INSTALLING A HOLLOW-CORE SLAB

Similar documents
Owner s Manual Gantry Cranes

COMPETENCY ANALYSIS PROFILE. Rodworker 452A. (All unshaded skill sets must be demonstrated/ completed) Lift equipment and materials

STEADYfast Stabilizer Installation Notes Fifth Wheel and Travel Trailers 11/23/13

I BEAM TRACK INSTALLATION

Bolt-on castor set B

INSTALLATION. General. Important Note. Design. Transport

Chapter 3 Pre-Installation, Foundations and Piers

Chapter 10 - Scaffolding Systems

SELF-STEERING AXLE TABLE OF CONTENTS

Pole Lathe and Shave Horse Design

Since it was established in 1989, with a small manufacturing base in Qwa Qwa and a hire yard in Botswana, Uni-Span

Packaged Terminal Air Conditioner Wall Sleeve Installation

Important Information

Hanson Building Products. precast basement solutions

Removable Aluminium posts

10 TON HYDRAULIC PRESS

Machine Moving. By Norm Berls

SCAFFOLDING RUNWAY SYSTEM

Directive 2006/42/EC Classification of equipment used for lifting loads with lifting machinery

PANELIZED HOME INSTALLATION GUIDELINE

Installation Instructions:

Directive 2006/42/EC. Classification of equipment used for lifting loads with lifting machinery

For ease of reference the clauses are arranged in 12 sections as follows:-

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

Fiberstars Mini Lighted Laminar Flow Fountains

INSTRUCTIONS: LocknCharge Laptop Carts

INSTALLATION INSTRUCTION - INSTRUCCIONES DE INSTALACION FOR DOUBLE-HUNG VENT REPLACEMENT WINDOW

FORM DESIGN. easy to work with, and generally available.

39HQ Airovision Air Handling Units

Safe & Sound Bridge Terminology

K. D. FRAME ASSEMBLY FOR CLOSED STEEL STUD WALLS...Ins 10. FRAME INSTALLATION DETAILS FOR CLOSED STEEL STUD WALLS...Ins 11

In-Track Repair of Concrete Ties. Deland Humpherys, Director Track Mtce

Replacement Window Installation Guide Non-Impact & Impact Resistant Windows without Nailing Fin

Vehicle Restraint Installation Manual

INSTALLATION OF A BAY WINDOW

FLAT ROOF CARPORT RECOMMENDED INSTRUCTION MANUAL

Installation Instructions Avalanche XUV Cap IMPORTANT! IMPORTANT!

The ACR : Advanced Design Features for a Short Construction Schedule

Contents. 1. Foreword Common accidents in lifting operations Legislative requirements and code of practice of lifting operations 2

2100 AD Mirror Elevator Ball Nut Replacement Procedure

HORIZONTAL INSTALLATION

Hive Top Ventilation Shims

Information Technology Solutions

Chapter 3: Fall Protection/ Scaffolding Safety

Mark Cramer Inspection Services, Inc.

COMBINATION SLAB & TRIM SAW INSTRUCTIONS 12, 14, & 16 MODELS

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

Ecoflex Wall Penetration Systems: An efficient, sustainable solution for penetrating concrete or block walls

The Drink-Aide The NEW look of independence

CHARISMA SHOWER/TUB DOOR INSTALLATION INSTRUCTIONS

for Phoenix II-2 Human Cremation Retort

OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

GENERAL SPECIFICATION FOR CIVIL ENGINEERING WORKS SECTION 13 WORK FOR ELECTRICAL AND MECHANICAL INSTALLATIONS

IMPORTANT INSTALLATION GUIDE VALENCIA SQUARE CORNER SHOWER READ ALL INSTRUCTIONS CAREFULLY BEFORE STARTING THE INSTALLATION

SITE SPECIFIC FALL PROTECTION PLAN

WorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

Installation Instructions

Industrial Guideline nr. 2

Folding Bath Screen Instruction Manual

Clad Direct Glaze Window Installation Instructions

SAFE HANDLING OF PRECAST CONCRETE PRODUCTS

Chapter. Restoration of Damaged Structures

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

CNC Tool Storage Solutions

Instruction Manual 19/9/01. Flat Roof Carport

Responsibilities of a Volunteer Leader

CNC Tool Storage Solutions

INSTALLATION INSTRUCTIONS for Vinyl Windows without Nailing Fin (JII011) ImPOrTANT INFOrmATION & GlOssAry. rough OPeNINGs

CA-6050 Solar Power Unit. User Guide. Designed to work with the Norsonic range of sound level meters to provide a DC supply in remote locations.

Ceiling Mounted Folding Attic Ladders Installation Instructions

INSTRUCTIONS FOR CHAIN LINK INSTALLATION Chain Link fence & Posts Meshdirect.co.uk

4 5/16 Subframe Installation

1 Ton Telescoping Gantry Crane

BUILD A TABLETOP LOOM

CNC Tool Storage Solutions

Diamond LOK-21 Assembly Information

INSTALLATION INSTRUCTIONS COMPETITION SERIES COILOVER SUSPENSION SYSTEM 03+ Scion xb

Round Housing with Side Ports

Lunette 2 Series. Curved Fixed Frame Projection Screen. User s Guide

NUMBER: 08 DD15-10 S.M. REF.: 3.2 ENGINE: DD15 DATE: September 2008

Xerox Nuvera Production System and Xerox igen Digital Production Press

Combination Unit 5'6" Windows a i o P t

Layher. Protective Systems. More Possibilities. The Scaffolding System. Layher Keder Roof and Keder Hall Instructions for Assembly and Use

WORKING AT HEIGHT & ITS WOES

Installation Instructions For Slider Casement Air Conditioners

More than shelving & racking. All for your storage demands.

