WATER PENETRATION TESTING OF STUCCO ON CONCRETE MASONRY CONSTRUCTION



Similar documents
NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)

Williamson and Associates, Inc. Report of Building Exterior Condition Evaluation, dated January 2 nd, (68 pages)

Dimensioning and Estimating Brick Masonry

LAYING BLOCK AND BRICK

STANDARD REQUIREMENTS FOR BONDING OR MECHANICAL ATTACHMENT OF INSULATION PANELS AND MECHANICAL ATTACHMENT OF ANCHOR AND/OR BASE SHEETS TO SUBSTRATES

R-VALUES AND U-FACTORS OF SINGLE WYTHE CONCRETE MASONRY WALLS. TEK 6-2C Energy & IAQ (2013) Related TEK: 2-5B, 6-1C, 6-4B, 6-11A, 6-12C, 6-12D, 6-12E

Technical Notes 3B - Brick Masonry Section Properties May 1993

FACT SHEET: HYDRATED LIME FOR MASONRY PURPOSES

Mortars for Brickwork - Selection and Quality Assurance

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

Weather Resistive Barriers: Building Science Makes a Case for Two Layers by Dave Olson Technical Services Manager, Fortifiber Building Systems Group

R-VALUES AND U-FACTORS OF SINGLE WYTHE CONCRETE MASONRY WALLS. TEK 6-2B Energy & IAQ (2009) Related TEK: 6-1B, 6-11, 6-12C INTRODUCTION

How To Test Water Penetration On Concrete Block And Mortar

cement Masonry Cement Engineered for quality and reliability, Lafarge cements for masonry deliver consistent performance. page 2 Lafarge Cement

Testing Water Penetration Resistance of Window Systems Exposed to Realistic Dynamic Air Pressures

StuccoSpec Moisture Testing Inspection

Resurfacing Concrete. Page 1 of 5

T R A N S F E R A B L E F U L LY

continuing professional education. As such, it construed to be an approval or endorsement by

MOCK-UP TEST REPORT. Rendered to: TUBELITE, INC. PROJECT: 200 Series Curtain Wall Mock-Up

UPDATE October 8, 2012 Chicago Roofing Contractors Association CHICAGOLAND S ROOFING, INSULATION, AIR-BARRIER REQUIREMENTS

SECTION ALUMINUM FRAMED ENTRANCES and STOREFRONTS. System 402 Flush-Glazed Screw Spline Storefront

Quality Assurance and Diagnostic Water Leakage Field Check of Installed Storefronts, Curtain Walls and Sloped Glazing Systems

December 24, SEDA Construction Attn: Ted Walker 2120 Corporate Square Boulevard Jacksonville, Florida 32216

How to Identify, Evaluate & Repair Shrinkage Cracks in Poured Concrete

Evaluating the Field Performance of Windows and Curtain Walls of Large Buildings

Ver. 2. Guide to. Inspecting Residential Brick Veneer

Springlok Flashing System

NRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS

The Science of Rough Opening Preparation and Window Installation to Minimize Air Leakage

Water Damage & Repair

SECTION 3 ONM & J STRUCTURAL ANALYSIS

ASTM E 1886 and ASTM E 1996 TEST REPORT. Rendered to: NORSE, INC.

MATERIALS. Table 1 Mortar Proportions by Volume (Ref. 12)

GYPSUM BOARD, GYPSUM PANEL PRODUCTS AND PLASTER

STANDARD PROCEDURES FOR INSTALLATION OF METAL ROOF SYSTEMS

10DBMC International Conference On Durability of Building Materials and Components LYON [France] April 2005

CGA Standard Practices Series. Article 600 Standard for Pozzolan Enhanced Grouts Used in Annular Seals & Well Destruction

The Difference Between Cast Stone and Adhered Manufactured Stone Masonry Veneer

SECTION FLUID APPLIED ROOFING (LIGHT TRAFFIC DECKS OVER CONCRETE)

The Florida Building Code

Standard Method for Sampling and Analysis of. of Chlorine Containing Bleaches. Soap Products

Wastewater Capital Projects Management Standard Construction Specification

September 3, Ric Boyd, Public Works Director Ketchikan Gateway Borough 344 Front St. Ketchikan, AK 99901

PERFORMANCE EVALUATION OF THE CERAMITEX RVR SYSTEM IN ACCORDANCE WITH AAMA FOR PRESSURE EQUALIZATION BEHAVIOR & WATER PENETRATION RESISTANCE

Mark Cramer Inspection Services, Inc.

