Stone Way N Rechannelization: Before and After Study. N 34th Street to N 50th Street



Similar documents
BICYCLE TRENDS IN CAMBRIDGE

Protected Bicycle Lanes in NYC

Pedestrian and Bicycle Crash Data Analysis:

Accident Analysis of Sheridan Road between Isabella Street and South Boulevard

TEST ON Driving Safely Among Bicyclists and Pedestrians

EPA Technical Assistance for Sustainable Communities Building Blocks


Near Westside Neighborhood and University Avenue Corridor Transportation Study. Public Workshop #2. September 12 and 23, 2013

Why Do We Bike? And where, how, who, when, and with what

Measuring the Street:

Crash Report Calendar Years 2003 through 2006 August 2007

Road Safety Authority Provisional Review of Road Crashes 2013

Route Development Plan

Doing a little can accomplish a lot. Proposed Change of Municipal Class Environmental Assessment from Schedule from B to A+

RESOLUTION NO

For more information, visit: rethinkingstreets.com

Safety Evidence for Bicycling

SAN DIEGO - A BICYCLE FRIENDLY CITY

SAFE Streets for CHICAGO

Needs Analysis. Long Beach Bicycle Master Plan. Bicycle Commuter Needs. LONG BEACH BICYCLE MASTER PLAN Needs Analysis

ELMHURST SPEEDWAY A STUDY OF LAWBREAKING IN ELMHURST

Transportation Management Plan Template

Deaths/injuries in motor vehicle crashes per million hours spent travelling, July 2008 June 2012 (All ages) Mode of travel

Associati. The Annex Residents Association. The Annex Residents Association Cycling Policy Adopted by the Board, January 13, 2011.

New Jersey SRTS Travel Plan Guide

Children and road safety: a guide for parents

N Street Protected Bikeway

the Ministry of Transport is attributed as the source of the material

Speeding. Probability of death at different impact speeds

North Avenue Corridor Study. Advisory Committee Meeting #5 June 11, 2014

Appendix J Santa Monica Travel Demand Forecasting Model Trip Generation Rates

Child Road Safety Audit for South Gloucestershire

HOW WILL PROGRESS BE MONITORED? POLICY AREA. 1. Implement the 2040 Growth Concept and local adopted land use and transportation plans

30 Years of Smart Growth

Advantages and Disadvantages of One Way Streets October 30, 2007

RULES OF THE ROAD BY LWTL Staff Writer

Performance Measures for RIDOT s Traffic Management Center

The Seattle Department of Transportation 2011 TRAFFIC REPORT

Lincoln Downtown Master Plan Update

Addendum to the Arterial Transitway Corridors Study

PEDESTRIAN AND BICYCLE ACCIDENT DATA. Irene Isaksson-Hellman If Insurance Company P&C Ltd.

In 2005, the City of Pasadena, CA, USA, with the support of consultants,

A Bicycle Accident Study Using GIS Mapping and Analysis

ENGINEERING SOLUTIONS FOR DESIGNING YOUR SAFE ROUTES

TERMINAL 91 TRAFFIC MONITORING STUDY

Route Optimisation / Traffic Signals Efficiency

STAFFORDSHIRE COUNTY COUNCIL ROAD CASUALTY REVIEW

Effect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain

Evaluation of the Shared-Use Arrow

Executive Summary. Transportation Needs CHAPTER. Existing Conditions

Traffic Impact Study for the North Broadway Mixed-Use Development Chicago, Illinois. Prepared by

How To Know If A Motorcyclist Is Safe

Comprehensive Plan Policies that support Infill and Mixed Use

Florida Avenue Multimodal Transportation Study. June 19, 2013

Where Do We Want to Go? How Can We Get There?

CAPACITY AND LEVEL-OF-SERVICE CONCEPTS

Bicycle Safety Webinar December 1 st 2010

BEST PRACTICES. Smart Transportation is a key concept for the Paoli Roadway Improvement Project.

Nearly 38,000 vehicles cross the Shinnecock Canal on Sunrise Highway (NYS Route 27) daily, during peak summer months.

CHAPTER 5-CMPO TRANSPORTATION VISION PLANS (2035 & BEYOND)

Chapter 5. Transportation. Decatur County Comprehensive Plan. Introduction. Goals and Objectives. Goal. Objectives. Goal.

Narrative Response/Attachment 1 (WisDOT TAP- Second Round Application ID-SWBP22)

Goals & Objectives. Chapter 9. Transportation

Lawson Outline Plan External Traffic Analysis Working Paper

Corridor Goals and Objectives

REGIONAL NON-MOTORIZED TRANSPORTATION NETWORK

Is Encouraging More Bike Ridership On El Camino Real A Good Idea?

