Winona Bridge Work Package #5 Bridge No. 5900 (Existing Bridge) Rehabilitation and Reconstruction Installment #4



Similar documents
Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A

REHABILITATION PACKAGE 1-a

School Construction Projects

Project Delivery Methods & Contract Types CSTM 102 Spring 2013

Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector

JD EDWARDS WORLD HOMEBUILDER AND REPETITIVE BUILDER MANAGEMENT

NON-TRADITIONAL UTILITY COORDINATION on KYTC Projects. KYTC Partnering Conference September 9, 2014

REQUEST FOR PROPOSAL. Consulting Services for a Thomas Street Corridor Master Plan

BRG Look Back Study. November 30, 2015

RBRC Combo Project Request for Qualifications Additional Information and Clarifications #1. RFQ No Issued: March 9, 2011

The programming, design

RHODE ISLAND TURNPIKE AND BRIDGE AUTHORITY NEWPORT, RHODE ISLAND CONTRACT NO

CONSTRUCTION COST ESTIMATES

REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER

CITY OF TRAIL MEMORANDUM

Notes from National Contract Management Association (NCMA) Panel Understanding the Proposal Bid-No Bid Decision How to Increase Competition

3.1 Historical Considerations

DESIGN-BUILD PROCUREMENT AND ADMINISTRATION GUIDE

Roadway Cost Per Centerline Mile Revised June 2014

Section 000 Organization of an Engineering District (Construction)

Prepared by David Willson, OCIO in consultation with Marc Buchalter, Procurement Please send comments to David Willson at

Building Capital Projects in Tough Times John Lynch, State of Washington

Covance Construction Management Staffing Plan Chandler, Arizona

Puget Sound Emergency Radio Network: Project Schedule and Cost Risks

Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way

MPO Staff Report MPO Technical Advisory Committee: March 13, 2013 MPO Executive Board: March 20, 2013

Value Engineering vs. Alternate Designs in Bridge Bidding

Evaluating Project Delivery Options

BLUEPRINT PROJECT INSURANCE: OWNER S PROFESSIONAL LIABILITY EXPOSURES AND SOLUTIONS CONSTRUCTION PRACTICE

Lessons Learned/Best Practices: Case Study- Design-Build at SFO

City of Red Wing REQUEST FOR QUALIFICATIONS. Levee Park - Riverboat & Transient Boat Dockage, Park and Promenade Improvements Professional Services

P. ALTERNATE TECHNICAL CONCEPTS FOR CONSTRUCTION, STAGING AND TRAFFIC CONTROL

Decision making in ODOT s Project Development Process. How to Use the Feasibility Study and Alternatives Evaluation Report in the PDP

CONTRACTOR DEFAULT & SURETY PERFORMANCE:

An Owner s Guide To Construction Management Assuring Project Success Under Any Delivery Method

Request for Proposals. Site C Clean Energy Project. Worker Accommodation RFP #1807

Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting

RED RIVER DIVERSION FARGO MOORHEAD METRO FLOOD RISK MANAGEMENT PROJECT, FEASIBILITY STUDY, PHASE 4

Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices

3 Tappan Zee Bridge Rehabilitation Options

REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office

PUBLIC RIGHT-OF-WAY ACCESSIBILITY TRANSITION PLAN

Design Build Institute of America (DBIA)

How to Estimate the Cost of Interior Building Finishes from Schematic Drawings. CPE Candidate No December 2014

Windows Server 2003 migration: Your three-phase action plan to reach the finish line

Purchasing Services AOC East Fowler Avenue Tampa, Florida (813) Web Address:

Work Type Definition and Submittal Requirements Work Type: Construction Contract Administration & Management

PROJECT MANAGEMENT HANDBOOK, PART 2 - PHASE SPECIFIC PROJECT MANAGEMENT ISSUES

BANKA SOCIETE GENERALE ALBANIA

EAST HARLEM COMMERCIAL RFP PROPOSAL Q&A

Project Information. New Hope - Lambertville Toll Bridge - Pavement Rehabilitation & Approach Bridges Repairs -