RESIDENTIAL MASONRY A BEST PRACTICES GUIDE

SINGLE FAMILY RESIDENCE HURRICANE MITIGATION APPLICATION

TEST REPORT. Report No.: A Rendered to: BAMCO INC. Middlesex, New Jersey. PRODUCT TYPE: Wall Cladding System SERIES/MODEL: Dry Concept

ROOF FLASHING SPRINGLOK FLASHING SYSTEM FEATURES & BENEFITS PRODUCT DESCRIPTION

How To Replace A Roofing System In Florida

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

Section 4: Architectural Design

How To Make A House Safe

SECTION PRECAST CONCRETE UTILITY STRUCTURES

UX-30 PERFORMANCE TESTING SUMMARY REPORT Revision 0

Roof Inspection. Summary Report

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

TEST PROCEDURE FOR FIELD WITHDRAWAL RESISTANCE TESTING

The entire document shall be read and understood before proceeding with a test. ISTA 3B Page 1 of 35

RECOMMENDATIONS FOR REPAIR OF SPRAY POLYURETHANE FOAM (SPF) ROOF SYSTEMS DUE TO HAIL AND WIND DRIVEN DAMAGE

Metropolitan Builders Association Masonry & Concrete Standard

LEGACY REPORT. (800) (562) A Subsidiary of the International Code Council. *Corrected March 2014

Lighthouse Engineering, L.L.C.

FIELD TESTING SERVICES

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

APPLICATION INFORMATION FOR RESIDENTIAL ROOFING AND RESIDENTIAL ROOFING PACKET

C. Section TESTING LABORATORY SERVICE.

CA-48 TECHNICAL SPECIFICATION

SECTION SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS

COMMONLY USED RESIDENTIAL BUILDING CODES

RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000

METHOD OF TEST FOR UNIT WEIGHT OF FRESH CONCRETE

CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS

Section EXTERIOR STONE VENEER Full Mortar

Load Design Charts. R-CONTROL SIPs STRUCTURAL INSULATED PANELS. CONTROL, NOT COMPROMISE.

APE T CFRP Aslan 500

Terms and Definitions In Canada

R E S I D E N T I A L H O U S I N G

3 Masonry and Manufactured Stone (Interior and Exterior)

High Performance Building Materials SCREEDS REPAIR MORTARS LEVELLING & SMOOTHING WATERPROOFING TILE ADHESIVES & GROUTS PRIMERS & ADDITIVES

DIVISION: THERMAL AND MOISTURE PROTECTION SECTION: CONCRETE ROOF TILES REPORT HOLDER:

ICC-ES Evaluation Report

SPECIFICATIONS. INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP)

SECTION PLAYGROUND SURFACING TILES

Design II: Water Penetration and Leakage Through Greenstar Blox

Commonwealth of Pennsylvania PA Test Method No. 632 Department of Transportation October Pages LABORATORY TESTING SECTION. Method of Test for

WATER LEAKAGE IN GLAZED CURTAIN WALL SYSTEMS:


Installation Solutions for: Manufactured Stone, Natural Thin Veneer, and Thin Brick ARCHITECTURAL SPECIFICATIONS / CAD MODELS TVISTM WARRANTIES

WATERPROOFING OF WET ROOMS

(800) (562) A Subsidiary of the International Code Council *Revised April 2014

Coursing Tables, Metric Shapes and Sizes

Avoiding Air Barrier Pitfalls

LEGACY REPORT. (800) (562) A Subsidiary of the International Code Council RETAINED ON U.S.

Adding Brick Veneer to Existing Construction

HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS

NEW ELECTRICAL SUBSTATION Building 300 SECTION ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING WORK

Moisture Mitigation for Concrete Slabs

Transcription:

WATER PENETRATION TESTING OF STUCCO ON CONCRETE MASONRY CONSTRUCTION for Florida Concrete & Products Association and NCMA Education and Research Foundation Conducted by: Masonry Information Technologists Jim Gulde, President Project No. 05-466B Date: May 2007

