How To Get A Power Line Extension
|
|
|
- Brice Wheeler
- 5 years ago
- Views:
Transcription
1 GUIDELINES FOR COMMERCIAL ELECTRIC SERVICE HOOKUP 1
2 Steps to Commercial Service Pay the Design Deposit Commercial Buildings: Up to 1, sq ft = $1,. 1, 5, sq ft = $2,. Over 5, sq ft = $3,. Commercial jobs require meter department approval on load calculation and line drawings before engineering starts. All new permanent connections are required to be underground. Apply for Membership: The Customer has the option of using his membership for all tenants or he may require that they provide their own. In either case, the Customer will be required to be a member of the Company. Complete and submit Load Information and Details form Complete and Submit a Load Data Sheet for each metered space Submit Construction Plans and Specifications Site Plan showing: o Any building on the property o Street designation and address o Location of service entrance, switchgear, and meter centers o North or direction arrow o Property boundary designations o Legal description (as required) o All existing and proposed: utilities, buildings, parking lots and roadways Building drawings showing: o Electrical rooms (must be pre-authorized by Company) o Square footage o Building Layout (see sample) with location of electrical panels, and each separate metered space showing ID of each space. This drawing must be signed by the developer once finalized. o A detailed sketch of the proposed route of service conductors from the service termination point to the main disconnect or bus o Provisions for metering o Switchgear Drawings Electrical drawings showing: o Meter Base Configuration (see sample) showing layout of all meters and associated power distribution equipment. Space ID s must be shown (unit 32, etc). o 1 line electrical drawing from the service termination point to the main disconnect or bus Specifications Including: o Switch gear specifications o Voltage requirements o The size of the main disconnect bus o The size, type, and number of service conductors and conduits 2
3 Pay for Estimated Construction Costs: Prior to ordering materials and/or transformer(s), the Company will require that the Customer pay the estimated construction costs of the project. Other Useful Information: Available Voltage: Electric service will be made available at alternating current, 6 hertz, at one of the nominal voltages stated below: A. SINGLE PHASE SERVICES are available on all primary circuits except for network metering. However, depending on the primary distribution system, there may be voltage and loading limitations for some applications and the Customer should check with the Company prior to purchasing his equipment. Network metering will only be available on three phase primary systems. Single phase voltages are as follows: 1. 12/24 volts, 3 wire, grounded neutral 2. 24/48 volts, 3 wire, grounded neutral 3. 12/28 volts, 3 wire, grounded neutral, network metering B. THREE PHASE SERVICES are available on three phase primary circuits. However, depending on the primary distribution system, there may be voltage and loading limitations for some applications and the Customer should check with the Company prior to purchasing his equipment. Available three phase voltages are: 12/28 volts, 4 wire, grounded wye 277/48 volts, 4 wire, grounded wye If a non-standard voltage is desired, the Customer is responsible for installing transformation or conversion on the load side of their meter base. Three phase and network secondary voltages are only available in areas that have three phase primary power available. Any existing 3 phase delta loads that are replaced need to be converted to 3 phase wye. Notify PLC prior to conversion for the needed transformer modification. C. THREE PHASE SERVICE: The Company will only provide three phase power for loads equal to or greater than 3 kva of demand load. Loads smaller than 3 kva will be served single phase unless there is an existing three phase transformer bank available that can be utilized. D. POWER QUALITY: Motor starting at full voltage can cause voltage reductions that will cause lights to dim and electronic equipment to stop operating properly. The voltage reductions can affect several customers in the general area of the motor being started. To protect customers in the area from a customer who operates a motor, the Company requires the following: 1. For motors greater than 5 Hp and less than or equal to 1 Hp, a reduced voltage motor starter shall be installed. 2. For motors greater than 1 Hp, a soft start type motor starter shall be installed. 3
4 TRENCHING: All secondary trenches (from building to electric power device or electric power pole) must allow at least 24 inches of earth cover over the service conductor from final grade of ground. Joint utilities are allowed in a secondary trench (power, phone, water, CATV) with a minimum horizontal or vertical separation of 6 inches. Gas lines require a minimum horizontal separation of 12 inches from secondary power cables. Sewer tight lines installed parallel to service conductors shall have a horizontal separation of no less than 4 feet. In order to reduce the risk of an accident or electrocution during excavation, service laterals shall have their location identified by a warning ribbon that is placed in the trench at least 12 inches above the underground installation. Trenching is the responsibility of the developer/contractor. All trenching must be completed to within 2 feet of the power source. Telephone and cable TV companies need to be contacted to determine their installation