POWER GRID. A subsidiary of Singapore Power ENERGISATION OF SERVICE CONNECTION

Similar documents
Application Procedures For Electricity Connection To Consumers Electrical Installations In The New Electricity Market

APPLICATION FOR RENEWAL OF LICENCE TO USE OR OPERATE AN ELECTRICAL INSTALLATION (Please read Explanatory Notes before completing the Forms)

How to Apply For Electricity Connection

Application of Electrical Installation Licence

Circuit Electrical Testing

MEDIUM VOLTAGE SUBSTATION PRACTICES Medium Voltage (MV) is defined as: 1000V< MV 44kV

METERING CODE. Energy Market Authority of Singapore

CHECKING AND TESTING ELECTRICAL INSTALLING WORK

Electrical Shore Connections / Cold Ironing

TRANSMISSION SERVICE RATE SCHEDULE Effective from 1 April 2015

(dd/mm/yyyy) Landlord (1) Name: NRIC No. (4) : Address: Landlord (2) Name: NRIC No. (4) : Address: Landlord (3) Name: NRIC No.

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

I USE OF SYSTEM CHARGES EFFECTIVE FROM 1 APRIL 2015

CAPACITOR BANK TESTING SWP

CONSULTATION PAPER FOR PROPOSED MODIFICATIONS TO THE TRANSMISSION CODE

The following components are common to most cubicles; this example is an ABB HK cubicle.

11. Assessment of service 12. S-phase supply 13. Water heaters NORTHERN TERRITORY OF AUSTRALIA ELECTRICITY BY-LAWS T ABLE OF PROVISIONS

How To Get A Power Line Extension

How To Choose A Transformer

STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK

INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION

TARIFF SCHEDULE FOR THE 2014/2015 FINANCIAL YEAR

NOTES ON AURORA LINE CHARGES FOR NETWORK DESIGNERS, CONSULTANTS AND ELECTRICAL CONTRACTORS

Trouble-shoot and repair faults in low voltage electrical apparatus and circuits

High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance

Monitor electricity supply power network system

Earth Fault Detection Basics in Theory

SCADA Controlled Multi-Step Automatic Controlled Capacitor Banks & Filter Banks

Contractor Connect Scheme Electrical Contractor and Worker Handbook

Electricity at work Safe working practices

Applying For New or Revised Electric Service

Good Industry Best Practice Safety Co-ordinator ordinator Guide

New electricity connection, substantial increase in load and major headworks

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V V V (at 50 Hz)

TABLE OF CONTENTS 1.0 INTRODUCTION PURPOSE DEVIATION INTERTIE PROTECTION REQUIREMENTS... 4

TERMS AND CONDITIONS

CODE OF PRACTICE NINE

Engineering innovation

FIT TIER 2 Application

Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation

Hyperlinks are Inactive

G8 - Contracts for Difference Metering

N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS

Advantages of Fixed Circuit Breaker Switchgear

KERALA STATE ELECTRICITY REGULATORY COMMISSION

TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT

Chapter 1. Network Structures

Reyrolle Protection Devices. 7PG17 - XR Intertripping, Interposing, Supervision and Special Purpose Relays. Answers for energy

SPECIFICATION COG-2007

CHECK LIST OF SITE INSPECTION ON LV ELECTRICAL INSTALLATION (Basic Information to be filled by Consultant)

Schedule GS-3 LARGE GENERAL SERVICE SECONDARY VOLTAGE I. APPLICABILITY AND AVAILABILITY

Effective 15 Jul 2015 Conditions of Service for Contestable Consumers

KERALA STATE ELECTRICITY REGULATORY COMMISSION

3. TYPES OF SERVICE AVAILABLE. 3.1 Scope

PUBLIC LIGHTING CODE April 2005

ELECTRICIANS LICENSING

The Electrical Safety Regulation (pre and post 1 January 2014)

SWITCHGEAR SOLUTIONS FOR MISSION CRITICAL APPLICATIONS. Presented by SAI Advanced Power Solutions

Addendum #2 Contract UK-11-13

Dakota Energy Cooperative, Inc. POLICY STATEMENT

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Metering and Monitoring. Basis of Design

Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva

SINGAPORE POLICE FORCE CERTIFICATE OF CLEARANCE (COC)

Model Renewable Energy Wheeling Agreement under Renewable Energy Certificate (REC) scheme