How To Understand The Safety Of A Motorcycle

COURTING YOUR BICYCLE AND PEDESTRIAN FACILITIES... FROM A FORENSIC ENGINEERING AND PLANNING PERSPECTIVE

Smart Cycling IN SANTA MONICA SANTA MONICA POLICE DEPARTMENT BE SMART. BE VISIBLE. BE ATTENTIVE. HAVE FUN!

the Ministry of Transport is attributed as the source of the material

3 Tappan Zee Bridge Rehabilitation Options

Pedestrian and Bicycle Crash Types

a U.S. Department of Transportation National Highway Traffic Safety Administration Computer Accident Typing for Bicyclist Accidents Coder's Handbook

Light Rail Transit in Phoenix

CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR

(Version 1.0 August 2014) Cover Letter. (See Paragraph 9 of Section 1A.10)

Chapter 1: Background

6: LANE POSITIONS, TURNING, & PASSING

Bicycle riding is a great way to get into shape

11 p.m. to. Tuesday, June. will remain open. 14. closed

FMCSA Webinar Nov.18th to Examine Large Truck Crash Fatalities Involving Pedestrians & Bicyclists. New Technology for Better Fleet Management

VISION, DESIGN PRINCIPLES & OVERALL PLANNING STRATEGY

Road Traffic Accidents in Japan. October 25, 2012

- FREE! - The Official San Francisco BIKE GUIDE. 1st Edition

Bicycle Laws in North Carolina and the U.S.

Transcription:

City of Seattle Department of Transportation Stone Way N Rechannelization: Before and After Study N 34th Street to N 50th Street May, 2010

INTRODUCTION Population density in Seattle is increasing within a fully built urban environment. Widening roadways to accommodate additional motor vehicles is frequently not an option within such a built environment. To improve safety and mobility, Seattle will increasingly rely on transportation modes such as bicycling, walking and transit. In order to complete the city s bicycle and pedestrian network, motor vehicle lanes must often be removed to create space for bicycle and pedestrian facilities (often referred to as a road diet ). As of April, 2010 Seattle has implemented 24 lane reduction rechannelizations. The first such rechannelizations were implemented in 1972 on California Ave SW and N 45 th St. Studies have indicated that lane reductions can result in lower motor vehicle speed, improved pedestrian safety, increased bicycling trips and fewer collisions while maintaining through capacity of the corridor. Implementation of the Bicycle Master Plan, adopted in 2007 and the Pedestrian Master Plan, adopted in 2009, is likely to include similar lane reduction projects in the future. To ensure that these projects result in the expected benefits, the effects of such projects on all road users must be considered and sufficiently studied after implementation. This case study focuses on Seattle s experience with Stone Way N from N 34 th Street to N 50 th Street a distance of approximately 1.2 miles (Figure 1). The Stone Way rechannelization was the 23 rd Figure 1 such lane reduction project undertaken by the city since 1972. Stone Way is a north south roadway that carries approximately 13,000 vehicles per day. The roadway connects the Fremont and Wallingford urban villages. Numerous Metro bus routes run along or across the corridor. Adjacent land use is mixed use residential, retail and commercial. Within five blocks of the corridor there are numerous pedestrian generators, including eight schools, two public Stone Way Before and After Study Page 1

libraries, and five parks. Adjacent zoning is primarily Commercial or Neighborhood Commercial. At the south end is the Burke Gilman Trail and Gas Works Park. At the north end is Woodland Park, the Woodland Park Zoo and Green Lake. STUDY BACKGROUND In July, 2007 Stone Way N was repaved from N 34 th St to N 45 th St. Prior to the paving project, the street consisted of 4 general purpose travel lanes. Uncontrolled marked crosswalks existed at N 38, N 41, N 47 and N 48 St. There were no bike facilities on the street. (Figure 2) Before Rechannelization, looking south from 35th St After Rechannelization, looking south from 35th St Figure 2 The following factors contributed to the decision to rechannelize: The guidelines for uncontrolled marked crosswalks changed in 2004. As a result, the uncontrolled marked crosswalks along this corridor did not meet current guidelines and would have to be removed. The Bicycle Master Plan adopted in 2007, specified bicycle facilities on the corridor. The paving project provided a leveraging opportunity to make changes. After the paving project was complete, the roadway was rechannelized in two phases: In August, 2007 the street was striped from N 40 th St to N 50 th St to provide 2 general travel lanes, a two way left turn lane and bike facilities (combination of bike lanes and sharrows). Marked crosswalks were retained at N 41, N 47 and N 48 St. The marked crosswalk at N 38 th St no longer met our guidelines and was removed. In April, 2008, the street was rechannelized between N 34 th St and N 40 th St. The marked crosswalk at N 38 th St was restored. This study compares data from the following time periods: Before period includes April 5, 2005 through August 6, 2007 when the roadway was four general purpose lanes. Stone Way Before and After Study Page 2