Intranet Buyers Workbook

AN OWNER'S GUIDE TO PROJECT DELIVERY METHODS

Contracting Practices in Mega Projects

IH-635 MANAGED LANES PROJECT, SEG. 3.2

SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION. Request for Qualifications

State of Accelerated Bridge Construction (ABC) in the United States

FEBRUARY 2014 LRFD BRIDGE DESIGN 4-1

MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS

PROJECT PROCUREMENT PROCEDURES AND GUIDELINES

Supporting high quality development in Haringey- Our pre application advice services

I-25/ARAPAHOE INTERCHANGE RECONSTRUCTION PROJECT

Los Angeles Community College District PROGRAM MANAGEMENT SERVICES. Terri Mestas Program Director

CONSTRUCTION MANAGEMENT

Public Information & Public Scoping Meeting

Oral Defense of the Dissertation

Chapter 22. Lump Sum Project Guidelines

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: 1 DISCUSSION ITEM

Sample interview question list

Request for Proposal No. RFP Project Construction Management Services. for. Capital Levy BTA IV Project: Ingraham High School Classroom Addition

CONTRACT ENGINEERING AN ALTERNATE EMPLOYMENT PATH BY RICHARD F. TAX 3/28/97

DOT Use of Lump Sum Contracts for Design Tasks

Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel

Report to INFRASTRUCTURE SERVICES Committee for noting

Best-Value Procurement Manual. MnDOT Office of Construction and Innovative Contracting (OCIC)

Appendix 18 NEC3 Options

RFP GUIDELINES REQUEST FOR PROPOSALS FOR RELOCATION MANGEMENT AND GLOBAL MOBILITY SERVICES

4.3 Project Construction

6.0 Procurement procedure 1 Infrastructure

On-Call Management and Economic Development Consulting Services RFP (Project #2664) Questions and Answers Summary

DGS (VCCS Rev. 04/15) Page 1 of 7 REQUEST FOR PROPOSALS

N O T I C E REQUEST FOR STATEMENT OF QUALIFICATIONS RFQ# POLICE DEPARTMENT PARKING GARAGE

GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES

PROPRIETARY MEETINGS. Are they legal in Washington? Robynne Thaxton Parkinson, J.D, DBIA

Open House Public Meeting for the Thurmond Bridge Rehabilitation Project State Project: State Project S310-25/ Federal Project: BR-0252(001)D

GUIDELINES FOR THE ENGAGEMENT OF EXTERNAL CONSULTANTS/PROFESSIONAL SERVICES AT MEMORIAL UNIVERSITY

Aging sewer pipes buried in the Bow River bed, from the foot of Muskrat Street to Glen Avenue must be replaced A raised crossing pipes crossing over

Moving Home Guide. A simple step by step guide to buying & selling

How B2B Customer Self-Service Impacts the Customer and Your Bottom Line. zedsuite

The unit costs are based on the trend line of the 3 low bids for the average quantity.

KOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER

Hands-on Sessions Each attendee will use a computer to walk-through training material.

Schedule Acceleration Techniques Using a CM

GIS Based Risk Analysis Simplifying the Risk Assessment Process

Project Management Manual for Design and Construction Projects. (Revised August 2010)

Business Case. Ottawa Public Library Main Library Facility May 2015

TOWN OF FORT MYERS BEACH CAPITAL IMPROVEMENT PLAN DRAFT BUDGET

GUIDEBOOK MICROSOFT DYNAMICS SL

ATTACHMENT A. Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects

Transcription:

