See any red flags? Let s take a look at the problems that occurred on the job and how to avoid making the same mistakes.
|
|
|
- Myles Allison
- 10 years ago
- Views:
Transcription
1 providing insights for today s hvac system designer Engineers Newsletter volume 43 2 Chilled-Water Systems Design Issues Learning from past mistakes As with anything in life, you can learn HVAC design the hard way, from painful and costly mistakes, or the easy way, from veteran engineers who can help you avoid those mistakes. The purpose of this EN is to help new engineers with the latter. Background The following three cases are composite scenarios of various chilledwater system design issues we have witnessed over the years. In each scenario, the design issues are highlighted and followed by possible solutions. By sharing the hard-earned HVAC design wisdom that comes from trial and error, we hope to shorten the learning curve for new engineers. Case 1: New Variable Primary Flow A new system has been designed using an increased system chilledwater temperature difference as recommended in the ASHRAE GreenGuide 1 and by Taylor 2. The chillers are selected at low design evaporator pressure drops (5 ft of head [15 kpa]) per chiller to minimize pump power and energy. To reduce installed cost and operating costs, the system is designed as variable primary flow (VPF). The bypass line (sized the same as the supply manifold) and valve that allow minimum chiller flow rate are located in the mechanical room, as are the air handlers. A differential pressure sensor across the evaporator is used to determine flow rate and to control the bypass valve.(figure 1). See any red flags? Let s take a look at the problems that occurred on the job and how to avoid making the same mistakes. Issue 1: Flow sensing device is not accurate enough at the minimum flow rate. As mentioned, the design evaporator pressure drop is 5 ft of head [15 kpa]. At the minimum flow rate of 1.2 gpm per ton [0.022 L/s per kwr], the pressure drop will be about 3 ft of head Figure 1. Case 1: New variable primary flow (VPF) 56ºF (13.3ºC) variable-speed drive () modulating control valve for minimum chiller flow 40ºF (4.4ºC) [9.0 kpa]. Even if the differential pressure sensor is of high quality, it will be difficult to select one that has the required precision to accurately measure such a small difference between design flow and minimum flow pressure drops. Solution 1: Select the proper flow sensing technology. Flow meters are generally more expensive, require more calibration, and must be installed per the manufacturer's requirements with a specific amount of straight piping up- and downstream. Despite these limitations, they're better suited to monitor flow for this system. Issue 2: Loop volume does not meet the chiller unit control requirement. Chiller unit controls often require a certain loop volume to maintain good chilled-water 200-ton helical rotary chillers: minimum flow rate: 1.2 gpm/ton design pressure drop: 5 ft of head 6 in pipe AHUs in same equipment room 2014 Trane, a business of Ingersoll Rand. All rights reserved. 1
2 temperature control and ensure that compressors are not cycled unnecessarily. The loop volume includes the fluid in the evaporator bundle, pipes, and coils. In many closecoupled systems for example where the air handlers and chillers are in the same equipment room the loop volume will not be adequate. The required loop volume varies by chiller manufacturer, chiller type, and unit control capabilities. Check with the manufacturer for each chiller specified. In this case, the required loop time was two minutes. So the system water volume required is the loop time multiplied by the water flow: 2 min. x 300 gpm = 600 gal [2 min. x 60 sec. per min. x 18.9 L/s = 2270 liters] Solution 2: Increase the loop volume to the required level. If the loop volume is close to that required, increasing the piping manifolds may be adequate. Otherwise add a buffer tank, preferably on the return side of the system, and on the chiller side of the bypass line. Ensure the system volume with the tank meets the required loop volume. To attain smoother system control, consider making the tank a little larger than the absolute minimum requirement. The additional cost and space will likely be small. Many designers will use 4 in [10 cm] line for this flow rate. Then select a valve to give proper bypass control. While not required, some consulting engineers specify a pressure independent valve for bypass. Issue 4: Flow can't be significantly reduced. Chiller design flow rate is 1.5 gpm per ton [0.027 L/s per kwr] and the minimum is 1.2 gpm per ton [0.022 L/s per kwr]. This means the flow rate can only be reduced 20 percent before reaching minimum. That's not much for a system that is supposed to be variable primary flow. Solution 4: Put the chillers in series! With chillers in series (Figure 2), the design flow rate per chiller is about 3.0 gpm per ton [0.054 L/s per kwr], allowing significant turndown. Design evaporator pressure drop increases since water must flow through both evaporator bundles. This increases design pump power. However, in many systems the flow rate is less than design flow much of the year, so the resulting pump energy increase may be small. To allow for servicing, engineers often design manual bypass lines into the system. The series chiller layout has two significant benefits: The upstream chiller operates at an elevated