The following personnel and Companies of Florida donated time and materials to complete this project. Florida Concrete and Products Association Robert Sitter, President Providing Promotional and Technical Services to Architects, Engineers, Contractors, The Design and Construction Industry of Florida Artisan Industries Stucco Consultant CB Goldsmith and Associates, Inc. Architect and Stucco Consultant Cemex USA Florida Rock Industries J D B Code Services Code Consultant Masonry Information Technologists, Inc. Masonry & Stucco Consultant Rinker Materials Corp. Cement Div. Stucco Solutions Stucco Consultant Tarmac, Titan America, LLC Marvin Stokoe, President Charles Goldsmith AIA Steve French, Field Specialist Russ Flynn, Director of Technical & Marketing Services- Cement Group Joe Belcher, President Jim Gulde, President Al Barenthin, Mgr. Logistics and Technical Services Bobby Wilson, Area Sales Mgr. Paul Owen, President Mike Starks, Specifications Rep. Testing and Data Generation Conducted by NCMA RESEARCH AND DEVELOPMENT LABORATORY National Concrete Masonry Association Research and Development Laboratory 13750 Sunrise Valley Drive Herndon, VA 20171 (703) 713-1900 This publication is intended for use by professional personnel competent to evaluate the significance and limitations of the information provided herein, and willing to accept total responsibility for the application of this information in specific instances. Results from tests may vary and the research participants do not warrant the results contained herein for specific uses or purposes and the findings are not a substitute for sound engineering evaluations, judgment and opinions for specific projects or uses. The participants are not responsible for the use or application of the information contained in this publication and disclaim all responsibility therefore.

Table of Contents 1.0 INTRODUCTION.. 1 2.0 WALL CONSTRUCTION. 3 3.0 PHASE ONE INITIAL TESTING... 8 WIND SPEEDS OF 62 AND 110 MPH (100 AND 177 KPH) 4.0 PHASE TWO EXTREME HURRICANE CONDITION... 14 WIND SPEEDS OF 155 AND 180 MPH (249 AND 290 KPH) 5.0 SUMMARY AND CONCLUSIONS 20 6.0 REFERENCES... 21

1.0 INTRODUCTION This project was jointly funded through NCMA s Education and Research Foundation in cooperation with The Florida Concrete and Products Association and their members. Jim Gulde of Masonry Information Technologists, Inc. served as the Principal Researcher. Stucco on block is a very popular finish representing 20% of the block sales in the USA. It provides the plain gray block a whole new look - a very economical and attractive finish. Stucco has done much to promote concrete masonry and improve its image. The hurricanes that inundated Central Florida in 2004 caused significant damage to residential construction due to water intrusion, mainly to houses built after 2001. All building components typical of this type of construction came under severe scrutiny. This created the motivating factor for the development of this project, as CBS (concrete block-stucco) residential construction represents about 85% of the homes in Florida. While it is assumed that stucco increases the resistance to water penetration of concrete masonry, a review of the literature has found no comprehensive tests on this subject. This research was undertaken to provide some information as to how effective stucco is in preventing water intrusion through the CBS wall system. Coincidentally, the Florida Building Code 2001 Edition (ref. 2) introduced a new term of Decorative Cementitious Coating(DCC), defined as a skim coat as defined in ASTM C 926, of Portland cement based plaster applied to concrete or masonry surfaces intended for cosmetic purposes. as an alternate to traditional Portland cement-based stucco. Following the adoption of the 2001 code, many builders began using a DCC (which has no thickness requirements) in lieu of the standard stucco and stucco thicknesses required by ASTM C 926, Standard Specification for Application of Portland Cement-Based Plaster (ref. 5). ASTM C926 is the national standard for application of stucco, and is referenced in the building code (refs. 2 & 3). ASTM C 926 Table 1* defines required thicknesses of stucco over various substrates which is based on empirical historical performance. For stucco applied directly to concrete masonry units, the required thickness is ½ in. (13 mm) for 2 coat work and ⅝ in. (16 mm) for three-coat work. However, to date, little is known about the relative resistance to water intrusion based on varying thicknesses of stucco. The effectiveness of a skim coat at ⅛ in. (3mm) thickness to resist water penetration was added to the research project. *Table 1 Stucco Thickness. It should be noted that the thicknesses shown in the Table are Nominal Thickness. Nominal is defined here as a dimension to which variations are to be anticipated and expected. However, care was exercised to assure that the thickness of the stucco application on these laboratory walls was the thickness indicated in the report. Water Penetration Testing of Stucco on Concrete Masonry Construction Page 1

1. Project Objectives: A. To develop elementary data on water intrusion through various thicknesses of stucco applications applied on Concrete Block Walls. B. To determine if thicknesses less than those required in ASTM C 926 can function adequately compared to the required thickness. C. To assist in the continuing of the marketing of the Concrete Block Stucco (CBS) walls throughout the United States. 2. Project Description: The purpose was to test for water penetration resistance of concrete masonry walls with varying thicknesses of stucco and various levels of workmanship of both the masonry and the stucco. This involved testing wall samples that were built 4 ft (1.2 m) wide and 6 ft (1.8 m) tall using the ASTM E 514 (ref. 6) protocol. The project was broken into two phases utilizing different wind pressures: 1. Phase I utilizing pressures representative of 62 and 110 mph (100 and 177 kph) winds 2. Phase II utilizing pressures representative of 155 and 180 mph (249 and 290 kph) winds Water Penetration Testing of Stucco on Concrete Masonry Construction Page 2