needs, as they can share the same trench that you have made for the power system. Contact them early as they may need their trench to branch off the power line trench to their connection points. Be sure to keep all utilities at least 6 inches apart in the trench to improve heat dissipation and reduce interference. Utility Type Contact Name Contact Number Centurylink Telephone Customer Svc Comcast Cable Customer Svc Wave Cable Customer Svc Puget Sound Energy Gas Customer Svc NOTE: State law requires that before any underground digging begins of 12 inches in depth or more, customers must contact the Utilities Underground Location Center, Phone # , and request utility lines to be marked. A minimum two business days notice is required, and there is no charge to the customer for this service. Facility Ownership: Peninsula Light Co. owns and maintains the power distribution system up to the transformer or secondary junction box (handhole). Secondary wiring (at facility voltage) is owned and maintained by the customer. Service Disconnected over a Year: PLC s primary goal is to cost-effectively provide safe, reliable service to every member on a fair and equal basis. The determination of safe, reliable, fair and equal is at the sole discretion of PLC. To that end, in most cases, PLC will require electric services which have been disconnected for over twelve consecutive months to have a current L & I safety inspection prior to being reconnected. PLC may additionally require some services disconnected for less than twelve consecutive months to have a current L & I safety inspection prior to reconnection. L &I requires that the property owner request the permit for the safety inspection. PLC may also require any service that has been disconnected and requires inspection for reconnection be updated to current PLC metering standards and guidelines. Please contact PLC Engineering for information and requirements regarding a disconnected service. 4
5 Important Contact Numbers Peninsula Light Company Goodnough Dr NW Gig Harbor, WA (253) Engineering (253) Main Office Toll Free State of Washington Department of Labor and Industries Electrical Division 95 Broadway Suite 2 Tacoma, WA 9842 (253) Utilities Underground Location Center Call Before You Dig 811 or
6 Engineering Services Fee Schedule Effective December 1, 29 MEMBERSHIP FEE. $1. Peninsula Light Company, a Mutual Corporation, is a non-profit organization that is owned by its members and governed by an elected Board of Directors. All new services must be covered by a membership. The membership Fee is refundable, provided there are no outstanding bills, if the member leaves the Company's serving area. ENGINEERING DESIGN DEPOSIT. $5. The Engineering Design Deposit is assessed for jobs more involved than a simple connection from the member s service to an existing adequately sized underground transformer or connection point, and is intended to help recover some of the costs incurred when it is necessary for the engineer to visit the project site, discuss the project details, consult with other utilities or public agencies, and to calculate associated labor and material costs. Upon request, Peninsula Light Company will provide rough cost estimates free of charge for any standard line extension project. Overhead to underground conversions or system relocations shall require detailed cost estimates since costs may vary considerably depending on extent of job. Those requests that require a detailed cost estimate shall first pay the design deposit. The design deposit shall be based on a percentage of the anticipated cost of construction or a minimum flat deposit, and shall be applied toward the final job costs provided full payment is received within 9 days of the estimate date. Detailed cost estimates are valid for a period of 9 days from the date of the estimate. Additional design deposits shall be required if the 9 days has expired OR if any changes require the project to be redesigned or costs recalculated. TEMPORARY SERVICE HOOKUP FEE $2. Underground Service to an adequately sized transformer or connection point - In addition to the hookup fee, all equipment, conductor, and trenching is the responsibility of the customer. Overhead Service - In addition to the hookup fee all equipment is the responsibility of the customer. Overhead temporary services are limited to a maximum drop distance of 2 feet. Beyond 2 feet, consult the company for details. Overhead services that require more than a 25 triplex drop from a PLC pole to the temporary service shall be assessed additional charges. RESIDENTIAL PERMANENT SERVICE HOOKUP FEES 1 Phase 2 or 32 AMP self contained meter. $ Phase 4 or 6 AMP CT meter...includes meter base, meter labor & TS.... $4. Underground service to adequately sized transformer or connection point - In addition to the hookup fee, all conductor, conduit, and trenching is the responsibility of the customer. 6
