TRITON KNOLL ELECTRICAL SYSTEM CONSULTATION: QUESTIONNAIRE



Similar documents
Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan

Who is National Grid?

Viking Link Interconnector

Wind turbines on your land. Renewable energy development for landowners

1 Welcome. The exhibition comprises a series of boards which provide some background information to show you our initial ideas for the site.

Our approach to the design and routeing of new electricity transmission lines

environment briefing02

Experience from the first large scale tidal turbine EIA in Europe. How do we work towards effective and proportionate EIA?

Firth of Forth Offshore Wind Farm Zone. Offshore and Onshore Project Information

East Midlands Intermodal Park, South Derbyshire Proposals for a Strategic Rail Freight Interchange

Galloper Wind Farm Project. Traffic Management Plan May 2013 Draft v1 Document Reference GWF/TMP/ Galloper Wind Farm Limited

Who are we? *Based on an average annual domestic household electricity consumption of 4,700KWh (DECC).

1.0 THE PROPOSAL...2. Introduction 2 Project Description THE APPLICANT OUR APPROACH TO COMMUNITY CONSULTATION...2

Developing Ocean Energy in Ireland. Belmullet Wave Energy Test Site

Development proposals will require to demonstrate, according to scale, type and location, that they:-

AGENCY COORDINATION AND PUBLIC INVOLVEMENT

4 Alternatives and Design Evolution

Planning Act 2008: Guidance on Changes to Development Consent Orders. December 2015 Department for Communities and Local Government

COPCUT RISE COPCUT RISE DROITWICH SPA CONSULTATION STATEMENT. November Prepared by Capita Lovejoy on behalf of William Davis Limited

Alphington sewer replacement

WELCOME TO THE BAD Á CHEÒ WIND FARM EXHIBITION

APPLICATION FOR PLANNING PERMISSION FOR A SOIL TREATMENT FACILITY AT KINGS CLIFFE LANDFILL SITE, STAMFORD, NORTHAMPTONSHIRE

5 ALTERNATIVE SOLUTIONS AND EVALUATION

There are access points readily available into the site.

Site Deliverability Statement Development at: Beech Lane, Kislingbury. Persimmon Homes Midlands March 2015

Offshore Work Packages

Charging for Pre-application Advice. WSCC Guidance Note

Undergrounding high voltage electricity transmission. The technical issues

Overhead lines in Ireland

PLANNING SERVICES UNIT

2015 No. 595 TOWN AND COUNTRY PLANNING, ENGLAND. The Town and Country Planning (Development Management Procedure) (England) Order 2015

A new Garden Neighbourhood for West Guildford An opportunity for Smart Growth. university of surrey November 2013

Development Management Report

PB POWER ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS

I refer to the application made by Aquamarine Power Ltd. ( the Company ), dated 17 th June 2011 for:

23.1 RENEWABLE ENERGY

Advice can also be sought from specific specialist officers in the Council.

November 2013 PLANNING PRE- APPLICATION ADVICE AND PLANNING PERFORMANCE AGREEMENT SERVICE

REPORTS SUSTAINABILITY AND ENVIRONMENT 11 MAY 2015 ORDINARY COUNCIL MEETING OF COUNCIL

HS2 Phase One Planning Forum Highways Sub-group. Meeting #2 November 2014

Eldorado-Ivanpah Transmission Project WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE

Once an assessment has been made, the decision on whether the scheme will be put forward to the Panels will be reported to you.

SAN DIEGO GAS & ELECTRIC COMPANY SOUTH BAY SUBSTATION RELOCATION PROJECT TRAFFIC MANAGEMENT PLAN SEPTEMBER 2014

Appendix C. Municipal Planning and Site Restoration Considerations

Position Statement regarding Offshore Wind Proposals on Lake Huron. Lake Huron Centre for Coastal Conservation

Sector Design Concepts

Do you own or operate underground facilities?

