Impulse Voltage Test of Power Transformers

Similar documents
Lightning current simulation in the laboratory - parameters, procedures and test equipment -

INTERNATIONAL STANDARD

Guidance for upgrading to GB (IEC : 2005, MOD)

Impedance Matching and Matching Networks. Valentin Todorow, December, 2009

GUIDE FOR TESTING POWER TRANSFORMERS

Unified requirements for systems with voltages above 1 kv up to 15 kv

A Practical Guide to Dielectric Testing

Testing of Power Transformers. Routine tests, Type tests and Special tests

How to design SMPS to Pass Common Mode Lightning Surge Test

However, industrial applications may utilize a relay, which short-circuits the ICL path after the inrush sequence.

Instrument Transformers Application Guide

SUITABILITY OF DIFFERENT TEST VOLTAGES FOR ON-SITE TESTING OF XLPE CABLE SYSTEMS

CHAPTER 28 ELECTRIC CIRCUITS

BASIC ELECTRONICS AC CIRCUIT ANALYSIS. December 2011

Discussion on Class I & II Terminology. IEEE PES Transformers Committee Fall Meeting 2011 Boston, MA

Power transformers. Special transformers Railway

AS A Low Dropout Voltage Regulator Adjustable & Fixed Output, Fast Response

Circulating Current Relay. Type IRXm

TAN δ (DELTA) CABLE TESTING OVERVIEW AND ANSWERS TO FREQUENTLY ASKED QUESTIONS. What Is Tan δ, Or Tan Delta?

TYPE TEST CERTIFICATE OF SHORT-CIRCUIT PERFORMANCE. A three-phase outdoor oil-immersed distribution transformer

AC Direct Off-Line Power Supplies

Power Supplies. 1.0 Power Supply Basics. Module

Electricity. Confirming Coulomb s law. LD Physics Leaflets P Wie. Electrostatics Coulomb s law

Line Reactors and AC Drives

The full wave rectifier consists of two diodes and a resister as shown in Figure

Inrush Current. Although the concepts stated are universal, this application note was written specifically for Interpoint products.

Application Note, Rev.1.0, September 2008 TLE8366. Application Information. Automotive Power

Application Note AN- 1095

ACCURACY OF POTENTIALTRANSFORMERS

Capacitor Voltage Transformer. Answers for energy.

Charged cable event. 1 Goal of the ongoing investigation. 2 Energy sources for the CDE. Content

Understanding Power Impedance Supply for Optimum Decoupling

Three phase circuits

Transformers. Special transformers Reactors products

Lightning Impulse Discharge Behaviour in Tap -Water Gap

Slide 1 / 26. Inductance by Bryan Pflueger

14.5GHZ 2.2KW CW GENERATOR. GKP 22KP 14.5GHz WR62 3x400V

SURGE PROTECTIVE DEVICES

Coordination of Telecommunications Surge Protective Devices in Countries with Unstable AC Power

The Importance of the X/R Ratio in Low-Voltage Short Circuit Studies

The Bergeron Method. A Graphic Method for Determining Line Reflections in Transient Phenomena

CAN Bus Transceivers Operate from 3.3V or 5V and Withstand ±60V Faults

INTERNATIONAL STANDARD

SANS : 2008 CODE OF PRACTICE THE WIRING OF PREMISES Part 1 : Low Voltage Installation

High Voltage Circuit Breakers 3AP Type 72.5 kv to 800 kv Answers for energy.

Diode Circuits. Operating in the Reverse Breakdown region. (Zener Diode)

Inductors in AC Circuits

Using Current Transformers with the 78M661x

New Distribution Class Arrester Ground Lead Disconnector Design Enhances Detonation Reliability and Improves Arrester Performance

Electronic timer CT-AHD.12 OFF-delayed with 1 c/o (SPDT) contact

Power measurement in balanced 3 phase circuits and power factor improvement. 1 Power in Single Phase Circuits. Experiment no 1

Circuits with inductors and alternating currents. Chapter 20 #45, 46, 47, 49

SECTION 2 Transmission Line Theory

Three-phase monitoring relay CM-PFE

Power System review W I L L I A M V. T O R R E A P R I L 1 0,

BSNL TTA Question Paper-Instruments and Measurement Specialization 2007

How To Understand The Electrical Power Supply Of A Power Supply System

A Simple Current-Sense Technique Eliminating a Sense Resistor

Automated test systems for distribution transformers Part II. Detailed analysis of the test system features EVENTS ABSTRACT KEYWORDS

Eðlisfræði 2, vor 2007


INTERNATIONAL STANDARD

LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS

SERIES-PARALLEL DC CIRCUITS

Let s examine the response of the circuit shown on Figure 1. The form of the source voltage Vs is shown on Figure 2. R. Figure 1.

