1 UEENEEG108A Trouble-shoot and repair faults in low voltage electrical apparatus and circuits AS3000:2007 & AS3017:2007 Summary MANUFACTURING AND ENGINEERING DIVISI M & E UEENEEG108A
2 TESTING Before any installation is connected to the supply it is necessary for the electrician to determine that the installation is safe. To prove safety the following tests must be carried out. (a) Visual Inspection. - Use the checklist given in Clause to ensure all visual inspections are carried out. (b) Electrical Testing - There are six (6) Mandatory tests that must be carried out. These are 1. Earth Continuity Test Insulation Resistance Test Polarity Test This test completes the / Transposition Test not switched 4. Correct circuit connections Test This test completes the / Earth Transposition Test and belong to the same circuit / Earth Transposition Test. Earth Fault Loop Impedance Test Operation of RCD s Test UEENEEG108A Page 2
3 Test 1 Earth Continuity Test Pur p ose f or Test To keep exposed metal at earth potential To allow circuit protection to operate under fault conditions Test Inst r um ent :-Ohm m et er How t o Per f orm Test The resistance of a protective earthing conductor must be low enough to ensure the circuit breaker will trip within 0.4 seconds. The FAQ for AS 3000:2000 still applies. FAQ 009/2001: AS/NZS 3000:2000 CLAUSE & CLAUSE INSPECTI AND TESTING Test results Continuity of earthing system TESTING Mandatory tests Continuity of the earthing system Question 009/2001. Is there an appropriate single value of resistance that could be used to show compliance with the continuity of earthing system test? Answer. No. An appropriate value of resistance is related to the type and rating of the protective device used to protect the circuit under test. An appropriate table has been included in AS Disconnect the Earth from the neutral link Disconnect the from the neutral link If the circuit has an alternative earth path (eg the water pipes to a hot water system), then disconnect the sub circuit earth from equipment. Use ohms range of megger to measure earth resistance to every earth point. Results should comply with table shown. RECNECT THE EARTH TO THE HWS CE THE EARTH HAS BEEN TESTED Turn on all switches as you go Disconnect sub-main at sub-board Turn off sub-board isolator Table 8.2 AS id en t if yin g t h e m axim um p erm issib le resist an ces o f act ive (Rp h ) an d p rot ect ive eart h in g (Re) co n d uct o rs m easured at an am b ien t t em p. o f 20 C. LEAVE MAIN EARTH DISCNECTED LEAVE MAIN NEUTRAL DISCNECTED UEENEEG108A Page 3
4 Test 2 Insulation Resistance Test Pur p ose To avoid exposure to live components To prevent short circuits NOTE: DO NOT MEGGER TEST BETWEEN ACTIVE AND NEUTRAL OF FINAL SUBCIRCUITS, BUT YOU MUST TEST BETWEEN ALL CIRCUIT CDUCTORS OF MAINS AND SUBMAINS. Test Inst r um ent Insulation Resistance Tester (Megger) 00V see clause (noting exceptions 1 & 2) How t o Test range and hot water service. Earth AND are still disconnected from link. Switch ALL switches Turn ALL circuit breakers Bridge to Link Megger Test between the bridge (joined active / neutral) and Earth Reading should be greater than or equal to 1M If reading is less than 1M disconnect and conductors from Range and HWS. (See Note) Change any multi-position switches (eg two way) and repeat megger test. Megger heaters & busways individually Reconnect the active and neutral to the Note. Sheathed heating elements (as found in HWS and ranges) can have insulation resistances as low as 10 k Clause Number (i) &(ii) Insulation Resistance between conductors of mains and sub mains would be expected to be much higher - Say 0 M M RECNECT THE MAIN EARTH AND MAIN NEUTRAL TO THE NEUTRAL LINK UEENEEG108A Page 4
5 HAS THE MAIN EARTH & MAIN NEUTRAL BEEN RECNECTED? Test 3 Polarity Test for loaded circuits A) Circuits with load connected eg Water Heaters, Urns, Ranges Test Inst r um ent Ohm meter How to test: On active side you should get Resistance of the load R= U 2 P On side you should get zero ohms Ensure the Earth AND has been reconnected to the Link Switch off Circuit breaker off All load switches, including simmerstats and thermostats, on For wall ovens where no access to terminal block, make definite check prior to installation. UEENEEG108A Page
6 Test 3 Polarity Test - Also tests all other transpositions, circuit intermix and short circuits between active and neutral. B) Unloaded Circuits Including fluorescent luminaries Test Instrument: Ohmmeter How to test: 10 C/B Switch closed Infinite Switch open Close only one circuit breaker Disconnect only its corresponding Connect resistors as shown Test ALL points on this circuit Result other than those shown indicates a FAULT Faults indicated by readings other than above: Reverse Polarity and Transposition Earth reversed 10 C/B 3 3 being switched C/B being switched UEENEEG108A Page 6