2.0 WALL CONSTRUCTION The NCMA Research and Development Laboratories, under the direction of Bob Thomas and Jeff Greenwald conducted basic research on the water integrity of stuccoed masonry walls. The walls were built in the NCMA lab in the late fall of 05. Steve French, a stucco applicator from Florida, traveled with a trailer to NCMA the week of 14 November and applied the stucco to the walls. Thirteen (13) walls were built to be tested in accordance with ASTM E514 Standard Test Method for Water Penetration and Leakage Through Masonry (ref. 6) as described in Table 1. The ½ in. (13 mm) stucco was applied in accordance with ASTM C926, Standard Specification for Application of Portland Cement-Based Plaster (ref. 5), which allows this thickness to be applied in a double-up method where the second coat is applied as soon as the first coat can hold the second coat. The other stucco thicknesses were applied in a single coat. Pressure Cabinet Water Collection Trough Figure 1 All Walls were 8 in. (203 mm) Nominal Thickness, 3-½ Units Wide and 9 Courses High Water Penetration Testing of Stucco on Concrete Masonry Construction Page 3

Table 1 Wall Specimens and Stucco Thicknesses Stucco Thickness Number of Walls Description None 1 Control wall no stucco ⅛ in. (3 mm) 4 Skim coat of stucco material ¼ in. (6 mm) 4 ½ the code required thickness ½ in. (13mm) 4 ASTM C926 required thickness Total 13 Mortar Joint Strategy: This project was developed for the sole purpose of testing the stucco coating, not the block or mortar joints. However, it is found upon occasion that the workmanship on mortar joints leaves something to be desired. Therefore one wall of each stucco thickness was constructed with flawed mortar joints as described in Table 2. Table 2 Flawed Mortar Joint Strategy Head joints 12 available on each side of wall within pressure cabinet area. 8 of the 12 head joints to be flawed 4 of the 12 head joints to have no flaw. Flawed technique as follows: Number of flawed joints per wall H1: No mortar; butt CMU head joints tight 2 H2: Mortar; 1 in. (25 mm) wide; full mortar joint - 2 H3: Mortar; 1 in. (25 mm) wide; ½ full mortar joint - 2 H4: Mortar; ⅜ in. (10 mm) wide; ½ full mortar joint - 2 Total flawed head joints per wall 8 Bed joints 5 available on each side of wall B1: Missing along 3 ft (0.9 m), four 2-in. (51 mm) long no mortar -33 percent B2: Correct along 3 ft (0.9 m), full mortar joint 33 percent B3: Incorrect along 3 ft (0.9 m), ½ full mortar joint 33 percent Water Penetration Testing of Stucco on Concrete Masonry Construction Page 4

Pressure cabinet H3 H4 H2 B1 H2 H3 H1 H4 H1 B3 top bottom Back Figure 2 Wall 1 Assembly Faces Front Figure 3 Wall 1 Photo Front Face Water Penetration Testing of Stucco on Concrete Masonry Construction Page 5

y Pressure cabinet H3 H2 H1 H3 H1 H2 H4 H3 B3 B1 B3 top bottom Back Figure 4 Wall 2 Assembly Faces Front Pressure cabinet H4 H2 H1 H2 H1 B1 H3 H4 H3 B3 top bottom Back Figure 5 Wall 3 Assembly Faces Front Water Penetration Testing of Stucco on Concrete Masonry Construction Page 6

Figure 6 The final step in the building of the walls - the application of the stucco to the block. The walls were generally built to meet the standards of Building Requirements for Masonry Structures (ACI 530/ASCE 5/TMS 402) and Specification for Masonry Structures (ACI 530.1/ASCE 6/TMS 602) (MSJC) (refs. 2 & 3) using type S masonry cement. Since this project was developed to test the stucco, not the block or mortar, one wall of each stucco thickness was constructed with flawed mortar joints. The flawed joints were inserted to determine if stucco would perform even with some reduced quality in the masonry. Water Penetration Testing of Stucco on Concrete Masonry Construction Page 7

