Tips to Reduce Chilled Water Plant Costs



Similar documents
TES for Medical Center

By Steven C. Severini, P.E., Member ASHRAE

Second Place: Industrial Facilities or Processes, New

Data Realty Colocation Data Center Ignition Park, South Bend, IN. Owner: Data Realty Engineer: ESD Architect: BSA LifeStructures

Commissioning - Construction Documents (Page 1 of 6)

Enclosed Football Stadium Design History and Lessons Learned

VARIABLE VOLUME / VARIABLE SPEED SYSTEMS APPLICATIONS

Optimizing Design & Control Of Chilled Water Plants Part 5: Optimized Control Sequences

Denver International Airport Total Facility Optimization. Josh Foerschler Aurom Mahobian

COMMERCIAL HVAC CHILLER EQUIPMENT. Air-Cooled Chillers

Applying Pressure Independent Control Valves in H.V.A.C. Systems. A Presentation to: Orange Empire ASHRAE Santa Ana Nov. 17, 2009

Chilled Water System Commissioning: Variable Primary Flow. John D. Villani, P.E. Associate Grumman/Butkus Associates

CHILLED WATER PLANT PUMPING SCHEMES. James J. Nonnenmann, PE Stanley Consultants, Inc. Muscatine, Iowa

CHILLER PLANT CONTROL MULTIPLE CHILLER CONTROLS

See any red flags? Let s take a look at the problems that occurred on the job and how to avoid making the same mistakes.

OPTIMIZING CONDENSER WATER FLOW RATES. W. A. Liegois, P.E. Stanley Consultants, Inc. Muscatine, Iowa

Example Retrocommissioning Measure: Opening Throttled Discharge Valves

NYC Department of Education Building Condition Assessment Survey BROADWAY EDUCATION CAMPUS - MANHATTAN, 26 BROADWAY, MANHATTAN, NY, 10004

Heating, ventilation and air conditioning equipment. A guide to equipment eligible for Enhanced Capital Allowances

CGC s Hybrid System Loop Control

CURBING THE COST OF DATA CENTER COOLING. Charles B. Kensky, PE, LEED AP BD+C, CEA Executive Vice President Bala Consulting Engineers

Secondary Loop Chilled Water In Super High-Rise

Digital Realty Data Center Solutions Digital Chicago Datacampus Franklin Park, Illinois Owner: Digital Realty Trust Engineer of Record: ESD Architect

Heating, ventilation and air conditioning (HVAC) equipment. A guide to equipment eligible for Enhanced Capital Allowances

Heating, Ventilation, Air Conditioning and Refrigeration (HVACR)

Subtropical Cities September Design for Energy Efficiency in Commercial Buildings in Queensland

Overview. Introduction Cooling Tower Basics Principles of Operation Types of Cooling Towers Common Applications Design Considerations

HIGH PERFORMANCE CHILLED WATER SYSTEMS. EarthWise HVAC. EarthWise HVAC High Performance CHW Plants

RULES FOR THE SETTING UP OF SUSTAINABLE BRANCHES Summary

DIABLO VALLEY COLLEGE CATALOG

In the compression-refrigeration loop (air conditioning), which is likely to be warmer? 1. Condenser coil 2. Evaporator coil

The main steam enters the building in the basement mechanical room; this is where the condensate line also leaves the building.

Hot Water Boilers and Controls Why Condensing Boilers are Different. Presented Oct. 14, 2008 Long Island Chapter, ASHRAE

Wet Bulb Temperature and Its Impact on Building Performance

COOLING WATER MANAGEMENT


Presentation Outline. Common Terms / Concepts HVAC Building Blocks. Links. Plant Level Building Blocks. Air Distribution Building Blocks

Heat Recovery In Retail Refrigeration

A discussion of condensate removal systems for clarifier and thickener drives for water and wastewater facilities.

How Ground/Water Source Heat Pumps Work

Data Center Precision Cooling: The Need For A Higher Level Of Service Expertise. A White Paper from the Experts in Business-Critical Continuity

HVAC Processes. Lecture 7

Statement of Work. 3.0 Details of Service Pre Start-up Cooling Start-up Service. Installation Service. Table of Contents. 1.0 Executive Summary

Building Performance With District Cooling

Ammonia Detection System Codes and Design Specifications

Design guidelines for hybrid boiler systems.