7 COMMERCIAL PERMANENT SERVICE HOOKUP FEES: 1 Phase self contained meter.. $ Phase CT meter..includes meter base, test switch, meter labor. $4. 3 Phase self contained meter.. $ Phase CT meter..includes meter base, test switch, meter labor. $65. Metering with customer interface (ie: KYZ pulses) quote based on customer needs Underground service to adequately sized transformer or connection point - Apartment buildings OR commercial projects that utilize a common service cable will pay a hookup fee of $245. for the first self contained meter. Additional meters for that project will be charged $125. for each self contained meter connected at the same time as the first meter. OVERHEAD TO UNDERGROUND SERVICE CONVERSIONS - All equipment, conductor, conduit, and trenching is the responsibility of the customer. Peninsula Light Company installs the conduit riser on the power pole at the customer's expense. RENTAL LIGHTS $8. Installation of a rental light will be charged a trip fee plus the cost of any additional materials that are needed to operate a rental light. Rental lights must be installed for a minimum of 1 year. Peninsula Light Company has the option to charge the customer for the removal of a rental light if it s removed prior to the first year. TRIP FEE $8. Trip fees shall be charged when the following situations occur: A hook-up is requested by a customer prior to the service connection approval by the State Electrical Inspector. Additional trips are necessary for disconnecting and/or reconnecting temporary services, altered services, or permanent services. Additional trips are necessary to check for trench backfill or service approval. All Engineering fees must be paid before any service connections will be made. NOTE: If customers are connecting to a Private Main Line they will also need to pay a proportionate share of repayment. Private Main Line repayments, if any, are in addition to normal Engineering fees and shall be paid prior to hookup. 7
8 LOAD INFORMATION AND DETAILS ORDER INFORMATION WO#: ENGR: PROJECT NAME: SERVICE ADDRESS: BILLING NAME & ADDR: CONTACT INFORMATION Primary Contact person: Phone # Electrical Contractor: Phone # Company Name: SERVICE SPECIFICATIONS Residential Commercial 1 Phase or 3 Phase Service Entrance Size: Voltage: / Total Connected KVA: Secondary Cable Info: Aluminum or Copper Size Per Phase: Size Per Neutral: Number of Runs: Conduit: Size: Number of Runs: Type: PVC or Steel: TRANSFORMER SPECIFICATIONS (PLC Use Only) KVA: Impedance: In Stock CO# Ordered Date: Estimated Delivery: Secondary Connectors: # of Blocks # of Places Item # PO# Transformer Pad: Existing In Stock Needs New Needs to Be Ordered Available Fault Current at Transformer Secondary Terminal Is: Amps Symmetrical Based on % Impedance METERING SPECIFICATIONS (PLC Use Only) Meter: Meter Spec Code Network Demand Switchboard # of units OR Switchgear Manufacturer: Meter and Switchgear Location: Meterbase Issued: Date: Issued By: Received By: Meter Layout: Plans submitted per PLC specs (See Commercial Specs, Page 2, Section D) Current Transformers: CT s NOT Required CT s Required: In Stock Ordered Date: PO# Type: Ratio: RF: Quantity: CT s Issued: Date: Issued By: Received By: APPROVALS: Service Connection by L&I: Approved By: Date: Permit # Meter Shop: Meter Layout Plans Approved By: Date: Meter and Switchgear Location Approved By: Date: CT s and Meterbase Wired Approved By: Date: Meter Installed By: Date: Service Energized By: Date: 8
9 Project Name: Air Conditioner Heat Pump Compressor Load Number of Units: Total Tonnage: Largest Single Unit: Load Data Order Number: PLC Use Only Total KW % Load Factor Estimated KW Heat Gas? Yes No Strip Heat: Resistance Heat: Air Handling Fans: Lighting (list type) Indoor: Outdoor: Water Heater Gas? Yes No Number: Gallons: Motors (over 7.5 HP) Number of Units: Total Horsepower: Largest Motor: Receptacles Other (describe) Future (describe) Outbuilding (describe use) Totals: Other factors used in determining transformer size: Transformer Size - PLC Use Only Transformer size to be set: Approved By: Date: 9
10 Sample Building Layout Map 1
11 Sample Meter Base Configuration 11
4. REQUEST FOR ELECTRIC SERVICE. 4.1 General Service Information
4. REQUEST FOR ELECTRIC SERVICE To establish an electric service, temporary or permanent, contact UI s Customer Care Center by calling: 1-800-722-5584 (7:00 a.m. 7:00 p.m., Monday Friday and 7:00 AM to
Applying For New or Revised Electric Service
Applying For New or Revised Electric Service Dear Customer: ComEd is happy to assist you in initiating new or revised electric service to your location. Please complete, sign and return the attached service
REQUEST FOR ELECTRIC SERVICE Commercial
This form should be completed if you are applying to have new electric facilities installed on your property for the purpose of providing electric service to a commercial entity. PROJECT CHECKLIST Below
CARROLL COUNTY ELECTRICAL DEPARTMENT SERVICE POLICIES. EFFECTIVE MARCH 1, 1995 Revised 1/01/2013
CARROLL COUNTY ELECTRICAL DEPARTMENT SERVICE POLICIES EFFECTIVE MARCH 1, 1995 Revised 1/01/2013 CARROLL COUNTY ELECTRICAL DEPARTMENT 103 WEST PARIS ST. P. O. BOX 527 HUNTINGDON, TENNESSEE 38344 Telephone
IRRIGATION PUMPING Table of Contents - Section 900
IRRIGATION PUMPING Table of Contents - Section 900 PARAGRAPH 900.1 GENERAL 1 900.2 METERING REQUIREMENTS 1 900.3 CUSTOMER S CONTROL EQUIPMENT 2 900.4 SERVICE CONDUCTOR REQUIREMENTS 2 900.5 RECOMMENDATIONS
3. TYPES OF SERVICE AVAILABLE. 3.1 Scope
3. TYPES OF SERVICE AVAILABLE 3.1 Scope UI supplies 60 hertz, alternating current with different voltage and ampere ratings. Not all voltage and ampere ratings are available throughout the entire service
BGE Service Application Guidelines Commercial & Industrial Projects
BGE Service Application Guidelines Commercial & Industrial Projects To the Customer Following is important information to assist you in applying for BGE gas and/or electric service and in completing the
INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION
INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION February 2013 NOTE: If conflict exists between St. Thomas Energy s Conditions of Service and this document, the Conditions
Underground Commercial Electric Service