= (0.400 A) (4.80 V) = 1.92 W = (0.400 A) (7.20 V) = 2.88 W

A wave lab inside a coaxial cable

Lecture - 4 Diode Rectifier Circuits

Voltage Regulator SPAU 341 C. Product Guide

ALTERNATIVE METHODS FOR INTERNAL ARC TESTS ON 12 KV AND 24 KV METAL-ENCLOSED SWITCHGEARS WITH COMPACT RMU

Selection Guide for Conversion of Carbon Composition Resistors

REPORT ON CANDIDATES WORK IN THE CARIBBEAN ADVANCED PROFICIENCY EXAMINATION MAY/JUNE 2008 ELECTRICAL AND ELECTRONIC TECHNOLOGY (TRINIDAD AND TOBAGO)

TWENTIES WORKSHOP, EWEA 2012 Unveiling the future energy system: full scale demonstrations to reach 2020 targets. 17th April 2012

MOBILE SYSTEM FOR DIAGNOSIS OF HIGH VOLTAGE CABLES (132KV/220KV) VLF-200 HVCD

EDEXCEL NATIONAL CERTIFICATE/DIPLOMA UNIT 5 - ELECTRICAL AND ELECTRONIC PRINCIPLES NQF LEVEL 3 OUTCOME 4 - ALTERNATING CURRENT

Class I surge protection with sparkover gaps

CURRENT ELECTRICITY INTRODUCTION TO RESISTANCE, CAPACITANCE AND INDUCTANCE

RC NETWORKS SALES GUIDE

F05D Meeting on Damped AC Voltage Testing

CAPACITOR BANK TESTING SWP

AMIS. Automated Metering and Information System. Integration of meters from other manufacturers

Electrical network protection. Protection guide. Guide G 51G 51G 51G 51G. network protection solutions

DIMENSIONING OF CURRENT TRANSFORMERS FOR PROTECTON APPLICATION

Case Studies in On-Line Measurement of PD in Motors Fed by Voltage Source PWM Drives

Load Dump Pulses According to Various Test Requirements: One Phenomenon Two Methods of Generation A Comparison

TESTS OF 1 MHZ SIGNAL SOURCE FOR SPECTRUM ANALYZER CALIBRATION 7/8/08 Sam Wetterlin

IEC ESD Immunity and Transient Current Capability for the SP72X Series Protection Arrays

Transformer Bushings for GIS

Residual Current Circuit Breaker

Trip circuit supervision relay. Type RXTCS

Current and voltage measuring relays

AC Generators. Basic Generator

Chapter 3. Diodes and Applications. Introduction [5], [6]

HOW TO SELECT VARISTORS

Understanding Ignition Waveforms

Pluggable interface relays CR-P Pcb relays

Design of High Voltage Low Power Supply Device

ABB 1. Three-phase monitoring relay CM-PFS. Data sheet. Features. Approvals. Marks. Order data. Order data - Accessories. Application.

Low Voltage, Resistor Programmable Thermostatic Switch AD22105

7-41 POWER FACTOR CORRECTION

Transcription:

Impulse Voltage Test of Power Transformers Lukesh Kumar Sahu 1, Shruti Soni 2, Chandra Shekhar Chandrakar 3 1, 2, 3 Department of Electrical and Electronics Engineering, KITE Raipur Chhattisgarh Swami Vivekananda Technical University Raipur (C.G.) India lukesh1987@gmail.com shrutisoni021290@gmail.com cchandrakar943@gmail.com Abstract: During the Lightning Impulse (LI) test of transformer windings with a low impedance it is difficult to ensure a minimum time to half-value of 40 μs in accordance with IEC 60076-3 and IEC 60060-1. This is caused by the oscillating discharge determined by the impulse voltage test generator capacitance and the transformer impedance. In most cases using special adapted circuits can solve the problem Keywords: Impulse Voltage, Resistive earthing, Projection of an impulse voltage, effective impulse capacitance. 1. Introduction 1.1 Impulse voltage test generator with capacitive load For the LI testing of basic arrangements but also of different electrical components a purely capacitive load can be assumed. The impulse voltage shape generated by an impulse voltage test generator based on the MARX multiplier circuit can be described by two exponential functions with different time constants. Whereas the LI front time T1 according to IEC 60060-1 [1] is essentially determined by the resistance of the front resistor Rs located in the impulse voltage test generator and the load capacitance Ct, see Figure 1, the time to half-value T2 is determined by the impulse capacitance of the impulse capacitor Ci and the resistance of the tail resistor Rp being part of the impulse voltage test generator. According to IEC 600060-1 there are the following time parameters and tolerances for the standard LI 1.2/50: Front time T1 = 1.2 μs + 30 % Time to half-value T2 = 50 μs + 20 % (b) Figure 1: LI test at a capacitive load a) Principal circuit b) Standard LI 1.2/50 (IEC 60060-1) with time parameter T1 and T2 Equation for the voltage shape Vi t = V K e 1 t2 e 1 t1 ` (1) 1.2 Impulse voltage test generator with inductive load (a) Ci Impulse capacitance Ct Capacitance of the load (including voltage divider) Rp Tail resistor Rs Front resistor SG Switching spark gap In most of the cases power transformers cannot be assumed as a purely capacitive load for the LI testing. Usually the LI test voltage is applied to one winding terminal of the transformer to be tested, whereas all other terminals are connected with the earth. Hereby, not only the input capacitance of the transformer winding acts as the load for the impulse voltage test generator but also its impedance to all other short-circuited windings. The principal circuit (Figure 1) must be extended by the transformer inductance Lt that is connected in parallel to the test capacitance Ct (Figure 2). 120

(a) Ci -Impulse capacitance Ct- Capacitance of the load including voltage divider) Lt- Inductance of the load Rp- Tail resistor Rs- Front resistor SG -Switching spark gap International Journal of Science and Research (IJSR) the aperiodic discharge of the impulse capacitance turns to a damped oscillating cosine shape. This is permitted in principle acc. to IEC 60076-3 [2]. However, the lower tolerance limit for the time to half-value of T2 min may not remain under 40 μs (= 50 μs - 20 %). At the other side the amplitude of opposite polarity of the LI voltage dmax should not exceed 50 %. To fulfill these both requirements the impulse voltage impulse voltage test generator must have a minimum required impulse capacitance Ci req, which can be calculated closely as following C i req 2 T 2 2min (4) L l With T2 = 40 μs Hence it follows with equation (3): C i req 2 T 2 min 2 1oo ω P tot V imp% V P P 2 (5) (b) Figure 2: LI test at an inductive/capacitive load a) Principal circuit b) Voltage shape depending on the -inductance factor Ll Equation for the voltage shape is V i t V K 1 e δt cos ωt φ K 2 e 1/t (2) Though the requirement for a minimum impulse capacity Ci req of the impulse voltage test generator is necessary but it is not sufficient to meet the requirements T2 min 40 μs (IEC) and dmax 50 %. Moreover, the oscillating circuit formed by the impulse capacitance Ci of the impulse voltage test generator and the winding inductance Lt must have a certain characteristic damping. This is mainly determined by the front and tail resistors (Rs, Rp) located in the impulse voltage test generator. If the damping is to low, a minimum time to half-value T2min 40 μs can be reached but the amplitude of opposite polarity d is more than 50 %. For a higher damping the requirement for the amplitude of opposite polarity d 50 % can be fulfilled, but the time to half-value may remain smaller than 40 μs, see Figure 3. In the case that the impulse capacitance of the impulse voltage test generator Ci is not greater than the minimum required impulse capacitance Ci req according to equation (5), the adjustment of the damping of the test circuit must be done very exactly. The margin for the adjustment, i.e. for the sufficient circuit damping, becomes greater the more the impulse capacitance of the applied impulse voltage test generator Ci exceeds the minimum required impulse capacitance Ci req according to equation (5). Thereby the inductance Lt of the load becomes smaller with decreasing impedance voltage V imp % with decreasing rated phase-to-phase voltage VP-P and with increasing power P tot of the transformer winding to be tested. Therefore the lowest values of the inductance Lt have to be considered by testing the low-voltage side windings for power transformers. For a three-phase winding in a star connection the following equation can be applied: L l = V 2 imp% V P P (3) 100 ω P tot ω =2πƒ Lt Inductance (stray inductance) of the winding to be tested Vimp% Impedance voltage of the winding to be Tested VP-P Rated phase-to-phase voltage of the three-phase winding to be tested Ptot Rated total power of the three-phase winding to be tested f Rated frequency With decreasing inductance Lt the impulse capacitance Ci of the impulse voltage test generator is not only discharged via the tail resistor Rp but also via the low inductance Lt of the winding to be tested. Thereby the time to half-value T2 of the LI is reduced and Figure 3: LI test of power transformers with different damping of the test circuit (a), (b): Damping to low - the amplitude of opposite polarity d of the LI is too high (d > 50%) (c): Optimal damping (T2 > 40μs, d < 50%) 121