After period includes August 7, 2007 to December 4, 2009, which reflects both the interim channelization and the final channelization. SPEED The speed limit on this street is 30 miles per hour. There is a gradual grade uphill in the northbound direction. Speed data was collected at N 38 th and N 42 nd Streets. Speeds declined at both locations after channelization changes were complete. Before data was collected prior to repaving in June, 2007. After data was collected in June, 2008 and again in October, Figure 3 2008 after channelization changes were complete. Speed studies in October, 2008 reveal a stabilization in motor vehicle speeds. 85 th percentile speed is the speed at or below which 85% of motor 4.0% Motorists Driving 40mph+ at N 38th vehicles are traveling. This is 3.5% 3.6% commonly used to set and 3.0% 3.5% 3.1% 3.1% measure compliance with speed 2.5% 3.0% 3.0% limits. Prior to rechannelization, 2.0% 85 th percentile speed was 1.5% 1.0% 1.0% approximately 37 mph. After 1.0% 0.8% 0.8% 0.6% 0.6% rechannelization, 85 th percentile 0.5% speeds dropped approximately one 0.0% mile per hour northbound and Wednesday Thursday Friday Saturday Sunday Monday three miles per hour southbound 2008 2007 (Figure 3). Actual traffic speed is nearer to the posted speed limit as Figure 4 a result of the rechannelization. With one lane of traffic, a lead vehicle traveling at the speed limit can set the pace for traffic. More dramatically, the number of motor vehicles exceeding the speed limit by 10 miles per hour or more dropped approximately 75%. When the road was four lanes wide, approximately 4% of motor vehicles (150 vehicles per day) were traveling in excess of 40 miles per hour. After the rechannelization 1% or less (25 vehicles per day) were traveling more than 40 miles per hour. (Figure 4) Lowering vehicle speed is critical to pedestrian safety because both the driver and the pedestrian have more time to react to situations, and the chance of a pedestrian surviving a Stone Way Before and After Study Page 3

crash decreases sharply as a vehicle s speed increases. ( A study in the United Kingdom (Killing Speed and Saving Lives) showed that reduced speed improves pedestrian safety. Research revealed that a pedestrian has an 85% chance of survival if struck by a vehicle traveling at 20 MPH, and only 15% if the vehiclee is traveling at 40 MPH. VOLUME Mode Split Motor vehicle traffic volume decreased Change approximately 6% in the corridor after the Stone Way N at N 42 nd St 2007 10 channelization changes were complete. Meanwhile, bicycle traffic increased 35%. Daily Motor Vehiclee Traffic 6% (Figure 5) Some of the decline in motor vehicle traffic may reflect the state of the Six hour Bicycle Count 35% economy (the recession that began in Figure 5 January 2008) but the concurrent increase in bicycle trips indicates there may also be a mode shift associated with the new channelization. At the morning southbound peak hour, there are 93 bicycles and 658 motor vehicles meaning that bicycles represent almost 15% of the peak traffic volume on Stone Way. Motor Vehicle ADT Citywide, traffic volumes declined on many Seattle arterials between 2006 08. (see http://www.seattle.gov/transportation/tfdmaps.htm) Consistent with this finding, volume on Stone Way declined slightly during the same time period. At N 42 nd Street, motor vehicle volume decreased 6% after rechannelization. (Figure 6) At N 48 th Street, volume decreasedd 15%. (Figure 7) Generally, the decline was greatest in the northern segments of the corridor. Figure 6 Figure 7 Peak Motor Vehicle Volume Peak traffic volume is measured in peak flow as well as AM/PM peak hour volume. The peak flow on Stone Way N is southbound in the morning, northbound in the afternoon as peoplee Stone Way Before and After Study Page 4

generally travel downtown to jobs and back home to the residential areas of north Seattle at night. Peak traffic volumes followed a similar pattern as the average daily volume that is, they decreased slightly. At N 42 nd Street peak flow dropped less than 5% (Figure 8) while offpeak flows actually increased approximately 2%. At N 48 th Street, both peak flow and offpeak flow declined. Peak flow declined 13% while offpeak flow declined approximately 5%. (Figure 9). Peak traffic volume declined at rates similar to those seen in the ADT decline, indicating that the roadway has maintained its ability to accommodate peak traffic volume even after the rechannelization. Peak Volume at 42nd Peak Volume at 48th 750 700 650 600 550 500 450 400 350 PM N Peak AM S Peak PM S Peak AM N Peak 700 650 600 550 500 450 400 350 300 PM N Peak AM S Peak PM S Peak AM N Peak 250 May 07 Sep 07 Jan 08 May 08 Sep 08 Figure 8 Figure 9 Stone Way Before and After Study Page 5

