1 UPDATE October 8, 2012 Chicago Roofing Contractors Association CHICAGOLAND S ROOFING, INSULATION, AIR-BARRIER REQUIREMENTS Executive Summary: There is a proposal at the Joint Committee on Administrative Rules being reviewed Oct. 16, The proposal is for the State of Illinois to adapt the 2012 International Energy Conservation Code (IECC). This new code has some rather large implications for the roofing industry. First, the 2012 IECC increases the insulation R-Value on roofs by 20% from R-20 to R-25. The costs to install this added insulation on an existing building adds about 20 % to the cost of roof assembly construction. Second, the 2012 IECC code also requires a new continuous air barrier. This adds another 30% to the cost building owners and managers who need reroofing or roof replacement. Reroofing and roof replacement existing buildings creates jobs. New construction job growth has declined significantly the past few years. The new code will cause building owners and managers to not replace existing roofs because it just costs too much. This will affect jobs in the only remaining healthy part of the roofing economy, replacing roofs on existing buildings. CRCA has submitted a proposal to keep the insulation value for existing buildings the same and not requiring the air barrier. This saves big money in rooftop alterations needed to upgrade insulation while not adding a roof air barrier. The roof air barrier is not effective when it is not tied in with a wall air barrier. Building Owners can t take the walls of the building off because they are putting a new roof on the building. Support CRCA s proposals to alter the IL adaption of the 2012 IECC code. This will help keep building owners and managers in a position to keep Illinois roofers working. Chicago & Suburbs Insulation Requirements Will Increase by 20% January 1, 2013 The current Chicago Energy Code uses in its entirety the 2006 International Energy Conservation Code ( IECC ) for building envelope insulation requirements and adds the reflectivity requirements of.72 initial and.50 aged 3 years. The current roofing Chicago Energy Code insulation requirements are R-20 for new low sloped commercial roofs and reroofing and roof replacement. The R Value refers to the thermal resistance of the insulation where heat flows from one surface to another. The higher the R-Value, the more insulation is required. The State of Illinois had legislation enacted some time ago that mandates the current version of the International Energy Conservation Code as state law 12 months from publication by the International Code Council. This is similar to what happens when the Americans with
2 Disabilities Act changes. Rather than the normal jurisdictional code adaption process through each legislative body in Illinois, the 2012 International Energy Conservation Code becomes state law 16 months after publication.and that is January 1, 2013.unless a formal statement is made altering this requirement. According to the Chicago Department of Buildings, since the 2012 International Energy Conservation Code becomes State Law, Chicago will have to comply. That will mean the Chicago Energy Code will update from the 2006 version to the 2012 version of the IECC. As a result, insulation required on commercial roofs in Chicago, suburbs and all of the State of Illinois will increase by over 20% from R-20 to R-25 effective on buildings permitted after January 1, 2013, unless there are exceptions added to the code. The new Chicago Energy Code causes an increase in insulation requirements from R-20 to a minimum of R-25 to comply with the IL State Law. This applies to all commercial low sloped roofs including new construction, reroofing and roof replacement (tear offs). Exceptions are allowed only if the Authority Having Jurisdiction allows a variance in writing. Reasons for the variance could include impracticality in the opinion of the building official, based on of the Building Code, Alternative Methods. Economics Roofing Contractors state the prospective increase in insulation will cost an additional $1.25 to $3.00 per square foot (assuming a 10,000sf roof) to meet the new requirements depending on the building configuration. That could be about 20%. Service items on the roof such as heating and air conditioning equipment, doors and windows at penthouses and building abutments already exist and have acceptable flashing heights. Adding more insulation means that all these services have to be raised to accommodate flashing height requirements, a costly endeavor. Higher building perimeter nailers and sheet metal flashing will add to the cost of the roof and insulation installation. Plus, high rise buildings will very likely cost much more due to limited access for crane operations, etc.
3 For the building owner and manager, the question remains, is the additional R-5 worth the extra money? Studies show that there is a diminishing return on investment for insulation after R First, the thermal resistance optimizes at R Additional heat flow gains are very small when adding insulation. Therefore, additional dollars spent on extra insulation produce show returns when related to payback periods. Heat Flow Reduction through Insulation at varied thicknesses " 2" 3" 4" 5" 6" 7" 8" 9" 10" 11" 12" SOURCE: MASSAVE.com How does a slow payback period for R-25 insulation affect investment decisions? The life expectancy of a typical low sloped commercial roof is 17 years. Calculating the return time on the investment in additional insulation shows a payback period of 43 years. With the prospective changes in the insulation requirements, that s 2.5 times the life expectancy of the roof. And, since the building code requires all new materials, the existing insulation nor ballast cannot be reused. The Chicago Roofing Contractors Association ( CRCA - crca.org) has suggested that the State of Illinois provide an exception to buildings already constructed and undergoing reroofing or roof replacement. Where height of building equipment and perimeter is impractical, an exception would be granted to allow the insulation thickness to be the same as before, but with an R value that does not increase the energy usage of the building. An R-Value, or LTTR, of 6.0 per inch material makes most sense. The exception would allow the building owner and manager to replace less efficient insulation with equal thickness at higher efficiency insulation. How to Comment on the New Law Anyone can public comment supporting the CRCA positions during the Joint Committee on Administrative Rules during the first 45 day posting period in the Illinois Register.
