The chemical process industries (CPI) have made

Similar documents
Heat Recovery and Compressed Air Systems

Energy Efficiency in Steam Systems

APPLIED THERMODYNAMICS TUTORIAL 1 REVISION OF ISENTROPIC EFFICIENCY ADVANCED STEAM CYCLES

Steam Generation Efficiency Module Blowdown Losses Section

Overview of Heat Recovery Boiler Systems and Operating Costs Factors Effecting Blowdown Blowdown Heat Recovery The Energy Tank

Thermal Coupling Of Cooling and Heating Systems

Printing and Publishing Energy Savings Guide

SECTION 5 COMMERCIAL REFRIGERATION UNIT 22 CONDENSERS

How To Power A Power Plant With Waste Heat

Water Efficiency. Water Management Options. Boilers. for Commercial, Industrial and Institutional Facilities. Boiler Water Impurities

Example Retrocommissioning Measure: Opening Throttled Discharge Valves

Torino Nord. Cogeneration Plant. The gas turbine. The steam generator. The Torino Nord cogeneration plant produces electricity and heat for district

Heat Integration Complicates Heat Pump Troubleshooting

PERFORMANCE EVALUATION OF NGCC AND COAL-FIRED STEAM POWER PLANTS WITH INTEGRATED CCS AND ORC SYSTEMS

Commissioning - Construction Documents (Page 1 of 6)

FLASH TANK ECONOMIZER PRODUCT GUIDE

Increasing Natural Gas Boiler Efficiency by Capturing Waste Energy from Flue Gas

COGENERATION. This section briefly describes the main features of the cogeneration system or a Combined Heat & Power (CHP) system. 36 Units.

steam centre of excellence Steam Boiler System Optimization

HEAT RECOVERY FROM CHILLED WATER SYSTEMS. Applications for Heat Reclaim Chillers

Modelling and Simulation of the Freezing Systems and Heat Pumps Using Unisim Design

V. ENERGY SAVINGS IN INDUSTRY

System Assessment Capabilities for Fossil Fuel Power Stations

Saving Boiler Fuel. Figure 1: Boiler System Operation Costs

The. Brendan P. Sheehan, Honeywell Process Solutions, USA, and Xin Zhu, UOP, a Honeywell Company, USA, explore energy optimisation in plant processes.

ALUMINUM. BestPractices Assessment Case Study. Alcoa North American Extrusions Implements Energy Use Assessments at Multiple Facilities.

C. starting positive displacement pumps with the discharge valve closed.

How To Calculate The True Cost of Steam

Introduction to Process Engineering Economics. based on size of major equipment items allow to decide whether to invest in a detailed study

Boiler Blowdown. Boiler Blowdown Benefits. Best Operating Practices for Boiler Blowdown

Heat Recovery from Compressed Air Systems. kaeser.com

Ambient Temperature Operation and Matching MAN B&W Two-stroke Engines

Steam System Best Practices Condensate System Piping

Energy Conservation Opportunities in Carbonated Soft Drink Canning/Bottling Facilities. Ahmad R. Ganji, Ph.D., P.E. + Bryan Hackett and Sandra Chow

Why and How we Use Capacity Control

Improved Modern Control Station for High Pressure Bypass System in Thermal Power Plant

GAS HEATING IN COMMERCIAL PREMISES

HIGH-EFFICIENCY CO 2 HEAT PUMP WATER HEATER SYSTEMS FOR RESIDENTIAL AND NON-RESIDENTIAL BUILDINGS

CHAPTER 7 THE SECOND LAW OF THERMODYNAMICS. Blank

Introduction. Motor Types

ECONOMICAL OPTIONS FOR RECOVERING NGL / LPG AT LNG RECEIVING TERMINALS

BOILER EFFICIENCY F7 Energy eco-efficiency opportunities in Queensland Foundries

DESIGN CHALLENGES AND OPERATIONAL EXPERIENCE OF A MEGA MED SEAWATER DESALINATION PLANT IN TIANJIN

Energy Saving Ideas for Your Box Plant

DEGASSED CATION CONDUCTIVITY MEASUREMENT

Balance of Fuel Cell Power Plant (BOP)