Underground Commercial Electric Service SCANA Corporation 2013 Revised: June 2013 Table of Contents SECTION PAGE I. Specification and Requirements 2 A. General B. Definition of Terms C. Company and Developer
BGE Service Application Guidelines Residential Modification/Relocation Projects
BGE Service Application Guidelines Residential Modification/Relocation Projects To the Customer Following is important information to assist you in applying for BGE gas and/or electric modification or
BUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE
BUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE Toll Free Telephone Numbers Residential Services 800.454.3853 Commercial Services 800.653.5307 Utility Locating Company N.C. 800.632.4949 S.C. 888.721.7877
Approved Meter Sockets and Cabinets
Single Unit Residential Guide 1 PHASE, 120/240 VOLT S METERING (Metering sockets and cabinets are supplied by Customer). Outdoor meter mounting height is 1730 mm ( 5 8 ) to center of meter ± 100 mm ( 4
Electric Service Guide for Commercial Construction
Electric Service Guide for Commercial Construction Contents Contacting KCP&L... 2 Voltages... 2 Temporary Service... 2 Customer-Provided Temporary Service... 2 KCP&L-Provided Temporary Service.... 2 Current
BASIC NEC CODE RULES AND DESIGN PRACTICE
BASIC NEC CODE RULES AND DESIGN PRACTICE Wire Ampacity and Size Circuit Breaker Size 1. Maximum loading for any branch circuit is 80% of rating of circuit for ampacity of wire for any load. NEC 220-2,
New Commercial Service Application
Please submit with this form an application fee of $500.00 and an Electronic CAD file of your preliminary plat. CAD file can be emailed to [email protected]. Member Information Work Order Number:
Internet Application for New Multi-Family Electric Service Builders/Developers Fax to: (800) 351-3853 or call (800) 454-3853 Date Faxed: 1
Internet Application for New Multi-Family Electric Service Builders/Developers Fax to: (800) 351-3853 or call (800) 454-3853 Date Faxed: 1 2 Service address City 3 (Inside city: Yes No) State 4 Complex
TABLE OF CONTENTS. PUD SERVICE TERRITORY & CONTACTS... Page 1. NEW SERVICE QUESTIONNAIRE... Page 2. GENERAL... Page 3
UNDERGROUND TABLE OF CONTENTS PUD SERVICE TERRITORY & CONTACTS... Page 1 NEW SERVICE QUESTIONNAIRE... Page 2 GENERAL... Page 3 TRENCHING SECONDARY (120/240 volts)... Page 3 CONDUITS FOR PUD-INSTALLED CONDUCTORS...
Please Refer to Attached Sample Form
Pacific Gas and Electric Company San Francisco, California U 39 Revised Cal. P.U.C. Sheet No. 32104-E Cancelling Revised Cal. P.U.C. Sheet No. 28312-E Electric Sample Form No. 62-0685 Application for Service
Underground Service Requirements and Instructions
This packet includes all FKEC underground service requirements, instructions, procedures and drawings. If you are considering underground power service please review this document in its entirety (3 page
METER REQUIREMENTS GENERAL REQUIREMENTS SECTION D
12 - ELECTRIC SERVICE HANDBOOK SECTION D METER REQUIREMENTS This chapter gives you information on Central Lincoln s metering requirements. It's divided into three sections: General requirements This section
Considering UNDERGROUND. tampaelectric.com
Considering UNDERGROUND Electric Service? tampaelectric.com INTRODUCTION The majority of Tampa Electric s customers receive their electric service through overhead construction, which is the standard type
PWC SCHEDULE OF DEPOSITS, FEES AND CHARGES. Table of Contents
PWC SCHEDULE OF DEPOSITS, FEES AND CHARGES Table of Contents I. DEFINITIONS... 2 II. DEPOSITS... 3 A. Establishment of Credit:... 3 B. Deposit Refunds:... 4 III. CUSTOMER SERVICE FEES AND CHARGES... 4
Call the Experts at REA Energy Services for all of Your Electrical and HVAC Needs.
Call the Experts at REA Energy Services for all of Your Electrical and HVAC Needs. REA Energy Services Sells and Installs: Heating and Air Conditioning Electrical Contracting Geothermal Heat Pumps Back-Up
In the year Two Thousand Eleven.. Resolved by the City Council of the City of Burlington, as follows:
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 APPROVAL OF AMENDMENTS TO BURLINGTON ELECTRIC DEPARTMENT S OPERATING GUIDELINES In the year Two Thousand Eleven.. Resolved
Homeowner Information Guide Electrical Safety. British Columbia Safety Authority
Homeowner Information Guide Electrical Safety British Columbia Safety Authority The following information should be carefully reviewed before performing any electrical work. The information contained in
Please check with your local inspection authority for any additional requirements before installation.
Specifications for Residential Overhead Electric Service Installation This brochure addresses most typical residential overhead service installations. Variances for the following specifications must be
Application for. Commercial New Service
Application for Commercial New Service Welcome to Lake Country Power! In order to make your new service installation easy, we provide individualized help to process and install a new service. In order
Hyperlinks are Inactive
Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)
ELECTRIC SERVICE HANDBOOK General Information Residential Service Portable/Standby Generators Temporary Service Commercial Service Metering
ELECTRIC SERVICE HANDBOOK General Information Residential Service Portable/Standby Generators Temporary Service Commercial Service Metering Requirements Clearance Requirements August 2015 A current version
PLEASE NOTE. For more information concerning the history of these regulations, please see the Table of Regulations.
