IEEE C IEEE Standard General Requirements for Liquid-Immersed Distribution, Power, and Regulating Transformers

Similar documents
Digital Energy ITI. Instrument Transformer Basic Technical Information and Application

GUIDE FOR TESTING POWER TRANSFORMERS

VOLTAGE REGULATOR AND PARALLEL OPERATION

Transformer Design & Design Parameters

CAPACITOR BANK TESTING SWP

2. A conductor of length 2m moves at 4m/s at 30 to a uniform magnetic field of 0.1T. Which one of the following gives the e.m.f. generated?

The full wave rectifier consists of two diodes and a resister as shown in Figure

3) What is the difference between "Insulating", "Isolating", and "Shielded Winding" transformers?

Generator Stator Protection, under/over voltage, under /over frequency and unbalanced loading. Ramandeep Kaur Aujla S.NO

Line Reactors and AC Drives

CT Application Guide for the 489 Generator Management Relay

A Practical Guide to Dielectric Testing

THE VALUE OF POWER FACTOR TESTING

Selecting Current Transformers Part 1 By Darrell G. Broussard, P.E.

Discussion on Class I & II Terminology. IEEE PES Transformers Committee Fall Meeting 2011 Boston, MA

GenTech Practice Questions

PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS

BSNL TTA Question Paper-Instruments and Measurement Specialization 2007

Single and Three Phase Transformer Testing Using Static Motor Circuit Analysis Techniques

Power transformers. Special transformers Railway

Circuits with inductors and alternating currents. Chapter 20 #45, 46, 47, 49

BASIC ELECTRONICS AC CIRCUIT ANALYSIS. December 2011

Diode Applications. by Kenneth A. Kuhn Sept. 1, This note illustrates some common applications of diodes.

DHANALAKSHMI COLLEGE OF ENGINEERING DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING EE ELECTRICAL MACHINES II UNIT-I SYNCHRONOUS GENERATOR

WINDING RESISTANCE TESTING

The Importance of the X/R Ratio in Low-Voltage Short Circuit Studies

Guidance for upgrading to GB (IEC : 2005, MOD)

Selecting IHLP Composite Inductors for Non-Isolated Converters Utilizing Vishay s Application Sheet

HPS Universal. Single and Three Phase Potted. Buck-Boost Transformers. Buck-Boost Applications & Standard Specification... 80

Testing of Power Transformers. Routine tests, Type tests and Special tests

CHAPTER 5 PHOTOVOLTAIC SYSTEM DESIGN

INTRODUCTION TO SYSTEM PROTECTION. Hands-On Relay School 2012

Drive circuit basics + V. τ e. Industrial Circuits Application Note. Winding resistance and inductance

Power Quality Paper #3

Current and Temperature Ratings

TAN δ (DELTA) CABLE TESTING OVERVIEW AND ANSWERS TO FREQUENTLY ASKED QUESTIONS. What Is Tan δ, Or Tan Delta?

Power Supplies. 1.0 Power Supply Basics. Module

Presentation of the France Transfo factories

Understanding the Alternator

DIRECT CURRENT GENERATORS

Aircraft Electrical System

Properties of electrical signals

WIRE AND CABLE ENGINEERING GUIDE

Bourns Resistive Products

SUITABILITY OF DIFFERENT TEST VOLTAGES FOR ON-SITE TESTING OF XLPE CABLE SYSTEMS

Application Note. So You Need to Measure Some Inductors?