Natural Gas Energy Efficiency Opportunities for Commercial & Industrial Customers. Michael Pace Lead Engineer C & I Efficiency Programs

Process retrofitting. Davide Manca. Lesson 5 of Process Systems Engineering Master Degree in Chemical Engineering Politecnico di Milano

A CASE STUDY: PERFORMANCE AND ACCEPTANCE TEST OF A POWER AND DESALINATION PLANT. Keywords : Power Plant, Boiler Capacity, Electrical Power

Evaluation Of Hybrid Air- Cooled Flash/Binary Power Cycle

10 Strategic Steps to Reducing Your Energy Costs AEE Regional Chapter Meeting February 2, 2005

Boiler Efficiency. Charles Stark Department of Poultry Science.

Siemens Steam Turbine SST-600

Heating Water by Direct Steam Injection

OPTIMIZING CONDENSER WATER FLOW RATES. W. A. Liegois, P.E. Stanley Consultants, Inc. Muscatine, Iowa

Efficiency on a large scale CFB Steam Boilers

5.2. Vaporizers - Types and Usage

AM Cost Effective Solutions for Reduction of Benzene in Gasoline

CCS in the Oil refining Industry System Solutions and Assessment of Capture Potential

BIOPOWER 5 CEX. 1 Wärtsilä 10 January 2012 Presentation name / Author

Turbo Tech 101 ( Basic )

Desuperheater Online Program Sizing Guidance

How To Make A High Co 2 Gas Blend

How does solar air conditioning work?

Steam System Efficiency. Bill Lumsden Leidos Engineering

IEA Workshop Copenhagen Small scale biomass co-generation with modern steam engines

8. Refrigeration. 4. Liquid. Refrigerant. 4. Liquid Refrigerant. Figure 8.1 Refrigeration system layout (single stage)

20,000 Barrel Per Day Crude Oil Refinery

PLANT LOCATION AND LAYOUT

ARP Food Industry, Portugal

INSTALLATION INSTRUCTIONS HOT GAS BYPASS SYSTEM DESIGN MANUAL

AIR CONDITIONING TECHNOLOGY

VACUUM REFRIGERATION SYSTEMS

Condensing Economizers Workshop Enbridge Gas, Toronto. MENEX Boiler Plant Heat Recovery Technologies. Prepared by: Jozo Martinovic, M A Sc, P Eng

Drying of Woody Biomass. Process Engineering / GEA Barr-Rosin

BOILER FEED AND CONDENSATE RECOVERY SYSTEMS Extend the life and efficiency of your boiler system

Operational Flexibility Enhancements of Combined Cycle Power Plants. Dr. Norbert Henkel, Erich Schmid and Edwin Gobrecht

Drives and motors. A guide to using variable-speed drives and motors in retail environments

Forgotten savings: Heat recovery from surface blowdown

Top Technology for Industry, Agriculture, Business and Communities

Centrifugal Fans and Pumps are sized to meet the maximum

GreEnergy. Power Plants. ELECTRICAL POWER from CEMENT PLANT WASTE HEAT. for the Cement Industry

Boiler Preparation, Start-Up and Shutdown

LEAN LNG PLANTS HEAVY ENDS REMOVAL AND OPTIMUM RECOVERY OF LIGHT HYDROCARBONS FOR REFRIGERANT MAKE-UP

MAINTENANCE INSTRUCTIONS. Thermia Robust heat pump

Heat Recovery In Retail Refrigeration

Fault codes DM1. Industrial engines DC09, DC13, DC16. Marine engines DI09, DI13, DI16 INSTALLATION MANUAL. 03:10 Issue 5.0 en-gb 1

