rights reserved. Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26 Brandon Chavel, PhD, P.E.,
More informationMicropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com
More informationREPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE MAULE EARTHQUAKE
Proceedings of the International Symposium on Engineering Lessons Learned from the 2011 Great East Japan Earthquake, March 1-4, 2012, Tokyo, Japan REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE
More informationHIGHWAYS ASSET MANAGEMENT STRUCTURES TEAM GUIDANCE NOTE SMT/GN/03/10 TECHNICAL APPROVAL
HIGHWAYS ASSET MANAGEMENT STRUCTURES TEAM GUIDANCE NOTE SMT/GN/03/10 TECHNICAL APPROVAL Rev Purpose of Issue Originated Reviewed Authorised Date 0 First issue Anil Kumar Ken Duguid Stephen Pottle 21-07-2010
More informationSECTION 1 GENERAL REQUIREMENTS
Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,
More informationREPORTS & PRESENTATIONS AGENDA ITEM #III-3 CORTEZ BRIDGE PROJECT DEVELOPMENT AND ENVIRONMENT (PD&E) STUDY
NOTES REPORTS & PRESENTATIONS AGENDA ITEM #III-3 CORTEZ BRIDGE PROJECT DEVELOPMENT AND ENVIRONMENT (PD&E) STUDY Presenter: Summary: Tony Sherrad, FDOT Project Manager The Cortez Bridge in Manatee County,
More informationPENNDOT e-notification
PENNDOT e-notification Bureau of Project Delivery Bridge Design and Technology Division BRADD No. 036 October 18, 2013 Release of BRADD Version 3.2.0.0 The next release of PennDOT's Bridge Automated Design
More informationBRIDGES ARE relatively expensive but often are
Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the
More informationCITY OF TRAIL MEMORANDUM
0 C CITY OF TRAIL MEMORANDUM DATE: TO: FROM: SUBJECT: March 24, 2011 FILE NO. 5400-02 DAVID PEREHJJDOFF, CHIEF ADM1NTSTRATIVE OFFICER WARREN PROULX, ENGINEERING TECHMCIAN OLD TRAIL BRIDGE With the interest
More informationEmergency repair of Bridge B421
Emergency repair of Bridge B421 over the Olifants River after fl ood damage INTRODUCTION AND BACKGROUND Bridge B421 is located on the R555 at km 5.03 on Section 01E between Witbank (now known as emalahleni)
More informationEvaluation of Appropriate Maintenance, Repair and Rehabilitation Methods for Iowa Bridges
T. J. Wipf, F. S. Fanous, F. W. Klaiber, A. S. Eapen Evaluation of Appropriate Maintenance, Repair and Rehabilitation Methods for Iowa Bridges April 2003 Sponsored by the Iowa Department of Transportation
More information5 ALTERNATIVE SOLUTIONS AND EVALUATION
Page 23 5 ALTERNATIVE SOLUTIONS AND EVALUATION The process used for the assessment and evaluation of the alternatives follows the procedures of the Municipal Class EA, as described below: Identify a reasonable
More informationPENNDOT 3D MODELING FOR STRUCTURES WORKSHOP. Presented by: Steven Pletcher and Chris Daniels, P.E. October 21, 2014
PENNDOT 3D MODELING FOR STRUCTURES WORKSHOP Presented by: Steven Pletcher and Chris Daniels, P.E. October 21, 2014 Agenda Introduction G.A. & F.C. Wagman History Process used to prepare 3D models Estimating
More informationThe Rehabilitation Alternative Huey P. Long Bridge Case Study. Bruce E. Peterson, P.E. Project Manager Modjeski and Masters, Inc.