7 Circuit Intermix The neutral disconnected does NOT belong to the circuit being tested. 10 being switched 0 Transposition Earth C/B Wrong! When testing using this method with intermixed circuits it is possible to get some unexpected results as follows. If the circuits are supplied by combination RCD/MCB s, there will be no return path for an intermixed neutral. The active - earth test will show up as the expected 10 however the intermixed neutral will show up as an open circuit. This occurs because to isolate the actives, only the RCD/MCB for the circuit you are testing is turned on. There are several ways to get around this: 1. Bypass all RCD/MCB neutrals before you start with the polarity tests 2. If you find what appears to be an open circuit neutral, turn each combination RCD/MCB on, then off individually. If the multi-meter continues to show the neutral as an open circuit, then it probably is. If it is intermixed with another circuit, when you turn on the combination RCD/MCB with which it is intermixed the multi-meter reading will drop to a low value, and the intermix will be exposed. UEENEEG108A Page 7
8 Sub Board Sub Polarity Test: A) Where supplied via sub circuit earth Infinite SUB MAINS SUB BOARD These were opened from previous test. Zero Ohms Test: Ohmmeter E N = 0 E A = Infinite B) Where sub board is separate M.E.N. system Infinite SUB MAINS SUB BOARD These were opened from previous test. Reading * M 00 V Megger * Reading may be high, but a circuit will be indicated on the NEUTRAL. UEENEEG108A Page 8
9 Test 4 Short Circuit Test. Pur p ose To avoid damage to circuit components if excessive current flows due to short circuits Test Inst r um ent : Ohm m et er How t o Test Ohmmeter will indicate the resistance of these loads in parallel Remove test resistors Leave all switches Turn all circuit breakers Take reading between and Link Actual reading will depend on connected load Power circuit infinite 10.2 kw Range.3 ohms 3.6 kw HWS 16 ohms With all circuits connected loads will be in parallel, giving an even lower reading Individual circuits can be checked by turning all breakers OFF then turning each breaker and OFF in turn Fluorescent luminaires with p.f. correction capacitors may give low readings, increasing as capacitor charges. It also should also be noted that the polarity test conducted earlier with the resistors will also expose a short circuit between active and neutral as indicated above. The ohmmeter will read the same value on both terminals, which will be approximately 3.3 ohms, plus cable resistance. This occurs because the active to neutral fault places the and 10 ohm resistor in a parallel configuration to earth. UEENEEG108A Page 9
10 Test - Earth Loop Impedance Test This is required for circuits containing socket outlets that are not protected by a RCD. Purpose of Test To ensure that the resistance of the fault loop is low enough to allow the circuit protection to operate in the specified time (0.4 seconds) Test Instrument: Ohm meter How to Test No supply available. (If supply is available use test method (b)) This first method enables the fault loop impedance to be checked as part of the polarity test using and 10 ohm resistors. Close circuit breaker for circuit under test. Ensure resistors are connected from polarity test. Turn the switch controlling the socket outlet Measure the resistance between the and Earth at the socket outlet under test Note: this test needs only to be done on the most distant part of the circuit from the switch board The measured resistance must not exceed the values given in Table 8.2 of AS3000 (see below) Subtract 10 ohms from your measured result. To obtain the maximum allowable fault loop impedance see Table 8.2 Check your result to ensure the measured value is satisfactory Notes to Table 8.2 show how the values have been derived. Table 8.2 AS id en t if yin g t h e m axim um p erm issib le resist an ces o f act ive (Rp h ) an d p rot ect ive eart h in g (Re) co n d uct o rs m easured at an am b ien t t em p. o f 20 C. UEENEEG108A Page 10
11 The earth loop impedance test can also be carried out as follows without using the resistors by following this second method as outlined in AS3017 How to Test No supply available. (If supply is available use test method (b)) OFF Open circuit breaker for circuit under test. Connect the Load side of the Circuit Breaker to the Earth Link. Turn the switch controlling the socket outlet Measure the resistance between the and Earth at the socket outlet under test Note this test needs only to be done on the most distant part of the circuit from the switch board The measured resistance must not exceed the values given in Table 8.2 of the rules. Notes to Table 8.2 show how the values have been derived. Test 6 - RCD Test. (supply needs to be available) Test Equipment Test button on RCD or special test equipment. How to Test Supply must be available Operate the integral test device of the RCD Check that it trips the designated circuit. If using a special test device follow manufactures instructions DATE OF INITIAL ENERGISATI OF AN INSTALLATI The date of initial energisation of an installation should be available on-site, either by marking or in an accessible record. UEENEEG108A Page 11
CHECKING AND TESTING ELECTRICAL INSTALLING WORK
CHECKING AND TESTING ELECTRICAL INSTALLING WORK Department of Consumer and Employment Protection Energy Safety Preface It is a requirement of the Electricity (Licensing) Regulations 1991 that all electrical
Polarity. Electrical Quals 2007 1
Polarity Electrical Quals 2007 1 Polarity testing Introduction The polarity test is the 8th test in the sequence. Some people will think of it as the 4th test, (which to a certain extent they are correct).