ELECTRIC SERVICE RULES

New Supervisory Control and Data Acquisition (SCADA) Based Fault Isolation System for Low Voltage Distribution Systems

SUBJECT: How to wire a motor starter Number: AN-MC-004 Date Issued: 2/08/2005 Revision: Original

Regulation IO-6.0: Electrical Safety Regulations

Effective: September 10, 2006 Vermont Attachment 1 to Rule Public Service Board Page 1 of 6

Comparison of Interconnection Standards 3/28/2003

SWITCHGEAR. EGP Switchgear

PacifiCorp Original Sheet No. 476 FERC Electric Tariff, Substitute 6 th Rev Volume No. 11 APPENDIX 2 TO SGIP

Integrated Power Systems for Data Centers

Vision. Mission. Shared values

Electrical Safety. At Construction Worksites. Use electricity safely at worksites and avoid injury and hazards

TITLE PAGE MINNESOTA POWER ELECTRIC RATE BOOK

The Electrical Contractor Safety Program Guide

AUTOMATIC TRANSFER SWITCH. Changeover Type from 250A to 2500A

Connecting to the network information pack Version 2

Hazardous location. Definitions

CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services

How To Charge For Electricity In Texas

DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations)

CERTIFICATE ISO 9001:2008 ISO 14001:2004 BS OHSAS 18001:2007. hereby certifies that the company

OPTIONAL INFORMATION ELECTRICAL SAFETY WORK PRACTICES SELF INSPECTION CHECKLIST

SECONDARY SUBSTATION INSTALLATION AND COMMISSIONING SPECIFICATION

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation

GROUND DETECTION CIRCUITS FOR STATIONARY APPLICATIONS (IN PLAIN DOWN TO EARTH LANGUAGE)

REQUIREMENTS FOR CUSTOMER-OWNED PRIMARY SERVICES SUPPLIED AT 4 kv TO 35 kv PRIMARY GUIDE

NET METERING SUB-CODE. for Connecting Renewable Energy Generating Systems to the Distribution Network in Ghana

SIEMENS Transmission and Distribution

Simple Methods for Calculating Short Circuit Current Without a Computer By Dennis McKeown, PE GE Senior System Application Engineer

Technical Specification Of Substation Protection & Control System with IEC BHEL s Perspective

Electrical Practices for Construction Work

RESIDENTIAL SERVICE SCHEDULE R

TERMS AND CONDITIONS

1. The type of service available at any particular location should be determined by inquiry at PG&E's local office.

SUGGESTED SPECIFICATION for Series 185 Service Entrance Rated Automatic Transfer Switches

TARIFF SCHEDULES FOR HIGH TENSION CONSUMERS. Table of Contents

Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems

Transcription:

A subsidiary of Singapore Power ENERGISATION OF SERVICE CONNECTION

Energisation of Service Connection Prior to Energisation Contestable Consumers - Consumer Connection Agreement - Connection Charges Non-Contestable Consumers - Supply Agreement - Connection Charges Obtain Licence for Electrical Installation (EI) from EMA Open Utilities Account with Market Support Services Licensee (MSSL) Pay Security Deposit 2

Energisation for Supply Capacity >45 kva up to 22 kv (Direct Connected Consumers) Roles of LEW To supervise and ensure that the electrical set up is in accordance with the relevant Codes of Practice (CP) and Regulations Ensure equipment tested (inclusive of Protection System) and Safety Inspection work done Arrange for meter fixing and testing by Meter Section Submit COC when request MSSL for an appointment of Energisation 3

Energisation for Supply Capacity >45 kva up to 22 kv (Direct Connected Consumers) Roles of LEW On the day of Energisation Submit COR to PowerGrid s (PG) project officer Perform Interlocking Tests on Incoming Circuit Breaker (CB) Perform Tripping Tests on Incoming CB Immediately after Energisation Phasing of Incoming Supplies Acknowledge on the Statement of Turn-on of Electricity 4

Energisation for Supply Voltage at 66 kv and above Roles of LEW To supervise and ensure that the electrical set up is in accordance with the relevant CP and Regulations Ensure equipment tested and Safety Inspection work done Joint preparation of Switching Procedures with PG for Power System Operator (PSO) s approval Perform Pre-Commissioning Tests on Protection System Arrange for meter fixing and testing by Meter Section Submit COC when request PG s Project Officer for an appointment of Energisation 5

