CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE Updated 29 May 2009



Similar documents
Virginia Approach Spans

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

Safe & Sound Bridge Terminology

Source: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009.

Guide to the Jamey Stillings Photographs of the Mike O Callaghan-Pat Tillman Memorial Bridge and the Hoover Dam

Introduction to Architecture. Lesson 13: Hoover Dam

FLAT ROOF BOX SPAN CARPORTS

Dulles Corridor Metrorail Project

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway:

INSTALLATION. General. Important Note. Design. Transport

Prestressed Concrete I-Beam and TxGirder Haunch Design Guide

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

Overhang Bracket Loading. Deck Issues: Design Perspective

Design of Bridges. Introduction. 3 rd to 4 th July Lecture for SPIN Training at the University of Dar es Salaam

COLUMN-FREE OFFICE SPACE RISES IN CHICAGO S LOOP

J. David Rogers Natural Hazards Mitigation Center University of Missouri-Rolla

Statics of Structural Supports

U.S. Department of Labor Occupational Safety and Health Administration Directorate of Construction. April 2015

Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.

MANUFACTURED HOME INSTALLATION FOR PERMANENT FOUNDATIONS (TRANSVERSE FLOORS) (SUPPLEMENT TO MANUFACTURED HOME INSTALLATION MANUAL)

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE

KOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER

Instruction Manual 19/9/01. Flat Roof Carport

IH-635 MANAGED LANES PROJECT, SEG. 3.2

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Project Report. Structural Investigations Hotel del Sol Yuma, Arizona

Pro-Lift Steel Pile Foundation Repair

Type of Force 1 Axial (tension / compression) Shear. 3 Bending 4 Torsion 5 Images 6 Symbol (+ -)

REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE MAULE EARTHQUAKE

Index Series Prestressed Florida-I Beams (Rev. 07/12)

Coyote popup features

Managing North Carolina's MSE Wall Assets through Design, Construction and Performance

Case Study: Milwaukee Art Museum. ARCH 631: Structural Systems Prof. Anne Nichols Aaron M. Vorwerk

CITY OF TRAIL MEMORANDUM

Numerical Analysis of the Moving Formwork Bracket Stress during Construction of a Curved Continuous Box Girder Bridge with Variable Width

Coyote popup features

Drexel-SDP GK-12 ACTIVITY

Historic Bridges of Frederick County. Frederick County, Maryland Division of Public Works Department of Highways and Transportation (301)

How To Repair A House

Coyote popup features

Söderströmtunnel: immersion in downtown Stockholm, Sweden

Since it was established in 1989, with a small manufacturing base in Qwa Qwa and a hire yard in Botswana, Uni-Span

The minimum reinforcement for the stem wall is the placement of:

11 Guardrail. W-Beam Guardrail Pre-Installation Inspection During Installation Basis for Use. Modified Guardrail. End Treatments and Transitions

Buildings Construction Procurement Strategy

L_All_Vocatinal_Ed_Construction. Sector: Construction. Sr. No Specialisation Page No 1 Construction and Building Technology 02.

US 51 Ohio River Bridge Engineering and Environmental Study

INSTALLATION INSTRUCTIONS COMPETITION SERIES COILOVER SUSPENSION SYSTEM 03+ Scion xb

INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE.

RHODE ISLAND TURNPIKE AND BRIDGE AUTHORITY NEWPORT/PELL BRIDGE APRIL 1, 2014 TEN YEAR RENEWAL AND REPLACEMENT PLAN (IN 2013 DOLLARS)

ABSTRACT 1. INTRODUCTION 2. DESCRIPTION OF THE SEGMENTAL BEAM

WorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

Chaudière Crossing Bridge Rehabilitation

San Francisco Oakland Bay Bridge East Span Seismic Safety Project

Structural Performance of Highway Bridges under Given Foundation Settlements

Universal Installation and Maintenance Instructions Double Wall Spill Containment Bucket (5 and 15 gal)

8/18/14. Introduction to. Framing. Terminology and Concepts

PRESTRESSED CONCRETE. Introduction REINFORCED CONCRETE CHAPTER SPRING Reinforced Concrete Design. Fifth Edition. By Dr. Ibrahim.

Evaluating. A Case Study

Fabrication, Delivery and Installation

San Francisco Oakland Bay Bridge SELF-ANCHORED SUSPENSION (SAS) SPAN

NUMERICAL ANALYSIS OF A HORIZONTALLY CURVED BRIDGE MODEL

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

Analysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico

DESIGN OF PRESTRESSED BARRIER CABLE SYSTEMS

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

Fiberstars Mini Lighted Laminar Flow Fountains

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA

FLAT ROOF CARPORT RECOMMENDED INSTRUCTION MANUAL

Project Information. New Hope - Lambertville Toll Bridge - Pavement Rehabilitation & Approach Bridges Repairs -

Emergency repair of Bridge B421

1,045 m length of the Deh Cho Bridge

REHABILITATION PACKAGE 1-a

The unit costs are based on the trend line of the 3 low bids for the average quantity.

FORM DESIGN. easy to work with, and generally available.