EVERYTHING YOU WANTED TO KNOW ABOUT GLYCOL A Brewery Glycol System Guide. Updated

Flexibility, Efficiency In San Antonio Arena

Chilled Water Plant Design

UNIVERSITY OF MISSOURI Heating Ventilating and Air-Conditioning (HVAC) March

Sample - Existing Building Commissioning Plan

HVAC Preventative Maintenance Basics. Presented by Mike Crawley

2 STEPS TO CONDUCTING YOUR HVAC ASSESSMENT

Ener.co & Viridian Energy & Env. Using Data Loggers to Improve Chilled Water Plant Efficiency. Randy Mead, C.E.M, CMVP

KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM

Creating Efficient HVAC Systems

Mechanical, Plumbing, and Fire Protection Conditions

Chilled Water HVAC Systems

Water Fired Chiller/Chiller-Heater. WFC-S Series: 10, 20 and 30 RT Cooling

Verizon SMARTS Data Center Design Phase 1 Conceptual Study Report Ms. Leah Zabarenko Verizon Business 2606A Carsins Run Road Aberdeen, MD 21001

Venice Library Humidity Study. for Williams Building Diagnostics, LLC th Street West Bradenton, FL Report April 13, 2015

Maximize energy savings Increase life of cooling equipment More reliable for extreme cold weather conditions There are disadvantages

Nordic Heat Pump Product Guide

HEATING, VENTILATION & AIR CONDITIONING

Data Centers. Data Center Commissioning

VertiCool Space Saver 2 to 15 tons Water-Cooled and Chilled Water

Federal Wage System Job Grading Standards for Air Conditioning Equipment Operating, Table of Contents

The Data Center Dilemma - A Case Study

*At the AHRI Standard flow rate of 3 gpm/ton, using today s efficient chillers, the ΔT is 9.3 F rather than the 10 F often assumed.

Blade Server & Data Room Cooling Specialists

Modeling and Simulation of HVAC Faulty Operations and Performance Degradation due to Maintenance Issues

HOW TO CONDUCT ENERGY SAVINGS ANALYSIS IN A FACILITY VALUE ENGINEERING STUDY

CODE ON PERIODIC ENERGY AUDIT OF BUILDING COOLING SYSTEM. 1 st Edition. 1 P a g e

Defining Quality. Building Comfort. Heating and Cooling Coils

Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+)

HYDRONIC DESIGNER / INSTALLER MODULE DESCRIPTIONS

HOT WATER SYSTEMS CONTENTS

Dr. Michael K. West, PE 1 Dr. Richard S. Combes, PE 2 Advantek Consulting / Melbourne, Florida

Indoor coil is too warm in cooling mode or too cold in heating mode. Reversing valve or coil thermistor is faulty

INSTALLATION MANUAL. Address card EKAC10B

ENERGY SAVING STUDY IN A HOTEL HVAC SYSTEM

Collaborative Laboratory Commissioning and Sustaining the Optimal Building. By E. Lon Brightbill, P.E Facility Dynamics

The Chilled Water and Hot Water Building Deferential Pressure Setpoint Calculation Chilled Water and Hot Water Pump Speed Control

ENHANCED LABORATORY HVAC SYSTEM

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.

NEW JERSEY CENTER OF EXCELLENCE

Facilities Maintenance Standards rev

THERMO KING TRUCK & TRAILER UNIT ALARM CODES THIS DOCUMENT SHOWS ALL CURRENT ALARM CODES FOR THERMO KING TRUCK AND TRAILER UNITS.

AIR-CONDITIONERS CONDENSATE RECOVERY SYSTEM FOR BUILDINGS

Principals of Condensing Boiler System Design

PAYGO for Data Center -- Modular Infrastructure

How To Improve Energy Efficiency Through Raising Inlet Temperatures

Data Center Design Guide featuring Water-Side Economizer Solutions. with Dynamic Economizer Cooling

The Different Types of Air Conditioning Equipment for IT Environments

Fundamentals of HVAC Control Systems

ORC TURBOGENERATOR TYPE CHP - Organic Rankine Cycle Turbogenerator fed by thermal oil, for the combined production of electric energy and heat -

ELECTRIC/DIESEL FIRE PUMP CHECK LIST

IDEA Presentation SMALL CAMPUS CHILLED WATER PLANT OPTIMIZATION.

HVAC Checklist - Long Form

Transcription:

This article was published in ASHRAE Journal, October 2013. Copyright 2013 ASHRAE. Posted at www.ashrae.org. This article may not be copied and/or distributed electronically or in paper form without permission of ASHRAE. For more information about ASHRAE Journal, visit www.ashrae.org. Tips to Reduce Chilled Water Plant Costs Steven T. Taylor BY STEVEN T. TAYLOR, P.E., FELLOW ASHRAE A chilled water plant can be conceptually well designed but implemented in a manner that unnecessarily increases first costs, sometimes substantially. Here are a few tips to reduce the first costs of a chilled water plant without reducing performance. Tip 1: Piping and Pumps Figure 1 shows a chilled water plant with primary-only pumping. Conceptually the design is fine, and in fact the primary-only design is a good step in reducing plant costs since it is less expensive than primary-secondary pumping. 1 But the designer of this plant unnecessarily increased first costs. First, reverse return piping was provided for both condenser water and chilled water systems. Reverse return, where the first device supplied is the last returned, is a piping scheme intended to self-balance hydronic systems, but more importantly, to keep the pressure drop across modulating two-way control valves relatively low and equal among all valves as they open and close with changing loads. It can be an effective technique to improving controllability of large (high pressure drop) variable flow hydronic distribution systems. 2 But in this case, the valves at each chiller are essentially two-position and the difference in pressure across each valve is very small even if the system is directreturn (first supplied, first returned) and was not manually balanced. A balanced direct-return piping system will result in the same flow rates across each chiller as the reverse-return design regardless how many chillers were enabled. So there is absolutely no value in performance to reverse-return in this application, yet it substantially increases first costs. Another often expensive design concept is to gang pumps together and pipe all the pumps first to a larger common pipe before distributing the supply water to the chillers. In this example, the common pipe size is 12 in. (nominal 300 mm) on the chilled water side and 14 in. (nominal 350 mm) on the condenser water side. It is not uncommon to see all the pumps squished into a corner of the chiller room. There is little synergy to ganging pumps next to each other yet doing so can increase first costs and reduce space around the pumps for maintenance. Figure 2 shows the same plant as Figure 1 but instead of reverse-return and ganged pumps, the pumps are aligned with chillers and are piped into a common header on the discharge side of the pump and also on the discharge side of the condensers. (The discharge side of the evaporators is the same as that in Figure 1.) This design still allows any pump to serve any chiller, but it shortens piping runs and it reduces pipe sizes because there is no common pipe that sees the total system flow. On the condenser water side, all pipes are 10 in. (nominal 250 mm) the 14 in. (nominal 350 mm) common pipe is eliminated. Similarly, the 12 in. (nominal 300 mm) chilled water piping at the discharge of the pump to the evaporators is eliminated; all pipes are 8 in. (nominal 200 mm). First costs are substantially reduced with no impact on performance. This layout also usually reduces the footprint of the plant, reducing the floor area required for the chiller room. In fact, locating the equipment as close together as possible is key to the first cost savings. Figure 3 shows a floor plan of the plant shown schematically in Figure 2. The chilled and condenser Steven T. Taylor, P.E., is a principal of Taylor Engineering in Alameda, Calif. He is a member of SSPC 90.1 and chair of TC 4.3, Ventilation Requirements and Infiltration. 48 ASHRAE JOURNAL ashrae.org OCTOBER 2013

Advertisement formerly in this space.

Advertisement formerly in this space.

water pumps align with the chillers but are offset to provide tubepull space and piping connections between the pumps. This is a very compact layout but it still provides adequate maintenance access for all equipment. FIGURE 1 Expensive chilled water plant. 14 in. CWS Tip 2: Cooling Tower Makeup And Level Control Typically, makeup water to cooling towers is provided by domestic or industrial water piped to a float valve in each tower basin. Float valves, which are similar to those in tank-type toilets, are not very reliable they tend to get stuck open and leak. An alternative is to install an electronic level switch in each tower basin wired to an electric slow-closing solenoid makeup water valve. Another novel makeup water system design is summarized as follows: No makeup water connection or assembly is provided with the cooling towers. The cooling tower equalizers are fitted with shutoff valves at each cell and a standpipe is installed in the common equalizer pipe as shown in Figure 4. The standpipe is open at the top and is fitted with an analog level sensor, such as a conductivity type, silicone diaphragm type, or sonar type. This is tied to the building energy management and control system (EMCS). The level of water in the standpipe is the same as the cooling tower basins for any basin open to the equalizer. A basin that is valved off and drained, e.g., for cleaning, has no impact on the level sensor reading. Makeup water is piped through a slow-closing valve to the condenser water system in either the supply or return piping to the tower it does not matter which, provided the makeup water pressure is higher than that in the piping and there are no automatic valves or check valves between the connection point and the towers. Typically, the connection will be indoors near the chillers. The valve is wired to the EMCS. Chiller 1 Chiller 2 Chiller 3 8 in. 8 in. 8 in. 14 in. CWS Cooling Cooling Cooling Tower 1 Tower 2 Tower 3 12 in. 14 in. CWS Flow Meter 12 in. 6 in. 8 in. 8 in. 8 in. Min. Flow Bypass FIGURE 2 Less expensive chilled water plant. Cooling Cooling Cooling Tower 1 Tower 2 Tower 3 10 in. 10 in. 10 in. 10 in. Chiller 1 Chiller 2 Chiller 3 8 in. 8 in. 8 in. 8 in. 8 in. 8 in. 8 in. 8 in. Flow Meter 6 in. Min. Flow Bypass 12 in. CHWS 12 in. CHWR 12 in. CHWS 12 in. CHWR OCTOBER 2013 ashrae.org ASHRAE JOURNAL 51