Electrical Practices for Construction Work
1. Purpose Electrical Practices for Construction Work The purpose of this Code is to provide practical guidance and set minimum safety requirements for electrical practices on all construction sites in
Electrical Resistance Resistance (R)
Electrical Resistance Resistance (R) Any device in a circuit which converts electrical energy into some other form impedes the current. The device which converts electrical energy to heat energy is termed
A Guide to 17th Edition Testing
Seaward, Bracken Hill, South West Industrial Estate, Peterlee, County Durham, SR8 2SW United Kingdom Tel: +44 (0) 191 586 3511 Fax: +44 (0) 191 586 0227 Email: [email protected] Web: www.seaward.co.uk
GUIDE TO THE AM2 EXAM
AM2 GUIDE TO THE AM2 EXAM What is AM2? AM2 or the Achievement Measurement 2 is a practical performance skill test administered by the National Electrotechnical Training (NET). You must take the AM2 test
MEM10019 Select circuit protection devices by type and rating, fit to switchboards and install earthing
MEM10019 Select circuit protection devices by type and rating, fit to switchboards and install earthing Release: 1 MEM10019 Select circuit protection devices by type and rating, fit to switchboards and
Section B: Electricity
Section B: Electricity We use mains electricity, supplied by power stations, for all kinds of appliances in our homes, so it is very important to know how to use it safely. In this chapter you will learn
Experiment NO.3 Series and parallel connection
Experiment NO.3 Series and parallel connection Object To study the properties of series and parallel connection. Apparatus 1. DC circuit training system 2. Set of wires. 3. DC Power supply 4. Digital A.V.O.
chapter8 Testing and commissioning Unit 2 outcome 2
Testing and commissioning chapter8 Unit 2 outcome 2 It is important that electricians are not just able to construct; they should also be able to recognise faults and take action to help prevent them.
CAPACITOR BANK TESTING SWP
1. PURPOSE AND SCOPE The purpose of this Standard Work Practice (SWP) is to standardise and prescribe the method for testing Capacitor Banks including capacitors, tuning reactors and inrush limiting reactors.
Fig. 1 Analogue Multimeter Fig.2 Digital Multimeter
ELECTRICAL INSTRUMENT AND MEASUREMENT Electrical measuring instruments are devices used to measure electrical quantities such as electric current, voltage, resistance, electrical power and energy. MULTIMETERS
Circuit Electrical Testing
Safe Isolation Procedure Circuit Electrical Testing Site Safety Management It is essential from the outset that effective management and control of the system, apparatus and equipment used on site is achieved
Experiment #3, Ohm s Law
Experiment #3, Ohm s Law 1 Purpose Physics 182 - Summer 2013 - Experiment #3 1 To investigate the -oltage, -, characteristics of a carbon resistor at room temperature and at liquid nitrogen temperature,
Pump Maintenance - Repair
Pump Maintenance - Repair Brian Trombly Mo Droppers Cummins Bridgeway, Gaylord, Mi The basic centrifugal pump consists of two main elements: 1. The rotating element which includes an impeller and a shaft.
CHAPTER 4 UTILITY SYSTEMS ELECTRICAL. Utility Systems Electrical. Main Panel
CHAPTER 4 UTILITY SYSTEMS ELECTRICAL Utility Systems Electrical The electrical supply to your home begins outside, where you will see either an overhead feed and piping down the side of your home or (if
PROTECTION AGAINST ELECTRIC SHOCK by John Ware
16 become live under fault conditions. The potential of the metal enclosure is higher than that of the main earthing terminal of the installation (and that of Earth) because of a potential difference created
Parallel Circuits. Objectives After studying this chapter, you will be able to answer these questions: 1. How are electrical components connected
This sample chapter is for review purposes only. Copyright The Goodheart-Willcox Co., Inc. All rights reserved. Electricity Objectives After studying this chapter, you will be able to answer these questions:.