3.0 PHASE I - INITIAL TESTING WIND SPEEDS OF 62 AND 110 MPH (100 AND 177 KPH) Phase I testing consisted of testing 6 walls described as follows: 6 Walls were tested as follows (See Table 2 for flawed construction description): Wall 1: Good block construction Control Wall with no stucco. (Blank Wall) Wall 2: Good block construction - ⅛ in. (3 mm)skim coat, Wall 3: Good block construction - ½ in. (13 mm) stucco, Wall 4: Flawed construction - ⅛ in. (3 mm) skim coat, Wall 5: Flawed construction - ¼ in. (6 mm) skim coat, Wall 6: Flawed construction - ½ in. (13 mm) stucco. Figure 7 Phase I Test Walls (Photo taken: December 19, 2005) The walls in Phase I were tested at two pressures. Round one was tested at ASTM E514 prescribed water flow and pressure of 40.8 gallons per hour and 10 lbs per square foot (0.47 kpa) (2 in. (51 mm) of water) where wind velocity, V = approximately 62 mph (100 kph). Round two was tested at ASTM E514 prescribed water flow and 31 lbs per square foot (1.5 kpa) (6 in. (13 mm) of water) pressure. The higher pressure was calculated from the equation: p = 0.00256(V) 2 with V = 110 mph (177 kph) wind speed. Water Penetration Testing of Stucco on Concrete Masonry Construction Page 8

Phase I Test Results And Observations In testing the blank (control) wall, the water and pressure commensurate with the 62 mph (100 kph) wind speed were maintained for 4 hours. Visible water was observed in the wall cores and the wall face within ½ hour. In addition, approximately 20 gallons of water penetrated the wall face under pressure and approximately 0.1 gallons migrated through the wall cross section. It is estimated that water flow rates of 5 gallons per hour and 0.03 gallons per hour would be attained for the wall face and wall cross section, respectively. Table 3 Control Wall Performance, Phase I Observation Time (hr) Control wall at 62 mph (100 kph) wind speed 0.5 1.0 1.5 Water Penetration Testing of Stucco on Concrete Masonry Construction Page 9

Observation Time (hr) Control wall at 62 mph (100 kph) wind speed 2.0 2.5 3.0 4.0 Water Penetration Testing of Stucco on Concrete Masonry Construction Page 10

In testing the 5 stuccoed walls: two at ⅛ in. (3 mm) skim coat, one at ¼ (6 mm) skim coat and two at ½ in. (13 mm) stucco, the water and pressure were maintained for 4 hours for the 62 (100 kph) wind speed followed by another 24 hours at 110 mph (177 kph). In both rounds of testing, no visible water was observed in any of the wall cores or on the leeward wall face. Table 4 Flawed Wall with ⅛ in. (3 mm) Skim Coat Performance, Phase I Flawed wall with ⅛ in. (3 mm) skim coat after 4 hours at 62 mph (100 kph) Flawed wall with ⅛ in. (3 mm) skim coat after 4 hours at 62 mph (100 kph) plus 24 hours at 110 mph (177 kph) Table 5 Test Results - Area of Dampness on Leeward Wall Surface, percent Wall Specimen Length of Exposure, hours 0 4 4.5 5 5.5 6 6.5 7 7.5 8 12 22 28 Wall 1-Control 0 45 Stopped after 4 hours Wall 2 (⅛) 0 0 0 0 0 0 0 0 0 0 0 0 0 Wall 3 (½) 0 0 0 0 0 0 0 0 0 0 0 0 0 Wall 4 (⅛F) 0 0 0 0 0 0 0 0 0 0 0 0 0 Wall 5 (¼F) 0 0 0 0 0 0 0 0 0 0 0 0 0 Wall 6 (½F) 0 0 0 0 0 0 0 0 0 0 0 0 0 Table 6 Test Results Water Collected on Through-Wall Flashing, lbs. (kg) Wall Specimen Length of Exposure, hours 0 4 4.5 5 5.5 6 6.5 7 7.5 8 12 22 28 Wall 1-Control 0 20 (9.0) Wall 2 (⅛) 0 0 0 0 0 0 0 0 0 0 0 0 0 Wall 3 (½) 0 0 0 0 0 0 0 0 0 0 0 0 0 Wall 4 (⅛F) 0 0 0 0 0 0 0 0 0 0 0 0 0 Wall 5 (¼F) 0 0 0 0 0 0 0 0 0 0 0 0 0 Wall 6 (½F) 0 0 0 0 0 0 0 0 0 0 0 0 0 Water Penetration Testing of Stucco on Concrete Masonry Construction Page 11