Winona Bridge Work Package #5 Bridge No. 5900 (Existing Bridge) Rehabilitation and Reconstruction Installment #4 Construction Manager General Contractor (CMGC) and Work Package #5 Cost Estimating March 13, 2016 As regular readers of our Winona Bridge Work Package #5 updates know, the Winona Bridge project is the Minnesota Department of Transportation s first use of the CMGC (Construction Manager General Contractor) procurement methodology (see the CMGC infographic in Appendix A). We ve discussed the two primary reasons for selecting CMGC: 1. To build the new bridge as fast as possible, and 2. To gain an early understanding of the existing bridge through-truss rehabilitation costs and risks. But how is CMGC beneficial in these areas and how does it work? Let s go behind the scenes to address these questions. Basically, within CMGC, MnDOT hires a contracting team to work with us during the design phase to better understand costs, construction schedules, construction risks, and to prepare a more contractor friendly set of design plans and specifications (contract documents). That same contracting team, in this case Ames Construction, is the only contractor bidding the work or work packages. They are competing against one or more independent estimates to ensure MnDOT is receiving a fair market value from the CMGC contractor s bid. Work Package #5: MnDOT, Final Design and Ames team meeting to discuss through-truss risks

The construction of the new bridge and through-truss rehabilitation work fit the criteria regarding potential benefits of using the CMGC procurement methodology in several areas, including 1 : When there are aggressive scheduling constraints. When there is Construction work that is high risk. When the Design and/or Construction work are highly complex. When there is Construction work that requires complex staging. When early knowledge of costs is necessary. When the ability to bid early work packages is necessary. When the current Project Management team was assigned to the project in May 2013, the letting date of the project was March of 2015, but the overall project was behind schedule and the delivery of the right-of-way parcels was viewed as the cause of the delay. The project was planned to be one overall single bid package (contract) using our traditional design-bid-build methodology. If the project had met this March 2015 letting and the low bidding contractor awarded the project, which may have been highly unlikely, the new bridge would have been opened to traffic by the end of 2017 or later, a full one calendar year later than the current path. The Winona Bridge team needed to simultaneously work quickly on the new bridge and build the CMGC program from the ground up as MnDOT did not have any internal CMGC processes or procedures when CMGC was selected for the Winona Bridge project. New Bridge No. 85851 progress 1 NCHRP Project 10-85 A Guidebook for use of Construction Manager /General Contractor (CMGC) Contracting for Highway Projects (Page 4). 2 P age

Goal #1 Open the New Bridge as Fast as Possible Our team knew the only way to accelerate the construction of the new bridge was to break the construction into separate work packages (contracts) and schedule the right-of-way delivery so it was not delaying the overall project. We accomplished this by breaking up the new bridge construction into four (4) work packages and starting construction on the new bridge as follows: Work Package #1 Procurement of river pier piling. Anticipated 12-14 weeks to get the new piling to the project site. Letting Date: May 1, 2014. Work Package #2 Temporary contractor access facilities. Letting Date: May 15, 2014. Work Package #3 Construct non-land piers for new bridge. This removed the land piers from the contract as right-of-way was needed for them. Letting Date: July 30, 2014. Work Package #4 Complete new bridge, including necessary roadway work. Letting Date: February 18, 2015. Start of New Bridge construction in July 2014 Latsch Island tree clearing Work Packages #1 and #2 were fully funded with state funds to streamline the review and approval processing. The right-of-way acquisitions were needed for Work Package #4 and this approach gave approximately one full calendar year for the property owners to consider the offers from MnDOT before we needed possession of the properties. This was important to 3 P age

Winona leaders to maximize the timeline and potential for re-development within the community. While these four (4) work packages may have been able to be delivered using our traditional design-bid-build or the design-build procurement methodologies, coordination would have been very challenging. Additionally, it s important to note that while using the CMGC approach is partially to thank for our ability to stay on schedule to open the new bridge by the end of 2016, it also taken extraordinary efforts from Ames Construction and the project team. Bridge No. 85851 scheduled to be opened in fall 2016 Goal #2 Understand Existing Bridge Through-Truss Costs and Risks Earlier The second primary reason for utilizing the CMGC procurement methodology was based on concerns from the project management team regarding the rehabilitation and reconstruction of the through-truss of the existing bridge. As was previously mentioned, projects with similar scopes of work had historically cost considerably more than planned. The rehabilitation of the through-truss within a historical context was viewed as a significant challenge, if not the biggest challenge on the project. 4 P age Bridge No. 5900 Through-Truss