PLEASE NOTE This document, prepared by the Legislative Counsel Office, is an office consolidation of this regulation, current to August 1, 2013. It is intended for information and reference purposes only.
Electric Service Guide for Residential Construction
Electric Service Guide for Residential Construction Table of Contents Contacting KCP&L... 2 Existing Home Remodeling or Additions... 2 Changing your electric service... 2 What you need to know before you
Step 1: Application Instructions
Step 1: Application Instructions CONTENTS Introduction Customer and Electrician Instructions Completing Section 1 or Section 2 Definitions INTRODUCTION Every effort has been made to provide clear instruction
LADWP CITY OF LOS ANGELES DEPARTMENT OF WATER AND POWER ELECTRIC SERVICE REQUIREMENTS 2010 EDITION NOTICE
LADWP 2010 EDITION NOTICE This manual is designed to provide you with the most current information on the Los Angeles Department of Water and Power s (Department) service equipment and installation requirements.
COUNTY OF LOS ANGELES BUILDING AND SAFETY DIVISION ELECTRICAL CODE FEE SCHEDULE (Title 27 of the County of Los Angeles Code, Ord No.
COUNTY OF LOS ANGELES BUILDING AND SAFETY DIVISION ELECTRICAL CODE FEE SCHEDULE (Title 27 of the County of Los Angeles Code, Ord No. 2013-0049) Effective July 1, 2014, Electrical Permit Fees in the unincorporated
All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations.
DIVISION 16 ELECTRICAL SECTION 16100 - ELECTRICAL PART 1 - GENERAL SCOPE All electrical work as shown on the drawings and as necessary to provide a complete electrical system. Include primary service,
PRIMARY SERVICE LINE: The Company's conductors which connect the supply line with a transformer located on private property.
INTRODUCTION These rules are issued for use by Customers, builders, electrical contractors, architects, engineers, etc. The rules require the installation of safe and adequate wiring and electrical equipment,
CONSTRUCTION STANDARD ELECTRIC OPERATIONS ORGANIZATION
Page 1 of 11 ****This Standard Supercedes BECo CS2.13-2.3 & ComElectric OH Construction Manual, System Grounding Section, drawings CGND, GRDSUM, and C2**** 1.0 Bill of Materials GROUNDING AND BONDING POLE-MOUNTED
Customer Low-Voltage Switchboards Service Cable Terminal Compartment Arrangements and Clearances
Page 50 of 100 Customer Low-Voltage Switchboards Service Cable Terminal Compartment Arrangements and Clearances (Replaces A-190556) THIS CUSTOMER REFERENCE SPECIFICATION (CRS) IS PART OF THE RULES FOR
Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage:
Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016 * Garage construction requires permits (electrical, building) * Permits must be applied for at the time. * Dial
Services. Three Phase Service
Services Primary Service vs Secondary Service Overhead vs Underground Common Service Types Three Phase Wye Closed Open Delta Corner Grounded Center Tapped Open Single Phase Three Phase Service Wye Delta
SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL
SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL 1.1 SUMMARY A. This section describes the requirements for the installation of Power Monitors and associated
GENERATOR SELECTION. a. Three phase - 120/208V, 3 phase, 4W wye; 277/408, 3 phase, 4W wye; * 120/240V 3 phase, 4W Delta
GENERATOR SELECTION Generators must be sized to handle their load based on the continuous KW, kilowatt load, and KVA, kilovoltamp load, and the worst case starting load KW + KVA. They must be derated for
NORTHERN LIGHTS, INC. SINGLE PHASE APPLICATION CHECKLIST
NORTHERN LIGHTS, INC. SINGLE PHASE APPLICATION CHECKLIST SUBDIVISIONS, MULTI-FAMILY, LARGE COMMERCIAL AND 3-PHASE PROJECTS NEED TO USE OUR DEVELOPER S APPLICATION ITEMS NEEDED BEFORE PROJECT IS ENGINEERED:
Section 2 General Requirements
Table of Contents Section 2. General Requirements Section 2 General Requirements A. SCOPE... 2-3 B. AVAILABILITY OF SERVICE... 2-3 C. APPLICATION FOR SERVICE... 2-4 D. SERVICE ENTRANCE LOCATION / METER
MLGW Contact Numbers. Memphis Light, Gas and Water Division P.O. Box 430. Memphis, TN 38101-0430
MLGW Contact Numbers Address Assignment 901-729-8620 To obtain or verify addresses for new services. Builder Services 901-729-8630, Option 1 Initial meter turn-ons- FOR NEW CONSTRUCTION ONLY Billing inquiries
Line Loss WSDOT Winter 2008 BZA
Electrical Design Training Class Line Loss WSDOT Winter 2008 BZA Presented by: Keith Calais 1 OHM S LAW P = Watts (Power) I = CURRENT (AMPERES) R = RESISTANCE (OHMS) E = ELECTROMOTIVE FORCE (VOLTS) P =
NTUA GUIDELINES FOR DESIGNING AN ELECTRICAL POWER DISTRIBUTION SYSTEM FOR NEW DEVELOPMENTS
