Indianapolis Midfield Terminal Thermal Utility Construction



Similar documents
University of Maryland College Park District Energy System. IDEA Campus Energy Conference February 9, 2012

District Cooling Best Practices Piping Systems

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

Special Specification 7021 Water Main and Sewer Line Replacements

CyberFortress Data Center at Innovation Park Infrastructure and Topology Guide. Innovation Park Charlotte. NC DRAFT V0.

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, Underground branch circuit feeding a detached garage:

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

Flowtite Jacking Pipe

PIPING SYSTEM - ABRASIVE SLURRIES Engineering Standard Specification. 96 B. Riutta

REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING

TOWN of NEW BOSTON. Bid Package. Refurbishment and Upgrade of Basement of the New Boston Town Hall

Gas Meter Clearances and Service Installation Requirements

Depend-O-Lok FxE Expansion Coupling. System No. Submitted By Spec Sect Para Location Date Approved Date. DEPEND-O-LOK FxE EXPANSION COUPLING

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS

TBM CROSSING OF STATIONS

4 Installation Requirements

Historic Georgia Tech Archibald D. Holland Central Heating and Cooling Plant

Whitepaper. Modular Substation Cable Termination Design. Author: Allan Bozek P.Eng, MBA, EngWorks Inc, Calgary, Canada

Tremco Fire Protection Systems Group Technical Bulletin

Model Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer

Challenges of District Cooling System (DCS) Implementation in Hong Kong

AT&T Specifications Trenching Conduit Boxes and M anholes Aerial Entrance Masts Service Cabinets Bonding and Grounding

Water Main Lining A Sustainable Alternative to Open Cut Replacement

Standards. 5 ANSI/TIA/EIA-569-A (CSA T530)

Dewatering - Time and Cost Relief by way of Trenchless Construction

Rehabilitation Alternatives. MWEA Collection System Seminar October 1, 2009

METHOD OF STATEMENT FOR STATIC LOADING TEST

A World Class Manufacturer of Induction Bends

Meeting the Challenge of Pipeline Emergency Repair

City of Hilshire Village Pine Creek Ln Reconstruction

Dallas/Fort Worth International Airport District Energy Plant Upgrades Project Making More with Less Sustainable Communities Conference Dallas, TX

This will also provide you with the knowledge to insure long life for your Investment

Machine Foundation Design

Cellar Tech Containment Well Cellar Systems

ModuSec. Secure and efficient IT room solutions Composite Panel Systems Compared. Panel Systems are not all the same!

One of the many issues facing cities, towns and campuses throughout. Making Connections in Miami: Cover Story

Los Angeles County Department Of Public Works. Land Development Division. Bond Calculation Sheets

1 Campus Cabling Systems Introduction

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements

Texas State University Utility Analysis. Sheri Lara, CEM, CEFP Texas State University Morgan Stinson, PE, LEED AP - EEA Todd Schmitt, PE, LEED AP EEA

Underground Cable Temperature Monitoring in the Real World

Pipe Bursting. Case Study at Zeeland, MI Collections Seminar September 6, Presentation Agenda. What is Pipe Bursting? What is Pipe Bursting?

B. ASTM C 533 Calcium Silicate Block and Pipe Thermal Insulation. C. ASTM C 547 Mineral Fiber Preformed Insulation

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects

SECTION HVAC INSULATION. A. All work specified in this Section is subject to the provisions of Section

BILL OF QUANTITY FOR THE HVAC WORKS OF The Institute of space technology, near Toll Plaza (G.T. Road,) Islamabad

National Science Foundation Funds Request

Installation of Large Diameter Buried Pipes

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

State Route 640 Itinerary Agrigento-Caltanissetta-A19. Description of work

University of Missouri Power Plant Combined Heat and Power Upgrades Columbia, Missouri

