1 Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASE 2 AS OF JULY 31, 2015 SEPTEMBER 2015
2 Phase 2 Cost Summary July Expenditures $ 19.2 Million Total Expenditures $ Million Total Budget $ Billion Total Forecast $ Billion
3 Phase 2 Contingency Utilization Total Contingency Contingency Utilized through June 2015 Contingency Utilized in July 2015 Total Contingency Utilized through July 2015 Remaining Contingency $ Million $ 46.8 Million $ 1.0 Million $ 47.8 Million $ Million
4 Phase 2 July Contingency Utilization Total Contingency Utilized in July 2015 $ 1.0 Million WMATA Open Office Space Build-out - Design Voice Over Internet Protocol (VOIP) Telephones - Design and Construction Building Automation System Modification - Design Proposed Contact Rail Heater Controller - Design Miscellaneous (Items less than 0.1 million) $ 0.2 Million $ 0.2 Million $ 0.1 Million $ 0.1 Million $ 0.4 Million
5 Current Advancement of Design Packages 88% Complete Advancement of Building Permits for Design Packages: DP018.1 Reston Town Center Station Foundations (July 17, 2015) DP019 Herndon Station (July 23, 2015) DP022 Loudoun Gateway station (July 10, 2015) DP012.2 Civil West Storm Water Management (July 16, 2015) DP026.4 Traction Power Substation #20 (July 8, 2015) DP026.1 Te Breaker Station #8 (July 6, 2015) DP026.3 Traction Power Substation #19 (July 6, 2015) DP042 Reston Town Center Parkway Track Support (August 24, 2015) 10 Design Change Permit Revisions (July-August 2015) 25 Design Packages and Changes Issued for Construction (July-August 2015) 106 Supplier Documents ( Shop Drawings ) Processed (July-August 2015)
6 Widening access to Dulles Airport
7 M ET R O P O L IT A N W A S H I N GT O N A I R P O RT S A UT H O R ITY Saarinen Circle Road Shift
8 M ET R O P O L IT A N W A S H I N GT O N A I R P O RT S A UT H O R ITY Excavation for Dulles Station 7
9 M ET R O P O L IT A N W A S H I N GT O N A I R P O RT S A UT H O R ITY Tower Crane erected at Innovation Station
10 M ET R O P O L IT A N W A S H I N GT O N A I R P O RT S A UT H O R ITY Innovation Station Looking West from Tower Crane
11 M ET R O P O L IT A N W A S H I N GT O N A I R P O RT S A UT H O R ITY Aerial Abutment A East of Airport
12 M ET R O P O L IT A N W A S H I N GT O N A I R P O RT S A UT H O R ITY Aerial Guideway Columns approaching the Future Maintenance Yard
13 Set Aerial Guideway Girders at Span 63
14 M ET R O P O L IT A N W A S H I N GT O N A I R P O RT S A UT H O R ITY Aerial Guideway Drilling Shafts (On Airport and Yard Leads)
15 M ET R O P O L IT A N W A S H I N GT O N A I R P O RT S A UT H O R ITY Centerville Bridge Abutments
16 M ET R O P O L IT A N W A S H I N GT O N A I R P O RT S A UT H O R ITY Hand Mining, Jack and Bore, and Directional Drilled Utility Crossings
17 Current Herndon Station Hand tunneling for utilities, and installation of 34.5 KV duct bank Innovation Center Station Concrete foundations and directional drilling for sanitary line Innovation Station segment - DIAAH median (West of Horsepen Run bridge) Cast-inplace track wall/retaining wall and storm drainage Airport Station Mass excavation and force main sewer line installation Airport Station segment S1 guideway at entrance to Airport abutment A foundation Reston Town Center Station segment- DIAAH median work for lane shifts and pits for utility crossing operations Aerial Guideway Pour drilled shafts, columns, and pier caps (Airport and Yard Leads) 34.5 KV duct bank and manhole installation along DIAAH and Autopilot
18 Current Airport Segment/Autopilot Drive 34.5 KV duct bank installation Greenway/Yard Leads Segment Widening for aerial guideway abutment installation Centerville Road bridge Piles installation at the abutments Broad Run bridge Center piers completed, abutment construction to follow Centerville Bridge work
19 Upcoming Reston Station Lane Shifts; Utility tunnels under DIAAH and Toll Road Herndon Station Continue Lane Shifts; Small utility tunnels for Storm drainage Innovation Station Hand tunnels for utilities and station foundation work Dulles Station Mass excavation Aerial Guideway Pour drilled shafts, columns, and pier caps (on Airport and Yard Leads). Erect precast girders along Autopilot starting with Span 64.