I. STEAM GENERATION, BOILER TYPES

Research on the Air Conditioning Water Heater System

Overview. Introduction Cooling Tower Basics Principles of Operation Types of Cooling Towers Common Applications Design Considerations

Petroleum Refinery Hydrogen Production Unit: Exergy and Production Cost Evaluation

Design Guide. Retrofitting Options For HVAC Systems In Live Performance Venues

Thermodynamics - Example Problems Problems and Solutions

SULFUR RECOVERY UNIT. Thermal Oxidizer

HEAT RECOVERY OPTIONS FOR DRYERS AND OXIDIZERS

Open Cycle Refrigeration System

Efficiency of Hydrogen Liquefaction Plants

Air-sourced 90 Hot Water Supplying Heat Pump "HEM-90A"

Integrated Performance and Condition Monitoring at DuPont

GE Oil & Gas. Air Cooled Heat Exchangers. Robust and reliable for all loads and applications

Transcription:

A CEP Preprint 2012 AIChE Easy Ways to Improve Energy Efficiency Alan P. Rossiter Rossiter & Associates Veerasamy Venkatesan VGA Engineering Consultants Managing the energy consumption of a process does not need to be complicated. Here are some examples of less-complicated strategies. The chemical process industries (CPI) have made great strides toward energy efficiency. New, highyield catalysts, equipment advances, improvements to process design procedures, process control and real-time optimization, energy-focused maintenance programs, and changes in corporate policies have contributed to this progress. In addition to these sophisticated strategies, simple, often-overlooked changes and activities can yield dramatic gains in energy efficiency. This article presents several effective and relatively easy changes that operators and process engineers can implement to minimize energy consumption, and provides guidance on how to avoid some of the common pitfalls. Unnecessary cooling of process streams A common inefficiency in a chemical plant or refinery is the cooling of process streams that should not be cooled. A petrochemical facility installed an air cooler on the feed line of a distillation column (Figure 1) to prevent the condenser from being overloaded during certain abnormal operating conditions (1). Although the air cooler was designed for use only during abnormal conditions, it ran continuously during normal operations. Removing heat from the feed during normal conditions required the reboiler to work harder, thereby increasing the boiler s heat load. Changing operating procedures to reflect the original intent of the air cooler shutting off the air cooler fan dur- Before Mofications After Modifications Air Cooler Top Air Cooler Top Reboiler Reboiler Bottom Bottom p Figure 1. A distillation column was designed with an air cooler on the feed line. Although the cooler was designed for use only during abnormal conditions, it was run continuously, resulting in an increased reboiler heat load. Shutting off the air cooler during normal operations did not completely solve the problem, as a significant amount of heat was wasted due to convection in the cooler. A simple fix: Install a bypass line around the air cooler (green). 16 www.aiche.org/cep December 2012 CEP