ELECTRIC HEATER COMPANY Operating and Maintenance Manual For Immersion Heating Elements
ELECTRIC HEATER COMPANY Operating and Maintenance Manual For Immersion Heating Elements HUBBELL ELECTRIC HEATER COMPANY P.O. BOX 288 STRATFORD, CT 06615 PHONE: (203) 378-2659 FAX: (203) 378-3593 INTERNET:
Regulation IO-6.0: Electrical Safety Regulations
Regulation IO-6.0: Electrical Safety Regulations 6.1 Workmanship & Material 6.2 Electrical Conductors 6.3 Overcurrent Protective Devices 6.4 Precautions against Earth Leakage and Earthfault Currents 6.5
Electrical test equipment for use on low voltage electrical systems
Electrical test equipment for use on low voltage electrical systems Guidance Note GS38 (Fourth edition) This general series guidance note is aimed at people (including electricians, electrical contractors,
Aquamax Australia Pty Ltd ABN 17 138 189 689
Aquamax Australia Pty Ltd ABN 17 138 189 689 AQUAMAX SERVICE MANUAL Stainless Steel Electric Water Heaters AQ0903010-A Revision: A Published: November 2012 E80 to E315 Series Contents Introduction... 3
Electrical Safety Tester Verification
Ensuring Validity of Regulatory Tests Verification of electrical safety testing equipment is a procedure that is often overlooked by manufacturers. Running test verification is crucial to ensuring that
Electric Instantaneous. Water Heaters. Service manual
Electric Instantaneous Water Heaters Service manual Before installation quoting stage Work out with the customer what is the right model to install for the application Site assessment 1. The electrician
Heading FACT SHEET. Overview. www.safeworkaustralia.gov.au
ELECTRICAL RISKS AT THE WORKPLACE Heading FACT SHEET Overview This fact sheet provides general guidance for persons conducting a business or undertaking (PCBUs) and workers on managing electrical risks
Contractor Connect Scheme Electrical Contractor and Worker Handbook
Contractor Connect Scheme Electrical Contractor and Worker Handbook January 2016 Document release information Document number 13553681 Document title Revision status Contractor Connect Scheme handbook
DIOCESE OF LINCOLN GUIDELINES
DIOCESE OF LINCOLN GUIDELINES FOR ELECTRICAL INSTALLATIONS INSIDE CHURCHES Diocesan Advisory Committee for the Care of Churches Revised March 2006 Electrical Installations inside Churches As with all
12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting
12 SOLAR PHOTOVOLTAIC POWER by John Ware IT IS PLANNED for BS 7671:2008 to include a new Section 712 providing additional requirements for safety applicable to solar photovoltaic (pv) power supply systems.
ELECTRICAL PRACTICES FOR CONSTRUCTION WORK
CONTRACTOR S CHECKLIST ELECTRICAL PRACTICES FOR CONSTRUCTION WORK 2007 WorkCover. Watching out for you. New South Wales Government Disclaimer This publication contains information regarding occupational
Fundamentals of Power
Fundamentals of Power Fundamentals of Power 2008 American Power Conversion Corporation. All rights reserved. All trademarks provided are the property of their respective owners. Learning Objectives At
Annual testing programme will be reported, by the department, as part of the annual hazard review process due to be completed by 31 March each year.
HR Heath and Safety Policy Health and Safety Electrical Appliances Testing and Inspection Policy The University of Auckland provides for specific safe operating practices for the safety testing and inspection
RCD Inspection Log Book
RCD Inspection Log Book This book is the property of: Commenced: / /. Completed: / /. 2 Clipsal Australia Pty Ltd Clipsal Australia Pty Ltd 3 4 Clipsal Australia Pty Ltd Clipsal Australia Pty Ltd 5 6 Clipsal
ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV
1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled
CSA Z32 TESTING GUIDELINE AND PROCEDURES
PO Box 20020 Red Deer, AB T4N 6X5 Phone: 403.986.2939 Web: www.908eng.com July 9, 2012 CSA Z32 TESTING GUIDELINE AND PROCEDURES This document is intended to outline the various tests, procedures and preparations
SERVICE MANUAL RESIDENTIAL ELECTRIC AND LIGHT DUTY COMMERCIAL ELECTRIC WATER HEATERS. Troubleshooting Guide and Instructions for Service
RESIDENTIAL ELECTRIC AND LIGHT DUTY COMMERCIAL ELECTRIC WATER HEATERS SERVICE MANUAL Troubleshooting Guide and Instructions for Service (To be performed ONLY by qualified service providers) Models Covered
Lab E1: Introduction to Circuits
E1.1 Lab E1: Introduction to Circuits The purpose of the this lab is to introduce you to some basic instrumentation used in electrical circuits. You will learn to use a DC power supply, a digital multimeter
NATIONAL CERTIFICATE (VOCATIONAL)
NATIONAL CERTIFICATE (VOCATIONAL) SUBJECT GUIDELINES ELECTRICAL PRINCIPLES AND PRACTICE NQF Level 4 September 2007 ELECTRICAL PRINCIPLES AND PRACTICE LEVEL 4 CONTENTS INTRODUCTION 1 DURATION AND TUITION
High kw Electric Tankless Water Heater Troubleshooting Guide
Technical Service Bulletin High kw Electric Tankless Water Heater Troubleshooting Guide Models: WH17, WH27, WH36 AE115, AE125, (FD108 and higher) DANGER: ELECTRIC SHOCK ELECTRICITY IS EXTREMELY DANGEROUS.