temperature and increased efficiency. Very often this compensates for any increase in pump energy. When chillers are piped in parallel in a VPF system, there is a significant flow rate change in the operating chiller when the second chiller is added. When the chillers are piped in series, there is no flow rate transition when the second chiller is enabled. This can greatly simplify system control. It may be beneficial to pipe the chillers in series if the system is designed for variable primary flow, has a chilled-water design temperature difference of 14 F [7.8 C] or larger, has two chillers, and is not likely to require a future expansion. If the system ΔT is 10 F [5.6 C], consider increasing it to 14 F [7.8 C] or larger. Issue 3: Oversized bypass line and valve do not provide adequate control. The bypass line is the same size as the pipe manifold. Given this fact, if a large valve is installed in this line, control at the minimum flow rate may be a challenge, since initially opening the valve a little allows significant flow to be bypassed. Solution 3: Size the bypass line and valve properly. In a variable primary flow system, size the bypass line for the largest minimum flow rate. In this case: 200 tons x 1.2 gpm per ton = 240 gpm [15 L/s] Figure 2. New variable primary flow (VPF) series chillers buffer tank 56ºF (13.3ºC) 47.5ºF (8.6ºC) manual bypass for servicing 40ºF (4.4ºC) flow meter Solution: install flow meter increase loop volume by adding a buffer tank size the bypass line for the largest minimum flow rate 2 Trane Engineers Newsletter volume 43 2 providing insights for today s HVAC system designer
3 Case 2: Conversion from Primary Secondary to Variable Primary Flow The system includes two 500-ton chillers in a primary-secondary configuration. The owner wants to convert the system to variable primary flow (VPF) and add a small (30-ton) heat recovery chiller. This job is "value engineered" to: use the existing secondary pumps (which can handle the flow and pressure drop requirements), switch out the high quality differential pressure sensor, which costs $1500, to a $100 sensor, and connect the heat recovery chiller in parallel with the existing chillers (Figure 3). Issue 1: The pumps are positioned incorrectly to allow bypass for minimum flow. Water cannot flow from right-to-left in the bypass line, so minimum flow cannot be maintained. Solution 1: Rather than converting to full variable primary flow, consider converting to variable primary/variable secondary. As its name implies, a variable primary/variable secondary system (Figure 4) employs variable primary (chiller) flow as well as variable secondary (coil) flow. In retrofitting a system, the use of the existing pumps already installed is generally simple. In contrast, converting to primary secondary requires significant piping changes, and the present secondary pumps must be moved and possibly increased in size. Figure 3. Case 2: After value-engineered conversion to VPF 54ºF (12.2ºC) Add a matched pair of temperature sensors to monitor the system returnwater temperature and the chiller return-water temperature. Control the primary pump s to maintain the chiller return-water temperature a degree or two lower than the system return-water temperature. This ensures there is always a little more chilled water being produced than demanded. If the temperature control results in chiller flow dropping below its minimum flow rate, increase the pump speed to maintain the required minimum chiller flow rate. Issue 2: It is likely the flow-sensing device is not accurate enough. A $100 differential pressure sensor is very unlikely to provide the accuracy, reliability 44ºF (6.7ºC) control valve Figure 4. Convert to variable primary-variable secondary VPF conversion plan: additional 30-tons of heat recovery Value engineering: pumps - use secondary pumps, don t move them - remove primary pumps $100 sensor rather than magnetic flow meter and repeatability required to operate a variable primary flow system. Unfortunately this seems to occur often. We suggest you resist the temptation to reduce costs when value will be lost. A VPF system operates on flow rate, so accuracy is critical. Solution 2: Specify and install an accurate, reliable and repeatable flowsensing device. It's very important that the flow-sensing device is accurate, reliable, and repeatable. Another benefit of a higher quality sensor is that, in general, it requires less calibration. The cost of a proper flow-sensing device will often be closer to $1000 than $100. Informative Appendix E of ASHRAE Guideline provides an example of flow measurement accuracy and precision specification language. To convert to variable primary/variable secondary: Contact the chiller provider to ensure that chiller unit controls can tolerate variable evaporator water flow. If not, update the unit controls. Add variable-speed drives (s) to the primary pumps (make sure the pump motors are compatible). Add a high quality differential pressure sensor across each evaporator. ΔT 54ºF (12.2ºC) 44ºF (6.7ºC) Solution: keep primary pumps and add s add and ΔT sensors control primary pump speed to maintain ΔT of 1-2 F if necessary, override temperature control to maintain minimum flow rate control valve providing insights for today s HVAC system designer Trane Engineers Newsletter volume