20 New Girder Design Travel (cable) strands used to strengthen beam for transport have been relocated Travel strands stress lowered from 44,000 lbs to 25,000 lbs Girder rebar relocated closer to outside edge of flange MWAA independent engineer, PB/AECOM finite element analysis confirms stress lowered to within allowables CRC given green light to resume installing 84 high girders which have the new design details
21 M ET R O P O L IT A N W A S H I N GT O N A I R P O RT S A UT H O R ITY Girder Replacement Resumed
22 Current Phase 2 WMATA Rail Yard & Maintenance Facility Project wide buildings 60% comments resolution meetings Early Civil Sitework (IPP #1) Submitted to AHJ for permit Final Grading/Utilities/Yard layout design (IPP #2) 90% comments resolution meetings Construction activities within limits of IPP #0 Permit
23 Phase 2 WMATA Rail Yard & Maintenance Facility Upcoming Project wide 90% design submission Structures and Long Lead (IPP #3) 100% design submission Construction activities throughout the site with receipt of the Early Civil Permit (IPP #1)
24 Phase 2 WMATA Rail Yard & Maintenance Facility Begin Excavation and Fill Operations
25 Ronald Reagan Washington National Airport Dulles Corridor Metrorail Project Dulles Toll Road Washington Dulles International Airport
26 Dulles Rail DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 MONTHLY COST SUMMARY As of July 31, 2015 Description Budget Total Expenditures to Date Contract Contract Amount 1 Forecast 2 Amount Total NTP Substantial Percent b c c/b DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 DESIGN-BUILD Package A 1,193,777,000 1,248,825, ,403,594 22% 8-Jul-13 7-Aug-19 DESIGN-BUILD Package B + S 273,280, ,570,297 26,540,402 10% 18-Nov Jun-18 ROW 58,600,000 58,600,000 4,784,548 8% 8-Jul Sep-17 WMATA 305,324, ,324,718 45,085,228 15% N/A 3-Feb-20 PRELIMINARY ENGINEERING 75,000,000 75,000,000 71,107,066 95% 15-Jul Dec-13 PROJECT MANAGEMENT 320,802, ,231,409 89,763,314 28% N/A 2-Jan-19 CONTINGENCY 551,451, ,683,681 TOTAL FOR DCMP 2,778,235,564 2,778,235, ,684,152 Notes: 1 Budget Amount includes contingency as separate line item and does not include finance costs. 2 Total Forecast includes funded changes. It does not include finance costs. 3 Budget Amount includes commodity escalation of $20 million for Package A & B+S. 4 Package A Contract Substantial Completion date changed from 7-Jul-2018 to 7-Aug-2019
27 Dulles Rail DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 CONTINGENCY UTILIZATION As of July 31, 2015 ATTACHMENT 2 Description Amount in million ($) DULLES CORRIDOR METRORAIL PROJECT - PHASE 2 Total Contingency Contingency Utilized through June 2015 $ $ 46.8 Expended Contingency in July 2015* $ 1.0 Total Contingency Utilized through July 2015 $ 47.8 Remaining Contingency $ *See table below for details WMATA Open Office Space Build-out - Design $ 0.2 Voice Over Internet Protocol (VOIP) Telephones - Design and Construction $ 0.2 Building Automation System Modification - Design $ 0.1 Proposed Contact Rail Heater Controller - Design $ 0.1 Miscellaneous (Items less than 0.1 million) $ 0.4 TOTAL $ 1.0
Safe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network
IH-635 MANAGED LANES PROJECT, SEG. 3.2
IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,
Virginia Approach Spans
Virginia Concrete Conference 2009 Woodrow Virginia Approach Spans David Tackoor, HNTB Formerly of URS Corp for Potomac Crossing Consultants Woodrow 1 Second Severn Crossing 2 Medway Crossing (Channel Tunnel
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017
From -JAN- To -JUN- -JAN- VIRP Page Period Period Period -JAN- 8 -JAN- 8 9 -JAN- 8 8 -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -FEB- : days
Buildings Construction Procurement Strategy
Buildings Construction Procurement Strategy Graham Strickleton Site, Buildings and Power supplies Procurement Manager JOURNEE DEDIEE AUX INDUSTRIELS ET AUX MEMBRES DU RESEAU A.P.I Disclaimer: these slides
DULLES CORRIDOR METRORAIL PROJECT TIMELINE
DULLES CORRIDOR METRORAIL PROJECT TIMELINE 1958 Construction of Washington International Airport begins. 1962 Construction of Main Terminal is completed. 1962 Official operations begin at "Dulles International
Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26
2014 HDR Architecture, 2014 2014 HDR, HDR, Inc., all all rights reserved. Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26 Brandon Chavel, PhD, P.E.,
SECOND PENANG BRIDGE PROJECT
INTRODUCTION PROJECT PARTICULARS Jambatan Kedua (JKSB), a wholly-owned company of the Minister of Finance, Incorporated (MoF Inc.) was appointed as the concessionaire for the Second Penang Bridge Project
Source: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009.