TECHNICAL SERVICE DEPARTMENT Technical Service Bulletin 1-800-432-8373. Tankless Electric (RTE) Troubleshooting
Sequence of Operations 1 Power supply and field wiring block 2 Energy Cut Off (ECO) 3 Water flow plunger and cold inlet 4 Magnetic flow switch 5 Water temperature thermistor 6 Control panel and circuit
GROUND DETECTION CIRCUITS FOR STATIONARY APPLICATIONS (IN PLAIN DOWN TO EARTH LANGUAGE)
GROUND DETECTION CIRCUITS FOR STATIONARY APPLICATIONS (IN PLAIN DOWN TO EARTH LANGUAGE) Matthew Theriault Designer Hindle Power Inc. Easton, PA SCOPE AND PURPOSE OF THE PAPER Why do we bother to monitor
Grounding of Electrical Systems NEW CODE: Grounding and Bonding
Grounding of Electrical Systems NEW CODE: Grounding and Bonding Presented By Scott Peele PE Grounding of Electrical Systems Outline Defining the Terms Why should I Ground? Types of Grounding Systems Separately
CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE
CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE 8.1 SYSTEM 8.1.1 Armoured, screened underground cables are used for control communication in electrified areas to limit induction effect. 8.2
Mobile Device Power Monitor Battery Connection Quick Start Guide
Mobile Device Power Monitor Battery Connection Quick Start Guide Distributed By: Monsoon Solutions, Inc. www.msoon.com Introduction The Power Tool software and the Mobile Device Power Monitor hardware
What are the basic electrical safety issues and remedies in solar photovoltaic installations?
What are the basic electrical safety issues and remedies in solar photovoltaic installations? Presented by: Behzad Eghtesady City of Los Angeles Department of Building and Safety Topics Covered Photovoltaic
ANALOG AND DIGITAL METERS ANALOG VS. DIGITAL METERS VOLTMETERS ANALOG AND DIGITAL
ANALOG VS. DIGITAL METERS Ultimately, your diagnosis of vehicle electrical system problems will come down to using a voltmeter, ammeter, or ohmmeter to pinpoint the exact location of the problem. There
Candidate Self-Assessment Checklist
General Information This is a compulsory document which must be completed by all candidates due to undertake the AM2 Assessment of Occupational Competence and provided to the assessment centre prior to
A.Y. McDonald Mfg. Co. Troubleshooting Submersible and Jet Pumps
A.Y. McDonald Mfg. Co. Troubleshooting Submersible and Jet Pumps Troubleshooting Submersible Pumps Fuse overload or circuit breaker trips when motor is started 1. Incorrect line voltage. Check the line
GUIDELINES FOR ELECTRICAL WIRING IN RESIDENTIAL BUILDINGS
GUIDELINES FOR ELECTRICAL WIRING IN RESIDENTIAL BUILDINGS 2008 EDITION www.st.gov.my CONTENTS Chapter Title Page 1. 1.1 1.2 1.3 Introduction Purpose References 4 4 5 2. Supply System 6 2.1 Electricity
Determining the Cause of AFCI Tripping Branch/Feeder and Combination Arc Fault Circuit Interrupters Class 760
Data Bulletin Determining the Cause of AFCI Tripping Branch/Feeder and Combination Arc Fault Circuit Interrupters Class 760 Retain for future use. 0760DB0204 Replaces 0760DB0204 R09/07 Precautions DANGER
CONTINUOUS MONITORING AND AVOIDANCE OF RESIDUAL CURRENTS IN DATA CENTRES WITH RCM White paper Revision 2
IT Power Solutions CONTINUOUS MONITORING AND AVOIDANCE OF RESIDUAL CURRENTS IN DATA CENTRES WITH RCM White paper Revision 2 Thomas B. Jones 1 Introduction Operators and managers consider outages, operational
Guidance notes for the installation of electrical supply in mobile trailers for breast screening
NHS Breast Cancer Screening Programme Cancer Screening Programmes Guidance notes for the installation of electrical supply in mobile trailers for breast screening B Mansfield, CP Lawinski NHSBSP PUBLICATION
ELECTRICAL INSTALLATION CONDITION REPORT (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations)
Original Certificate DETAILS OF THE CLIENT Certificate reference: ELECTRICAL INSTALLATION CONDITION REPORT (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations) Name: Address: PURPOSE
Unit 4: Electricity (Part 2)
Unit 4: Electricity (Part 2) Learning Outcomes Students should be able to: 1. Explain what is meant by power and state its units 2. Discuss the importance of reducing electrical energy wastage 3. State
TESTING AND COMMISSIONING PROCEDURE FOR ELECTRICAL INSTALLATION GOVERNMENT BUILDINGS THE HONG KONG SPECIAL ADMINISTRATIVE REGION
TESTING AND COMMISSIONING PROCEDURE FOR ELECTRICAL INSTALLATION IN GOVERNMENT BUILDINGS OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION 2012 EDITION ARCHITECTURAL SERVICES DEPARTMENT THE GOVERNMENT OF THE
By Mark Coles. This article looks at the temporary use of portable generators in floating, earthed and reference-earthing scenarios.