London Array Off-Shore Wind Farm

THIS PAGE INTENTIONALLY LEFT BLANK

Site Alternative Deliverability Report. SALT 034 Ty Nant, Groesffordd Resubmission: Deliverable. Local Development Plan

Basics of Sustainability. Environmental Impact Assessments (EIA)

Overview of Atlantic Offshore Renewable Energy Studies Program. Brian Hooker Office of Renewable Energy Programs

Prior Notification of Proposed Demolition Validation Checklist

Construction Management Plan Template

Development Brief for New Lodge, Bank Mill Lane Berkhamsted. Adopted November 2007

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS

What do we already know about Bradford-on-Avon community area?

TRAFFIC MANAGEMENT PLAN

8.0 Construction Cost Estimates

Construction Traffic Management Plan

HUNTER WATER CORPORATION Review of Environmental Factors Guidance Notes EG0041

Significant investment and improvement of infrastructure and transport networks, delivered at no cost and no risk

Tidal Energy. Wind Energy. Transmission & Distribution Network. Offshore Substation. Onshore Substation. Tidal Stream Energy.

IALN / FAO: The Planning Department The Royal Borough of Windsor and Maidenhead Town Hall, St. Ives Road Maidenhead SL6 1RF

CONSTRUCTION TRAFFIC MANAGEMENT PLAN Issue 2, V5, 11/11/13

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot

Development Management Officer Report Committee Application. Summary

APPLICATION FOR AN ELECTRICITY CONNECTION (PROJECTS)

Application No.: Steve Rush, representing Rocky Mountain Power Rocky Mountain Power Project Location: approximately 1600 N E.

Submission. 2. PURPOSE OF THE SUBMISSION To inform the NCC Board of Directors on the approach to implement the 2013 Greenbelt Master Plan.

Questions Regarding Proposed Utility Undergrounding in Kensington

BASILDON BOROUGH COUNCIL

Best practice guide for Councils when initially dealing with NBN Co. June 2011

CHAPTER 24: ENVIRONMENTAL MANAGEMENT

Purpose of the Local Liaison Committee

Pre-application service for Nationally Significant Infrastructure Projects

Gas to the West INFORMATION LEAFLET. gastothewest.com. www

8 Strait of Belle Isle Marine Cable Crossing

How To Write A New Bill On Flood Management In Scotland

DEVELOPMENT MANAGEMENT

Renewable Energies WIND

Recycling & Energy Recovery Facility

DESCRIPTION OF WORK:

Rampion Offshore Wind Farm proposal

River Wensum Restoration Strategy Swanton Morley Restoration Scheme Reach 14a

How To Conduct An Environmental Impact Assessment

LANDSCAPE AND DEVELOPMENT CHECKLIST FOR MONMOUTHSHIRE COUNTY COUNCIL

Overview of the 500MW EirGrid East-West Interconnector, considering System Design and Execution-Phase Issues

Electromagnetic Radiation

NAPA COUNTY WATERSHED SYMPOSIUM

Chapter 7 COMMUNITY FACILITIES and SERVICES PLAN

Construction Management Plan (CMP) Application

Key Facts. Passenger growth at the airport is projected to grow to approximately 3 million passengers per annum by 2030.

Environmental Compliance Questionnaire for National Oceanic and Atmospheric Administration Federal Financial Assistance Applicants

PLANNING & REGULATION COMMITTEE 16 JANUARY 2012

Taylor Wimpey UK Ltd. December 2007

A2 Pepperhill to Cobham Highway Widening project, UK

2015 AVAGO 2D SEISMIC SURVEY ENVIRONMENTAL MANAGEMENT PLAN SUMMARY

Submarine Power Cables. State-of-the-art production facility, more than 100 years of experience and reference installations around the world.

