The Fort Edmonton Footbridge Project

Similar documents
Safe & Sound Bridge Terminology

San Francisco Oakland Bay Bridge East Span Seismic Safety Project

ROTATED-ELLIPSE ARCH PEDESTRIAN BRIDGE FOR THE CALGARY WEST LIGHT RAIL TRANSIT EXTENSION PROJECT

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

Chaudière Crossing Bridge Rehabilitation

Cable-Stayed Bridge Uses New Post-Tensioning System

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

Source: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009.

COMPETENCY ANALYSIS PROFILE. Rodworker 452A. (All unshaded skill sets must be demonstrated/ completed) Lift equipment and materials

Söderströmtunnel: immersion in downtown Stockholm, Sweden

IH-635 MANAGED LANES PROJECT, SEG. 3.2

HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

1.2 Advantages and Types of Prestressing

GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

Strengthening of Large Storage Tank Foundation Walls in an Aggressive Environment by External Post-tensioning. May 7th 2013: Dominique Deschamps

How To Build A Luxury Apartment Complex In London

US 51 Ohio River Bridge Engineering and Environmental Study

Norwegian Public Roads Administration. Photo: Håkon Matre HARDANGER BRIDGE INFORMATION ENGLISH

Cable-Stayed Bridge as an Alternative for Medium and Short Span Bridges

Investigation of the November 2, 2013 collapse of concrete beams at Fort Lauderdale-Hollywood Airport runway project

CITY OF TRAIL MEMORANDUM

METHOD OF STATEMENT FOR STATIC LOADING TEST

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

Scope of EN Clarification Document

Scaffolding. The University of Tennessee Office of Environmental Health & Safety

Residential Deck Safety, Construction, and Repair

DUDERSTADT FOUNDATION & CONSTRUCTION, LLC.

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

Dead load (kentledge) A structure over the test pile. Ground anchorage either by tension piles or ground anchors. Bi-directional (Osterberg-cell)

BRIDGES ARE relatively expensive but often are

Value Engineering vs. Alternate Designs in Bridge Bidding

Chapter 3: Fall Protection/ Scaffolding Safety

High Capacity Helical Piles Limited Access Projects

OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

Technical Assignment 2 TABLE OF CONTENTS

University of Missouri Hospitals and Clinics. Structural Repair and Protection of Post-tensioned Parking Garage

Ross River Suspension Bridge Ross River, Yukon. Life Cycle Cost Analysis

9.3 Two-way Slabs (Part I)

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE

Hunter College school of Social Work Thesis Proposal

Quality Control and Quality Assurance Guide

3M Mobile SkyWalk Series Horizontal Lifeline Product Return Form

Optimum proportions for the design of suspension bridge

WI LEY Blackwell. Multi-storey Precast Concrete Framed Structures. Colin K. Jolly MSc, PhD, CEng, MICE, FIStructE

DESIGNING STRUCTURES IN EXPANSIVE CLAY

Virginia Approach Spans

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

Design of Bridges. Introduction. 3 rd to 4 th July Lecture for SPIN Training at the University of Dar es Salaam

INSTALLING SEISMIC RESTRAINTS FOR MECHANICAL EQUIPMENT

Granger Bay Boulevard and Green Point Roundabout

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

Emergency repair of Bridge B421

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

4B The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.

Certification: Building Plans Examiner. Exam ID: B3

INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE.

Transmission Foundations Case History : Helical piles Hydro One Networks Inc.

High Strain Dynamic Load Testing of Drilled Shafts

Pro-Lift Steel Pile Foundation Repair

Truss. are both simple and A Matsuo Example continuous trusses. The

Hanson Building Products. precast basement solutions

Numerical Analysis of the Moving Formwork Bracket Stress during Construction of a Curved Continuous Box Girder Bridge with Variable Width

BUTE Department of Construction Management and Technology

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR

DESIGN OF PRESTRESSED BARRIER CABLE SYSTEMS

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

Stay Cable Replacement of the Luling Bridge

San Francisco Oakland Bay Bridge SELF-ANCHORED SUSPENSION (SAS) SPAN

Bridge Type Selection

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig some of the trusses that are used in steel bridges

REPAIR AND STRENGTHENING OF HISTORICAL CONCRETE BRIDGE OVER VENTA RIVER IN LATVIA

Robert B. Bittner, P.E., President, Ben C. Gerwick, Inc. San Francisco, CA, USA

How To Build A Road Into A Lake In The North Of The Korean Island Of Hongkoon

The unit costs are based on the trend line of the 3 low bids for the average quantity.

CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE Updated 29 May 2009

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM

WORK SCOPE. Domains in which we work:

Guide to the Jamey Stillings Photographs of the Mike O Callaghan-Pat Tillman Memorial Bridge and the Hoover Dam

Engineers at Liftech designed the structure of the first container crane and have designed and reviewed thousands of container cranes since.

MEMORANDUM West Swann Avenue, Suite 225 Tampa, Florida Phone (813) Fax (813)

L_All_Vocatinal_Ed_Construction. Sector: Construction. Sr. No Specialisation Page No 1 Construction and Building Technology 02.

Since it was established in 1989, with a small manufacturing base in Qwa Qwa and a hire yard in Botswana, Uni-Span

Wisconsin Building Products Evaluation

Buildings Construction Procurement Strategy

SECTION WINDOW WASHING SYSTEMS

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

Beginning on Friday, Jan 22, and on subsequent investigations, the following issues were identified:

Professional Engineers Providing Structural Engineering Services In Buildings

Infrastructure Cost Data

Steel and composite bridges in Germany State of the Art

Dulles Corridor Metrorail Project

U.S. Department of Labor Occupational Safety and Health Administration Directorate of Construction. April 2015

Chapter 3 Pre-Installation, Foundations and Piers

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

Transcription:

The Fort Edmonton Footbridge Project

The Fort Edmonton Footbridge is a signature pedestrian suspension bridge located in SW Edmonton.