4 Another New Twist Air Barriers The 2012 International Energy Conservation Code also contains requirements for a continuous Air Barrier. Continuous means the complete building envelope. That includes the roof. Additionally, continuous means joints sealed, penetrations sealed, and more. To meet the new IECC Code requirements, there are several materials that are deemed to qualify as air barriers. What materials qualify as part of a continuous air barrier? Can an assembly qualify? Answer: Ask the manufacturer of the product configuration proposed if it has installation instructions that state the material is suitable as an air barrier and meets the following requirements when tested as shown below, or are deemed to comply from the list. Yes, and Yes Materials are listed below, and Assembly test requirements are on the next page. C Air barrier compliance options. A continuous air barrier for the opaque building envelope shall comply with Section C , C , or C C Materials. Materials with an air permeability no greater than cfm/ft2 (0.02 L/s m2) under a pressure differential of 0.3 inches water gauge (w.g.) (75 Pa) when tested in accordance with ASTM E 2178 shall comply with this section. Materials in Items 1 through 15 shall be deemed to comply with this section provided joints are sealed and materials are installed as air barriers in accordance with the manufacturer s instructions. 1. Plywood with a thickness of not less than 3/8 inch (10 mm). 2. Oriented strand board having a thickness of not less than 3/8 inch (10 mm). 3. Extruded polystyrene insulation board having thickness of not less than 1/2 inch (12mm). 4. Foil-back polyisocyanurate insulation board having a thickness of not less than 1/2 inch (12 mm). 5. Closed cell spray foam a minimum density of 1.5 pcf (2.4 kg/m3) having a thickness of not less than 11/2 inches (36 mm). 6. Open cell spray foam with a density between 0.4 and 1.5 pcf (0.6 and 2.4 kg/m3) and having a thickness of not less than 4.5 inches (113 mm). 7. Exterior or interior gypsum board having a thickness of not less than 1/2 inch (12 mm). 8. Cement board having a thickness of not less than 1/2 inch (12 mm). 9. Built up roofing membrane.
5 10. Modified bituminous roof membrane. 11. Fully adhered single-ply roof membrane. 12. A Portland cement/sand parge, or gypsum plaster having a thickness of not less than 5/8 inch (16 mm). 13. Cast-in-place and precast concrete. 14. Fully grouted concrete block masonry. 15. Sheet steel or aluminum. What qualifies an assembly as an air barrier? C Assemblies. Assemblies of materials and components with an average air leakage not to exceed 0.04 cfm/ft2 (0.2 L/s m2) under a pressure differential of 0.3 inches of water gauge (w.g.)(75pa) when tested in accordance with ASTM E 2357, ASTM E 1677 or ASTM E 283 shall comply with this section. Assemblies listed in Items 1 and 2 shall be deemed to comply provided joints are sealed and requirements of Section C are met. 1. Concrete masonry walls coated with one application either of block filler and two applications of a paint or sealer coating; 2. A Portland cement/sand parge, stucco or plaster minimum 1/2 inch (12 mm) in thickness. Can the whole building be tested to see if it complies? C Building test. The completed building shall be tested and the air leakage rate of the building envelope shall not exceed 0.40 cfm/ft2 at a pressure differential of 0.3 inches water gauge (2.0 L/s m2 at 75 Pa) in accordance with ASTM E 779 or an equivalent method approved by the code official. What about holes in the air barrier? C Air barrier penetrations. Penetrations of the air barrier and paths of air leakage shall be caulked, gasketed or otherwise sealed in a manner compatible with the construction materials and location. Joints and seals shall be sealed in the same manner or taped or covered with a moisture vapor-permeable wrapping material. Sealing materials shall be appropriate to the construction materials being sealed. The joints and seals shall be securely installed in or on the joint for its entire length so as not to dislodge, loosen or otherwise impair its ability to resist positive and negative pressure from wind, stack effect and mechanical ventilation. To learn more about roofing installations check out the Whole Building Design Guide Resources from NIBS.