NON-TECHNICAL SUMMARY OF ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT FOR THE BAHCE WINDFARM PROJECT (135 MW)

Transcription:

RWE Innogy UK TRITON KNOLL ELECTRICAL SYSTEM CONSULTATION: QUESTIONNAIRE The Planning Act 2008 requires developers to undertake pre-application consultation before submitting an application for a Development Consent Order (DCO). This questionnaire is part of our community consultation under s47 of the Planning Act 2008. We have described how we will consult with the public and other consultees in our Statement of Community Consultation, which was consulted on with Lincolnshire County Council, East Lindsey District Council, Boston Borough Council and the Marine Management Organisation. Please use the Consultation Signpost Document to understand the different documents that are available to help you respond to the consultation. The responses we receive to this consultation will help shape our proposals before we apply for a Development Consent Order to the Secretary of State. How to participate Please answer as many of the questions in this questionnaire as you feel able to. You can also complete a questionnaire online by downloading the editable version available from www.rweinnogy.com/tritonknoll How to respond Any responses made must include contact information including a name and an address to which any correspondence relating to the consultation can be sent. Your comments will be made public in a consultation report. The report will record comments received and explain how the views of consultees have been considered in finalising the application. This report will form part of our application for development consent. Please respond by returning the completed questionnaire using this freepost address: FREE POST RTBK-ABSH-TGLU Triton Knoll Offshore Wind Farm RWE Innogy UK, Auckland House, Lydiard Fields, Great Western Way, Swindon SN5 8ZT The consultation runs from 15 October until 19 November 2014. Please note that consultation responses must be received by 5pm on 19 November 2014. If you would like this questionnaire in larger print or in another format, please contact us on: 01793 474 244

QUESTIONNAIRE SECTION 1 THE LANDFALL The landfall at Anderby Creek is where the offshore and onshore electricity cables are joined in the transition joint bays. Construction activities are likely to have the following impacts: temporary visual and noise impacts from vehicles and machinery temporary beach closures temporary increases in construction traffic. Further detail can be found in the Non-Technical Summary (NTS) of the Preliminary Environmental Information (PEI). Chapter 5 (Onshore Project Description) and Chapter 13 (Traffic and Access) of the Environmental Statement (ES) set out principles that could be applied to the management and the Outline Traffic Management Plan of construction activities. The following measures have been identified for the landfall works. These include: traffic management of construction vehicles to minimise congestion and impacts on local roads alternative pedestrian access for beach users set working hours that minimise impacts on the local community by limiting evening and weekend working. A. To what extent do you agree that the construction principles set out above will reduce the potential impacts? Please tick box B. Would you suggest any additional measures to reduce construction impacts? SECTION 2 ONSHORE CABLE INSTALLATION The onshore electrical cables will be buried underground, avoiding the need for overhead pylons. The cable route has been defined considering environmental and technical factors and also by consulting with landowners and the public as part of our Cable Route Consultation held during February and March 2014. The following measures have been proposed: where possible, locating the cable route a minimum distance of 70m from residential dwellings a burial depth below existing identified land drains to reduce impacts on farming activities avoiding environmental and archaeological constraints where possible. Further detail can be found in the NTS.

The Onshore Project Description Chapter and the outline Code of Construction Practice Document (CoCP) set out the following principles for how we propose to manage the construction activities when building the cable route. These include: Horizontal Directional Drilling (HDD) under roads, railways and larger watercourses a dedicated temporary haul road along the cable route to reduce traffic on local roads restoration after completion and the land returned to its former use. A. To what extent do you agree that the construction principles set out above will reduce the impacts of cable installation? B. Would you suggest any additional measures to reduce disruption? SECTION 3 THE INTERMEDIATE ELECTRICAL COMPOUND (IEC) AND THE ONSHORE ELECTRICITY SUBSTATION (SUBSTATION) The IEC and Substation contain electrical equipment that is necessary for the transmission of electricity from the offshore array and connection of the Triton Knoll Offshore Wind Farm to the national grid. The photomontages and other designs displayed at the public exhibitions and in the ES show what the infrastructure could look like from certain viewpoints. We have identified a set of principles that will be applied to the final design of the IEC and the Substation in the Design Considerations Document. Our landscaping principles include the following: a 50m area available for landscaping around the IEC and the Substation planting would begin during construction to allow screening to become established a mixture of slow and fast growing native species are proposed. A. Which do you think is the most appropriate screening for the Substation and IEC? Please tick box Substation A mixture of slow and fast growing native species Fast growing non-native species No screening IEC A mixture of slow and fast growing native species Fast growing non-native species No screening B. Do you have any other comments about our landscaping and screening principles?