Total project cost $2.5 billion (Canadian) Financed by tolls about $3 each direction. Total project length 37 km (McGill St in Vancouver to 216 th in Langley) The new Port Mann bridge 10 lanes (existing
Soapstone Connector Feasibility Study
Technical Report Soapstone Connector Feasibility Study Prepared by ATCS, plc., 2553 Dulles View Drive, Herndon, VA 20171, (703) 430-7500 www.atcsplc.com In association with: Michael Baker Corporation,
CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE Updated 29 May 2009
CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE Updated 29 May 2009 www.maximumreach.com 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: November 2010 Artists conception of the
Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8
Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138 Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 2 of 138 Domain Name: CELLULARVERISON.COM Updated Date: 12-dec-2007
Notice of Public Hearing Washington Metropolitan Area Transit Authority Docket B13-01
Notice of Public Hearing Docket B13-01 PROGRAM OF PROJECTS FOR FEDERAL FISCAL YEAR 2013 FUNDS AUTHORIZED UNDER THE MOVING AHEAD FOR PROGRESS IN THE 21 ST CENTURY ACT (MAP-21) AND THE PASSENGER RAIL INVESTMENT
Technical Assignment 2
Architectural Engineering 2012 Senior Thesis -+ + Technical Assignment 2 Reston Station Phase 1 Garage Reston, VA Jonathan A Fisher Oct. 12, 2012 A d v i s o r : D r. R o b e r t L e i c h t Executive
Owner s Procurement Forum
Washington Metropolitan Area Transit Authority Construction Management Association of America National Capitol Chapter Owner s Committee Owner s Procurement Forum February 24, 2015 OVERVIEW of WMATA INFRASTRUCTURE:
MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5
Rendering Provided by McKissick Associates MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5 Additions and Alterations to Williamsport Area Middle School Williamsport Area School District 17 July 2012 Geo-Thermal
SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM
Shepherd University Board of Governors June 9, 2005 Agenda Item No. 9 SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM In 1994 construction began on the Byrd Science and
Northwest Light Rail Extension Pre-Construction/Final Design. Public Meeting November 27 & 29, 2012
Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 6:00 6:30 p.m. Open House 6:30 7:00 p.m. Presentation 7:00 8:00 p.m. Open House 2 Project Overview Carla
The total estimated PFC revenue for the application is $266,900,000. The estimated charge effective date for this application is December 1, 2016.