6 There is a lot to learn about the new 2002 International Energy Conservation Code. What is clear is that there are changes coming unless there are reprieves given by the State of Illinois during the 45 day Joint Committee on Administrative Rules Comment Period that is coming to a close in late October, The key points for contractors, consultants, building owners and managers to meet the new Air Barrier Requirements are 1. Air Barriers will be required - Ask the manufacturer for published literature that states the products qualify as an Air Barrier as defined in this code. It is up to the manufacturer to provide testing that the materials comply. Check the deemed to comply list of materials. There may be materials 2. Impractical to make the insulation thickness work? Request a variance from the Authority Having Jurisdiction (building official) during the permit application process. It may be difficult since the energy code is now Illinois State Law. That is also true for the air barrier. Both codes have an administrative section that allows alternative methods to meet the intent of the code. CRCA is constantly working with the various local governmental agencies and with the National Roofing Contractors Association (NRCA) at the national level to insert these exceptions and provide some incentives for commercial property owners and managers to keep their buildings code compliant. Bill McHugh, Executive Director & CRCA s Industry Affairs Committee Chicago Roofing Contractors Association 4415 W. Harrison St, #436 ~ Hillside, IL ph ~ fx ~ bill@crca.org
'Roofing Code & Licensing Laws'
'Roofing Code & Licensing Laws' CRCA June 20, 2012 'Roofing Code & Licensing Laws' Outline Welcome, CRCA Steep & Shingle Committee Who is CRCA? 2012 Code Requirements What s s Illinois Roofing Licensing
More informationNRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS
NRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS The (NRDCA) has prepared this document to provide customers and installers information that the industry
More informationR-VALUES AND U-FACTORS OF SINGLE WYTHE CONCRETE MASONRY WALLS. TEK 6-2C Energy & IAQ (2013) Related TEK: 2-5B, 6-1C, 6-4B, 6-11A, 6-12C, 6-12D, 6-12E
An information series from the national authority on concrete masonry technology R-VALUES AND U-FACTORS OF SINGLE WYTHE CONCRETE MASONRY WALLS TEK 6-2C Energy & IAQ (201) INTRODUCTION Single wythe concrete
More informationLow-slope reroofing guidelines
Low-slope reroofing guidelines by Thomas Bollnow and Joan P. Crowe, AIA The NRCA Roofing and Waterproofing Manual, Fifth Edition, contains reroofing guidelines for steep- and low-slope roofing. The August
More informationPinpoint Seminar: Technical Update
Aurora, CO Wednesday, December 16, 2015 Pinpoint Seminar: Technical Update presented by Mark S. Graham Vice President, Technical Services NaBonal Roofing Contractors AssociaBon 1 Energy code update Interna'onal
More informationCHAPTER 7: Building Systems ROOFING SYSTEMS
ROOFING SYSTEMS Purpose Examples 1. Shingle roof system 2. Metal roof with blanket insulation 3. Metal roof with rigid insulation 4. Built-up asphalt roof system 5. Single-ply roof system 6. Modified Bitumen
More informationContinuous Insulation Using Polyiso Wall Sheathing
PIMA Technical Bulletin #403 Continuous Insulation Using Polyiso Wall Sheathing What it is, what it does, and why you need it About Polyiso Insulation Polyiso is a rigid foam insulation used in over 70%
More informationComment Form on Proposed Gut Rehabilitation Alternatives
Comment Form on Gut Rehabilitation Alternatives Name: Organization: Email: Instructions Submission: Please submit this form to energystarhomes@energystar.gov by October 10 th, 2012 with the subject line
More informationDuPont Tyvek Commercial Air Barrier Assemblies Exceed Air Barrier Association of America, ASHRAE 90.1
Building Science Bulletin DuPont Tyvek Commercial Air Barrier Assemblies Exceed Air Barrier Association of America, ASHRAE 90.1 and IECC Air Leakage Requirements When Tested in Accordance with ASTM E2357
More informationDetermining Air Barrier Performance
solutions for the construction industry december 2009 Determining Air Barrier Performance The Offi cial Magazine of the q Construction Specifi cations Institute also in this issue Using CPVC for Industrial
More informationR-Value and Densities Chart
R-Value and Densities Chart Material R-Value Per Inch R-Value Per Unit Inside Air Film 0.68 Air Space between Studs 0.95 Building Pa 0.06 ½ in. Fiberboard Sheathing 1.52 Gypsum Wallboard or Drywall 0.90
More informationR-VALUES AND U-FACTORS OF SINGLE WYTHE CONCRETE MASONRY WALLS. TEK 6-2B Energy & IAQ (2009) Related TEK: 6-1B, 6-11, 6-12C INTRODUCTION
An information series from the national authority on concrete masonry technology R-VALUES AND U-FACTORS OF SINGLE WYTHE CONCRETE MASONRY WALLS TEK 6-2B Energy & IAQ (2009) INTRODUCTION Single wythe concrete
More informationAvoiding Air Barrier Pitfalls
Avoiding Air Barrier Pitfalls Design & Durability November 2013 Air barriers, when correctly installed, help buildings achieve high levels of energy efficiency by decreasing heat loss. For example, great
More informationRoof insulations must perform the basic function of helping to control fluctuations in building interior temperature
Thermal Values Roof insulations must perform the basic function of helping to control fluctuations in building interior temperature relative to changing exterior temperatures. By reducing interior temperature
More informationalso in this issue Automatic Doors for the People Calculating Roof Insulation R-values Waterproofing and Concrete Balconies
$7.00 solutions for the construction industry august 2012 56 TH CSI ANNUAL CONVENTION SHOW PREVIEW also in this issue Automatic Doors for the People Calculating Roof Insulation R-values Waterproofing and
More informationAsphalt Shingle Application Requirements
Alberta Allied Roofing Association Asphalt Shingle Application Requirements Section 1 Roof Decks 1.1 General Asphalt Shingles are not permitted to be installed directly over rigid insulation. When Asphalt
More informationCOMMERCIAL BUILDING APPLICATIONS
EXPANDED POLYSTYRENE FOR COMMERCIAL BUILDING APPLICATIONS www.falconfoam.com Commercial Building Ap Expanded Polystyrene Insulation Falcon Foam leads the commercial building industry with products that
More informationSECTION 07550 - MODIFIED BITUMINOUS MEMBRANE ROOFING. A. Vapor barrier (base ply); cover board at existing roof deck.
SECTION 07550 - PART I GENERAL 1.01 SECTION INCLUDES A. Vapor barrier (base ply); cover board at existing roof deck. B. Roof insulation at new roof deck. C. Modified bitumen membrane. D. Fluid applied
More informationThe existing roof angle change terminations and flashings when sound and intact can be reused.