16 Operation of portable generators Operation of portable generators By Mark Coles This article looks at the temporary use of portable generators in floating, earthed and reference-earthing scenarios.
Pontyclun Electrotechnical Training Ltd. (P.E.T. Ltd.)
Pontyclun Electrotechnical Training Ltd. (P.E.T. Ltd.) Our highly-skilled and knowledgeable staff boast extensive industry experience as well relevant teaching qualifications. We are fully accredited by
Experiment #5, Series and Parallel Circuits, Kirchhoff s Laws
Physics 182 Summer 2013 Experiment #5 1 Experiment #5, Series and Parallel Circuits, Kirchhoff s Laws 1 Purpose Our purpose is to explore and validate Kirchhoff s laws as a way to better understanding
Experiment 4 ~ Resistors in Series & Parallel
Experiment 4 ~ Resistors in Series & Parallel Objective: In this experiment you will set up three circuits: one with resistors in series, one with resistors in parallel, and one with some of each. You
PAT400 Series. Portable Appliance Testers. User Manual
M PAT400 Series Portable Appliance Testers User Manual Thank you for purchasing the Megger PAT400 portable appliance tester. For your own safety and to get the maximum benefit from your instrument, please
4 IX D N E P P A Installation methods Current-carrying capacity and voltage drop for cables Reference method IET Wiring Matters
8 Appendix 4 of BS 7671 by Mark Coles Appendix 4, Current-carrying capacity and voltage drop for cables and flexible cords, has seen significant changes with the publishing of BS 7671:2008. This article
http://waterheatertimer.org/how-to-troubleshoot-gas-water-heater.html
http://waterheatertimer.org/how-to-troubleshoot-gas-water-heater.html TECHNICAL SERVICE DEPARTMENT Effective October 2007, we transitioned to the White Rodgers (Intelli-Vent TM )Thermostat Control for
Cable Size Selection for Energy Efficiency
Cable Size Selection for Energy Efficiency Introduction The traditional method for determining the appropriate cable size for a particular installation involves the selection of the smallest size conductor
Electrical Grounding. Appendix C
Appendix C Electrical Grounding Low-Voltage Equipment Grounding The most frequently cited Office of Safety and Health Administration (OSHA) electrical violation is improper occupational grounding of equipment
Experiment1: Introduction to laboratory equipment and basic components.