Sewing Methods Chicago Style Stitch

Truss. are both simple and A Matsuo Example continuous trusses. The

Installation Instructions

EFFECTS ON NUMBER OF CABLES FOR MODAL ANALYSIS OF CABLE-STAYED BRIDGES

Beam bridges are the oldest known bridges and tend to be the simplest to design and build. Roughly half of all bridges

LEGACY REPORT ER ICC Evaluation Service, Inc. Reissued November 1, Legacy report on the 1997 Uniform Building Code

College of Computing, Engineering & Construction Building Construction Management Course Descriptions

Beam Load Ratings. Tandem Flatbed Trailers. M-52 (52K - 48 Tandem) 52,000# - 4 span 55,000# - 10 span 60,000# - 20 span 90,000# - 48 span

The Stabilizer TM. Benefits. Supplemental support system for sagging beams and floor joists within a crawl space

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

Optimum proportions for the design of suspension bridge

CAPPELEN MEMORIAL BRIDGE REHABILITATION

Granger Bay Boulevard and Green Point Roundabout

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

Coyote popup features

MAT 75 STRUCTURAL SUPPORT SYSTEM

Handling, Erection and Bracing of Wood Trusses

Transcription:

CONSTRUCTION OF THE HOOVER DAM BYPASS BRIDGE Updated 29 May 2009 www.maximumreach.com 1,600 FT. SOUTH OF THE DAM 900 FT. ABOVE WATER 2000 FT. LONG COMPLETION DATE: November 2010

Artists conception of the bypass bridge in the foreground Pier 5 Pier 14

Pier 5 Pier 14 BRIDGE DETAILS LOOKING NORTH

13' high x 20' wide x 1' walls

The erection of the twin cableways was completed last year (2008). This made it possible to finish setting the beams from each abutment, pouring the decks out to piers 5 and 14 and completing the construction of the temporary towers. Now the thrust is to complete construction of the twin arches. The twin arches will be poured in 21' - 25' segments utilizing the green traveling forms. Five segments were poured before forestay lines were attached for support. Once the sixth arch segments were poured, forestay lines were connected between them and the top of the temporary towers. At the same time backstay lines were connected from the top of the temporary towers back down across each abutment to deadmen. CONSTRUCTION OF THE TWIN ARCHES

This will be repeated for every other newly poured arch segments. Simultaneous tightening up the forestay lines and backstay lines with the correct tension will keep the temporary support towers approximately plumb. The temporary support towers are supported on bearings so the lean is not critical. The forestay and backstay lines will be tightened up utilizing strand jacks. The jacks will be sized for the maximum tension in the forestay or backstay lines. The appropriate number of strands will be used in each jack to develop the safe working load required. The jacks for the forestay lines will probably be located at the top of the temporary towers, while the jacks for the backstay lines will probably be at the deadmen. See slide numbers 12, 13 & 14 for information on strand jacks.

Slide No. 11 graphically shows the temporary towers on piers 5 and 14 with backstay and forestay lines attached. The green forms are traveling forms, not slip forms, ie, the forms are expanded/contracted as required after each arch segment is poured and the green forms are traveled up the already poured arch segments, reset and the next arch segment poured, etc. Each concrete arch cross section is 20' wide x 13' high with 1' walls. That is why the outer section of the green traveling forms must be expanded and the inter section must be contracted. There is no adjustment for the camber or sideways alignment of the arches after they have been poured.

As the green traveling forms are being set for each segment of arch to be poured, adjustments to the curvature, side alignment, etc, must be made at that time. If the arches sag a little after that segment has been poured and cured, then the curvature must again be adjusted when the forms are set the next time. The arches will not have a smooth radial curvature from bottom to top, but will be a series of short straight cord lines. Hopefully, when the four arches meet at the middle of the span, there will be enough adjustment in the green traveling forms for them to all meet together to form the capstones.

Notice that slide 17 shows the X-bracing being installed between the arches at the 6 th and 12 th segments on the Nevada side. The X-bracing will also be installed at the 18 th and the top of the arches. Slide 23 shows the same thing for the Arizona side.

Once arch construction is complete, the backstay lines, forestay lines and the temporary towers can be removed. After the temporary towers have been removed, piers 6 through 13 can be completed. These piers are located on the arches. The bridge beams can be placed and then the remaining deck poured. At this point, the need for the cableways is at an end and they can also be removed. This time in a preplanned operation.

Nevada Side Strand Jacks Arizona Side Note the 150' temporary towers located over the inboard columns

PSC Strand Jacks May Not Be The Brand Used, But Theirs Are Similar To Most Strand Jacks

Overall view of the twin cableways and the bypass bridge at Hoover Dam. Note the 150' temporary towers are in place over piers 14 & 5 (pier 5 is on the Nevada side). View is to the south and Nevada is on the right side.

Looking South at the Nevada Side of the bridge

Note steel X-Bracing installed between arches at segments 6 & 12. Steel X-Bracing is in the process of being installed between the 18 th segments. Note the work platform is already installed.

Top forestay lines hooked to the 20 th segments

Preparing to pour the 21 st segments. There are 26 segments on each side of the twin arches with the capstone segments in between at the top.

Note forestay lines going to the 20 th, 18 th, 16 th, 14 th, 12 th, 10 th, 8 th & 6 th segments (L to R). Green traveler forms are being positioned for pouring the 21st segments.

Looking south at the Arizona side of the bridge.

FINÉ