January 2, 2015 Summary Specification Re-Skinning an Existing Roof Maintenance and Repair Warranty Upgrade for Up to 30 Years Re-Skinning Over an Existing Roof with a New C-EPDM Membrane Using The Existing
More informationROOFING APPLICATION STANDARD (RAS) No. 150 PRESCRIPTIVE BUR REQUIREMENTS
ROOFING APPLICATION STANDARD (RAS) No. 150 PRESCRIPTIVE BUR REQUIREMENTS 1. 2. 3. 3.0 Scope 1.1 This application standard shall be used where the authority having jurisdiction has adopted its use, and
More informationThe Prefab Package. Modular EIFS construction offers benefits to today s busy jobsites. Building Envelope. Roland Serino, P.E., of Dryvit Systems Inc.
26 D+D MARCH 2015 Building Envelope Roland Serino, P.E., Dryvit Systems Inc. here has always been a need for a more efficient way to build in large cities like Chicago, New York, Los Angeles or other central
More informationState of Connecticut Department of Public Health RADON PROGRAM
State of Connecticut Department of Public Health RADON PROGRAM Scope The Connecticut Department of Public Health (DPH) Radon Program is providing this information for contractors who decide to build radon
More informationENERGY STAR Qualified New Homes Thermal Enclosure Checklist. Water Management Checklist. Eli Caudill
ENERGY STAR Qualified New Homes Thermal Enclosure Checklist & Water Management Checklist Eli Caudill ENERGY STAR Version 3 Tighter Standards Whole Home Approach Better, More Sustainable Construction Surpasses
More informationArticle. Protecting the Building Envelope from Water Damage. MemBrain Smart Vapor Retarder & Air Barrier Film
Article Protecting the Building Envelope from Water Damage Vapor Retarders Play a Crucial Role in Moisture Management Whether we like it or not, moisture in the form of water vapor diffusion and humid
More informationSTAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM
STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM Installed in Pre-engineered Steel Buildings Provides Lowest Cost Construction Method for CORROSIVE AND WET Environments PREFERRED SOLUTIONS, INC.
More informationRe-Cover Board-3. Insulation for Above the Deck ROOF WALL SPECIALTY
Insulation for Above the Deck WALL SPECIALTY PRODUCT DESCRIPTION Rmax Re-Cover Board-3 is an energy-efficient thermal insulation board composed of a closed-cell polyisocyanurate (polyiso) foam core bonded
More information2009 IECC Update. Scope. Content. International Energy Conservation Code
2009 IECC Update International Energy Conservation Code Scope The code applies to both residential and commercial buildings. In the code, the United States is divided into eight climate zones which are
More informationCHAPTER VII. TITLE: STANDARDS FOR NEW ROOFING July 2015 CONSTRUCTION, RE-ROOFING CONSTRUCTION AND ROOFING SYSTEM GUARANTEE REQUIREMENTS
TITLE: STANDARDS FOR NEW ROOFING CONSTRUCTION, RE-ROOFING CONSTRUCTION AND ROOFING SYSTEM GUARANTEE REQUIREMENTS Responsible Organization: Office of Facilities Planning Instructions: This Manual supersedes
More informationCITY PLAN REVIEW AND INSPECTION. Lisa Fleming Brown, CPM
CITY PLAN REVIEW AND INSPECTION Lisa Fleming Brown, CPM Houston Commercial Energy Conservation Code (2011) A choice of 2009 IECC or ASHRAE 90.1-2007 with amendments. Effective September 2, 2011. Complete
More informationEnvelope INSULATION BATT (2) Avoid Using Batt Insulation With Metal Framing. Pressure or Friction Fit
R-H-DI1 INSULATION BATT NR-E-IB1 Avoid Using Batt Insulation With Metal Framing Batt insulation should not be used with metal framing systems. Although it is common to see fiberglass batt insulation installed
More informationHeating Load Calculation
Heating Load Calculation ME 425 Air Conditioning System Design Keith E. Elder, P.E. Heating Load Calculation The heating load calculation begins with the determination of heat loss through a variety of
More informationCOMMONLY USED RESIDENTIAL BUILDING CODES
COMMONLY USED RESIDENTIAL BUILDING CODES INTERNATIONAL RESIDENTIAL CODE (2009) form revised 5/10 FOUNDATION 1. DESIGN OF FORMWORK. Section 1906.1 IBC 2009, Section R404.1.2.3.6 IRC 2009, ACI 318 Section
More informationRenovating Your Basement
building science.com 2006 Building Science Press All rights of reproduction in any form reserved. Renovating Your Building America Report - 0309 2003 (revised 2007) Building Science Corporation Abstract:
More informationDollars & Sense of Compliance!