The Rehabilitation Alternative Huey P. Long Bridge Case Study Bruce E. Peterson, P.E. Project Manager Modjeski and Masters, Inc. March 22, 2010 Replacement vs. Rehabilitation Project Background Introduction
More informationPUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE
REGION OF PEEL PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE Storm Sewer Design Criteria REVISED July 2009 PUBLIC WORKS STORM SEWER DESIGN CRITERIA TABLE OF CONTENTS 1.0
More informationI-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA. PSPE Presentation, December 3, 2015
I-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA PSPE Presentation, December 3, 2015 Location Map N PROJECT LOCATION 22 nd 18 th Streets PHILADELPHIA, PA General
More informationCERTIFIED TECHNICIAN PROGRAM TRAINING MANUAL. Bridge Construction and Deck Repair
CERTIFIED TECHNICIAN PROGRAM TRAINING MANUAL Bridge Construction and Deck Repair Revised 2014 This material is to be used for training purposes only. Some of the procedures, field tests, and other operating
More informationENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE
ENGINEERED FOUNDATIONS Department of Public Works Jeff Hill, PE What is an engineered foundation. A Foundation Design Developed by a Trained Professional (Engineer) Types of Foundations (All of which can
More informationRoadway Cost Per Centerline Mile Revised June 2014
Rural Arterial From LRE MOT * Mobilization * Subtotal Total PE Design (15%) CEI (15%) Total Project ** New (2-Lane Roadway) with 5' Paved Shoulders $3,351,896 $335,190 $368,709 $4,055,794 $1,013,949 $5,069,743
More informationQuality Control and Quality Assurance Guide
Quality Control and Quality Assurance Guide Bridge Division, Design Section October 2013 Table of Contents Chapter 1 About this Guide... 3 Chapter 2 Goals and Objectives... 5 Chapter 3 Participants...
More information700 Life-Cycle Cost Analysis... 700-1
Table of Contents 700 Life-Cycle Cost Analysis... 700-1 701 Introduction... 700-1 701.1 Discount Rate... 700-1 702 Initial Construction... 700-1 703 Future Rehabilitation... 700-1 703.1 Introduction...
More informationSECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway.
Page 1 Revised 3/2/10 See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway. For New/Reconstruction projects: The cross slope of the driving lanes range from 1.5% to
More informationMEMORANDUM. 1509 West Swann Avenue, Suite 225 Tampa, Florida 33606 Phone (813) 258-8818 Fax (813) 258-8525
1509 West Swann Avenue, Suite 225 Tampa, Florida 33606 Phone (813) 258-8818 Fax (813) 258-8525 To: From: Date: Subject: Mr. Thomas Gibson, City of St. Petersburg Jeffrey D. Malyszek, PE and Deborah C.
More informationCONCEPTUAL REHABILITATION ALTERNATIVE
Appendix D While federal law requires preservation/rehabilitation of historic bridges be considered, there is no standard procedure to determine when rehabilitation is appropriate and when replacement
More informationREPAIR AND STRENGTHENING OF HISTORICAL CONCRETE BRIDGE OVER VENTA RIVER IN LATVIA
1 REPAIR AND STRENGTHENING OF HISTORICAL CONCRETE BRIDGE OVER VENTA RIVER IN LATVIA Verners Straupe, M.sc.eng., Rudolfs Gruberts, dipl. eng. JS Celuprojekts, Murjanu St. 7a, Riga, LV 1024, Latvia e-mail:
More informationREHABILITATION PACKAGE 1-a
1-a WINONA BRIDGE (BRIDGE 5900) REHABILITATION PACKAGE 1-a Rehab option 1-a is a rehabilitation package whereby all spans of the existing structure would be rehabilitated to the degree feasible and strengthened
More informationUncovered Decks & Porches
Uncovered Decks & Porches Building Guides for Homeowners Why Do I need a Permit? D I D Y O U K N O W? As owner-builder you are the responsible party of record on such a permit. If your work is being performed
More informationBMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.
BMP-7 BMP: STORM DRAIN INLET PROTECTION Definition A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. To prevent sediment from entering storm drainage systems
More informationVirginia Approach Spans
Virginia Concrete Conference 2009 Woodrow Virginia Approach Spans David Tackoor, HNTB Formerly of URS Corp for Potomac Crossing Consultants Woodrow 1 Second Severn Crossing 2 Medway Crossing (Channel Tunnel
More informationSTORM DRAINS CHAPTER 7
CHAPTER 7 Chapter 7 - Storm Drains A storm drain is a drainage system that conveys water or stormwater, consisting of two or more pipes in a series connected by one or more structures. Storm drains collect
More informationJ. David Rogers Natural Hazards Mitigation Center University of Missouri-Rolla
New Challenges for Army Combat Engineers: Bomb Damage Assessment, Fire Damage Assessment, Evaluation of Diminished Capacity, and Developing New Strategies for Short, Medium and Long-term Mitigation/Repair