(d), (e): Damping to high - T2 is to short (T2 < 40μs) International Journal of Science and Research (IJSR) 2. Resistive Earthing of Winding Terminals If the requirements acc. to equation (5) cannot be fulfilled for the LI test of power transformers with an existing impulse voltage test generator, IEC 60076-3 allows for the following exceptions: a) A shorter time to half-value than T2 = 40 μs can be agreed between the manufacturer and the customer of the transformer b) Winding terminals being not directly exposed to the test voltage, can be earthed via termination resistors The resistance of the termination resistors has to remain under 500 Ohm. Furthermore, it has to made sure that the voltage which will occur at the resistively earthed winding terminals will not exceed 75 % of the rated LI withstand voltage of these windings. With this method it is often possible to extend the operating range of an impulse voltage test generator considerably. Nevertheless, it must be noted that hereby, the impulse voltage stress of the tested windings may considerably deviate from the voltage stress for direct earthing. It has to be agreed between customer and manufacturer which exception is accepted. voltage and the stage energy of an impulse voltage test generator for the LI test. The total charging voltage of the impulse voltage test generator should lie for LI testing 30 % 60 % above the highest required LI test voltage. In many cases the value of 30 % is sufficient for routine tests. If development tests are to be carried out, a total charging voltage, which lays 60 % above the highest rated LI test voltage, is recommended. If the exception earthing via termination resistors is not considered, the required impulse capacitance Ci req can be calculated for each winding voltage level acc. to equation (5). Taking into consideration the different circuitry options of the impulse voltage test generator (parallel connection of stages, partial operation) and the above aspects regarding the total charging voltage the stage charging energy can be calculated in principle for each possible test case. Normally a stage energy of 5 10 kj per 100- kv-stage and a stage energy of 10 20 kj per 200-kV-stage will be sufficient. Whereas the lower values apply to transformers with lower power, the higher values apply to transformers with higher power (Figure 4). Often, impulse voltage test generators for power transformer testing have energy of 15 kj per 200-kVstage, see Figure 5. 4. Extension of The Loading Range of Impulse Voltage Test Generators Often it is required to test transformer with such a high power, for which the existing impulse voltage test generator has not been originally meant. In such cases it is necessary to utilize al reserves of the existing impulse voltage test generator. 4.1 Increasing the effective impulse capacitance The following generally known measures can be taken: a) running the impulse voltage test generator in partial operation, i.e. with the minimum number of stages, being necessary to reach the required test voltage level. b) Switching a certain number of generator stages respectively in parallel and connect this parallel stages in series to reach the required test voltage. 4.2 Increasing the parallel resistors If the time to half-value remains only a few below the permitted lower limit T2 min = 40 μs, it is possible to reach a value of T2 40 μs by increasing the tail resistors Rp. Usually the tail resistors meant for switching impulse voltage can be applied. Figure 4: Impulse Voltage Test System IP 360/3600 G (360 kj, 3600 kv) with impulse voltage divider and chopping multiple spark gaps, with stage energy of 20 kj being used for the LI test of power transformers up to 765 kv A further increase of the resistance of the tail resistors Rp above the resistance value for the SI generation does not have any result. 3. Projection of an impulse voltage test generator for the LI test of power transformers The main technical data of the transformers to be tested, like the circuitry and the arrangement of the windings, their rated voltage, rated power, impedance voltage and not at least the rated frequency determine essentially the total charging 122