Experiment1: Introduction to laboratory equipment and basic components. 1 OBJECTIVES. This experiment will provide exposure to the various test equipment to be used in subsequent experiments. A primary
Air Conditioning Sign-Off Sheet
Air Conditioning Sign-Off Sheet Printed Technician Name Address Social Security Number Telephone Number City State Zip Code Install Or Verify The Accuracy Of An Air Conditioner s Installation The candidate
Student Exploration: Circuits
Name: Date: Student Exploration: Circuits Vocabulary: ammeter, circuit, current, ohmmeter, Ohm s law, parallel circuit, resistance, resistor, series circuit, voltage Prior Knowledge Questions (Do these
What equipment needs RCD protection? 3. Testing and tagging of electrical equipment 6. Protectively earthed and double insulated equipment 8
ELECTRICAL SAFETY CONTENTS Introduction 2 Residual current devices 2 What equipment needs RCD protection? 3 Risk assessment examples 4 RCD testing 5 Testing and tagging of electrical equipment 6 Testing
Trade of Electrician. Three-phase Distribution Boards And Socket Circuits
Trade of Electrician Standards Based Apprenticeship Three-phase Distribution Boards And Socket Circuits Phase 2 Module No. 2.3 Unit No. 2.3.2 COURSE NOTES Created by Charlie Walsh - Athlone TC Revision
6.0 Electrical Installations
6.0 An electrical installation is a combination of electrical equipment installed to fulfill a specific purpose and having coordinated characteristics. In dealing with the electrical installation, it is
Experiment 8 Series-Parallel Circuits
Experiment 8 Series-Parallel Circuits EL 111 - DC Fundamentals By: Walter Banzhaf, E.K. Smith, and Winfield Young University of Hartford Ward College of Technology Objectives: 1. For the student to measure
Electrical Essentials for HVAC&R Engineers. Wednesday, October 7
Electrical Essentials for HVAC&R Engineers Wednesday, October 7 Main Components of an Electrical System Accessibility of Switchboards AS/NZS 3000-2007 REQUIRES SWITCHBOARDS TO HAVE ADEQUATE SPACE TO ALLOW
FREQUENTLY ASKED QUESTIONS TESTING AND TAGGING OF ELECTRICAL EQUIPMENT
FREQUENTLY ASKED QUESTIONS TESTING AND TAGGING OF ELECTRICAL EQUIPMENT HAS THE LAW CHANGED REGARDING TESTING AND TAGGING OF ELECTRICAL EQUIPMENT? Yes, Simplified safety regulations for electrical equipment
National Craft Assessment and Certification Program S P E C I F I C A T I O N S
National Craft Assessment and Certification Program S P E C I F I C A T I O N S INDUSTRIAL ELECTRICIAN V4 ELEC26_O4 Released September 2013 Focus Statement An Industrial Electrician must be able to interpret
Hyperlinks are Inactive
Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)
Type SA-1 Generator Differential Relay
ABB Automation Inc. Substation Automation and Protection Division Coral Springs, FL 33065 Instruction Leaflet 41-348.11C Effective: November 1999 Supersedes I.L. 41-348.11B, Dated August 1986 ( ) Denotes
Guidance for upgrading to GB4943.1-2011 (IEC 60950-1: 2005, MOD)
Guidance for upgrading to GB4943.1-2011 (IEC 60950-1: 2005, MOD) Note: This guidance document is a translation of official Chinese document which is issued by CQC (China Quality Certification Center) on
Handheld portable appliance testers
PAT100 SERIES Handheld portable appliance testers PAT100 SERIES Handheld portable appliance testers Simple Tick/Cross, pass/fail indication plus measurement Battery powered with rechargeable options Includes
Single Phase Soft Starter
Single Phase Soft Starter Installation & Operating Manual 6/02 Table of Contents Section 1 General Information................................................... 1 1 General Description................................................
6/14/02 Chapter 14: Use of Electrical Test Equipment 1/20
USE OF ELECTRICAL TEST EQUIPMENT Test equipment is necessary for determining proper set-up, adjustment, operation, and maintenance of electrical systems and control panels. The following is a general procedure
GUIDE TO THE MAINTENANCE, INSPECTION AND TESTING OF PORTABLE EQUIPMENT (ELECTRICAL APPLIANCES AND TOOLS) IN THE WORKPLACE
GUIDE TO THE MAINTENANCE, INSPECTION AND TESTING OF PORTABLE EQUIPMENT (ELECTRICAL APPLIANCES AND TOOLS) IN THE WORKPLACE ET 215:2008 ELECTRO-TECHNICAL COUNCIL OF IRELAND 2008 Page 1 of 6 Published by
LOXONE 12 Channel Amplifier
LOXONE 12 Channel Amplifier Item no.: 200110 Thank you for purchasing the Loxone Twelve Channel Amplifier. The versatility of the Amplifier makes it the perfect choice for almost every type of custom multi-room
Unified requirements for systems with voltages above 1 kv up to 15 kv
(1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements apply to
CHECK LIST OF SITE INSPECTION ON LV ELECTRICAL INSTALLATION (Basic Information to be filled by Consultant)