Public Notice of Application for Authority to Impose and Use Passenger Facility Charges (PFCs) at EWR, LGA, JFK and SWF and Amendment to Approved PFC Applications at EWR, LGA, and JFK The Port Authority
Alternatives Presentation Meeting Middlebury WCRS(23)
Alternatives Presentation Meeting Middlebury WCRS(23) Main Street (VT 30/TH 2 Bridge 102) and Merchants Row (TH 8 Bridge 2) over Vermont Railway June 4, 2013 Twilight Hall Auditorium, Middlebury College
Granger Bay Boulevard and Green Point Roundabout
Granger Bay Boulevard and Green Point Roundabout INTRODUCTION Aurecon was appointed for the design and construction supervision of the Granger Bay Boulevard and Green Point roundabout that provides access
PPP Experience on the Canada Line
PPP Experience on the Canada Line International Practicum on Innovative Transit Funding & Financing June 13, 2014 Fred Cummings, P.Eng. President and General Manager BC Rapid Transit Co. Outline TransLink
PENNDOT 3D MODELING FOR STRUCTURES WORKSHOP. Presented by: Steven Pletcher and Chris Daniels, P.E. October 21, 2014
PENNDOT 3D MODELING FOR STRUCTURES WORKSHOP Presented by: Steven Pletcher and Chris Daniels, P.E. October 21, 2014 Agenda Introduction G.A. & F.C. Wagman History Process used to prepare 3D models Estimating
11 p.m. to. Tuesday, June. will remain open. 14. closed
June 3, 2011 CONTACT: Marcia McAllister T: 703 572 0506 C: 571 730 9117 [email protected] Important Lane Closures June 5 11 Include Northbound Beltway Lanes, Eastbound Dulles Airport Access
C-2 Construction, Inc. - NAICS Codes
C-2 Construction, Inc. - NAICS Codes 212313 - Crushed and Broken Granite Mining and Quarrying This U.S. industry comprises: (1) establishments primarily engaged in developing the mine site, and/or mining
Request for Information (RFI) for
Request for Information (RFI) for Currently Marketed Software Solutions Used To Produce The Comprehensive Annual Financial Report For Governmental Entities Released on August 1, 2013 Issued by the Metropolitan
2012 CBECS: Preliminary Results and Timeline for Data Release
2012 CBECS: Preliminary Results and Timeline for Data Release Joelle Michaels, CBECS Survey Manager Interagency Sustainability Working Group September 18, 2012 Washington, DC U.S. Energy Information Administration
REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING
REQUIREMENTS AND SPECIFICATIONS FOR HIGH VOLTAGE CUSTOMER BUILT FACILITIES PEPCO ENGINEERING Revised October, 2013 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 2.0 REQUIRED DRAWINGS... 3 2.1 Site Plan... 3
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0
DULLES CORRIDOR METRORAIL PROJECT EXTENSION TO WIEHLE AVENUE
DULLES CORRIDOR METRORAIL PROJECT EXTENSION TO WIEHLE AVENUE Submitted to Federal Transit Administration For Construction Submitted by Metropolitan Washington Airports Authority In cooperation with Washington
Owner Controlled Insurance Program (OCIP) Overview
Owner Controlled Insurance Program (OCIP) Overview Prepared for Caltrans Oakland Touchdown Outreach Presented by: Willis One Bush Street, Suite 900 San Francisco CA 94104 (415) 981-1141 WHAT IS AN OCIP
Sewer System Improvement Program Update
August 20, 2014 Sewer System Improvement Program Update Tommy T. Moala SFPUC Assistant General Manager, Wastewater Enterprise Agenda 1. SF Sewer System 2. Our Challenges 3. Sewer System Improvement Program
San Francisco Oakland Bay Bridge East Span Seismic Safety Project
San Francisco Oakland Bay Bridge East Span Seismic Safety Project Presented To: Society of American Military Engineers May 16, 2013 Brian Maroney, P.E. Dr. Engr. Karen Wang, P.E. Pier E9 Following the
Residential Prototype III. Multi-Story. The Multi-Story. Your connection to ideas + answers. Prepared by: AISC Steel Solutions Center
Multi-Story Residential Prototype III The Multi-Story Residential Prototype III Prepared by: AISC Steel Solutions Center What s this? This package tells the story of a fictitious project with an imaginary
EXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 [email protected]
College of Computing, Engineering & Construction Building Construction Management Course Descriptions
CATALOG 2010-2011 Undergraduate Information College of Computing, Engineering & Construction Building Construction Management Course Descriptions BCN101: Construction & Culture: A Built Environment An
Module 6: QUALITY MANAGEMENT FOR CONSTRUCTION PROJECTS. Submodule 1: Introduction. Objectives: After completing this submodule, you will be able to:
Module 6: QUALITY MANAGEMENT FOR CONSTRUCTION PROJECTS Submodule 1: Introduction Objectives: After completing this submodule, you will be able to: Define the function and importance of Construction Quality
Our Capabilities The EAC Advantage. May 20, 2008
May 20, 2008 Mr. John Bardwell, Contracting Officer Federal Transit Administration 1200 New Jersey Avenue, SE, Room E-42-331 Washington, D.C. 20590 RE: Project Management Oversight (PMO) (Reference No.