CRCA s 29 th Annual Trade Show Oakbrook k Terrace, IL January 19 20, 2012 Dollars & Sense of Compliance! Mark S. Graham Associate ExecutiveDirector Director, Technical Services National Roofing Contractors
More informationRESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000
RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 SECTION R905 REQUIREMENTS FOR ROOF COVERINGS R905.1 Roof covering application. Roof coverings
More informationAir-Conditioning, Heating, and Refrigeration Institute. Sheet Metal and Air-Conditioning Contractors National Association
Air-Conditioning, Heating, and Refrigeration Institute Sheet Metal and Air-Conditioning Contractors National Association GUIDELINE B-1997 ACKNOWLEDGEMENT These guidelines for Roof Mounted Outdoor Air-
More informationThe Building Group First Tuesdays First Saint Paul s Lutheran Church 1301 North LaSalle Street, Chicago, Illinois
Wiss, Janney, Elstner Associates, Inc. 10 South LaSalle Street, Suite 2600 Chicago, Illinois 60603 312.372.0555 tel 312.372.0873 fax www.wje.com The Building Group First Tuesdays October 2, 2012 Jason
More informationPresented by: Jennifer Doyle, P.E., RRC, LEED AP
Presented by: Jennifer Doyle, P.E., RRC, LEED AP Moisture Gas: Molecules are spread out "Vapor" suspended in air forms a mixture, present everywhere Liquid: Molecules are closer Rain Condensation Pipes
More informationFIRESTOPPING & SMOKE SEALS
SPECIFICATION SECTION 07 84 00 FIRESTOPPING & SMOKE SEALS 1 GENERAL 1.1 SECTION INCLUDES 1.1.1 Comply with Division 1, General Requirements and Documents referred to therein. 1.1.2 It is the intent of
More informationFIELD TESTING SERVICES
FIELD TESTING SERVICES Chris Leach Director of Testing Baton Rouge, Louisiana Destin, Florida Scott Leach David Nichols Field Testing Representative Field Testing Representative 17485 Opportunity Avenue
More informationDIVISION: 07 00 00 THERMAL AND MOISTURE PROTECTION SECTION: 07 21 00 THERMAL INSULATION REPORT HOLDER: CERTAINTEED CORPORATION
0 ICC-ES Report ICC-ES (800) 423-6587 (562) 699-0543 www.icc-es.org 000 Most Widely Accepted and Trusted ESR-3758 Reissued 04/2016 This report is subject to renewal 04/2017. DIVISION: 07 00 00 THERMAL
More informationFOUNDATION INSULATING SYSTEM, INCLUDING WATERPROOFING AND DAMP PROOFING
FOUNDATION INSULATING SYSTEM, INCLUDING WATERPROOFING AND DAMP PROOFING insulation installed on foundation walls must be separated from the building interior with a code approved thermal barrier. Foam
More informationSpringlok Flashing System
Springlok Flashing System Why Fry Reglet? Fry Reglet s comprehensive selection of moisture prevention products offer the ultimate in protection from the elements. Available nationwide in a variety of materials
More informationfirst look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel
first look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel What is GigaCrete GigaCrete is a family of products based on low carbon footprint Green ceramic binders
More informationSECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS. System 402 Flush-Glazed Screw Spline Storefront
PART 1 GENERAL 1.01 Work Included SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS System 402 Flush-Glazed Screw Spline Storefront A. Furnish and install aluminum architectural storefront system
More informationresearch highlight Highly Energy Efficient Building Envelope Retrofits for Houses
research highlight June 2012 Technical Series 12-103 Highly Energy Efficient Building Envelope Retrofits for Houses introduction In Canada approximately 30% of all energy is consumed in buildings, with
More informationfoot skylight) is enough to knock a worker off their feet. A 10 mph wind gust on a 5 x 6 skylight develops a wind force of 270 lbs.
Skylight Installation Instructions This document provides instruction and guidelines for installation of both curb mount (CM) and self flashing (SF) unit skylights on flat, pitched (> or equal to 3/12
More informationFOAMULAR LT40, 400 and 600 insulations with minimum compressive strengths of
Technical Guide FOAMULAR Extruded Polystyrene Insulation For Cold Storage Applications FOAMULAR extruded polystyrene insulation is suitable for virtually all cold storage insulating needs, including floors,
More informationHEB 38 BLANCO AND WEST AVENUE FLUID APPLIED EPDM RUBBER ROOF RECOVERY SYSTEM APPLICATION
HEB 38 BLANCO AND WEST AVENUE FLUID APPLIED EPDM RUBBER ROOF RECOVERY SYSTEM APPLICATION David Marut TEST CASE REPORT July 1, 2014 Case Study Pro Guard EPDM Super Coat Liquid Rubber Membrane Roof System
More informationRetrofitting an Insulated Cold Roof
Retrofitting an Insulated Cold Roof As a metal-roofing contractor in the Upper Peninsula of Michigan, I am frequently asked to fix roof leaks that have less to do with roofing than with the way poorly
More informationROOF FLASHING SPRINGLOK FLASHING SYSTEM FEATURES & BENEFITS PRODUCT DESCRIPTION
SPRINGLOK SYSTEM PRODUCT DESCRIPTION FEATURES & BENEFITS Fry Reglet offers five flashing systems, each tailored for a particular type of substrate so you can get exactly what you need. SM Surface mounted
More informationGeorgia State University. Urban Life Building Roof Replacement
ENGINEERING AND ENVIRONMENTAL 140 DECATUR STREET SE, ATLANTA, GA 30303 GEORGIA STATE UNIVERSITY - FACILITIES DESIGN & CONSTRUCTION 34 BROAD STREET, SUITE 100 ATLANTA, GA 30303 DRAWING INDEX A-0 PROJECT
More informationFinal inspections are completed by site visit only. Access to fenced yards shall be planned.