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

CTI TECHNICAL BULLETIN Number 9: A publication of the Cable Tray Institute

Multiple Meter Installation Amperes Per Position -Single Phase, Self-contained

heat treatment equipment & accessories

Value Engineering Considerations for Cast Iron Soil Pipe and PVC in Commercial Sanitary and Storm Drainage Applications

Geotechnical Building Works (GBW) Submission Requirements

THE UNIVERSITY OF TEXAS MEDICAL BRANCH (UTMB) AT GALVESTON

NEW JERSEY CENTER OF EXCELLENCE

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

FIBERGLASS REINFORCED PLASTIC (FRP) PIPING SYSTEMS DESIGNING PROCESS / FACILITIES PIPING SYSTEMS WITH FRP

2. AIRCONDITIONING AND REFRIGERATION

ELECTRIC SERVICE GUIDELINES (For Indiana)

Repair or Replacement - Band-Aids vs. Surgery

TEXAS A&M CENTRAL ACADEMIC BUILDIING & PATRIOT S CASA SUBMITTAL Pre-Insulated Piping

Wholesale Data Center Suites Available Now

Sany Tunnel Boring Machines

Cannon T4 Modular Data Centres. For Outside Deployment & Challenging Environments

Acumen Enterprises, Inc.

Undergrounding high voltage electricity transmission. The technical issues

DESIGN AND INSTALLATION OF RESIDENTIAL FLEXIBLE DUCTWORK SYSTEMS

High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

Sewer Line Rehabilitation

National Transportation Safety Board Washington, DC 20594

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

Toscotec TT DOES Solution An Efficient Package to Optimize the Drying Section of a Tissue Machine

COFELY DISTRICT ENERGY DELIVERING LOW CARBON SUSTAINABLE ENERGY SOLUTIONS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

The surface roughness of the polyurethane lining is 10 times lower than cement-lined pipes.

SECTION SHEETING, SHORING AND BRACING

TARIFF CODE and updates standard

WATER MAIN CONSTRUCTION TECHNIQUES DEPARTMENT OF PUBLIC WORKS WATER & WASTEWATER DIVISION

Ecoflex Wall Penetration Systems: An efficient, sustainable solution for penetrating concrete or block walls

IBM Twin Data Center Complex Ehningen Peter John IBM BS 2011 IBM Corporation

SECTION MORTUARY REFRIGERATORS

High Strain Dynamic Load Testing of Drilled Shafts

University of Iowa Main Power Plant 2008 Flood Preparations, Event, & Recovery

TELUS Residential Service Conduit Requirements for Stand Alone Homes and Duplexes in Fibre Only Communities

Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology

Transcription:

Indianapolis Midfield Terminal Thermal Utility Construction

CGCU Background Public Charitable Trust is managed only for the benefit of customers and the community 266,000 customers 3,700 Miles of Gas Distribution Piping Underground Gas Storage & LNG Facilities Oil Operations District Energy (Steam/Chilled Water) Facilities Management

Steam Business (regulated) Production capacity 1.9 million lb/hr Plus Waste-to-Energy Steam add l 500 mlb/hr 240 customers, 31 miles of steam piping Chilled Water Business (unregulated) Total CHW Production 74,400 tons for 2008 Main System 47,900 + 6,500 (new) Indianapolis Campus Energy - 20,000 60 customers, 17 trench-miles of CHW piping Facilities Management (unregulated) Pharmaceutical production and research facilities Steam and chilled water for University Campus BHMM IMC Central Energy Plant

Formed in mid-2004 Responded to RFP for operation of IMC Central Energy Plant (CEP) at Indianapolis International Airport (IAA) CEP Operation by BHMM (4/1/06) Production capacity 237 mlb/hr steam (4 boilers, natural gas) 9,100 tons CHW (5 chillers) 12,000 CFM compressed air (3 compressors) 3.0 MWe (3 generators, diesel) 20,000 gpm fire protection system for IMC 12 full-time employees 2 customers Indianapolis Maintenance Center (IMC) 1.2 mm sq ft Indianapolis Midfield Terminal (MFT) 1.2 mm sq ft