% Area Dampness 50 45 40 35 30 25 20 15 10 5 0 Figure 8 Area of Dampness on Leeward Wall Surface, percent 4 hr @ 62 mph Dampness on Back Face of Walls 24 hr @ 110 mph Wall 1 - Control (no stucco) All other walls 0 5 10 15 20 25 30 Test Time (hours) Wall 1-Control Wall 2 (1/8) Wall 3 (1/2) Wall 4 (1/8F) Wall 5 (1/4F) Wall 6 (1/2F) Figure 9 Test Results Water Collected on Through-Wall Flashing, lbs. 4 hr @ 62 mph Water Collected from Bottom Flashing 24 hr @ 110 mph Cumulative Water Collected (lb.) 25 20 15 10 5 0 Wall 1 - Control (no stucco) All other walls 0 10 20 30 Wall 1-Control Wall 2 (1/8) Wall 3 (1/2) Wall 4 (1/8F) Wall 5 (1/4F) Wall 6 (1/2F) Test Time (hours) Water Penetration Testing of Stucco on Concrete Masonry Construction Page 12

Phase I Summary: In the control wall (with no stucco) water was observed penetrating into the cores and dampness on the leeward wall face within 30 minutes at the 62 mph (100 kph) wind speed. The walls with ⅛ in. (3 mm) and ¼ in. (6 mm) skim coats and ½ in. (13 mm) stucco showed no evidence of water penetration during the four hours of 62 mph (100 kph) wind driven rain. Additionally, in the following 24 hours at 110 mph (177 kph) there was no trace of water entering the cores or dampness appearing on the leeward face of the wall. Each of the stucco material thicknesses had one wall with flawed mortar joints. Phase I Conclusions Stucco material applications of ⅛ in. (3 mm), ¼ in. (6 mm) and ½ in. (13 mm) thicknesses dramatically increase the water penetration resistance of plain, gray, 8-in. (203 mm) concrete masonry walls. No water penetrated into the cores or to the leeward face of the test walls after 62 mph (100 kph) of wind driven rain for four hours followed by 110 mph (177 kph) wind driven rain for 24 hours in when tested in accordance with ASTM E514. Water Penetration Testing of Stucco on Concrete Masonry Construction Page 13

Phase II Testing 4.0 PHASE TWO - EXTREME HURRICANE CONDITION WIND SPEEDS OF 155 AND 180 MPH (249 AND 290 KPH) Due to the excellent performance at 62 and 110 mph (100 and 177 kph) during Phase I of the flawed ⅛ in. (3 mm) skim coat walls, no further testing was conducted on ¼ in. (6 mm) skim coated walls during Phase II. Phase II testing was conducted utilizing the following walls under higher pressures representing hurricane conditions of 155 and 180 mph (249 and 290 kph) wind speeds: 4 walls with ⅛ in. (3 mm) skim coat- one of these with flawed mortar joints 4 walls with ½ in. (13 mm) stucco- one of these with flawed mortar joints After 4 hours of testing at 155 mph (249 kph) no moisture was observed in any of the cores or leakage on the leeward face in any of the test specimens. In view of this, there was little reason to continue the test to 24 hours since the object was to determine the difference in performance between walls. The pressure was then increased to that of a 180 mph (290 kph) wind. Almost immediately moisture appeared in the cores of the ⅛-in. (3 mm) coated walls. Therefore the test at 180 mph (290 kph) was continued for full 24 hours. Moisture in some form appeared on the back surface on three of the four walls. See photos in Table 5 and 6. The ½ in. (13 mm) stucco walls were then tested at the same regimen as the ⅛-in. (3 mm) skim coat for comparison, i.e. 4 hrs at 155 mph (249 kph) followed by 24 hrs at 180 mph (290 kph). Again, there was no moisture observed in the first four hours at the lower wind pressure. Under the increased rate of 180 mph (290 kph), moisture was observed in the cores of these walls as well as moisture on the leeward face in some form on all four walls but in lesser overall amounts than for the ⅛-in. (3 mm) skim coat. See photos in Table 5 and 6. While there was variation between the walls in each set of 4, the dampness on the leeward face results was very similar between the ⅛ in. (3 mm) skim coat and the ½ in. (13 mm) stucco. However, there was a marked difference in the amount of water collected on the flashing, with a better overall performance of the ½ in. (13 mm) stucco at the higher wind speeds. Only one wall of the ½ in (13 mm) stucco collected water on the flashing in the bottom of the cells - and that was a small amount only at the final reading (final 4 hours of the 28-hour test). Two of the four ⅛ in. (3 mm) skim coat walls collected water - both of which occurred much earlier in the test at the 12 hour mark in the 28 hour test. One of these could have been slightly influenced by moisture entering the flashing from the front side as a result of leakage around the seal for the chamber under the elevated pressure. However, this same wall had the greatest amount of dampness penetrating to the leeward face confirming that it was the worst performing wall tested. It was also noted that Wall ½-2 which is the only ½ in. (13 mm) stucco specimen that accumulated any water on the flashing had dampening on the lower 3 courses above the flashing only whereas the others that were damp had damp spots throughout the test area. Water Penetration Testing of Stucco on Concrete Masonry Construction Page 14