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

DIMENSIONING OF CURRENT TRANSFORMERS FOR PROTECTON APPLICATION

Instrument Transformers Application Guide

How To Understand And Understand The Theory Of Electricity

45. The peak value of an alternating current in a 1500-W device is 5.4 A. What is the rms voltage across?

Power System Harmonics

A Guide to Transformer Winding Resistance Measurements

Exploring the Necessity of the Hot Hipot Test

Chapter 11. Inductors ISU EE. C.Y. Lee

AC Generators. Basic Generator

Iron Powder Cores for Switchmode Power Supply Inductors. by: Jim Cox

1. The diagram below represents magnetic lines of force within a region of space.

SECTION 4 ELECTRIC MOTORS UNIT 17: TYPES OF ELECTRIC MOTORS

MOBILE SYSTEM FOR DIAGNOSIS OF HIGH VOLTAGE CABLES (132KV/220KV) VLF-200 HVCD

Product Data Bulletin

ATTACHMENT F. Electric Utility Contact Information Utility Name. For Office Use Only

Modeling of Transmission Lines

Unified requirements for systems with voltages above 1 kv up to 15 kv

Why Buy HVI VLF Products?

SYNCHRONOUS MACHINE TESTING WITH MOTOR CIRCUIT ANALYSIS INSTRUMENTATION

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

Transformer Calculations

Step Voltage Regulators

Type SA-1 Generator Differential Relay

ABB ! CAUTION. Type COQ Negative Sequence Generator Relay. (50/60 Hertz) J. Instruction Leaflet

Practical Transformers: Operation, Maintenance and Testing

Direction of current flow through conductor. Fig. 1 Magnetic field generated by current flow

Current Transformers

OVERCURRENT & EARTH FAULT RELAYS. To study the protection of equipment and system by relays in conjunction with switchgear.

An equivalent circuit of a loop antenna.

Lab 14: 3-phase alternator.

ACCURACY OF POTENTIALTRANSFORMERS

TWENTIES WORKSHOP, EWEA 2012 Unveiling the future energy system: full scale demonstrations to reach 2020 targets. 17th April 2012

ANADOLU UNIVERSITY DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING

WIRE AND CABLE ENGINEERING GUIDE

EXTENDING THE LIFE OF POWER FACTOR CAPACITORS

RLC Series Resonance

Three phase circuits

Power surges can also be generated by equipment in your facility such as:

FAULT FINDING MANUAL. For Stamford AC Generators

2. INDUCTIVE VOLTAGE TRANSFORMERS Oil-paper insulation Gas insulation

ECEN 1400, Introduction to Analog and Digital Electronics

This webinar brought to you by the Relion product family Advanced protection and control IEDs from ABB

DC GENERATOR THEORY. LIST the three conditions necessary to induce a voltage into a conductor.

Eðlisfræði 2, vor 2007

100% Stator Ground Fault Detection Implementation at Hibbard Renewable Energy Center. 598 N. Buth Rd 3215 Arrowhead Rd

EE301 Lesson 14 Reading: , , and

Chapter 22 Further Electronics

Apprentice Telecommunications Technician Test (CTT) Study Guide

6 ELECTRICAL PARAMETERS

RADIANT PLASMA 4700 Plasma Spark Generator

FAULT FINDING MANUAL For Self Excited and Separately Excited Generators

IEC ESD Immunity and Transient Current Capability for the SP72X Series Protection Arrays

SURGE PROTECTIVE DEVICES

Transcription:

July, 2012 This goal for this month s paper is to provide a basic understanding of tests performed on each liquid filled transformer. The following standards detail the general construction requirements as well as the specific tests which the transformer must be subjected to. IEEE C57.12.00 IEEE Standard General Requirements for Liquid-Immersed Distribution, Power, and Regulating Transformers IEEE C57.12.90 IEEE Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating Transformers These standards define routine tests that are performed on all transformers as well as type tests which are performed on each unique design. Routine tests: 1. Winding Resistance 2. Ratio, Polarity and Phase Relation 3. Core Loss and Exciting Current 4. Load Loss and Impedance 5. Induced Potential 6. Applied Potential (Hi-Pot) 7. Production Line Impulse Test 8. Insulation Resistance 9. Insulation Power Factor 10. Leak (pressure) Test Type Tests: 1. Full ANSI impulse Voltage Test 2. Temperature rise test 3. Short Circuit Test Type tests are performed on new designs and are required to insure that the general design parameters are sufficient to insure reliable service. Pacific Crest Pacific Crest Transformers 300 West Antelope Road Medford, Oregon 97503 Tel : (541) 826 2113 Fax : (541) 826-8847