Energisation for Supply Voltage at 66 kv and above Roles of LEW On the day of Energisation Submit COR to PG s Project officer Perform PSO s approved Switching Procedures with PG Immediately after Energisation Acknowledge on the Statement of Turn-on of Electricity 6

CERTIFICATE OF COMPLIANCE [Regulation 5(2) of the Electricity (Electrical Installations) Regulations 2002] Particulars of Electrical Installation Name of Consumer : Address of Installation : Electrical Installation Licence No. MSS Account No. Approved load & Supply Voltage: kw Volts Generator(s) Installed: Operated in parallel with PowerGrid s supply. No. of generator: Rating: kva Standby generator. No. of generator: Rating: kva Not applicable Certification by Licensed Electrical Worker I certify that the above-mentioned Electrical Installation complies with the requirements of the Electricity (Electrical Installations) Regulations 2002 and the Singapore Standards CP 5. I further certify that the technical requirements as stipulated by the person responsible for turning on the switchgear which controls the supply of electricity to the said electrical installation have been complied with. I hereby request for the energisation of the supply line to the said Electrical Installation on (date). Name & Signature of LEW Licence No. Date Copy to: Market Support Services License 7

CERTIFICATE OF READINESS FOR THE ENERGISATION OF SERVICE CONNECTION Name of Customer Installation: Address: Customer Installation Licence No/Expiry Date: Connection Voltage: Approved Load: Name of Connection Cable(s): Owned by Connection Applicant (Yes / No) MSS Account No: Name of Retailer: Certification By LEW I, (name) the undersigned LEW, hereby certify that the service connection*, the equipment and works at the above installation (Licence No: ) are now ready and fit for energisation with effect from the date and time specified below. Date: Time: I certify that: a. protection details are as follows: CT Ratio: /1A or 5A* Main 1 Type: Main 2 Type*: O/C Type: Setting: E/F Type: Setting: b. the switching equipment/transformer/service connection* and all associated apparatus related to the service connection have been tested and checked by me and they have passed the pre-commissioning checks and tests in compliance with the Market Rules, Transmission Code, Handbook on How to Apply for Electricity Connection, Connection Agreement, all other applicable standards, and the associated protection systems have all been proven effective (the main protection schemes have been commissioned by load simulation method on date: ). c. all necessary meters have been installed. d. *for multi-metered installation with the exception of HDB residential installation, the metering scheme has been designed as master/sub-metering scheme. *Delete where not applicable 8

e. the safety coordination requirements of the Transmission code have been fully complied with. f. all workmen have been withdrawn and warned that it is no longer safe to continue to work on the equipment without a Permit-to-work (PTW), and that all tools, scaffolding, ladders, construction materials including any temporary local earthing connections have been removed from the equipment, and all protective screens or guards, if any, have been securely fixed and the appropriate warning signs displayed and that all keys, if any, necessary for the isolation and operation of the equipment have been handed to me. g. all circuit earth on equipment to be energised are removed. h. equipment to be energized in this request (the diagram must clearly indicate the portion of the equipment to be energised) is shown below: Name & Signature of LEW Licence No. Date 9

STATEMENT OF TURN-ON OF ELECTRICITY [Regulation 5(4) of the Electricity (Electrical Installations) Regulations 2002] ELECTRICITY SUPPLY TO (Name of Applicant) AT (Address of Installation) ELECTRICAL INSTALLATION LICENCE NO* : I agree that the above-mentioned electrical installation is suitable for connection to the electrical system. I certify that the supply line to the installation has been energised on at. (date) (time) Name & Signature of PowerGrid s officer NRIC No. Date I acknowledge that the supply line has been energised on the date and time indicated above. Name & Signature of LEW requesting for Licence No. Date energisation of supply line I acknowledge that the supply line has been energised on the date and time indicated above and confirm that I will be responsible for the operation of this electrical installation hereafter. Name & Signature of LEW responsible for the Licence No. Date operation of the electrical installation* I acknowledge that the supply line has been energised on the date and time as indicated above. Name & Signature of Applicant or NRIC / Passport No. Date his representatives * Applicable to licensed electrical installation only. Copy to: Market Support Services Licensee 10

A subsidiary of Singapore Power END