Specifically, with the through-truss, we have been able to explore the challenges and risks with the Ames Construction team with numerous field reviews and mock-up trials. In fact, our team has created a complete node mock-up and mock-ups of the intricate steel plating work that is proposed. Bridge No. 5900 field steel plate strengthening mock-ups Bridge No. 5900 field steel plate strengthening and complete node mock-ups These efforts resulted in several important enhancements in the scope of work to make things more efficient for the contractor and reduce costs and risks. These enhancements included: 5 P age Length of Bottom Chord Steel plating and splicing. The Final Design included 75-foot steel splice plates that would be difficult for the Ames team to handle in the field. Based on feedback from the CMGC team, splices will now be allowed in these plates, saving an approximate $100,000 in costs. Paint System specifications. Based on the complex staging for the through-truss work, after abrasive blasting, the prime paint coat will be on the bridge for an extended period of time. The risk is the extent of prime coat preparation to continue painting operations in later phases of the project. Revisions to the MnDOT standard painting specifications

accommodated this complex staging and saved an approximate $300,000 in costs. CMGC team feedback resulted in not having to replace existing bridge piers #21 and #23 in the river, as well as the north abutment. The cost savings for this is approximately $1.25 million. CMGC team feedback led to the use of MnDOT owned glu-laminated deck panels for the through-truss rehabilitation. The cost savings for this is approximately $300,000. The CMGC team found a way to build the Latsch Island deck truss approach spans without river equipment (barges) onsite. The cost savings for this is approximately $1 million. As a means to try and reduce cost growth on the through-truss during construction, the Final Design team reviewed the recommended strengthening work at each node of the through-truss and provided the CMGC team with criteria on maximum section loss of steel before the Engineer of Record needs to be contacted. This ensures the field team is as efficient as possible in making the important decisions as the work progresses. Even though the estimated construction costs are projected to be $20 million over budget, so far during the cost estimating phases on Work Package #5, the CMGC team has reduced the costs between $4-$5 million on this work package and approximately $10 million over all the work packages. So let s now explore how the cost estimating process works. The CMGC Cost Estimating Process: The cost estimating process in CMGC is vastly different from traditional design-bid-build. A small team of MnDOT staff is able to meet with the contractor and see all their estimated costs, including direct labor, materials and equipment rates, and all indirects. The contractor is expected to open their books to the owner. Besides the contractor s estimating team for Ames Construction on the project, MnDOT has employed an Independent Cost Estimator (ICE), Armeni Consulting Services, and an Owner s Design Estimate consultant, Stanley Consulting. Both of the estimating consultants, working on behalf of MnDOT, report to the MnDOT Estimating Office and not to the Winona Bridge Project Management team. Each consultant was selected based on their experience and expertise in estimating projects similar to the Winona Bridge project. All estimators have the ability to ask the CMGC contractor or the Final Design team clarification questions to ensure a comprehensive understanding of the scope of work and intent of the contract. Quantities, productivity rates, plans and special provisions and all contract requirements are discussed. What if scenarios can be and were considered from a cost perspective. 6 P age

Winona Bridge Estimating Team during a field site visit. On the Winona Bridge project, preliminary cost estimates have typically been performed at the 30%, 60% and 90% Final Design level, in advance of the bidding phase. This means that after the designs were 30% complete for example, they were provided to the estimators to price and estimate the cost. After the cost estimate pricing is received from the estimating teams, a variance report is developed and shared with the team to assist with efforts to reconcile any significant pricing differences. The contractor s pricing, along with the Owner s Design Engineers pricing was included with only the variance to the ICE pricing. During the bidding phase, the goal is to have the CMGC contractor s pricing be within 10% of the Independent Cost Estimator (ICE) and have it validated by the Owner s Estimate prior to award. All work packages on the Winona Bridge Project so far have been within 10% of the ICE. MnDOT s first CMGC variance report is shown in Appendix A. These efforts provide much earlier insight into the actual cost for the construction contract and allow the team to look at items that may be driving up the cost due to risk or complexity. Innovative ideas and other potential cost cutting ideas are generated as well. So, for the Winona Bridge work package #5, these efforts have allowed MnDOT to: Have a much earlier understanding of the Work Package #5 costs for rehabilitation and reconstruction of the existing bridge. Have a much higher confidence level in knowing where the actual bid pricing will be at in terms of cost. Potentially reduce cost growth after letting on Work Package #5 as all the contractors means and methods have been discussed and incorporated into the plans and specifications. 7 P age