Transformers performs ANSI impulse and temperature rise tests in house while short circuit tests are performed by an independent test laboratory. The capability to perform the required tests requires an extensive array of specialized equipment including multi-voltage test transformers, a high frequency generator, and an impulse generator. 2

The first 6 routine tests listed above are those typically performed as customer Factory witness tests. Following is a brief description of each as well as the PCT pass criteria. 1. Winding Resistance Measurement (Resistance) PURPOSE: To measure resistance of all windings in the transformer under test in order that the I²R losses can be calculated. Also, to verify, through acceptable resistance readings, that all bolted connections are tight, and that crimped connections and conductor splices are adequate. SETUP: A digital Wheatstone or Kelvin bridge is used to apply a very low DC current to each of the HV and LV windings which returns the result in ohms. The low current is necessary to insure against heating of the windings which would lead to false readings due to an increase in resistance. The variation in resistance measurements between phases of the same winding shall not exceed the limits specified by the transformer manufacturer. 2. Ratio Measurement and Vector Relationship Check (Ratio, Polarity and Phase Relation) PURPOSE: To verify the voltage ratio of each coil in the transformer under test by checking the turns ratio of the HV and LV windings and (2) to verify that the windings are connected correctly to provide the specified primary to secondary vector relationship. SETUP: A ratiometer is used to perform this test. This equipment connects to each phase of the HV and LV winding and via the application of a very low voltage determines the ratio of the high voltage windings to the low voltage windings. These values are compared to those supplied from Engineering. 3

Ratio: Compute ratio tolerances from nominal transformer rated voltages. Maximum tolerances from calculated ratio = ±0.5%. Vector Relationship: A correct ratio will verify the desired vector relationship, or polarity. A test that yields no ratio at all or one that is far different than the calculated ratio may indicate a connection problem in the transformer under test. Note: A large difference between exciting current readings while ratioing different coils of a transformer may indicate a problem such as a turn-to-turn short. 3. No Load Loss and Excitation Current Measurement (Core Loss and Exciting Current) PURPOSE: To measure no load loss (core loss) and excitation current, and verify that these values are within acceptable tolerance of the calculated values. This will confirm that the core design (i.e. cross-sectional area and lamination thickness) is adequate to handle the required flux density, and that the cores were properly assembled. SETUP: The secondary terminals of the transformer under test is connected to a variable AC voltage source with no connections to the primary bushings. The voltage is gradually increased until full rated voltage is obtained. The core loss in watts as well as the current is recorded and compared to design data supplied by Engineering. Core loss shall not exceed design value by more than 10%. Maximum excitation current: wound core 2% stacked core 5% 4

If tested core loss exceeds maximum allowance, another test shall be made at 110% of rated secondary voltage, and the resulting data shall be submitted to a design engineer for review. 4. Load Loss and Impedance PURPOSE: To determine, by test and calculation, load losses and total losses of a transformer under test. Also, to determine the impedance voltage of the transformer, expressed as a percentage of the rated primary voltage, from which may be calculated the winding currents under short circuit conditions. The losses obtained from this test combined with the core loss data validates if the transformer tank and radiators are sufficient to allow for proper cooling. SETUP: The LV terminals are shorted together. The HV terminals are connected to a variable AC voltage source. Voltage is than applied to the HV and increased until such time that rated current is reached. The voltage and wattage is recorded and compared to data supplied by Engineering. 5