More informationOverhang Bracket Loading. Deck Issues: Design Perspective
Deck Issues: Design Perspective Overhang Bracket Loading Deck overhangs and screed rails are generally supported on cantilever brackets during the deck pour These brackets produce an overturning couple
More informationUS 51 Ohio River Bridge Engineering and Environmental Study
US 51 Ohio River Bridge Engineering and Environmental Study ITEM NOS. 1-100.00 & 1-1140.00 Prepared by: Michael Baker Jr., Inc. 9750 Ormsby Station Rd Louisville, KY 40223 August 16, 2013 Table of Contents
More informationLOAD TESTING OF SOME NEW BRIDGES IN LATVIA
LOAD TESTING OF SOME NEW BRIDGES IN LATVIA Edmunds Akimovs, Civ.Eng., Bridge Engineer, Consulting Company Inzenierbuve, Address: Azenes st. 20, Riga, LV1048, Latvia. E-mail: eakimovs@inzenierbuve.lv Ainars
More informationSteve Brinkman Alain Pinel Realtors 167 S San Antonio Road Los Altos, CA 94022 RE: Foundation Inspection for 162 Del Monte Ave. Los Altos, CA 94022
M G C O N S T R U C T O R S & E N G I N E E R S, I N C. I N S P E C T O R S E N G I N E E R S B U I L D E R S C A L I F O R N I A E N G I N E E R I N G A N D B U I L D I N G L I C E N S E A / B 6 4 2 0
More informationTable of Contents. July 2015 12-1
Table of Contents 12.1 General... 3 12.2 Abutment Types... 5 12.2.1 Full-Retaining... 5 12.2.2 Semi-Retaining... 6 12.2.3 Sill... 7 12.2.4 Spill-Through or Open... 7 12.2.5 Pile-Encased... 8 12.2.6 Special
More informationRHODE ISLAND TURNPIKE AND BRIDGE AUTHORITY NEWPORT/PELL BRIDGE APRIL 1, 2014 TEN YEAR RENEWAL AND REPLACEMENT PLAN (IN 2013 DOLLARS)
APRIL, 04 TEN YEAR RENEWAL AND REPLACEMENT PLAN (IN 03 DOLLARS) 3/8/04 July 03- June 04 July 04- June 05 July 05- June 06 July 06- June 07 July 07- June 08 July 08- June 09 July 09- June 00 July 00- June
More informationStructure Design Manual
Structure Design Manual MARCH 2015 ILLINOIS STATE TOLL HIGHWAY AUTHORITY The Structure Design Manual dated March 2015 replaces the Structure Design Manual issued March 2014. Revision Summary Article 1.1:
More informationGeotechnical Building Works (GBW) Submission Requirements
Building Control (Amendment) Act 2012 and Regulations 2012: Geotechnical Building Works (GBW) Submission Requirements Building Engineering Group Building and Construction Authority May 2015 Content : 1.
More informationLighthouse Engineering, L.L.C.
Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website: www.lighthouseeng.com Email: Office@LighthouseEng.com Thursday, September 04, 2014 TO: Our Client RE: Initial Engineering
More informationDUDERSTADT FOUNDATION & CONSTRUCTION, LLC.
DUDERSTADT FOUNDATION & CONSTRUCTION, LLC. Drilling since 1916 2215 Belknap Place Phone (210) 824-3800 San Antonio, TX 78212-1904 Fax (210) 824-9525 www.duderstadtfoundation.com ABOUT THE COVER: Drilled
More informationTABLE OF CONTENTS. Section / Article Page
TABLE OF CONTENTS Section / Article Page 1. INTRODUCTION 1.1 Purpose................ 6 1.2 Definitions................ 6 1.3 Guidelines and References............ 7 2. AGREEMENTS 2.1 Applicant and Contractor
More informationSECTION 02100 SITE PREPARATION
SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division
More informationHistoric Bridge Alternatives Analysis Layout
Section 4(f) of the USDOT Act of 1966 (Title 49, USC, Section 303) requires special considerations be made regarding the use of any publicly owned park, recreation area, wildlife/waterfowl refuge or historic
More informationMobile Mapping Solutions for Ohio s Integrated Transportation Network. Brad Fugate, CP Nathan Fischer, PE
Mobile Mapping Solutions for Ohio s Integrated Transportation Network Brad Fugate, CP Nathan Fischer, PE About Woolpert Established in 1911 Over 600 Professionals 25 Offices $12,000,000 invested in new
More informationSCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM
Shepherd University Board of Governors June 9, 2005 Agenda Item No. 9 SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM In 1994 construction began on the Byrd Science and
More informationSECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or
More informationChapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
More informationHow To Check For Scour At A Bridge
Case Studies Bridge Scour Inspection and Repair Edward P. Foltyn, P.E. Senior Hydraulic Engineer ODOT Bridge Unit 2013 PNW Bridge Inspectors Conference April 2013 REFERENCES Stream Stability at Highway
More informationEXECUTIVE SUMMARY CHAPTER 6
EXECUTIVE SUMMARY CHAPTER 6 This Bridge Development Report was prepared to document the decision process and recommendations for constructing a bridge carrying Maitland Boulevard (eastbound) over I-4 as
More informationDate. Resubmit this form during the year if there are changes in your company ownership or financial standing.