Indianapolis Midfield Terminal $1.1 billion project 1.2 million sq ft Handle > 8 million passengers/year Reconfiguration of I-70 for easy access District Energy chosen by IAA as heating and cooling solution for new terminal Could utilize existing air permits Offered lower life-cycle cost Utility connector to existing plant vs new MFT plant June 2005 MFT site prep, foundation construction in-progress BHMM (w/cte) asked to evaluate proposed solution

Midfield Terminal Project Site Indianapolis International Airport

BHMM Evaluation/Proposal Initial IAA Concept Walk-thru tunnel (14 ft OD) All piping pre-fab, carbon steel Walk-in access to tunnel vaults Design Bid (firm price) ROM $42 - $50 million BHMM Proposal Temporary liner-plate tunnel (9 ft OD) Ductile iron for direct buried CHW piping Limited access vaults No tunnel access (piping grouted in-place) Value-Engineer as construction progresses Utilize Target Price Contract ROM $27.0 million

Utility Connector Route 2,016 ft tunnel 5,890 ft from CEP MFT U/G, direct-buried piping, electric and communications ductbanks

IAA Requirements and Considerations for Utility Connector Design and Construction Utility Connector Piping 8 HTHW - 300 psig, 325 F supply, 200 F return 24 CHW - 150 psig, 42 F supply, 54 F return FAA approvals for construction Construction Safety Phasing Plan 7460s for construction activity Site Security and Access Plan Runway and taxiways to remain open Zero ground settlement Develop Tunnel Risk Management Plan MBE/WBE participation (15/8/23 req d)

Project Team Indianapolis Airport Authority - Owner Aviation Capital Management - OTR Parsons Brinckerhoff Project Engineer BHMM / CTE Project Management and Financing Bowen Engineering General Contractor Midwest Mole Tunnel Contractor PermaPipe, US Steel Pipe Manufacturers

Design Development Reengineered tunnel design Liner plates Tunnel Boring Machine (TBM) EPB design Grout and soil conditioner designs Reengineered tunnel piping and manholes Finalized engineering for U/G and arbor piping systems Developed Construction Safety Phasing Submittals to FAA for 7460s Prepared Tunnel Risk Management Plan

Unique Aspects of Project TBM Design, Acquisition, and Delivery Bored Tunnel Construction Tunnel Utilities and Thermal Piping Underground and Arbor Piping

Tunnel Boring Machine Acquisition, Design, and Delivery Earth Pressure Balance (EPB) design Constant face pressure Steerable Mitigates ground settlement Colorado School of Mines study Disc cutters Soil conditioner maintain muck density of 85 100 lb/cu ft Grout design adequate compressive strength cure at < 180 F to protect conduits and pipe jacketing Mock-ups and testing Data acquisition and machine control

Fully Assembled EPB Tunnel Boring Machine

Tunnel Boring Machine Design Colorado School of Mines study Disc cutters Standard vs Special Soil conditioner maintain muck density of 85 100 lb/cu ft Grout design adequate compressive strength cure at < 180 F to protect conduits and pipe jacketing Mock-ups and testing

TBM Drill Head

Tunnel Boring Machine Design Data acquisition and machine control Data Acquisition and Monitoring Station TBM Operator Booth Seal Wall and Ring

TBM Delivery

TBM Drill Head 53 tons

Drill Head Placement

Bored Tunnel Construction 2,016 ft long x 9 ft OD Liner plate construction 4,750 cu yds material removed TBM Operation Started 6/26/06 Breakthrough 11/6/06 (18 wks) Grouting After installation of ductbank and piping Used ~3,000 cu yds cellular concrete Started 3/29/07 Finished 4/27/07 (4 wks)

Bored Tunnel Construction Liner plate construction Resist jacking force of TBM Compressive loading from airfield traffic 20 ft above crown at runway 8,064 liner plates (~104 lb ea) > 56,000 5/8 x 1-1/2 A307 bolts