ing normal operations reduced the reboiler duty by more than 30% and saved the plant more than $1 million/yr, at no cost to the facility. Turning the air cooler off during normal operations was a good first step. However, a significant amount of heat was still being wasted due to convection in the air cooler. This loss was eliminated by installing a bypass around the air cooler (Figure 1, green) a small project that saved an additional $200,000/yr. This example illustrates the importance of understanding the purpose of all the equipment in a process. Operators often place equipment in service inappropriately, and once these inappropriate operating norms have been established, they sometimes stay in place for years. Good operating procedures combined with training, including frequent refresher courses or continuing education, can go a long way toward minimizing this type of equipment misuse. Pump power In a plastics facility (2), a large high-pressure feed pump with a fixed-speed electric drive was operated with spillback control (Figure 2). In this arrangement, the pump operated at constant flow and delivery pressure, and adjustments to the opening of the spillback valve accommodated changes in the process demand. A cooler was incorporated in the spillback line to avoid overheating. Although the spillback control system provided operational stability and protected the pump from shut-in (a condition that could cause damage to the equipment), it did so at the expense of significant energy inefficiency. During normal operation, the pump ran at high throughput and relatively low head, with a large recycle flow, and thus high power requirements (Figure 3). Many options are available to reduce pump power requirements. These include the use of variable-speed drives or high-efficiency pumps and motors, trimming or replacing impellers, and adding a smaller pump for use during periods of low throughput. For various reasons, these options were not viable for the plastics facility in this example. However, throttle control i.e., the addition of a throttle valve in the line feeding the user of the pumped fluid offers a simple alternative (Figure 2, green). When a throttle valve is used for flow control with a fixed-speed pump, the flow through the pump is equal to the amount of feed required by the process user. This is significantly lower than the pump flowrate with spillback control. Throttling also introduces a backpressure on the pump, and this, together with the reduced flowrate, moves the operating point on the pump curve up and to the left, which corresponds to a reduced power requirement (Figure 3). It is important to keep the spillback valve in the system because of its ability to prevent the pump from being shut-in; the spillback valve opens if the process feed requirement falls below a predetermined minimum allowable flowrate. Installing throttle control in this system reduced the pump power by about 10%, which resulted in savings of about $150,000/yr. The only expenditures required were for the throttle valve and associated equipment, and reprogramming of the control system. This example highlights a common tendency of engineers and operators to accept the design of their control systems as long as the equipment functions reliably and safely. Safety and reliability are, of course, top priorities. However, many control systems are designed without regard to the energy losses they create. It is well worth reassessing these systems and questioning the losses. Maintenance tracking and communication While working in a refinery, one of the authors (Rossiter) noticed that a heat exchanger was out of service which was not unusual, as heat exchangers often require maintenance. However, the records showed that this particular heat exchanger had been idle for more than three months after Pump FIC Head Power CW Supply Throttle Valve CW Return Spillback Valve p Figure 2. A high-pressure feed pump in a plastics facility was operated with spillback control. This arrangement provides for operational stability, but at the expense of energy inefficiency. A throttle valve was added (green) to the high-pressure feed pump system to allow the pump to operate during normal conditions at a lower flowrate and thus lower power requirement. Operating with Throttle Flowrate Operating without Throttle p Figure 3. The pump curve for the pump shown in Figure 2 compares the operating point with and without throttle control. CEP December 2012 www.aiche.org/cep 17