NEIGHBORHOOD TRAFFIC Residents sometimes worry that rechannelization projects will result in traffic diversions onto residential streets. The results on Stone Way N show traffic has not diverted to adjacent streets. In fact, motor vehicle traffic on parallel routes has decreased even more substantially than the slight decline recorded on Stone Way. Midvale Interlake Midvale Ave N @ N 42 nd St May, September, Change 2007 2008 AM Peak 35 25 29% PM Peak 47 44 6% Average Daily (ADT) 389 320 18% Interlake Ave N @ N 42 nd St May, September, Change 2007 2008 AM Peak 45 23 49% PM Peak 44 36 18% Average Daily (ADT) 389 258 34% Figure 10 Figure 11 Stone Way Before and After Study Page 6

Woodland Park Woodlawn Woodland Park Ave N @ N 42 nd St May, September, Change 2007 2008 AM Peak 133 118 11% PM Peak 125 128 2% Average Daily (ADT) 1392 1151 17% Figure 12 Woodlawn Ave N @ N 50 th St May, September, Change 2007 2008 AM Peak 66 84 27% PM Peak 83 78 6% Average Daily (ADT) 811 716 12% Figure 13 Stone Way Before and After Study Page 7

COLLISIONS Figure 14 Collision records from April 5, 2005 through August 6, 2007 were compared with records from August 7, 2007 to December 4, 2009. This roughly compares the 28 months before Phase 1 was implemented to the 28 months after Phase 1 was implemented. During this time period, total collisions declined 14%. Injury collisions declined 33%. Angle collisions declined 56%. Pedestrian collisions declined 80% (from 5 to 1). Left turn collisions declined 25%. Parked car collisions declined 15%. While the number of cyclist collisions did not change (7 in each period), because the number of cyclists using the corridor has increased, the collision rate has declined. In other words, the number of bicycle collisions per bicycle trip has declined. With motor vehicle volume having decreased in the corridor, the trend in collision rates is more difficult to determine. Assuming a 5 10% decline in motor vehicle volume, the collision rate for injury collisions, angle collisions, pedestrian collisions and left turn collisions seems to have declined. COLLISIONS BY TYPE 2005 07 2007 09 Change Right Turn 1 0 100% Pedestrian 5 1 80% Sideswipe 14 6 57% Angle 34 15 56% Left Turn 12 9 25% Parked Car 34 29 15% Head On 1 1 0% Pedalcyclist 7 7 0% Rear End 17 28 65% Total 159 137 14% Injury 52 35 33% Percent Injury 33% 25% Figure 15 Stone Way Before and After Study Page 8

The number of rear end collisions increased, especially between N 39 th St and N 41 st St. This type of collision increased 65% during the study period (from 17 to 28) in spite of the overall reduction in the number of collisions. Since most of the increase was attributable to the section of roadway where there was a transition from 4 lanes to 3 lanes during the interim period between August 2007 and April 2008, one possible explanation is that drivers had difficulty making left turns in this transition area. While these types of collisions tend to be minor in nature, SDOT will again examine the rate of rear end collisions within the next two years to determine if the rate in fact declined after the roadway was rechannelized south of 40 th Street. Stone Way Before and After Study Page 9

CONCLUSIONS 1. Speed has declined. Motor vehicle speed is now closer to the posted speed limit of 30 mph. Top speeders those traveling over 40 mph declined more than 80% while 85 th percentile speed declined approximately 3 mph. 2. Collisions have declined. It s statistically difficult to determine collision trends based on two year comparison periods, but the results are encouraging. Total collisions have declined 14%. More importantly, the most traumatic types (injury and pedestrian) have sustained the steepest declines. The bicycle collision rate is down. Injury collisions are down 33%. 3. Pedestrian crossings are safer. Pedestrian collisions have been reduced 80%. Marked crosswalks are now compliant with federal and city guidelines. 4. Bicycle volume has increased. The volume of cyclists increased 35% from 2007 2010. 5. Motor vehicle traffic has not diverted to neighborhood streets. Daily traffic counts on parallel streets are down by 12 34%. 6. Peak hour capacity has been maintained. Average daily motor vehicle volumes have declined, especially north of N 45th St. Although the decline is consistent with citywide trends in the midst of the recession, the increase in bicycle trips indicates that mode shift is at least part of the explanation for the motor vehicle decline. In some cases south of N 45th St, peak hour motor vehicle volumes increased slightly. This confirms that the corridor has sustained its capacity to carry the same number of motor vehicles in spite of the reduction in the number of general travel lanes. Before Rechannelization, looking north at 3815 Stone Way N After Rechannelization, looking north at 3815 Stone Way N Figure 16 Stone Way Before and After Study Page 10