COLORADO DEPARTMENT OF TRANSPORTATION CONTRACTOR PREQUALIFICATION STATEMENT (EXPERIENCE, EQUIPMENT AND FINANCIAL) Return to: Contracts & Market Analysis Prequalification Unit 4201 E. Arkansas,4th Floor
More informationRole of Underwater Substructure Inspections in Bridge Management
Role of Underwater Substructure Inspections in Bridge Management R. RICHARD AVENT MOHAMED ALAWADY DAVID J. MUKAI Louisiana State University INTRODUCTION In the past, the condition of underwater substructures
More informationStorm Drain Inlet Protection
Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category
More informationOctober 30, 2014. Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR. Report of Findings, Structural Investigation, Benton, Arkansas, Dear Mr.
117 S. Market St. Benton, AR 72015 * 501-315-2626 * Fax 501-315-0024 October 30, 2014 Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR Re: Report of Findings,, Benton, Arkansas, Dear Mr. Vick: This
More informationUSE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch
USE OF MICROPILES IN TEXAS BRIDGES by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch DEFINITION OF A MICROPILE A micropile is a small diameter (typically less than 12 in.), drilled and
More informationSTORM WATER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix F
STORM WATER PROJECT COST ESTIMATES & LOCATION MAPS Appendix F RIVERDALE CITY CAPITAL FACILITIES PLAN STORM DRAINAGE Engineer's Cost Estimate January 2009 Project Name: 4400 South Street - Piping and Collection
More informationDisputes and Claims. 3 Processes Dispute Resolution and Administrative Claims Process
Disputes and Claims 3 Processes Dispute Resolution and Administrative Claims Process Default Process C&MS 108.02 Partnering OR PN 108 -Dispute Review Board (DRB) Considered for use on projects over $20
More informationBRIDGE DESIGN MANUAL
BRIDGE DESIGN MANUAL 2003 Edition (U.S. Customary Units) State of Connecticut Department of Transportation Revisions: 7/04, 11/04, 1/05, 3/05, 1/09, 3/09, 2/11 PREFACE The Connecticut Department of Transportation
More informationStructural Performance of Highway Bridges under Given Foundation Settlements
ASEE 2014 Zone I Conference, April 3-5, 2014, University of Bridgeport, Bridgeport, CT, USA. Structural Performance of Highway Bridges under Given Foundation Settlements Zhan Su*; Qian Wang, PhD, PE, Assistant
More informationLong-term serviceability of the structure Minimal maintenance requirements Economical construction Improved aesthetics and safety considerations
Design Step 7.1 INTEGRAL ABUTMENT DESIGN General considerations and common practices Integral abutments are used to eliminate expansion joints at the end of a bridge. They often result in Jointless Bridges
More informationMinimizes sediment and debris from entering storm drains that lead to waterways and watercourses.
4.5-p DRAIN INLET PROTECTION Alternative Names: DI protection, Drop Inlet Protection DESCRIPTION Storm drain inlet (DI) protection slows and ponds stormwater, and filters sediment and debris before it
More informationProject Manager & Key Staff Standards for Technical Proposals Projects using Level A and/or Level B prequalification disciplines
Projects using Level A and/or Level B prequalification disciplines Project Manager PROJECT MANAGER Key Staff/ ROADWAY DESIGN (TP Section 5) (TP Section 6) BACHELORS DEGREE 4 TO 8 YEARS (TP Sections 6 &
More informationA Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN.