FIGURE 3 Chilled water plant floor plan. The level sensor is programmed in the EMCS to open the makeup water valve as required to maintain the tower basin water level within the tower manufacturer s recommended range whenever the condenser water pumps are on. It can also be programmed to provide high and low level alarms. The advantages of this design include: Makeup water piping need not be piped to each cell and generally need not be piped outdoors. This is a particular advantage in freezing climates since it obviates the need for heat tracing and insulating the makeup water piping. The analog sensor provides control as well as high and low level alarms with setpoints easily adjusted in software. False alarms are virtually eliminated; when level switches are provided at each cell for alarming, a false alarm is generated if the cell is drained for cleaning. Float valves are eliminated. Costs are lower than electronic makeup water controls, especially if they include high and low level alarms to the EMCS. Costs are also typically lower than float valve makeup water when the system has more than two cells and in freezing climates. FIGURE 4 Cooling tower equalizer standpipe. 2 in. Open Standpipe with Level Sensor for Makeup Water Control (Terminate 6 in. Above Basin O.F. Level) CT CT 1 2 Equalizer Tip 3: Valves Chilled water plants, within the plant itself, should have only two kinds of valves for flow isolation and balance: butterfly valves for large piping (typically 3 in. [nominal 80 mm] and larger) and ball valves for smaller piping. These are not only the least expensive types of valves, they also are the easiest to use since they require only a quarter turn to open and close (unlike globe and gate valves) and they may be used for balancing 52 ASHRAE JOURNAL ashrae.org OCTOBER 2013

(unlike gate valves). They are also physically smaller than other valve types. Valves to avoid and/or are not needed include: Globe and gate valves. They provide no advantages over butterfly and ball valves and they cost more and require more space. Calibrated balancing valves. Most plants are almost self-balancing simply because their compact size does not result in large differences in pressure drop across each evaporator or condenser. Even if no balancing is done, the plant generally will work fine a small difference in chilled water or condenser water flow among chillers and towers has only a small impact on plant performance. What little balancing is needed can be accomplished by modulating the condenser/evaporator isolation butterfly valves to cause the pressure drop across the condenser/evaporator to be the same among the chillers (or proportionally the same if chillers are not all the same). Cooling tower balancing is almost never an issue and there is no need to create equal flow to each cell; the cells with excess flow will create warmer water and the ones with low flow will create colder water, but when they are mixed, the resulting temperature is almost exactly the same as it would be if the cells had equal flow. Flow limiting valves (aka, flow control valves). These valves should never be used in the chilled water plant. There are times when exceeding design flow is actually desired. For example, a chiller plant with degrading chilled water ΔT can be more efficient if higher flow is allowed to be forced through operating chillers rather than start another. 3 Exceeding the chiller manufacturer s maximum flow rate is rarely an issue because pressure drop increases with the square of the flow and pumps seldom have the capability to force this much water through the evaporator or condenser. Multipurpose (aka, triple-duty ) valves. These valves, typically located at pump discharges, provide three functions in one: shut-off valve, check valve, and flow measurement/balance. But they are hard to use as shut-off valves since they are multi-turn rather than quarter turn and a wrench is required; they generally do not include handles. They can also be hard to repair since they cannot isolate themselves. For these two reasons, building operators generally very much dislike multipurpose duty valves. When sized the same as the pipe size, as is typical, flow measurement is often not possible; they must be undersized to provide accurate flow readings which adds to pressure drop. Flow balancing is also not needed at the pump; it can and should be done at the heat exchangers and throttling flow for balance is not required at all if the pump has a variable speed drive. Finally, cost savings versus a check and butterfly valve are minor or nonexistent. Conclusions One would think that a chilled water plant that has x chillers and pumps and provides y tons of cooling capacity would cost about the same no matter how it is ultimately designed and configured. But that is not the case; first costs can vary substantially depending on the details. Hopefully, these three tips can help designers minimize central plant first costs. References 1. Taylor, S. 2002. Primary-only vs. primary-secondary variable flow systems. ASHRAE Journal (2). 2. Taylor, S., J. Stein. 2002. Balancing variable flow hydronic systems. ASHRAE Journal (10). 3. Taylor, S. 2002. Degrading chilled water plant Delta-t: causes and mitigation. ASHRAE Transactions 108(1). Advertisement formerly in this space. OCTOBER 2013 ashrae.org ASHRAE JOURNAL 53