Item #: BTOL Assembly Instructions

INSTALLATION INSTRUCTIONS for Premium Pocket Windows (JII022) IMPoRtaNt INFoRMatIoN & glossary. safety & HaNdlINg

SHUTTER INSTALLATION INSTRUCTIONS. AUGUST 2006 Version 2

Premier & Deluxe 3-Season Room Sliding Glass Door

E-Line and Braided Line. E-Line Open Hole wireline

It's large enough to handle most welding job shop projects, yet small enough to make it a worth while home-workshop tool

2010 APPLICATION REFERENCE GUIDE

IMPORTANT INFORMATION

MEASURING WHEEL ALIGNMENT

Awning Instructions. Standard Manual 1.5m to 4.5m

ISSUE 2. Installation Guide

BUILD A CARPORT. 2 - Planning the carport. 3 - Designing the carport

Combination Unit (shown from interior) WARNING

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta

Transcription:

Implementation and layout: Mittaviiva Oy Pictures: Mikko Marjasalo Copyright: Betoniteollisuus ry, Finland August, 2012 INSTALLING A HOLLOW-CORE SLAB Concrete Industry Association of Finland

PREPARING FOR THE INSTALLATION OF HOLLOW-CORE SLABS Draw up an installation plan well in advance and agree on the order of the delivery of the slabs. Select a lifting device that is suitable for the site conditions and the weight of the hollow-core slabs. Use personal safety equipment no matter the weather. Prepare a road that is sufficiently wide, even and stable. Check the ground bearing capacity under the crane outrigger. Be sure to use fall protection equipment. 500 mm Inspect the lifting device before starting work. Always store the hollow-core slabs on an even, stable surface and stack them on bottom and intermediate support timbers.

INSPECTING AND SUPPORTING HOLLOW-core SLABS Compare each slab with the plan. Inspect the slab labels in the level drawings, the supports for the installation phase, the lifting necks, the number of strands, the location of the deep-plugs and the slippage of the strands. Inspect the lifting groove and ensure that the protruding lip at the bottom of the clamp fits into it. Do not lift a damaged slab. Mark the location of the slabs and set installation shims or a neoprene bearing strip in place. Inspect the length of the bearing surface and the level and location of the installation shims at the web of the slab. Assemble the temporary supports for the work phase according to the plans, prior to the installation of the slabs. Prevent the tilting over of a beam by providing support, according to the plans, close to the end of the beam.

LIFTING A HOLLOW-CORE SLAB Place the protruding lip of the clamp carefully into the groove of the slab. Tighten and lock the safety chain when the height of the slab is less than 100 mm. The hollow-core slabs will be installed by using a spreader beam and lifting clamps. Maintain eye or radio contact with the crane operator. Watch out for any swinging movement of the slab and position yourself safely on the long side of the slab. < 10 Follow the manufacturer s instructions when selecting lifting points. The angle between the legs of the lifting chains must be less than 60 degrees. A slab that is shorter than three meters can be lifted with long lifting chains without a spreader beam.

LIFTING SPECIAL-PURPOSE SLABS Verify the amount and type of lifting clamps that are required for heavy slabs. Always lift by using lifting loops or anchors, if awailable in the slab. Use lifting loops or anchors to lift a narrow slab. Do not lift a damaged slab. Contact the site supervisor. Slabs that are meant to be installed in a tilted position should always be lifted by using lifting loops or anchors. If the narrowed end of the slab is short, attach the clamps 200mm from the edge of the narrowed part of the slab.

LIFTING SPECIAL-PURPOSE SLABS Make sure that the lifting grooves of bathroom slabs are in order. Use lifting loops to lift small slabs. Clamps can be used to lift reinforced long cantilevers. Use lifting loops to lift long cantilever slabs. Lift slabs with a lifting neck in the usual manner. Clamps can only be used to lift a notched slab if the intact part of the slab is at least 800mm long.

INSTALLING A HOLLOW-CORE SLAB If needed, attach a rope to the slab that is being lifted in order to assist in directing it. Do not detach the safety chain until the slab is no more than 100 mm above the support. Steer the slab into place with an installation bar. Be careful of slipperiness in the winter. Use support in the form of welded stoppers or by wedging a tilted slab into place when positioning. Level out differences in the slab camber, according to the plans, by using supports, adjuster bolts or installation shims. Assemble the railings immediately.

JOINT GROUTING AND FOLLOW-UP Clean snow, ice and debris from the joints. Inspect the void plugs and carry out formwork for the joints. Reinforce the joints and install an electrical conduit according to the plans. Carry out the joint grouting and seal it carefully. Remove any excess grout. Also clean the soffit of the slab. Carry out protection and curing according to the conditions. ISBN 978-952-269-070-8 ISBN 978-952-269-071-5 (pdf) Inspect and open drainage holes after joint grouting. Drill more holes if necessary. Notch the lifting neck off only after the joint grouting has been set. block and cover the area from below.