CHECK LIST OF SITE INSPECTION ON FORM EPS / E 5 PAGE 1 / 7 To : Head of District, SYABAS District Consultant : Name of Development : File No : Date : PUMP HOUSE 1.0 A. SQUIRREL CAGE MOTOR No. of Pump set
TECHNICAL SERVICE DEPARTMENT Technical Service Bulletin 1-800-432-8373. 2 Inch PowerVent LED Indicator Explanations & Troubleshooting Table
New Robertshaw control valve was introduced in May 2008 as a replacement part. See last page for troubleshooting this replacement part. All voltage inputs are 120V. All electrical connectors are Molex
BSNL TTA Question Paper-Instruments and Measurement Specialization 2007
BSNL TTA Question Paper-Instruments and Measurement Specialization 2007 (1) Instrument is a device for determining (a) the magnitude of a quantity (b) the physics of a variable (c) either of the above
WORLDWIDE. GW400k SERIES MAINTENANCE MANUAL PROVEN PERIMETER PROTECTION
ORLDIDE G400k SERIES MAINTENANCE MANUAL PROVEN PERIMETER PROTECTION GEOQUIP LIMITED Kingsfield Industrial Estate, Derby Road irksworth, Matlock, Derbyshire, DE4 4BG Tel : 01629 824891 Fax : 01629 824896
BASIC NEC CODE RULES AND DESIGN PRACTICE
BASIC NEC CODE RULES AND DESIGN PRACTICE Wire Ampacity and Size Circuit Breaker Size 1. Maximum loading for any branch circuit is 80% of rating of circuit for ampacity of wire for any load. NEC 220-2,
Table of Contents. The Basics of Electricity 2. Using a Digital Multimeter 4. Testing Voltage 8. Testing Current 10. Testing Resistance 12
Table of Contents The Basics of Electricity 2 Using a Digital Multimeter 4 IDEAL Digital Multimeters An Introduction The Basics of Digital Multimeters is designed to give you a fundamental knowledge of
INSTALLATION GUIDE AND OWNER S MANUAL
INSTALLATION GUIDE AND OWNER S MANUAL SINGLE POINT, FLOW CONTROLLED and THERMOSTATIC ELECTRIC INSTANTANEOUS WATER HEATERS BEFORE ATTEMPTING ANY INSTALLATION, MODIFICATION OR SERVICE OF THIS HEATER, MAKE
TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT
TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT 1.1 General 1.1.1 These Special Conditions of Contract supplement the General Instructions.
Heating, Ventilation, Air Conditioning and Refrigeration (HVACR)
Heating, Ventilation, Air Conditioning and Refrigeration (HVACR) I. Demonstrate safety skills in typical HVACR work situations to NATE Core Installer Knowledge Areas for Technician Excellence for Safety
MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING
Training Title MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING Training Duration 5 days Training Date MV, HV and EHV Switchgear Testing & Commissioning 5 20 24 Apr $3,750 Dubai, UAE In any of the 5 star
Electrical Fundamentals Module 3: Parallel Circuits
Electrical Fundamentals Module 3: Parallel Circuits PREPARED BY IAT Curriculum Unit August 2008 Institute of Applied Technology, 2008 ATE310- Electrical Fundamentals 2 Module 3 Parallel Circuits Module
GLOLAB Two Wire Stepper Motor Positioner
Introduction A simple and inexpensive way to remotely rotate a display or object is with a positioner that uses a stepper motor to rotate it. The motor is driven by a circuit mounted near the motor and
ELECTRIC INSTANTANEOUS WATER HEATER
ELECTRIC INSTANTANEOUS WATER HEATER EPS - 3,5 EPS - 4,4 EPS - 5,5R Please, read and follow the installation and operating instructions carefully, to ensure the long life and reliable operation of this
Electrical safety for entertainers
Electrical safety for entertainers Electrical safety for entertainers If you are an entertainer who uses electrical equipment for sound, lighting or other effects, this leaflet is for you. It sets out
I. R. D. T INSTITUTE OF RESEARCH DEVELOPMENT AND TRAINING
I. R. D. T INSTITUTE OF RESEARCH DEVELOPMENT AND TRAINING SYLLABUS SIX MONTHS FULL TIME Repair and Maintenance of Electrical gadgets EFFECTIVE FROM:- UNDER DEVELOPMENT Prepared By: Curriculum Development
Essential Electrical Concepts
Essential Electrical Concepts Introduction Modern vehicles incorporate many electrical and electronic components and systems: Audio Lights Navigation Engine control Transmission control Braking and traction
SERVICE SERVICE MANUAL FOR ALDE ELECTRICAL HEATER
SERVIE SERVIE MNUL FOR LDE ELETRIL HETER 2737 2762 2763 ontents Page hap Title 3 1:0 Flow chart 4 2:0 bout the electrical heater 4 2:1 Technical data 4 3:0 General faultfinding 4 4:0 Faultfinding 4 4:1
Listed are common requirements that apply to existing solar installations when altered, added to or reconfigured.
SOLAR ALTERATIONS REQUIREMENTS August 2015 These requirements address typical alterations to solar installations; they cannot address every scenario. In Victoria, an alteration to a solar installation