Liner Plate Construction Grout, Soil Conditioner, Air, and Water Piping, TBM Power Cable

Bored Tunnel Construction 4,750 cu yds material removed Soil Conditioner Grouting After installation of ductbank and piping Used ~3,000 cu yds cellular concrete Started 3/29/07 Finished 4/27/07 (4 wks)

Tunnel Muck into Cart

Tunnel Boring Machine Breakthrough 2,016 ft tunnel complete on Nov 6, 2006

Tunnel Utilities Communications Conduit 2-2 Steel Fiber Cabling 2-48-fiber cables Thermal Piping Electric Ductbank 12-4 PVC 2-2 PVC

Tunnel Thermal Piping 8 HTHW Piping PermaPipe UltraTherm 8 A53 Gr B Smls 100-mil FRP and polyurethane jacket over steel casing 3 mineral wool insulation 24 CHW Piping PermaPipe PolyTherm 24 A53 Gr B ERW Fiberglass jacket, polyurethane foam insulation

Thermal Piping at North Tunnel End (EP4)

Thermal Piping at South Tunnel End (EP8)

Excavation at Tunnel Entrance Jacking Pit (EP4) 55 x 60 x 22 ft deep

Jacking Pit (EP4) and Tunnel Entrance Sheet Piling, Bracing, Flooring and Seal Wall

Excavation at Tunnel End Receiving Pit (EP8) 30 x 30 x 43 ft deep

Receiving Pit (EP8) and Tunnel Exit Sheet Piling, Bracing, Flooring, Seal Wall

Drill Head Removal

Ductbank, Seal Wall, Piping, Exit Stairs Foundation for South Manhole (EP8)

Operation Noodle 8 HTHW Piping Supply & Return - pulled together Max connected load 260,000 lb Min bend radius - 675 ft 24 CHW Piping Supply & Return - pulled separately Max connected load 330,000 lb (3 1,000 ft segments) Min bend radius - 800 ft Above ground assembly and testing Estimated savings 5 months, ~$1,000k

Operation Noodle Above Ground Assembly and Test

Operation Noodle 8,000 ft Ready-to-Pull

Ramp and Rollers into EP4

HTHW Supports and Guides

HTHW Sling Supports Pulling Yoke

Track Hoe with Pipe Supports

HTHW Pipe Pull Complete Pipe Ends at EP4 Pulling Yoke thru at EP8

CHW Pipe Pull

CHW Pipe Pull Rigging and Supports at EP4 3,000 ft Connected

Pipe Tugger Tugger used for Pipe Pulls Protective Shield

Tunnel Pipe Support for Pulling HTHW Piping CHW Piping

Direct-Buried and Arbor Piping Direct-Buried Piping HTHW - PermaPipe, MultiTherm 500 8 A53 Gr B Smls 100-mil FRP and polyurethane jacket over steel casing 3 mineral wool insulation CHW US Pipe 24 cement-lined, ductile Iron Not insulated Arbor Piping HTHW - field insulated, 8 A53 Gr B Smls CHW - field insulated, 24 A53 Gr B ERW

Direct-Buried Piping into MFT

Direct-Buried Piping thru Hotel Vault

Direct-Buried Piping In/Out EP4

Direct-Buried Piping btwn EP4 and Arbor

Arbor Piping

Project Timeline Initial Concept to Final Design in ~24 wks (Sep 05 thru Feb 06) Construction took 20 months (Mar 06 thru Nov 07) In-Service Dates CHW 9/24/07 HTHW 10/31/07 (180 F); 12/1/07 (200 F); 1/22/08 (325 F)

Cost Summary Cost Utility Connector - $24,350,000 General Construction - ($16,220k) Tunnel and Grout - ($8,130k) MBE / WBE Participation Target 15 / 8 / 23 Actual 13.0 / 10.4 / 23.5 Utility Connector Savings Delivered to Owner >>> $3,859,000 <<<