Tested total losses shall not exceed design losses by more than 6%. The limits of tested impedance are ±7.5% of specified impedance. Losses or impedance values that exceed limits should be submitted to engineering for review. 5. Induced Voltage Test (Induced Potential) PURPOSE: To verify coil and lead insulation levels by inducing the transformer under test to twice its rated voltage at high frequency for 7200 cycles. This test verifies turn to turn and layer to layer insulation, as well as lead to lead insulation within the high voltage and low voltage lead assemblies. SETUP: This test is performed using a high frequency generator (180 HZ). Since frequency and inductive reactance are inversely proportional, the double voltage required for this test is made possible because the core does not saturate. There should be no collapse or pull down of the test voltage. Smoke and bubbles from coils or lead assemblies may also indicate an insulation failure. 6. Applied Potential Test (Hi-Pot) PURPOSE: To verify the adequacy of winding to winding, and winding to ground insulation in each coil of the transformer under test. This test also verifies the adequacy of all live-to-ground clearances in the transformer. SETUP: During this test, each winding is shorted out by connecting its bushings together. The ANSI specified voltage is then applied to the winding under test with the other windings connected to ground. No voltage is induced in the winding under test or magnetic flux induced in the core; hence the insulation between turns or between layers in the winding under test is not stressed. 6

Failure of a winding is indicated by loss of test voltage and/or test set circuit breaker tripping. Failure can also be indicated by smoke and bubbles from coils or lead assemblies, or by an audible thump from inside the tank. Tests 7 through 10 as listed above are not normally witnessed (for various reasons), but test data is available upon request at the time of the Factory Witness Test. 7. Production line impulse test PURPOSE: To verify, by application of two 1.2 x 50 µs negative impulse waves to each high voltage phase bushing, insulation levels and electrical clearances within the transformer under test. This test verifies the integrity of turn to turn, layer to layer, winding to winding, and lead to lead insulation, as well as live to live, and live to ground clearance distance. Impulse tests simulate switching and lightning surges that may be impressed on the transformer. SETUP: The transformer under test is connected to the impulse generator. Each phase of each winding (HV and LV) is subjected to a voltage level dependent on the BIL (basic insulation level) of the winding under test. The impulse generator is made up of a number of capacitors that are charged in parallel to a level that when discharged in series will combine to achieve the required test voltage. The image of the voltage surge through each winding is captured on an oscilloscope. There should be no significant differences between voltage traces, displayed on the oscilloscope, from any HV bushing. Particular attention should be paid to the wave shape and voltage decay rate after the peak voltage of each voltage trace. Failure may also be indicated by an audible thump from the transformer tank, or by smoke and bubbles from coils or lead assemblies. 7

8. Insulation resistance ( Megger ) PURPOSE: Insulation resistance tests are made to determine the insulation resistance from individual windings to ground or between individual windings. This test will determine the condition of the insulation and that proper internal clearances have been met and maintained. This test is performed as a routine test on 501kVA and larger transformers. SETUP: A digital megger with a maximum rating of 5 kv Insulation resistance measurements shall not be less than the minimum limits specified by the transformer manufacturer. 9. Insulation power factor The ratio of power dissipated in the insulation in watts to the product of the effective voltage and current in volt-amperes when tested with a sinusoidal voltage. This test is used to give an indication of the condition (dryness) of the transformer 8

insulation. There are no established limits for acceptable power factor readings in the transformer standards. A power factor value of 1.0% or less for distribution transformers is generally used as an acceptable value. SETUP: The measurement is made with a capacitance bridge, measuring the capacitance between windings and between windings and ground, together with the power factor or loss angle of this capacitance. 10. Leak (pressure) test PURPOSE:To apply pressure and check for leaks on the transformer. SETUP: The completed transformer (cover welded) is pressurized at 7 PSI. UNIT HAS PASSED if no leaks are found and pressure remains constant (or does not drop more than expected with consideration of temperature differences) after a minimum of twelve (12) continuous hours under pressure. UNIT HAS FAILED if a leak is found or if the pressure drops more than expected. If leaks are detected, repair the transformer as needed. If the pressure drops more than expected, investigate tank seams, handholes, cover mounted bushings, etc., to determine where the leak is located and repair the transformer as needed. 9