Capital Action Plan Status Thru Dec 2015
Freeway Projects: I-5, Pico to Vista Hermosa $113.0 Jun-09 Dec-11 Jun-11 Oct-13 Feb-14 Oct-14 Dec-14 Aug-18 Project C $91.9 Jun-09 Oct-11 Jun-11 Oct-13 May-14 Sep-14 Dec-14 Aug-18 I-5, Vista Hermosa to
How To Complete A Power Line Project
MTACC Quarterly Progress Report to CPOC East Side Access Project Overview Overall Status Item Schedule* Cost* Comments During January CPOC, preliminary end date forecasts were presented ranging between
CHAPTER 8 CIVIL DESIGN
CHAPTER 8 CIVIL DESIGN A. GENERAL This Chapter includes standards and design considerations for other civil engineering design in structural, drainage and utilities. Design considerations for electrical
WMATA S Automated Track Analysis Technology & Data Leveraging for Maintenance Decisions
WMATA S Automated Track Analysis Technology & Data Leveraging for Maintenance Decisions 1 WMATA System 6 Lines: 5 radial and 1 spur 234 mainline track miles and 91 stations Crew of 54 Track Inspectors
I-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA. PSPE Presentation, December 3, 2015
I-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA PSPE Presentation, December 3, 2015 Location Map N PROJECT LOCATION 22 nd 18 th Streets PHILADELPHIA, PA General
REPORTS & PRESENTATIONS AGENDA ITEM #III-3 CORTEZ BRIDGE PROJECT DEVELOPMENT AND ENVIRONMENT (PD&E) STUDY
NOTES REPORTS & PRESENTATIONS AGENDA ITEM #III-3 CORTEZ BRIDGE PROJECT DEVELOPMENT AND ENVIRONMENT (PD&E) STUDY Presenter: Summary: Tony Sherrad, FDOT Project Manager The Cortez Bridge in Manatee County,
Peer Review Scope of Work
1.0 PROJECT OVERVIEW The St. Croix River Crossing Project has been developed in response to traffic congestion, operation deficiencies, safety concerns, and structural deficiencies of the Stillwater Lift
Proposal to Reduce Opening Hours at the Revenues & Benefits Coventry Call Centre
Proposal to Reduce Opening Hours at the Revenues & Benefits Coventry Call Centre Proposal To change the opening hours of the Revenues & Benefits Call Centre to 9am until 5pm Monday to Friday with effect
Remote Monitoring of Soil Pressures on Bridge Footings
More Info at Open Access Database www.ndt.net/?id=18252 Remote Monitoring of Soil Pressures on Bridge Footings Michael DAVIDSON 1, Zhihui ZHU 2, Issam HARIK 3, Charlie SUN 4, Kevin SANDEFUR 5 1 Bridge
Analysis One Code Desc. Transaction Amount. Fiscal Period
Analysis One Code Desc Transaction Amount Fiscal Period 57.63 Oct-12 12.13 Oct-12-38.90 Oct-12-773.00 Oct-12-800.00 Oct-12-187.00 Oct-12-82.00 Oct-12-82.00 Oct-12-110.00 Oct-12-1115.25 Oct-12-71.00 Oct-12-41.00
FLAT ROOF BOX SPAN CARPORTS
AGS/NC/03 FLAT ROOF BOX SPAN CARPORTS Thank you for choosing this quality product. We strongly recommend that you read these instructions thoroughly. Please take your time and do not rush the erection
Chaudière Crossing Bridge Rehabilitation
Chaudière Crossing Bridge Rehabilitation Douglas K. Lowry P. Eng., Armtec Infrastructure Incorporated David Delicate, P.Eng. Public Works and Government Services Canada (Retired) Prepared for presentation
S-1 (1803) PROGRESS SCHEDULES-CRITICAL PATH METHOD (CPM) The provisions of MnDOT 1803 are deleted and replaced with these Special Provisions.