ROOFING RESIDENTIAL BUILDING INSPECTIONS DEPARTMENT www.ci.blaine.mn.us This handout is intended only as a guide and is based in part on the 2015 Minnesota State Building Code, Blaine City ordinances,
More informationSpecifications. Preformed Metal Wall and Roof Panels. Alcoa Cladding Systems Manufacturing Plant 100 Industrial Boulevard Eastman, Georgia 31023
Specifications Preformed Metal Wall and Roof Panels Alcoa Cladding Systems Manufacturing Plant 100 Industrial Boulevard Eastman, Georgia 31023 Section 07410 Preformed Metal Wall and Roof Panels Structural
More informationIf you are a web registered user of ArlingontPermits.com you may also request an inspection at:
TECHNICAL BULLETIN Community Development & Planning, Building Inspections TOPIC: Permits & Inspections for Roofing Replacement Effective November 1, 2011 Revised This Technical Bulletin will provide contractors
More information*Trademark of The Dow Chemical Company A business unit of The Dow Chemical Company and its subsidiaries Copyright 2003 The Dow Chemical Company.
Dow Chemical is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members.
More informationbout your HOUSE before you start Repairing And Replacing Materials Exterior Walls
A bout your HOUSE before you start Repairing And Replacing Materials Exterior Walls CE 28 h Exterior finish materials are expected to protect the house from the elements while providing an attractive appearance.
More informationTECH BULLETIN. Roofing No. Impact of Temperature on Polyiso R-value. Subject: Impact of Temperature on the R-value for Polyisocyanurate Insulation
TECH BULLETIN Roofing No. 3016 Subject: Impact of erature on the R-value for Polyisocyanurate Insulation Date: February 2014 (Revised May 2015) The blowing agents used in polyisocyanurate (polyiso) foam
More informationTEST REPORT. Rendered to: TFC A DIVISION OF CENTURION INDUSTRIES, INC. Garrett, Indiana
Architectural Testing TEST REPORT Report No.: D0162.02-201-44 Rendered to: TFC A DIVISION OF CENTURION INDUSTRIES, INC. Garrett, Indiana PRODUCT TYPE: Pressure Equalized Rainscreen SERIES/MODEL: 4 mm Composite
More informationDIVISION: 07 00 00 THERMAL AND MOISTURE PROTECTION SECTION: 07 41 13 METAL ROOF PANELS REPORT HOLDER: FIRESTONE BUILDING PRODUCTS COMPANY, LLC
0 ICC ES Report ICC ES (800) 423 687 (62) 699 043 www.icc es.org 000 Most Widely Accepted and Trusted ESR 3422 Reissued 09/201 This report is subject to renewal 09/2016. DIVISION: 07 00 00 THERMAL AND
More informationBuilt to Last. Built for Beauty. Good. Solid. Logix. TM
Built to Last. Built for Beauty. Good. Solid. Logix. TM Quality, Value and Service Introducing LOGIX Insulated Concrete Forms. Based on the simple concept of interlocking blocks, LOGIX ICF gives you a
More informationMeeting the Fire Code with Continuous Foam Plastic Insulation
Dow Building Solutions Meeting the Fire Code with Continuous Foam Plastic Insulation The 2012 International Building Code (IBC) specifies the fire tests that must be passed if a foam plastic material is
More informationRoof Inspection Report 3840 Greenway Circle, Lawrence Kansas, 66046 Sauer-Danfoss Building
Roof Inspection Report 3840 Greenway Circle, Lawrence Kansas, 66046 Sauer-Danfoss Building Prepared For: Ms Marilyn Bittenbender Colliers International 805 New Hampshire St Lawrence Kansas, 66046 Prepared
More information24.301.161 INCORPORATION BY REFERENCE OF INTERNATIONAL. (1) The Department of Labor and Industry adopts and incorporates by
24.301.161 INCORPORATION BY REFERENCE OF INTERNATIONAL ENERGY CONSERVATION CODE (1) The Department of Labor and Industry adopts and incorporates by reference the International Code Council's International
More informationBuilding Energy Codes 101 October 23, 2013. Matthew Giudice Building Policy Associate Midwest Energy Efficiency Alliance
Building Energy Codes 101 October 23, 2013 Matthew Giudice Building Policy Associate Midwest Energy Efficiency Alliance OVERVIEW 1. Introduction 2. Energy Code Development 3. Adoption Process 4. Elements
More informationUNIVERSITY OF WASHINGTON Facilities Services Design Guide. Architectural. Roofing. Basis of Design
Basis of Design This section applies to roofing membranes, flashing and accessories. Design Criteria Adhere to the standards and details of the latest editions of the National Contractors Association (NRCA)
More informationBest Practices in Roof Design: Sustainable Energy Efficient Reroofing
Best Practices in Roof Design: Sustainable Energy Efficient Reroofing Best Practice Roof Design: Sustainable Energy Efficient Reroofing Presented by Edis Oliver, PE Principal 9511 Lake Creek Parkway Austin,
More informationInsulating Basements: Part 3 Basement Wall Systems
The Pennsylvania Housing Research Center Insulating Basements: Part 3 Basement Wall Systems Builder Brief: BB0710 Brian Wolfgang, PHRC Fellow INTRODUCTION The perception of a basement has changed significantly
More information2008-2009 Cost Comparisons for Common Commercial Wall Systems
An Independent Study LA MS KY TN AL GA SC NC FL 2008-2009 Cost Comparisons for Common Commercial Systems CAPITAL BUILDING CONSULTANTS PROFESSIONAL CONSTRUCTION ESTIMATORS 2008 2009 INDEPENDENT COST COMPARISONS
More informationPIMA Technical Bulletin #115. The High R Roof: Guidelines for Energy-Efficient Roofing and Re-Roofing. What is a High R Roof?