NTUA GUIDELINES FOR DESIGNING AN ELECTRICAL POWER DISTRIBUTION SYSTEM FOR NEW DEVELOPMENTS These guidelines are intended to familiarize Developers regarding some issues that are important to get electric
Please Refer to Attached Sample Form
Pacific Gas and Electric Company San Francisco, California U 39 Revised Cal. P.U.C. Sheet No. 32106-E Cancelling Revised Cal. P.U.C. Sheet No. 28314-E Electric Sample Form No. 62-0687 Application for Service
SERVICE - GENERAL Residential, Commercial, Industrial
PAGE 1 OF 9 USE: Rules and procedures for overhead or underground services. PREVIOUS REVISION 10-01-01 ORIGINATED 03-94 PREVIOUS NUMBER ER 1-290-B, 07-15-93 LATEST REVISION: Remove details of Facility
SCHUYLER DEPARTMENT OF UTILITIES SCHUYLER, NEBRASKA ELECTRIC RATES
SCHUYLER DEPARTMENT OF UTILITIES SCHUYLER, NEBRASKA ELECTRIC RATES TABLE OF CONTENTS SECTION I SECTION II SECTION III SECTION IV SECTION V SECTION VI SECTION VII SECTION VIII SECTION IX SECTION X SECTION
Electric Service Requirement Handbook
INLAND POWER 10110 W. HALLETT RD. SPOKANE, WA 99224-7435 inlandpower.com Electric Service Requirement Handbook Table of Contents Contact Information... 1 1. Introduction... 2 2. Line Extension Policy...
Wellesley Municipal Light Plant. Standard Requirements for Electric Service
Wellesley Municipal Light Plant Standard Requirements for Electric Service Index Section 1... General Information Section 2..General Requirements for Service Section 3. Types of Available Service Section
ELECTRIC METERING COMMERCIAL & INDUSTRIAL
ELECTRIC METERING COMMERCIAL & 1.0 INDEX 1.0 INDEX 2.0 SCOPE 3.0 GENERAL REQUIREMENTS 4.0 METER LOCATIONS 5.0 UNDERGROUND TERMINATIONS 6.0 METERING TRANSFORMER ENCLOSURES 7.0 SINGLE CUSTOMER METER INSTALLATIONS
Three-phase AC circuits
Three-phase AC circuits This worksheet and all related files are licensed under the Creative Commons Attribution License, version 1.0. To view a copy of this license, visit http://creativecommons.org/licenses/by/1.0/,
ELECTRIC SERVICE HANDBOOK
ELECTRIC SERVICE HANDBOOK Revised July 2006 Table of Contents Electric Construction Title: Electric Service Handbook Page No. TOC Rev. July-06 Section 1: Introduction...1-010 Section 2: DP&L Offices...2-010
ELECTRIC SERVICE GUIDELINES (For Indiana)
ELECTRIC SERVICE GUIDELINES (For Indiana) FOR COMMERCIAL / INDUSTRIAL DEVELOPMENTS ELECTRIC SERVICE GUIDELINES FOR COMMERCIAL/INDUSTRIAL DEVELOPMENTS INTRODUCTION... 2 WHAT YOU NEED TO OBTAIN ELECTRIC
Tucson Electric Power Company Rules and Regulations
Original Sheet No.: 907 Introduction The Company will construct, own, operate and maintain lines along public streets, roads and highways which the Company has the legal right to occupy, and on public
208.652.7431 Report power outage after hours: 866.887.8442. 1150 N. 3400 E. Ashton, ID 83420 www.frr ec.com. Ashton, Idaho Headquarters Building
The aim of Fall River Rural Electric Cooperative, Inc. is to make electric energy available to its members at the lowest cost consistent with sound economy and good management. Ashton, Idaho Headquarters
New Electric Connection Application Packet Commercial and Industrial. City of Plummer P.O. Box B, Plummer, ID 83851 (208) 686-1641
New Electric Connection Application Packet Commercial and Industrial General Information: Maps: City of Plummer P.O. Box B, Plummer, ID 83851 (208) 686-1641 Please type or print plainly in ink. Applications
GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264
BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS Building Code compliance is the obligation of design professionals and/or contractors. Plan Review and Inspection Guidelines are intended to be used
Memphis Light, Gas and Water. ELECTRIC, GAS AND WATER Schedule of Charges
Memphis Light, Gas and Water www.mlgw.com ELECTRIC, GAS AND WATER Schedule of Charges 2015 EFFECTIVE 6/3/2015 MEMPHIS LIGHT, GAS AND WATER DIVISION MEMPHIS, TENNESSEE MEMPHIS LIGHT, GAS AND WATER DIVISION
Customer Metering and Services Guide
This document is an uncontrolled copy and may not be the most current copy. The most current copy is available at www.atcoelectric.com. This document is the property of ATCO Electric and may be updated
Electrical Grounding. Appendix C
Appendix C Electrical Grounding Low-Voltage Equipment Grounding The most frequently cited Office of Safety and Health Administration (OSHA) electrical violation is improper occupational grounding of equipment
TERMS AND CONDITIONS
XXII. ELECTRIC LINE EXTENSIONS AND INSTALLATIONS A. The Company will make electric line extensions for normal service to permanent service locations in accordance with the provisions stated herein. B.