Table 7 Walls After 4 Hours at 155 mph (249 kph) then 4 hours at 180 mph (290 kph), Phase II, Organized from Best to Worst Performing at Test Conclusion ⅛ in. (3 mm) skim coat ½ in. (13 mm) stucco Wall S-A Flawed Mortar Joints Wall ½-1 Wall S-3 Wall ½-2 Wall S-2 Wall ½-B Flawed Mortar Joints Wall S-1 Wall ½-3 Water Penetration Testing of Stucco on Concrete Masonry Construction Page 15

Table 8 Walls After 4 Hours at 155 mph (249 kph) then 24 hours at 180 mph (290 kph), Phase II, Organized from Best to Worst Performing at Test Conclusion ⅛ in. (3 mm) skim coat ½ in. (13 mm) stucco Wall S-A Flawed Mortar Joints Wall ½-1 Wall S-3 Wall ½-2 Wall S-2 Wall ½-B Flawed Mortar Joints Wall S-1 Wall ½-3 Water Penetration Testing of Stucco on Concrete Masonry Construction Page 16

Table 9 Test Results - Area of Dampness on Leeward Wall Surface, percent Wall Specimen Length of Exposure, hours 0 4 4.5 5 5.5 6 6.5 7 7.5 8 12 22 28 ½ - B 0 0 0 0 0 0.2 0.5 0.8 0.8 0.8 3.2 5.2 6.1 ½ - 1 0 0 0 0 0 0 0 0 0 0 0 0.2 0.3 ½ - 2 0 0 0 0.6 0.7 0.8 0.9 1 1.05 1.1 1.9 4.7 6.1 ½ - 3 0 0 0 0 0 0 0 0 0 0 0.7 8.9 13.5 S - A 0 0 0 0 0 0 0 0 0 0 0 0 0 S - 1 0 0 1.1 1.3 1.3 1.5 1.5 1.5 1.5 1.5 1.6 15.2 24.9 S - 2 0 0 0 0 0 0 0 0 0 0 0 1.5 4.5 S - 3 0 0 0 0 0 0 0 0 0 0 0 0.3 1.8 Table 10 Test Results Water Collected on Through-Wall Flashing, lbs. (kg) Wall Specimen Length of Exposure, hours 0 4 4.5 5 5.5 6 6.5 7 7.5 8 12 22 28 ½ - B 0 0 0 0 0 0 0 0 0 0 0 0 0 ½ - 1 0 0 0 0 0 0 0 0 0 0 0 0 0 ½ - 2 0 0 0 0 0 0 0 0 0 0 0 0 0.5 ½ - 3 0 0 0 0 0 0 0 0 0 0 0 0 0 S - A 0 0 0 0 0 0 0 0 0 0 0.34 (.19) 3 (1.4) 5.79 (2.6) S - 1 0 0 0 0 0 0 0 0 0 0 0.75 (.34) 8 (3.6) 18.7 (8.5) S - 2 0 0 0 0 0 0 0 0 0 0 0 0 0 S - 3 0 0 0 0 0 0 0 0 0 0 0 0 0 Water Penetration Testing of Stucco on Concrete Masonry Construction Page 17

30 4 hr @ 155 mph Dampness on Back Face of Walls 24 hr @ 180 mph % Area Dampness 25 20 15 10 5 1/2 - B 1/2-1 1/2-2 1/2-3 S - A S - 1 S - 2 S - 3 0 0 5 10 15 20 25 30 Test Time (hours) Figure 10 Area of Dampness on Leeward Wall Surface, percent % Area Dampness 9 8 7 6 5 4 3 2 1 0 4 hr @ 155 mph Dampness on Back Face of Walls (Average for Three Walls) 24 hr @ 180 mph 0 5 10 15 20 25 30 Test Time (hours) 1/2 - Average S - Average Figure 11 Test Results: Dampness ⅛ in. (3 mm) Skim Coat vs. ½ in. (13 mm) Stucco Water Penetration Testing of Stucco on Concrete Masonry Construction Page 18