S-1 (1803) PROGRESS SCHEDULES-CRITICAL PATH METHOD (CPM) The provisions of MnDOT 1803 are deleted and replaced with these Special Provisions. 1803.1 All SCHEDULES A General Requirements This section contains
Report to the Business Administration Committee. Recommendation to Award a Fixed Base Operator Contract at Washington Dulles International Airport
Report to the Business Administration Committee Recommendation to Award a Fixed Base Operator Contract at Washington Dulles International Airport July 2015 Purpose Staff requests that the Business Administration
TABLE OF CONTENTS. Section / Article Page
TABLE OF CONTENTS Section / Article Page 1. INTRODUCTION 1.1 Purpose................ 6 1.2 Definitions................ 6 1.3 Guidelines and References............ 7 2. AGREEMENTS 2.1 Applicant and Contractor
APPENDICES G) DETAILED BACKBONE INFRASTRUCTURE CONSTRUCTION COST ESTIMATE SUMMARY
ALAMEDA POINT MASTER INFRASTRUCTURE PLAN March 31, 2014 APPENDICES G) DETAILED BACKBONE INFRASTRUCTURE CONSTRUCTION COST ESTIMATE SUMMARY Carlson, Barbee & Gibson, Inc. Backbone Infrastructure Engineer
Budget Used Balance Obligation Based Budget: Infrastructure Renewal Program $290.1 $251.2 $38.9
FY 05 Metro Matters Summary End of Fiscal Year Status Dollars in Million Budget Used Balance Obligation Based Budget: Infrastructure Renewal Program $290.1 $251.2 $38.9 Expenditure Based Budget: Rail Car
Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective
Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective FHWA NATIONAL GEOTECHNICAL PROGRAM www.fhwa.dot.gov/engineering/geotech Why Geotechnical Instrumentation? Provide warning
Geotechnical Building Works (GBW) Submission Requirements
Building Control (Amendment) Act 2012 and Regulations 2012: Geotechnical Building Works (GBW) Submission Requirements Building Engineering Group Building and Construction Authority May 2015 Content : 1.
Cost Reduction Opportunities
Cost Reduction Opportunities 9 December 2015 Presentation to MassDOT Board of Directors & MBTA Fiscal and Management Control Board Arup 2 A global, integrated, multidisciplinary firm of professionals 13,000
Value Engineering vs. Alternate Designs in Bridge Bidding
Value Engineering vs. Alternate Designs in Bridge Bidding Compares the advantages and disadvantages of alternate designs and value engineering in bidding of bridges as experienced in the State of Florida.
Ashley Institute of Training Schedule of VET Tuition Fees 2015
Ashley Institute of Training Schedule of VET Fees Year of Study Group ID:DECE15G1 Total Course Fees $ 12,000 29-Aug- 17-Oct- 50 14-Sep- 0.167 blended various $2,000 CHC02 Best practice 24-Oct- 12-Dec-
Sector Design Concepts
Section C Sector Design Concepts C7 Sector 7 Great North Road Underpass 6 6 6 C7. Existing situation Sector 7 refers to the cut and cover section of the project linking the northern end of the deep tunnels
MOTION NO. M2015-63 WSDOT Task Order for Final Design Services PROPOSED ACTION
MOTION NO. M2015-63 WSDOT Task Order for Final Design Services MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee 07/09/15 Final Action Ahmad Fazel, DECM Executive Director Ron Lewis, East
The unit costs are based on the trend line of the 3 low bids for the average quantity.
Page 1 of 8 COST ESTIMATE GENERAL INSTRUCTIONS The unit costs are based on the trend line of the 3 low bids for the average quantity. Apply the Unit Costs to ordinary structures. Unit Costs should generally
KOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER
KOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER The New York State Department of Transportation (NYSDOT) is preparing an Environmental Impact Statement (EIS) to evaluate alternatives for the rehabilitation or
DUDERSTADT FOUNDATION & CONSTRUCTION, LLC.