MOBILE HOME SERVICE REQUIREMENTS GAS
ELECTRIC AND GAS 1.0 INDEX 1.0 INDEX 2.0 PURPOSE 3.0 GENERAL 4.0 REFERENCE MATERIAL 5.0 TYPICAL UNDERGROUND UTILITY LAYOUT 6.0 METER PAD DETAILS 7.0 GENERAL INSTALLATION PROCEDURES 8.0 PEDESTAL SPECIFICATIONS
Contents. Section 1 General Information 2. 1.A Introduction 3 1.B Overview 3 1.C Pricing, Billing, and Payment Policies 6
Contents Section 1 General Information 2 1.A Introduction 3 1.B Overview 3 1.C Pricing, Billing, and Payment Policies 6 Section 2 Engineering Design 7 2.A Introduction 8 2.B Pepco s Commercial Service
Town House 11265 Center Highway North Huntingdon, PA 15642
APPENDIX C SPECIFICATIONS FOR THE CONSTRUCTION OF BUILDING LATERAL SANITARY SEWERS DECEMBER 2004, INCLUDING AMENDMENTS ADOPTED ON FEBRUARY 6, 2008 AND APRIL 2, 2008; EFFECTIVE ON MAY 1, 2008 Town House
MISCELLANEOUS ELECTRICAL JOBS REQUIRING PERMITS
MISCELLANEOUS ELECTRICAL JOBS REQUIRING PERMITS 01. SAFETY INSPECTION of service equipment at FPL Power Source 02. Construction GFI power outlets (Temp Pole for Construction) 03. 90 day temporary power
Requirements for the installation of. Electric Services. September 8, 2003. Specifications for Electric Installations
Requirements for the installation of Electric Services & Meters September 8, 2003 Specifications for Electric Installations TABLE OF CONTENT Section I - Introduction... 1 Section II - Definitions... 3
Policy and Guidelines for Electric Service
Policy and Guidelines for Electric Service FRANKLIN MUNICIPAL POWER & LIGHT 1050 Pretlow Street Franklin, VA 23851 757-562-8568 757-562-7883 Fax January 2008 Franklin Power & Light HELPFUL TELEPHONE NUMBERS
COMMERCIAL CONDUIT RULES AND REGULATION
Electric Engineering Division COMMERCIAL CONDUIT RULES AND REGULATION S:\COO_ACM_US_Electric_Telecommunications\COO_ET_Engineering\Conduit Policies\Residential 1805 NE 30th Ave., Bldg. 400 Ocala, FL 34470-4875
ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1
KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1
Multiple Meter Installation - 200 Amperes Per Position -Single Phase, Self-contained
Overhead Meters TABLE OF CONTENTS D D Consumer Service Pole for Mobile Home Park Temporary Service -wire Single Phase D. Overhead Meter Installation - Single Phase D. Connection Diagram - Single Phase
Questions and Answers for Heating and A/C Contractors
1. How do we accomplish grounding of furnaces and / or water heaters on two wire circuits? 250.134 Equipment Fastened in Place or Connected by Permanent Wiring Methods (Fixed) Grounding. Unless grounded
Requirements for the Attachment of Communication Cable Facilities on PPL Poles
Page 99 of 137 Requirements for the Attachment of Communication Cable Facilities on Replaces: URS-3002 URS-3004 URS-101C-304 A-157649 Page 100 of 137 Reference Notes for Drawings: General 1. The term communication
Electric Service Guide for Residential Construction
Electric Service Guide for Residential Construction TABLE OF CONTENTS Contacting KCP&L... 2 Existing Home Remodeling or Additions... 2 Building a New Home... 3 KCP&L Services at a Glance... 4 Current Transformers...