PIMA Technical Bulletin #115 The High R Roof: Guidelines for Energy-Efficient Roofing and Re-Roofing About Polysio Insulation Polyiso is a rigid foam insulation used in over 70% of commercial roof construction,
More informationDurapax Coal Tar BUR Application Guide
400 Old Reading Pike, Suite 304 Pottstown, PA 19464 Tel: 610-579-9075 Fax: 610-323-0115 www.durapax.com Durapax Coal Tar BUR Application Guide DESIGN CONSIDERATIONS The proper specifications of any roof
More informationAUTHORIZATION TO MARK
AUTHORIZATION TO MARK This authorizes the application of the Certification Mark(s) shown below to the models described in the Product(s) Covered section when made in accordance with the conditions set
More informationSeptember 3, 2009. Ric Boyd, Public Works Director Ketchikan Gateway Borough 344 Front St. Ketchikan, AK 99901
September 3, 2009 Ric Boyd, Public Works Director Ketchikan Gateway Borough 344 Front St. Ketchikan, AK 99901 RE: Ketchikan Gateway Borough Gateway Recreation Center Roof Observations and Intrusive Inspections
More informationROOF ASSEMBLIES CHAPTER 9
CHAPTER 9 ROOF ASSEMBLIES SECTION R901 GENERAL R901.1 Scope. The provisions of this chapter shall govern the design, materials, construction and quality of roof assemblies. SECTION R902 ROOF CLASSIFICATION
More informationInsulation R-Value Comparisons
Insulation R-Value Comparisons American Ingenuity s component panels for the 22 48 domes contains seven inch thick rigid Expanded Polystyrene (E.P.S.) insulation which has an R value of 28. American Ingenuity
More informationTEST REPORT. Report No.: A9814.01 109 44. Rendered to: BAMCO INC. Middlesex, New Jersey. PRODUCT TYPE: Wall Cladding System SERIES/MODEL: Dry Concept
Architectural Testing TEST REPORT Report No.: A9814.01 109 44 Rendered to: BAMCO INC. Middlesex, New Jersey PRODUCT TYPE: Wall Cladding System SERIES/MODEL: Dry Concept AAMA 508 07, Voluntary Test Method
More informationCITY OF WHITE BEAR LAKE BUILDING INSPECTION DEPARTMENT 4701 Highway 61 White Bear Lake, MN 55110 Fax: 651-429-8503. Re-Roofing: Asphalt Shingles
CITY OF WHITE BEAR LAKE BUILDING INSPECTION DEPARTMENT 4701 Highway 61 White Bear Lake, MN 55110 Fax: 651-429-8503 Re-Roofing: Asphalt Shingles This is a summary of the standard requirements based on the
More informationSECTION 07530 SINGLE PLY MEMBRANE ROOFING. 4. Minor repair to adjacent clay tile roofing and flashings.
SECTION 07530 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section includes the flowing: 1. Removal of existing roofing membrane. Existing bur roof has one overlay and penetration mastic is asbestos containing.
More informationThe Harold J. Becker Company, Inc.
The Harold J. Becker Company, Inc. It is the mission of The Harold J. Becker Company, Inc. to deliver the absolute best possible quality product at the most efficient cost to our clients, while providing
More informationVOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10
VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 SECTION B1: PREPARATION GUIDE B1.1 INTRODUCTION... B1-1
More informationREPORT NUMBER: 100900226COQ-003 ORIGINAL ISSUE DATE: July 19, 2013
REPORT NUMBER: 100900226COQ-003 ORIGINAL ISSUE DATE: July 19, 2013 TEST REPORT EVALUATION CENTER INTERTEK TESTING SERVICES NA LTD. 1500 BRIGANTINE DRIVE COQUITLAM, BC V3K 7C1 CANADA RENDERED TO PHOENIX
More informationDEFAULT HEAT LOSS COEFFICIENTS
DEFAULT HEAT LOSS COEFFICIENTS SECTION A101 GENERAL REQUIREMENTS A101.1 Scope. The following defaults shall apply to Chapter 4 of both the (RE) and (CE) sections of the IECC. This chapter includes tables
More information2.18 INTERIOR & EXTERIOR FINISHES 2.18.1 VAPOR & AIR BARRIERS
2.18 INTERIOR & EXTERIOR FINISHES 2.18.1 VAPOR & AIR BARRIERS The LOGIX wall assembly has no need for an additional vapor barrier, the solid concrete core covered with the low permeance EPS (Type II) foam
More information2014 British Columbia Building Code Changes
District of Houston 250-845-2238 2014 British Columbia Building Code Changes A District of Houston interpretation of the 2014 Building Code Changes for 9.36 & 9.32 The following changes reflect the most
More informationRACKING AND ATTACHMENT CRITERIA FOR EFFECTIVE MEMBRANE ROOF SYSTEM INTEGRATION Public Version 1: July 9, 2012
RACKING AND ATTACHMENT CRITERIA FOR EFFECTIVE MEMBRANE ROOF SYSTEM INTEGRATION Public Version 1: July 9, 2012 Commercial rooftops represent the most available, sustainable and secure real estate for new
More informationInspecting to a higher standard.