C. Design options for the buildings and noise barriers at the IEC and Substation can be seen in the Design Considerations Document. What do you think is the most appropriate design for the IEC and Substation? Please tick box Substation Local vernacular (brick or stone) Modern design (wood cladding) Modern design (metal cladding) Modern design Noise barriers Pale grey Khaki Gradated green No preference IEC Local vernacular (brick or stone) Modern design (wood cladding) Modern design (metal cladding) Modern design Noise barriers Pale grey Khaki Gradated green No preference Do you have any other suggestions? SECTION 4 MANAGING CONSTRUCTION TRAFFIC Following comments about our access proposals during our Alternatives Consultation held during February and April 2013, and during the Parish Council update meetings in March and April 2014, we have modified our access proposals at the IEC to avoid the village of Orby and at the Substation to avoid the village of Bicker. A. Do you think that our alternative access proposals will reduce the impacts of construction traffic when compared to the original routes planned through the villages of Bicker and Orby? Please tick box The outline Traffic Management Plan sets out the main principles of managing traffic during construction of the project. These include: Horizontal Directional Drilling to avoid road closures notifications of roads to be used and when safety and traffic management measures to be put in place roads we will avoid. B. To assist us in developing a final Traffic Management Plan to minimise disruption, are there any specific additional measures you would suggest to reduce traffic impacts during construction, and why?

SECTION 5 MANAGING IMPACTS ON ECOLOGY The Landscape and Ecological Mitigation Strategy, which forms part of Chapter 6 (Landscape and Visual), sets out how we will manage impacts on ecology during construction, including: avoiding hedgerows and other sensitive habitats undertaking pre-construction surveys to avoid protected species ensuring best practice construction management techniques are used to reduce the risk of contamination of watercourses Project Ecologists overseeing environmentally-sensitive activities. A. To what extent do you agree that the principles set out will reduce ecological impacts? Please tick box B. Would you suggest any additional measures to reduce impacts? SECTION 6 THE OFFSHORE CABLE ROUTE The NTS and Offshore Project Description Chapter of the ES describe the key design principles which have shaped the offshore cable route, including: avoiding sensitive ecological areas minimising the amount of rock or concrete mattressing that will be required to protect the cable by routing the cable through areas of the seabed where the required burial depth can be achieved avoiding dredging areas reducing impacts on fishermen and other sea users. A. To what extent do you agree that we have captured the important issues for the offshore elements of the proposed electrical system? Please tick box B. Is there any other information about the offshore cable route you think we should consider?

SECTION 7 THE CONSULTATION A. How were you informed about the Triton Knoll Electrical System Consultation? Please tick box Newsletter Newspaper advert Local media other B. Have you found the public exhibitions helpful in answering questions or concerns you may have had? Please tick box Yes No C. Was the information available in the consultation documents and at the exhibitions helpful in answering questions or concerns you may have had? Please tick box Yes No D. If you would like to be kept up to date with the project, how would you like us to contact you? Please tick box Email Newsletter E. Do you have any other comments on the consultation or our proposals? (You can continue on a separate sheet for any of the questions)

YOUR DETAILS Any responses made must include contact information including a name and an address to which any correspondence relating to the consultation can be sent. Please provide details below: Name Address Telephone E-mail All personal details provided will be held in accordance with the Data Protection Act and will not be passed on to any third parties. Your comments will be made public in a consultation report. The report will record comments received and explain how the views of consultees have been considered in finalising the application. This report will form part of our development consent application. Thank you very much for taking the time to complete this questionnaire. Please give it to a member of staff or send by freepost to the address below. Contact us Email: Tritonknoll@rwe.com Telephone: 01793 474 244 Web: www.rweinnogy.com/tritonknoll Post: FREE POST RTBK-ABSH-TGLU Triton Knoll Offshore Wind Farm RWE Innogy UK Auckland House Lydiard Fields Great Western Way Swindon SN5 8ZT