A Solid Foundation Solution for Homeowners from Our products are made with 90% Recycled Material Down. Right. Solid. GREEN. Stop the damaging effects of foundation settling... Sinking foundations, cracked
More informationTransportation Infrastructure Asset Management
2015 NW Region TTAP& BIA Symposium Transportation Infrastructure Asset Management March, 2015 Happy Longfellow, PE hlongfellow@parametrix.com (206) 394-3649 ASSET MANAGEMENT OVERVIEW What? Why? How? Inventory
More informationHow To Manage The County Of Simcoe'S Infrastructure
Asset Management Plan Asset Management Plan Table of Contents 1.0 Executive Summary... 2 2.0 Introduction... 4 3.0 State of County of Simcoe s Infrastructure... 7 4.0 Levels of Service... 14 5.0 Asset
More informationHIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL
HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL Prepared for: Public Works and Government Services Canada Parliamentary Precinct Branch Prepared by: Halsall Associates 210 Gladstone
More informationCh a p t e r 5. Bridges Decks and Boardwalks
05 Ch a p t e r 5 Park Structures Bridges Decks and Boardwalks Intentionally Blank Br i d g e s Chapter 5: Park Structures Pu r p o s e Bridges shall facilitate safe access across bodies of water, unstable
More informationMPO Staff Report MPO Technical Advisory Committee: March 13, 2013 MPO Executive Board: March 20, 2013
MPO Staff Report MPO Technical Advisory Committee: March 13, 2013 MPO Executive Board: March 20, 2013 RECOMMENDED ACTION: Matter of MnDOT Kennedy Bridge Study and NDDOT Sorlie Bridge Phase I Report Matter
More informationSECTION 108 - INLETS 108.1 INLET LOCATIONS
Greene County Design Standards -Adopted April 5, 1999 SECTION 108 - INLETS SECTION 108 - INLETS 108.1 INLET LOCATIONS 108.2 INLET INTERCEPTION CAPACITIES 108.2.1 Clogging Factors 108.3 INTERCEPTION AND
More informationDrainage DR-701. Materials Field Sampling. Purpose of the Guidance Manual. General DR 701-1
DR-701 Chapter Materials Field Sampling Drainage Subject INLETS INTRODUCTION & STORM SEWERS General Purpose of the Guidance Manual DR 701-1 STORM SEWER DEFINITION KYTC defines a storm sewer as two or more
More informationBridge Office Policies and Procedures BOPP 2014
Bridge Office Policies and Procedures BOPP 2014 Nebraska Department of Roads Bridge Division Last updated: October 2014 Introduction Page I Purpose The BRIDGE OFFICE POLICIES AND PROCEDURES manual (BOPP)
More informationProject Information. New Hope - Lambertville Toll Bridge - Pavement Rehabilitation & Approach Bridges Repairs -
Project Information Existing Conditions Cracked and settled pavement. Structural failure within the asphalt pavement section. Anticipated Project Elements Reconstruction of all asphalt pavement on US Route
More informationGARDEN CITY SKYWAY SUBSTRUCTURE REHABILITATION
GARDEN CITY SKYWAY SUBSTRUCTURE REHABILITATION Issam ElKhatib, P.Eng., Dennis Baxter, P.Eng. Totten Sims Hubicki Associates, Canada Abstract The rehabilitation history of the Garden City Skyway Bridge
More informationIndex 20010 Series Prestressed Florida-I Beams (Rev. 07/12)
Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12) Design Criteria AASHTO LRFD Bridge Design Specifications, 6th Edition; Structures Detailing Manual (SDM); Structures Design Guidelines (SDG)
More informationChapter 7: Pavement Rehabilitation 7-1 Asphalt Pavement Overlays 7-1 Surface Preparation Methods 7-2 Concrete Pavement Preparation 7-3 Recycling
7-1 Asphalt Pavement Overlays 7-1 Surface Preparation Methods 7-2 Concrete Pavement Preparation 7-3 Recycling Asphalt Pavements 7-7 Chapter 7 Pavement Rehabilitation Pavement rehabilitation can be accomplished
More informationAlternatives Presentation Meeting Middlebury WCRS(23)
Alternatives Presentation Meeting Middlebury WCRS(23) Main Street (VT 30/TH 2 Bridge 102) and Merchants Row (TH 8 Bridge 2) over Vermont Railway June 4, 2013 Twilight Hall Auditorium, Middlebury College
More informationREHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE
REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE A.Rito Proponte, Lda, Lisbon, Portugal J. Appleton A2P Consult, Lda, Lisbon, Portugal ABSTRACT: The Figueira da Foz Bridge includes a 405 m long cable stayed
More informationKOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER
KOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER The New York State Department of Transportation (NYSDOT) is preparing an Environmental Impact Statement (EIS) to evaluate alternatives for the rehabilitation or
More informationIntroduction to Minimal Excavation Foundations
Introduction to Minimal Excavation Foundations What is a minimal excavation foundation? A construction technique that minimizes disturbance of the natural soil profile within the footprint of the structure
More informationMoving Small Mountains Vesuvius Dam Rehab
Moving Small Mountains Vesuvius Dam Rehab Susan L. Peterson, P.E., regional dams engineer, Eastern Region, Bedford, IN Note: The following article, Moving Small Mountains Vesuvius Dam Rehab, by Sue Peterson,
More information