Inspecting to a higher standard. Rob Hopkin Silver Spring, MD 20902 Monday, June 2, 2014 ProTec Inspection Services Inc. 19736 Selby Ave Poolesville, MD 20837 301-972-8531 www.protec-inspections.com rob@protec-inspections.com
More informationSTANDARD REQUIREMENTS FOR BONDING OR MECHANICAL ATTACHMENT OF INSULATION PANELS AND MECHANICAL ATTACHMENT OF ANCHOR AND/OR BASE SHEETS TO SUBSTRATES
ROOFING APPLICATION STANDARD (RAS) No. 117 STANDARD REQUIREMENTS FOR BONDING OR MECHANICAL ATTACHMENT OF INSULATION PANELS AND MECHANICAL ATTACHMENT OF ANCHOR AND/OR BASE SHEETS TO SUBSTRATES Scope 1.1.
More informationTechPractices: Home Front Homes:
TechPractices: Home Front Homes: PATH's Technologies in Practice are large scale housing projects throughout the U.S. where innovative technologies are being installed and used. Information is presented
More informationNRCA Union Roofing Contractors Council Industry Discussion - Jurisdiction
Outline Introductions NRCA s Union Roofing Contractors Council Purpose of Industry Discussion Jurisdiction Industry Discussion Roof Removal Metal Green Vegetative, PV, Pavers, Ballast Waterproofing, Air
More informationDIVISION: 07 00 00 THERMAL AND MOISTURE PROTECTION SECTION: 07 21 00 THERMAL INSULATION REPORT HOLDER: ICYNENE, INC.
0 ICC-ES Report ICC-ES (800) 423-6587 (562) 699-0543 www.icc-es.org 000 Most Widely Accepted and Trusted ESR-1826 Reissued 02/2016 This report is subject to renewal 02/2018. DIVISION: 07 00 00 THERMAL
More informationBuilding Owners Guide to a Duro-Last System!
Building Owners Guide to a Duro-Last System Table of Contents Section 1: Introduction to Duro-Last Roofing Systems Section 2: Benefits of a Duro-Last Roofing System Section 3: Comparing a Duro-Last Roof
More informationLEGACY REPORT. www.icc-es.org (800) 423-6587 (562) 699-0543 A Subsidiary of the International Code Council RETAINED ON U.S.
ICC-ES Legacy Report ER-5043* Reissued March 2004 www.icc-es.org (800) 423-6587 (562) 699-0543 A Subsidiary of the International Code Council Legacy report on the 1997 Uniform Building Code DIVISION: 09
More informationIn accordance with the Department of Labor and Industry s statute 326.0981, Subd. 11,
In accordance with the Department of Labor and Industry s statute 326.0981, Subd. 11, This educational offering is recognized by the Minnesota Department of Labor and Industry as satisfying 1.5 hours of
More informationPhoto courtesy of Delta Stone, Heber City, UT. Installation Solutions for: Manufactured Stone, Natural Thin Veneer, and Thin Brick
Photo courtesy of Delta Stone, Heber City, UT Installation Solutions for: Manufactured Stone, Natural Thin Veneer, and Thin Brick THIN VENEER INSTALLATION SYSTEMS PREMIUM BONDING MORTARS Premium PCL Stone
More informationSun Windows General Information Sun New Construction Window Installation Instructions
Sun Windows General Information Section 1 G F H H H A. Apply Weather Resistive Barrier B. Apply Sill Flashing Tape C. Place Waterproof Sill Shims D. Caulk Back of Nail Fin Sides & Top, Set Window, Fasten
More information07 5423-1 THERMOPLASTIC-POLYOLEFIN ROOFING (TPO) Data Center
PART 1 GENERAL 1.01 SECTION INCLUDES SECTION 07 5423 THERMOPLASTIC-POLYOLEFIN ROOFING (TPO) Data Center A. Tear off existing roof system down to wood deck and install new Thermoplastic membrane roofing
More informationRESIDENTIAL MASONRY A BEST PRACTICES GUIDE
RESIDENTIAL MASONRY A BEST PRACTICES GUIDE Build With Brick Build With Boral CONTENTS BRICK :01 MASONRY CEMENT :03 MASONRY SAND :04 WALL TIES :05 STEEL LINTELS :07 DRAINAGE WALL SYSTEM :09 FLASHING :11
More informationROOFS, SNOW AND ICE DAMS
ROOFS, SNOW AND ICE DAMS The Problem Ice dams are a common roof performance problem in cold climate buildings. Simply put, they are ridges of ice and icicles caused by melt water from further up the roof
More informationICC-ES Evaluation Report. ESR-3493 Reissued September 2014 This report is subject to renewal September 2015.
ICC-ES Evaluation Report www.icc-es.org (800) 423-6587 (562) 699-0543 ESR-3493 Reissued September 2014 This report is subject to renewal September 2015. A Subsidiary of the International Code Council DIVISION:
More informationWater Damage & Repair
Water Damage & Repair Chinatown Preservation Talks 2015 James Engler, P.A Glenn Mason, AIA Mason Architects Program Outline Terminology & Waterproofing Basics Discussion of why this is important Below
More information