8 P age Appendix A CMGC Infographic MnDOT s First Variance Report

Benefits of the Construction Manager/General Contractor (CMGC) Delivery Method What is CMGC? In the CMGC process the project owner hires a contractor to provide feedback during the design phase before the start of construction. It s an alternative contracting method to Design-Bid-Build or Design-Build. The 2013 2019 Winona Bridge project is MnDOT s first CMGC project DESIGNER Contractor The CMGC method is also called Construction Manager at Risk (CMR). CMGC is relatively new to the transportation industry. 2014: The Winona Bridge project was MnDOT s 1st CMGC project. CMGC is one of The Federal Highway Administration s Every Day Counts (EDC) initiatives being furthered as an accelerated project delivery method. The EDC initiative is designed to identify and deploy innovation aimed at reducing the time it takes to deliver highway projects, enhance safety, and protect the environment. 2How does it work? The CMGC process is broken down into 2 contract phases: In the 1st contract phase, the design phase, the contractor works with the designer and the project owner to identify risks, provide cost projections, and refine the project schedule. Then, the contractor and project owner negotiate on the price for the construction contract. If all parties are in agreement with costs, then the 2nd contract phase, the construction phase, is kicked off and construction begins. PHASES Why CMGC instead of a traditional delivery method? CMGC helps save time in 4 primary areas: Can begin the project earlier Design takes less time Construction takes less time Overlapping design and construction reduces project time independent cost estimator (ICE) In the CMGC bid process, an independent cost estimator (ICE) separately estimates the costs for different parts of the construction, to compare with the bid the CMGC submits. The CMGC s bid must be within 10% of the independent cost estimator in order to be accepted. BENEFITS What are the benefits of CMGC? Fosters Innovation Allows Flexibility Improves Cost Control and Cost Certainty Fewer Change Orders and Overruns Higher Design Quality Rreduces Risk Ooptimizes Schedules Enhances Collaboration Upfront Value Engineering Improves constructability (The design only includes features that can be built.) TRADITIONAL DESIGN BUILD CMGC DESIGN DESIGN RFQ RFP DESIGN SELECT RFP ADVERTISE/BID SELECT SELECT CONSTRUCTION CONSTRUCTION EARLY CONSTRUCTION CONSTRUCTION CMGC Impacts on the Winona Bridge Project Rreduced the complexity of dealing with multiple contractors aided in Winona community involvement Mmakes renovation of the adjacent historic bridge more predictable Aallowed earlier engagement of the historical team Reduced risks Ames Construction is the Winona Bridge CMGC Contractor Also the general contractor on the nearby Dresbach Interchange project (shown). Outstanding safety record. History of quality bridge projects, on-time delivery, and professionalism.

Cost Comparison Analysis S.P. 8503-46, Work Package 1 (Pile Procurement) Submission Date: April 9, 2014 Estimate No. 1 Contractor Bid Owner's Contractor/I Contractor/ Item No. Description Unit Qty W/O OH & Profit Estimate CE Owner 2104.601 Haul Structural Steel Lump Sum 1 $150,000.00 $150,000.00 Within 10% 100% 2452.507 CIP Concrete Piling Delivered LF 8762 $1,999,926.50 $1,999,751.26 Within 10% 100% Subtotal W/O Fixed Markup % 2,149,926.50 2,149,751.26 Within 10% 100% Total with Fixed Markup % $2,407,917.68 $2,407,721.41 Within 10% 100%