SPACE SURVEILLANCE AND TRACKING INTENDED PROCUREMENTS IN THE SST SEGMENT - 2013 EMMET FLETCHER Space Surveillance and Tracking Manager Space Situational Awareness Programme Office Page: 1
BACKGROUND Page: 2
SST COMPONENTS Page: 3
SST SEGMENT OUTLINE Page: 4
ACTIVITIES: PREPARATORY PROGRAMME Page: 5
DATA GENERATION CO-VI CO-VIII Coordinated Tracking Campaign La Sagra, TFRM, OGS, Starbrook, Zimmerwald Chilbolton, EISCAT, Monge SLAs with various telescope groups European Surveillance Campaign Specific evaluations Graz Laser Station Medicina Page: 6
DATA PROCESSING DC-II Data Processing Chain Orbit Determination Correlation Covariance Propagation Page: 7
DATA STORAGE CO-VI DC-II DC-IV Data Model Catalogue Maintenance Data Validation Data Retrieval Page: 8
PRODUCT PREPARATION / DISSEMINATION CO-VI CO-VIII Conjunction Prediction Collision Warning All-against-All Conjunction Prediction Re-Entry Prediction Collision Warning (CCSDS CDM) Re-Entry Alerts Page: 9
ARCHITECTURAL DESIGN CO-I.2 CO-II SSA Requirements and Analysis Architectural Design Page: 10
ACTIVITIES 2013 Page: 11
SST SEGMENT OUTLINE Page: 12
VALIDATION MONITORING - CONTROL WP-ID Title Budget Duration P2-SST-101 Development of Supporting Analysis Software and International Standard Validation 400 k 12 Develop toolbox of validation techniques for benchmarking Flexible Distributable International standards Page: 13
DATA GENERATION WP-ID Title Budget Duration P2-SST-303 P2-SST-401 P2-SST-404 Requirements analysis of an expert site for federated laser tracking observation Requirements analysis for an expert site for federated optical observation Acquisition of radar observations in support for the SST end-to-end validation and technology development. 50 k 12 50 k 12 250 k 12 Evaluate benefits/drawbacks for expert sites in optical and laser observations precursor to possible expert centre deployment Continue investigation into radar technologies for SST: a critical area for a future SST system. Page: 14
TECHNICAL SUPPORT AND CONSULTANCY WP-ID Title Budget Duration P2-SST-801 SST Segment Technical Support 600 k 24 Support activity to ESA team Assistance to prepare and monitor SST Segment activities Page: 15
ARCHITECTURAL DESIGN WP-ID Title Budget Duration P2-SST-802 SST Segment Architectural Consolidation 100k 12 Take the output of both CO-II activities Execute cost v. performance trade-offs Deliver a final definitive baseline architecture for the SST segment Page: 16
PROCUREMENT GROUPING 2013 Page: 17
SST PROCUREMENTS Procurement Activities Budget Schedule Duration P2-SST-I P2-SST-101 400 k Q3 2013 12 P2-SST-II P2-SST-404 250 k Q4 2013 12 P2-SST-III P2-SST-303 50 k Q3 2013 12 P2-SST-IV P2-SST-401 50 k Q3 2013 12 P2-SST-V P2-SST-701 P2-SST-703 Total 1,450 k 700 k Q3 2013 24 Page: 18