4 Issue 3: Poor heat recovery chiller location. Flow and control issues can result when a smaller chiller is piped in parallel with larger chillers. When evaporators are piped in parallel, the chillers are loaded to equal percentages. This does not allow the heat recovery chiller to be preferentially loaded or to deliver the desired hot water temperature and quantity. Solution 3: Pipe the heat recovery chiller in the sidestream position. The sidestream configuration (Figure 5) -allows the heat recovery chiller to: Be preferentially loaded, since it receives the warmest return water temperature. Operate as a heater to make the desired leaving condenser water temperature. The chilled water produced reduces the load on the central chillers. Meet its needed evaporator flow requirements independent of other chiller operation. Case 3: Conversion of a Parallel-piped System to Series, and from Conventional to Increased ΔT. This 400-ton system includes two water-cooled chillers piped in parallel. The chillers and air-handling coils were both selected with water temperatures of F. The system serves a school, which does not have a trained plant operator on site simplicity is beneficial. The school officials would prefer aircooled chillers to eliminate cooling tower maintenance requirements. They have decided to use 50 percent glycol to keep the fluid from freezing in the winter. No changes are to be made to the airside of the system. In addition, energy usage reductions are desired. For this scenario, let s examine some common misconceptions that might foil a new engineer. Figure 5. Value-engineered conversion heat recovery ΔT 54ºF (12.2ºC) 44ºF (6.7ºC) Misconception 1: Existing coils cannot be reselected at higher temperature differences. Solution 1: Coils are heat transfer media that can be selected at many conditions. Table 1 shows a coil originally selected for a 10 F [5.6 C] chilled water ΔT reselected to produce the same cooling capacity. This can be done if the entering water temperature is lower and results in a lower flow rate and higher chilled-water ΔT. This change has no effect on the airside of the system, but a substantial impact on the waterside. The advantages of series chillers (Figure 6) to produce the higher chilled-water ΔT was discussed earlier in Case 1. When making supply water temperature and flow rate changes to existing systems, consider the following factors: Many coils in air-handling units have adequate heat transfer area to perform similarly to the data in Table 1. On the other hand, if a coil has limited heat transfer capability (e.g., small, two-row fan-coils), reselecting at a higher ΔT is unlikely to work well. control valve Issues: flow balance between dissimilar chillers inability to fully load the heat recovery chiller due to mixed return water temperature Solution: put heat recovery chiller in "sidestream position load using either condenserleaving or chilled-water temperatures What is the coldest (or lowest) chilled-water supply temperature possible before condensation forms within the pipe insulation? Often with existing pipe insulation, supply water temperature reduced to 40 F [4.4 C] can be successful, but perhaps not 36 F [2.2 C]. If coil control valves were oversized at a 10 F [5.6 C] ΔT, they are even more oversized at a higher ΔT and lower flow rate. Valves may need to be changed to allow good control. Misconception 2: Use of three-way valves as the method of bypass can use more pump energy. Solution 2: Yes, but this is mitigated by a number of factors. First, the system flow rate dropped by nearly 38 percent because of the wider ΔT across the coils and reduced water flow rate. This lower flow rate results in lower system pressure drop and pump power. In many constant flow systems, it s difficult to retrofit a separate Table 1. Air-handler coil reselection using low entering-water temperature original selection reselection capacity (MBh) [kw] 504 [148] 504 [148] entering water temperature ( F) [ C] 44 [6.7] 41 [5.0] flow rate (gpm) [L/s] 101 [6.37] 63 [4.0] leaving water temperature ( F) [ C] 54 [12.2] 57 [13.9] water ΔT ( F) [ C] 10 [5.5] 16 [8.0] 4 Trane Engineers Newsletter volume 43 2 providing insights for today s HVAC system designer
5 bypass, control valve and controller into the system. Leaving enough three-way valves to allow the required minimum chiller flow rate can be a simple, cost-effective way to convert a system from constant to variable flow. Minimum pump speed can be set to attain the minimum flow rate with all converted two-way valves closed. Using three-way valves as a method of bypass is a good compromise between simplicity and performance. Figure 6. Retrofit VPF series chillers 57ºF (13.9ºC) 44ºF (6.7ºC) 50% glycol Retrofit changes: new chillers in series send 41 F water to existing coils to increase ΔT new pump with VFD leave 3-way valves equal to chiller minimum flow rate add differential pressure sensor at remote AHU to control pump speed add 50 percent glycol to the system for freeze Misconception 3: More glycol is better. When antifreeze is added to a system, fluid viscosity and pump power are often considered. However, these impacts may be small compared to the effect on chiller and coil heat transfer capability and capacity which can be degraded by 30 percent or more. Solution 3: Add only the level of antifreeze necessary. In general, use the smallest amount of antifreeze to adequately protect the system. This minimizes first cost of the antifreeze itself, plus minimizes the first cost and operating cost