Cumulative Water Collected (lb.) 7 6 5 4 3 2 1 0 4 hr @ 155 mph Water Collected from Bottom Flashing (Average for Three Walls) 24 hr @ 180 mph 0 5 10 15 20 25 30 Test Time (hours) 1/2 - Average S - Average Figure 12 Test Results Water Collected on Flashing ⅛ in. (3 mm) Skim Coat vs. ½ in. (13 mm) Stucco. Phase II Observation Summary At 155 mph (249 kph) for four hours, the four ⅛ in. (3 mm) skim coat walls and the four ½ in. (13 mm) stuccoed walls showed no visible water on the leeward face and no water in the cores. At 180 mph (290 kph) for 24 hours, the walls with ⅛ in. (3 mm) skim coat and the walls with ½ in. (13 mm) stucco passed water into the cores and to the opposite face. Although data above and the charts show some differences, the results for the amount of water collected on the flashing for the ⅛ in. (3 mm) skim coat and the ½ in. (13 mm) stucco were dramatically different at the higher pressure as shown in Figure 12. Also the time at which water began collecting on the flashing was much earlier for the ⅛ in. (3 mm) skim coat than for the ½ in. (13 mm) stucco. Water Penetration Testing of Stucco on Concrete Masonry Construction Page 19

5.0 SUMMARY AND CONCLUSIONS This two phase testing program found that: A. At wind speeds of 110 mph (177 kph), all the coated walls resisted water penetration regardless of stucco material thickness; while the walls with no stucco material failed early in the testing at the much lower wind speed of 62 mph (100 kph). B. At wind speeds exceeding 155 mph (249 kph), traditional ½ in. (13 mm) stucco as produced in Florida, and in accordance with ASTM C 926 provided excellent resistance to moisture penetration. C. At wind speeds of 180 mph (290 kph), the amount of dampness appearing on the leeward side of the wall was similar for both stucco material thicknesses. However, ½ in. (13 mm) stucco displayed a dramatic difference as compared to the ⅛ in. (3 mm) skim coat for the extended time and pressure in regard to the amount of water collected at the bottom of the cells on the flashing. D. The thickness of the stucco material, as constructed and tested in this environment; and, utilizing this test method does not appear to be a significant factor in resisting water penetration at low wind speeds. E. The quality of workmanship regarding the mortar joints appears to have little influence on the watertightness of stuccoed masonry walls with the stucco material apparently able to fill and bridge the gaps and holes in the mortar. However, even though this may have produce acceptable results for water penetration resistance, head and bed joints for the full thickness of the face shell are required by the building codes (refs. 1, 2, & 3) for structural purposes. Conclusions Stucco applied in accordance with ASTM C 926 ½ in. (13 mm) stucco and the skim coat of ⅛ in. (3 mm) thickness did provide comparable resistance to water penetration at low wind speeds. The ½ in. (13 mm) stucco did allow much less water into the cells, however, and delayed the entry for a much longer time than did the ⅛ in. (3 mm) skim coat at the higher wind speeds. However, it should be noted that these tests were conducted in a laboratory environment, and the walls and stucco material were cured as a condition of the test method. There were no instances of masonry or stucco material cracking observed in these test panels. Performance of masonry walls constructed in the field not adhering to recommended practice and industry standards, more than likely will experience a performance different than was experienced in this research project. There are many characteristics and conditions in the materials and construction practices of stucco that have determined the thickness requirements in ASTM C926. They include the tolerance criteria of the concrete masonry unit as well as the tolerance criteria in the construction of masonry walls. It is not the intention of this report to suggest that a skim Water Penetration Testing of Stucco on Concrete Masonry Construction Page 20

coat or reduced stucco material thickness is being recommended as a replacement of the existing criteria in ASTM C926 (ref. 5) and the building codes (refs. 2, & 3). 6.0 REFERENCES 1. Building Code Requirements for Masonry Structures, ACI 530/ASCE 5/TMS 402. Masonry Standards Joint Committee, 2005. 2. Florida Building Code, 2001 Edition and 2004 Edition with 2005 and 2006 Amendments. Florida Department of Community Affairs, 2001, 2004, 2005, and 2006. 3. International Building Code. International Code Council, 2000, 2003, and 2006. 4. Specification for Masonry Structures, ACI 530.1/ASCE 6/TMS 602. Masonry Standards Joint Committee, 2005. 5. Standard Specification for Application of Portland Cement-Based Plaster, ASTM C926-06. ASTM International, 2006. 6. Standard Test Method for Water Penetration and Leakage Through Masonry, ASTM E514-06. ASTM International, 2006. Water Penetration Testing of Stucco on Concrete Masonry Construction Page 21