Figure 5: Impulse Voltage Test System IP 150/2000 G (150 kj, 2000 kv) with impulse voltage divider and chopping multiple spark gap, with a stage energy of 15 kj being used for the I test of power transformers up to 245 kv 4.3 Decreasing the damping of the test circuit As already mentioned in chapter 2, if the circuit damping is to high, a time to half-value of T2 40 μs is not reached even with a sufficient impulse capacitance of the impulse voltage test generator (Ci Ci req), see Figure 3.The front and tail resistors in the impulse voltage test generator are mostly responsible for that damping. The damping caused by the tail resistors Rp can be considerably eliminated by their increase, as already recommended in chapter 5.2.. For a further reduction of the damping the resistance of the front resistor Rs has to be reduced. This would cause a shorter front time T1 of the LI. To keep the front time T1 unchanged, the capacitance of the load has to be increased corresponding to the reduction of the resistance of the front resistor Rs. This is easily realized by connecting an additional capacitor in parallel to the transformer winding to be tested. Unfortunately, the effect of this method is limited, because a reduction of the resistance of the front resistor Rs will lead to oscillations on the front of the LI voltage soon, which may exceed the permitted limit for the overshoot of 5 % /1/. Figure 6: Test circuit with Glaninger-circuit (Lg and R l ) for LI testing of power transformers with extremely low impedance Ci -Impulse capacitance C l -Capacitance of the load (including voltage divider) Lg -Glaninger-coil L l -Inductance of the load Rp -Tail resistor Rs -Front resistor R l -Resistor in parallel to the load SG- Switching spark gap The Glaninger-coil must have an inductance value ca. 100 200 μh, to be ineffective for the fast impulse front and to bridge the front resistor Rs during the much longer impulse tail. So the front of the LI impulse remains unchanged and the tail is extended. Consequently an additional resistor R l has to be switched in parallel to the load inductance Lt, to form a true voltage divider consisting of Rs//Lg and R l //L l. Figure 7: LI test of power transformers by using the Glaninger-circuit, adjustment of the voltage shape at the voltage crest by means of an additional resistor Rt (optimal adjustment Rt = 300 Ohm for this example) 4.4 Application of the Glaninger-circuit The disadvantage of oscillations on the voltage front after a reduction of the front resistor Rs is completely avoided with a circuit invented by GLANINGER [3]. Hereby the front resistor responsible for the voltage front remains unchanged but it is bridged by an additional inductance formed by an air-coil (Figure 6). 123

Figure 8: LI test of power transformers by using the Glaninger-circuit, adjustment of the time to half-value T2 and the amplitude of opposite polarity d by means of the tail resistor Rp (optimal adjustment Rp = 60 Ohm for this example, T2 > 40 μs, d < 50 %) With a Glaninger-circuit the front time T1, the time to halfvalue T2 and the amplitude of opposite polarity d of the LI test voltage can be set almost independently, i.e. T1 with the tail resistor Rs, T2 and d with the resistors Rp und Rt (Figure 7 and 8). A variation of the Glaninger-coil inductance is as a rule not necessary. The Glaninger circuit enables for LI testing the most effective adaptation of the impulse voltage test generator and the transformer to be tested. An existing impulse voltage test generator can be utilized optimally. 5. Conclusion The testing of power transformers with LI test voltage acc. to the IEC standards presupposes special knowledge of the interaction between the impulse voltage test generator and the inductive load. For example, there exists a close connection between the main data of the transformer to be tested and the required impulse capacitance of the impulse voltage test generator. There are also requirements related to the damping characteristic of the test circuit to utilize an existing impulse voltage test generator optimally. Some basic aspects and circuitries were described in this paper. References [1] IEC 60060-1 (1989-11), High-voltage test techniques. Part 1: General definitions and test requirements. [2] IEC 60076-3 (2000-03), Power transformers Part 3: Insulation levels, dielectric tests and external clearances in air. [3] Glaninger, P.: Stoßspannungsprüfung an elektrischen Betriebsmitteln kleiner Induktivität. ISH Zürich, 1975, Beitrag 2.1-05 HV. 124