being taken out of service for cleaning. The work had been completed within a few weeks, at which point the maintenance supervisor notified the shift supervisor that the heat exchanger was ready for use. But plant personnel were occupied with other activities, so the heat exchanger could not be put back into service at that time. The shift supervisor failed to pass the information on to the next shift, and no follow-up action was taken until the idle equipment was pointed out. Once the unit manager was informed of the situation, the heat exchanger was placed back in service within hours. The energy loss incurred during the 2.5 months that the heat exchanger had been left idle was worth over $100,000 (1). Management of heat-exchanger cleaning programs has become increasingly sophisticated, with both improved cleaning techniques and better tools for assessing appropriate cleaning intervals for the heat exchangers in the circuit. However, the best cleaning methods and the most elegant optimization of cleaning intervals are of little use when communication fails. In this example, better systems were needed for tracking the status of maintenance jobs on the unit. A simple electronic reminder system, for example, could have alerted the operators of the need to bring the heat exchanger back online. Optimizing steam systems Steam systems including boilers, steam distribution lines, and power generation with steam turbines present significant opportunities for improving energy efficiency. The final two examples illustrate this point. Returned Condensate Deaerator 60 65 F Softened Makeup Water for Deaerator Compressed Air to Process Cooler Third Stage Air Compressor Second Stage Preheating deaerator feedwater. Steam systems used for process heating in oil refineries and chemical plants commonly employ thermal deaerators to drive off oxygen and other dissolved gases from boiler feedwater. In principle, only a small amount of steam is needed to do this. However, the temperature of the incoming water is often much lower than the saturation temperature in the deaerator, so a substantial amount of additional steam is used to preheat the water. Preheating the feedwater to a deaerator can consume 10%, or even 15%, of the total steam generated on a site. For this reason, strategies are often developed to preheat deaerator feedwater with recovered waste process heat. In this example, the deaerator in a chemical plant processed a combination of warm returned condensate and softened makeup water that is available only at ambient temperature. Within the boiler house there were also several water-cooled air compressors (Figure 4), one of which was experiencing chronic maintenance problems in its cooling tower. During a project to replace this cooling tower, one of the authors (Venkatesan) noticed that the average quantity of softened makeup water (at ambient temperature) going to the deaerator () was almost identical to the amount of cooling water needed for the air compressor (120 gpm). Based on this observation, a new project was proposed to route the makeup water through the air compressor and isolate the cooling tower with blinds (Figure 5). The new proposal was evaluated and accepted, and the piping modifications were completed within two months. Heat from the air compressor is now recovered by preheating the softened water, saving $80,000/yr in deaerator Air Inlet First Stage Cooler Cooler Cooler Cooling Tower p Figure 4. A deaerator in a chemical plant processes a combination of warm returned condensate and softened makeup water at ambient temperature. Extra steam is consumed in this configuration to heat the softened makeup water. Coincidentally, the average quantity of softened makeup water going to the deaerator was almost identical to the amount of cooling water needed for one of the air compressors within the boiler house. steam usage. Implementation was very inexpensive, as it required only local piping changes. In addition, the project eliminated the need to maintain or replace the cooling tower, thus significantly reducing costs. This example illustrates the benefits of preheating deaerator feedwater. Perhaps even more importantly, it shows how a single project can achieve multiple objectives in this case, save energy and eliminate a chronic maintenance problem. It also illustrates the importance of looking for creative ways to redeploy 18 www.aiche.org/cep December 2012 CEP

Compressed Air to Process Air Inlet Air Compressor Deaerator Returned Condensate Preheated Makeup Water 85 90 F Cooler Third Stage Second Stage First Stage Cooler Cooler Cooler Softened Makeup Water for Deaerator 60 65 F Cooling Tower turbine, was used to let down high-pressure (HP), 930-psig steam to medium-pressure (MP), 290-psig steam. The second turbine, an extraction-condensing turbine, received MP steam, which was extracted as low-pressure (LP), 73-psig steam (in the extraction section) for process use, and the remaining MP steam was expanded into a vacuum condenser (Figure 6). In the original design, only the exhaust steam from the backpressure turbine was used to supply MP steam to the extraction-condensing turbine. Because the temperature of the outlet steam from the backpressure turbine was higher than 660 F (the maximum allowable steam inlet temperap Figure 5. To eliminate some of the extra steam required to heat the softened makeup water for the deaerator shown in Figure 4, the makeup water was rerouted (green) through the air compressor, which heats the water from 60 65 F to 85 90 F. existing equipment in situ to save energy. Of course, it is always essential to check equipment limitations and follow appropriate management-of-change procedures when making process modifications. In addition, when implementing steam-saving projects, one should consider the overall fuel and steam balances of the plant, and not focus purely on improving the efficiency of individual equipment (3). Adding excessive safety margins to steam consumption. In a commodity chemical plant in Europe, two steam turbines drove a large air compressor and an electric generator in a single-shaft arrangement. The first turbine, a backpressure Steam 930 psig 932 F Generator Extraction- Condensing Process Gas Compressor Backpressure 574 F Boiler water Cold Water 63 F Vacuum Cold Water 81 F 73 psig 550 F 600 F To Users Desuperheater Steam from Waste-Heat Boiler p Figure 6. At a commodity chemicals plant in Europe, two steam turbines (a backpressure turbine and an extraction-condensing turbine) drove a large air compressor and an electric generator. A desuperheater reduced the temperature of the MP backpressure steam before it entered the extraction-condensing turbine together with steam from a waste-heat boiler. CEP December 2012 www.aiche.org/cep 19