INSTRUCTIONS FOR PREPARING APPLICATIONS FOR ELECTRIC SERVICE & METER
INSTRUCTIONS FOR PREPARING APPLICATIONS FOR ELECTRIC SERVICE & METER Please refer to the sample application while reviewing the following notes. The letters below correspond with those on the sample. NOTE:
Permit No. Permit Fee: $295.00. Permit Expires (D+90 days): Business Name: Applicants Name: Telephone Number: E-mail Address:
City of Woodland Park Internet Service Provider (IPS) Permit for Installation of Telecommunication Infrastructure within City Owned Rights-of-Way (up to five locations per single permit) Permit No. Permit
Electrical Service Guidelines
Electrical Service Guidelines Middle Tennessee Electric Membership Corporation Revised: May 23, 2013 MTEMC's Electrical Guidelines TABLE OF CONTENTS Right-of-Way Clearance Guide 3 MTEMC Requirements 4
Information and Requirements for Electric Service. Chapters 1, 2, 4, 6 and Appendix
Organization: Manual: Section: Electric Distribution Information and Requirements for Electric Service Chapters 1, 2, 4, 6 and Appendix Tracking Number: 05-077 Date: January 6, 2006 SME: Jim Calore Contact
0095.05 June 30. 2011 July 18, 2014 1 of 7
Standard Number: Superseding: Effective Date: Page: 0095.05 June 30. 2011 July 18, 2014 1 of 7 Pole Attachments, Automated Meter Reading and Cellular Phone Antennas 1. Scope 2. Application This standard
ELECTRIC WATER HEATER CREDIT
RESIDENTIAL, FARM AND SMALL COMMERCIAL ELECTRIC WATER HEATER CREDIT AVAILABILITY Available to any member of the REMC, located on its lines for general residential, farm, and small commercial use up to
UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Metering and Monitoring. Basis of Design
Basis of Design This section applies to the design, installation and integration of metering and monitoring equipment, including: hardware installed in the electrical service and distribution equipment,
CUSTOMER INSTALLATION STANDARDS FOR ELECTRIC SERVICE
CUSTOMER INSTALLATION STANDARDS FOR ELECTRIC SERVICE February 1, 2013 A transition period will exist in which installations may be approved and connected as long as they meet either the 2008 or the 2013
QUESTIONS and ANSWERS RFB 745-15-9894, Metal Clad Switchgear and Power Control Room
QUESTIONS and ANSWERS RFB 745-15-9894, Metal Clad Switchgear and Power Control Room 1) When you click on the UTHSCSA Drawing the site takes you to the E-1 drawing no other. Will there be other drawings
FFI. Advances in Medium and Low Voltage Power Distribution ESS Metron Expo and Technical Seminars. Presented By: Greg Pelster & Robert Schmid
Advances in Medium and Low Voltage Power Distribution ESS Metron Expo and Technical Seminars Presented By: Greg Pelster & Robert Schmid FFI Ferrie, Franzmann Industries LOW VOLTAGE SWITCHGEAR & LOW VOLTAGE
Please Refer to Attached Sample Form
Pacific Gas and Electric Company San Francisco, California U 39 Revised Cal. P.U.C. Sheet No. 29987-G Cancelling Revised Cal. P.U.C. Sheet No. 22381-G Gas Sample Form No. 62-0982 Distribution and Service
DISTRIBUTION SYSTEMS INDEX NOV 06 SECTION 2. Detroit...2-1-5 Ann Arbor...2-1-6 Mt. Clemens...2-1-7 Port Huron...2-1-8
DISTRIBUTION SYSTEMS INDEX NOV 06 SECTION 2 Kinds and Uses of Service... 2-1-1 and 2-1-2 Wye Network Area Maps Detroit...2-1-5 Ann Arbor...2-1-6 Mt. Clemens...2-1-7 Port Huron...2-1-8 Transformer Connections
CHECKING AND TESTING ELECTRICAL INSTALLING WORK
CHECKING AND TESTING ELECTRICAL INSTALLING WORK Department of Consumer and Employment Protection Energy Safety Preface It is a requirement of the Electricity (Licensing) Regulations 1991 that all electrical
SHALLOW UTILITIES JOINT PROVISIONING GUIDELINES SCOPE
AN INFORMATION GUIDE SCOPE PROJECT MANAGER Joint Provisioning Guidelines for Shallow Utility Services in Residential Areas where the Electric, Gas, Telephone & Cable TV facilities are Buried in the same
Indianapolis Power & Light Company
Indianapolis Power & Light Company Electric Service and Meter Manual The Electric Service & Meter Manual is not copyrighted and permission is hereby given to reproduce this document. However, the Indianapolis
GENERAL ELECTRICAL REQUIREMENTS
GENERAL ELECTRICAL REQUIREMENTS RECEPTACLE SPACING Within 6-feet of the edge of any door HABITABLE Not more than 12-feet apart along wall ROOMS: At all wall spaces 24 or more wide Within 24 of edge of
SPECIFICATIONS FOR ELECTRIC SERVICE GARLAND POWER & LIGHT
FOREWORD This booklet is issued by the Electric Department of the City of Garland, herein after referred to Garland Power & Light or GP & L, to acquaint electric customers of Garland Power & Light, or
We look forward to serving you!
Dear Construction Customer: Enclosed you will find your DP&L Electric Construction Packet. This packet provides you with the information needed to obtain your new electric service or electric service change
Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS
Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...
Submit shop drawings for equipment provided under this section Shop drawings shall indicate:
Section 16435 - SWITCHBOARDS Introduction Part 1 - General Reference The work under this section is subject to requirements of the Contract Documents including the General Conditions, Supplementary Conditions,
REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING
REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING Revised October, 2013 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 2.0 REQUIRED DRAWINGS... 3 2.1 Site Plan... 3
Temporary Electric Service
Temporary - Electric Construction Packet Temporary Electric Service This packet explains what is required to construct your Single new Phase electric Service temporary service and will guide you through
New Residential Service Requiring Construction
New Residential Service Requiring Construction What you should know about having service connected to your new home visit us at www.flintenergies.com FEMC 593 R2/12 All references from NEC 2011 New Residential