The Fort Edmonton Footbridge project provides a river crossing and approach trails that further develop the Edmonton s River Valley. Tender Closing July 9, 2008 Construction Sept 6, 2008 to November 10, 2010 Construction Cost - $ 23 M

Bridge Details The bridge has three spans, including two 54 m side spans and the 138 m main span. Two continuous main cables support the precast concrete deck panels over the length of the bridge. The cables are anchored in abutments at both ends of the bridge, and are clamped into saddles at the tops of two towers.

Project Management Team The City of Edmonton Alberco Ch2MHill

Construction Team Erection Engineering & Construction Engineering Support Dialog Caissons AGRA Foundations Soil Anchors Beck Drilling Cast-in-place Concrete Alberco Reinforcing Steel A & H Rebar Bearings & Tower Saddles LCL Bridge Products Steel Tower Legs WF Welding & Overhead Crane Post Tensioning & Cable Anchorage Dywidag Systems International Steel Cable System Bridon International, UK Precast Panels Lafarge North America

Project Scope of Work Environmental management. River berm installation and removal. Concrete abutments with post-tensioned soil anchor foundations. Concrete/ Steel Towers with concrete belvederes. Suspension cable & support system. Precast deck panels. Post-tensioning Architectural steel components. Trail construction and landscaping. Environmental compensation.

Getting Started

Access Roads & Berm Construction - River berms constructed from both sides of river to access both Tower locations

Environmental Management - Aqua-Barrier water filled dams & floating silt curtains.

Berm footprints were minimized to provide less environmental impact. Berm elevations were approved at the 1:5 year water levels. Rock Rip Rap, concrete topping, and geotextile liner.

Tower Construction

Tower Foundations - Two belled caissons 2.4m diameter. 12.5m deep with 3.6m bell. Temporary steel casings used for water control.

Tower Foundations Caisson Installation

Tower Base - Solider pile & lagging shoring for tower base.

Tower Base Concrete Formwork & Shoring

Tower Columns 1.220m dia. steel pipe with tower head reinforcing cage.

Tower Columns - Survey control during erection using laser targets to achieve installation within 10mm tolerance at tower tops.

Tower Columns A-symmetrical concrete filled steel tower columns. - Horizontal & diagonal struts to control column positions.

Tower Head 53 m3 of cast-in-place post-tensioned concrete elevated 30m from river elevation.

Belvedere Construction Concrete Slab, post-tensioned, 100m3 each, elevated 12m.

Belvedere Construction Steel Shoring System: beams, H-Pile columns, steel scaffolding.

Belvedere Slab Transverse post-tensioning and post-tensioning ducts with anchorage for precast panel system.

Abutment Construction concrete raft slab with post-tensioned soil anchors.

Abutment Construction Soil Anchors, 60 per abutment, 16-22m depth.

Abutment Construction Anchors for suspension cable.

Abutment Construction Abutment chamber - 1.3m raft slab, 1.1m thick walls, 0.3m thick roof slab.

Abutment Construction Concrete Chamber

Abutment Construction Concrete Chamber

Suspension Cable - Socket anchor casting by ESCO foundry.

Suspension Cable Main cable anchors.

Suspension Cable - Tower Saddle radius plate with machined cable groove & matching clamping plate.

Suspension Cable Installation Installation of suspended walkway system to allow for winching cable across the river into position.

Walkway Installation Fall arrest mock drill

Suspension Cable Installation

Walkway for Cable Installation

Cable Spool & Socket - 255m long, 113mm diameter.

Suspension Cable Installation - Winching of Cables on suspended walkways

Suspension Cable Installation Winching of cables across tower head.

Suspension Cable Installation Winching of Cables on suspended walkways

Suspension Cable Installation Winching of Cables on suspended walkways

Suspension Cable Installation Cable clamps and hangers installed for precast panel installation.

Temporary High Line Precast installation using pulleys & tirfors.

Precast Panel Installation Erection sequence & engineering analysis.

Precast Panel Installation Remove walkways & install end spans with conventional cranes.

Precast Panel Installation Install center span panels with trolley system.

Precast Panel Installation Trolley wagon & cable system.

Precast Panel Installation Test lift of precast panels using hydraulic tirfors.

Precast Panel Installation Load panel on trolley cart, winch cart into position, attach hydraulic tirfors to temporary cables, jack panel into position.

Precast Panel Installation Trolley system using highline.

Precast Panel Installation Lower high line and hardware onto precast panels

Precast Panel Installation Install temporary wind bracing and grout panels

Post-Tension Panel System - 108 strands in precast panel curbs. Anchored at abutment & belvederes.

Damper System 4 vibration dampers (2 per abutment) to control deck movements.

Environmental Compensation Installation of 4 rock groynes, downstream of bridge.

Aerial View - panels erected.

Aerial View Berms removed.

Bridge completed!

2 years & 2 months to complete. Approx. 513 work days on site. Approx. 57,881 man hours 55-60 workers during construction peak ( 40 Alberco, 15-20 Sub-trades)

BRIDGE FEATURES Deck elevation looking East. Tower canopy, handrails, LED lighting.

BRIDGE FEATURES River Elevation - Looking East

BRIDGE FEATURES Belvedere seating area with canopy.

BRIDGE FEATURES Belvedere View from river elevation.

BRIDGE FEATURES Tower and deck view from river elevation. Looking West.

BRIDGE FEATURES Night View Bridge LED Lighting.

Project Awards ACI 2011 Awards of Excellence

Questions?