Steam 930 psig 932 F Generator Extraction- Condensing Process Gas Compressor Backpressure 622 F Boiler water Cold Water 63 F Vacuum Cold Water 81 F 73 psig 550 F To Users Desuperheater Steam from Waste-Heat Boiler p Figure 7. A study showed that the desuperheater in Figure 6 was unnecessary. A bypass line (green) was installed around the desuperheater and the desuperheating water was shut off, increasing power production by 500 kw. ture specified for the extraction-condensing turbine), before entering the turbine, the MP steam went through a desuperheater to reduce its temperature. The desuperheater was designed to produce MP steam at 600 F providing for a 60 F safety margin. (Note that the amount of work extracted from a steam turbine decreases as the inlet temperature goes down, so adding the desuperheater reduced the amount of work generated by the extraction-condensing turbine.) Literature Cited 1. Rossiter, A. P., Back to the Basics, Hydrocarbon Engineering, 12 (9), pp. 69 73 (Sept. 2007). 2. Rossiter, A. P., Simple Opportunities for Improving Energy Efficiency, AIChE Spring Meeting and 8th Global Congress on Process Safety, Houston, TX, Paper No. 119a (April 4, 2012). 3. Tanthapanichakoon, W., Saving Energy in Multilevel Steam Systems, Chem. Eng. Progress, 108 (1), pp. 27 32 (Jan. 2012). Alan P. Rossiter, P.E., PhD, is president of Rossiter & Associates, a consulting company based in Bellaire, TX (Email: alan@rossiters.org; Website: www.rossiters.org/associates) that provides consulting services on energy efficiency for the oil refining and chemical industries. He received his BA, MEng, and PhD, all in chemical engineering, from the Univ. of Cambridge, and he has more than 30 years of experience in process engineering and management. He is a chartered engineer in the U.K., and a registered professional engineer in the state of Texas. He is a past chair of the South Texas Section of AIChE. Ven Venkatesan, an energy expert, heads the consulting firm VGA Engineering Consultants (Email: venkatesan@vgaec.com; Phone: (407) 399-9316). With over 33 years of experience in the energy management field, he has conducted energy audits for more than 120 energyintensive process facilities around the world, and he has been involved in the U.S. Dept. of Energy s Save Energy Now program as a steam and process heating systems specialist. He also conducts international training programs for engineers through the United Nations Industrial Organization (UNIDO). He received his BS and MS, both in chemical engineering, from the Univ. of Madras, India. The original design was later modified to add steam from a waste-heat boiler to the steam from the backpressure turbine outlet, which increased the steam flow to the extraction-condensing turbine and thus raised its power output. The temperature of the steam from the waste-heat boiler was 550 F significantly cooler than the exhaust steam from the backpressure turbine. When the designers made this modification, they did not re-evaluate the use of the desuperheater. A subsequent study of this system by one of the authors (Venkatesan) found that the maximum temperature that can be reached with the combined steam flow to the extractioncondensing turbine is below 660 F, and desuperheating of the backpressure turbine exhaust steam can be safely eliminated. Based on this finding, a bypass line was installed around the desuperheater, and the water supply to the desuperheater was shut off (Figure 7, green). This change increased the amount of electricity generated by the turbine by 500 kw, resulting in an annual energy cost saving of $400,000. This example illustrates the need to challenge existing operating practices, and also to re-evaluate conditions when process changes are made. While it is always essential to operate within design limits, excessively large margins of safety can result in unnecessary losses of energy efficiency. Final thoughts No matter how sophisticated our energy management strategies become, it is imperative that we continue to pay attention to basic principles. We must understand the purpose and limitations of the equipment in our processes. And when changes are made to our facilities, we must consider their impact on all processes. Key principles of human interactions especially communication are also essential to all of our activities. CEP 20 www.aiche.org/cep December 2012 CEP