DUDERSTADT FOUNDATION & CONSTRUCTION, LLC. Drilling since 1916 2215 Belknap Place Phone (210) 824-3800 San Antonio, TX 78212-1904 Fax (210) 824-9525 www.duderstadtfoundation.com ABOUT THE COVER: Drilled
APEC CAPABILITIES PROJECT MANAGEMENT / SUPPORT
PROJECT MANAGEMENT / SUPPORT Capital Cost Savings Construction Monitoring and Assistance In-Plant Production Assistance In-Plant Maintenance Assistance Procurement Assistance Project Cost Estimating o
2016 Examina on dates
Please note the following informa on: The following exams are available throughout the year: Please click on the exam for which you wish to see the dates. When you have finished, you can select to return
Guide to the Jamey Stillings Photographs of the Mike O Callaghan-Pat Tillman Memorial Bridge and the Hoover Dam
Guide to the Jamey Stillings Photographs of the Mike O Callaghan-Pat Tillman Memorial Bridge and the Hoover Dam This finding aid was produced using ArchivesSpace on November 17, 2015. English 2015 The
Certificate of Registration
Certificate of Registration This is to certify that Clancy Docwra Limited Supplier Number: 061973 are now fully registered as a supplier on UVDB for the following products/services 1.4.25 Communication
Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS
Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS 1 Proposal & Plans Received? 2 Review Proposal, highlight important facts. Know proposal well to be able to find answers quickly.
COLUMN-FREE OFFICE SPACE RISES IN CHICAGO S LOOP
COLUMN-FREE OFFICE SPACE RISES IN CHICAGO S LOOP 30 x45 bay provides maximum tenant flexibility and increases leasing marketability By David E. Eckmann AIA, S.E. P.E. SURGING DEMANDS FOR RENTABLE OFFICE
2015 Examination dates
Please note the following information: The following exams are available throughout the year: BULATS Paper-based: Please click on the exam for which you wish to see the dates. When you have finished, you
Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations
Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet
FY08 SEWER POINT REPAIRS BID TABULATION
6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "
Quality and Risk Management Considerations for Very Shallow Soft Ground Conventional Tunnelling in Urban Settings
Quality and Risk Management Considerations for Very Shallow Soft Ground Conventional Tunnelling in Urban Settings Dr. Vojtech Gall, Gall Zeidler Consultants, LLC, USA, [email protected] Mr. Zaw Soe
REBUILDING THE CTA FORREST CLAYPOOL, PRESIDENT CHRIS BUSHELL, SVP, INFRASTRUCTURE
REBUILDING THE CTA FORREST CLAYPOOL, PRESIDENT CHRIS BUSHELL, SVP, INFRASTRUCTURE Our Commitment: Increasing Investment Despite Lean Times Even while facing a $277M deficit, we are finding ways to rebuild
3 Tappan Zee Bridge Rehabilitation Options
3 Tappan Zee Bridge Rehabilitation Options 3.1 Introduction This chapter describes possible options that rehabilitate and enhance the existing Tappan Zee Bridge. Four Rehabilitation Options have been developed:
The Gateway Program and Hudson Tunnel Project
The Gateway Program and Hudson Tunnel Project Presented to: NJ State Senate Oversight Committee Stephen Gardner Executive Vice President NEC Business Development August 10, 2015 1 The Need for Gateway
LBJ Freeway in Dallas
LBJ Freeway in Dallas Texas/USA Ferrovial Agroman is redeveloping the LBJ Freeway to increase capacity and relieve severe congestion in one of the fastest growing areas in the United States. Ribera del
CONTRACTOR S SCHEDULE TOOLKIT (CST): DEVELOPED FOR PRIMAVERA P6 VERSION NO. 1.6 (ISSUED: JANUARY 2011)
CONTRACTOR S SCHEDULE TOOLKIT (CST): DEVELOPED FOR PRIMAVERA P6 VERSION NO. 1.6 (ISSUED: JANUARY 2011) CONTENTS 1.0 INTRODUCTION 2 1.1 BUSINESS NEED 2 1.2 DISCLAIMER 2 2.0 TOOLKIT COMPONENTS 3 2.1 SCHEDULE
Oxfam GB Digital Case Study - email
Oxfam GB Digital Case Study - email Friday 19 th July Lizzie Williams Email Marketing Manager Holly Bolter Senior Analyst Mark Lumby Selections & Analysis Manager Emergencies Get Together Campaigns Regular
NEW BLUE LINE CONNECTIONS
Washington Metropolitan Area Transit Authority NEW BLUE LINE CONNECTIONS 3/31/2014 A Major Capital Project of Momentum s Metro 2025 Program In support of its new strategic plan, Metro has considered the
Chapter 22. Lump Sum Project Guidelines
Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11