impact on the heat transfer surfaces and pumps. When adding antifreeze to an existing system, ensure the chiller and coil capacities are adequate given the level of antifreeze. Final Thoughts While it's often more memorable to experience issues in the field, it's cheaper and much less painful to learn from others! We can all listen to those with experience, ask probing questions, and attempt to learn. By doing so the industry can be elevated, deliver higher performing systems that result in more satisfied building owners and occupants. Freeze vs. Burst Protection As the temperature drops below the glycol solution's freeze point, ice crystals begin to form. Because the water freezes first, the remaining glycol solution is further concentrated and remains a fluid. The resulting ice crystals and fluid combination make up a flowable slush. The fluid volume increases as this slush forms and flows into available expansion volume. Freeze indicates the concentration of antifreeze required to prevent ice crystals from forming at the given temperature. Burst indicates the concentration required to prevent damage to equipment (e.g., coil tubes bursting). Burst requires a lower concentration of glycol, which results in less degradation of heat transfer. Concentration required for freeze vs. burst temperature ºF ( C) ethylene glycol concentration volume (% volume) freeze burst For a chilled-water VAV system, since the cooling coil is typically shut off during subfreezing weather, burst is usually sufficient. Freeze is mandatory in those cases where no ice crystals can be permitted to form (such as a coil loop that operates during very cold weather). When an air-cooled chiller is used, an alternative approach is to use a packaged condensing unit (condenser and compressor) located outdoors, with a remote evaporator barrel located in an indoor equipment room. The two components are connected with field-installed refrigerant piping. This configuration locates the part of the system that is susceptible to freezing (evaporator) indoors and still uses an outdoor air-cooled condenser. propylene glycol concentration volume (% volume) freeze burst 20 (-7) (12) (-18) (-23) (-29) (-34) (-40) (-46) (-51) Source: Dow Chemical Company HVAC Application Guide: Heat Transfer Fluids for HVAC and Refrigeration Systems providing insights for today s HVAC system designer Trane Engineers Newsletter volume
6 This article is based on a seminar presented by Mick Schwedler, Trane and Jason Atkisson, Affiliated Engineers,during the 2013 ASHRAE annual meetings in Denver. The acknowledgment of Mr. Atkisson in this newsletter in no way implies the endorsement of a specific system provider or manufacturer by either Affiliated Engineers or Mr. Atkisson. You can find this and previous issues of the Engineers Newsletter at To comment, us at [email protected]. Learn HVAC design strategies and earn credit References [1] American Society of Heating, Refrigerating and Air-Conditioning Engineers ASHRAE Green Guide: The Design, Construction, and Operation of Sustainable Buildings, 3rd ed. Atlanta, GA: ASHRAE. [2] Taylor, S Optimizing Design & Control of Chilled Water Plants; Part 3: Pipe Sizing and Optimizing ΔΤ. ASHRAE Journal. 53(12): [3] American Society of Heating, Refrigerating and Air-Conditioning Engineers ASHRAE Guideline 22: Instrumentation for Monitoring Central Chilled Water Plant Efficiency, Appendix E. Atlanta, GA: ASHRAE Engineers Newsletter LIVE! For event details and registration contact your local Trane office. May Applying Variable Refrigerant Flow (VRF) October Chilled-Water Terminal Systems Air conditioning clinics. A series of educational presentations that teach HVAC fundamentals, equipment, and systems. The series includes full-color student workbooks, which can be purchased individually. Approved by the American Institute of Architects for 1.5 (Health, Safety and Welfare) learning units. Contact your local Trane office to sign up for training in your area. Engineers Newsletter Live. A series of 90- minute programs that provide technical and educational information on specific aspects of HVAC design and control. Topics range from water- and airside system strategies to ASHRAE standards and industry codes. Contact your local Trane office for a schedule or view past programs by visiting On-demand continuing education credit for LEED and AIA. These 90-minute ondemand programs are available at free of charge. The list of HVAC topics includes many LEED-specific courses. Check out the latest courses: Single-Zone VAV and All -Variable- Speed Chilled-Water Plants. All courses available at continuingeducation. Engineers Newsletters. These quarterly articles cover timely topics related to the design, application and/or operation of commercial, applied HVAC systems. Subscribe at Application manuals. Comprehensive reference guides that can increase your working knowledge of commercial HVAC systems. Topics range from component combinations and innovative design concepts to system control strategies, industry issues, and fundamentals. The following are just a few examples. Please visit for a complete list of manuals available to order. Central Geothermal Systems discusses proper design and control of central geothermal bidirectional cascade systems that use borefields. This manual covers central geothermal system piping, system design considerations, and airside considerations. (SYS-APM009-EN, February 2011) Chilled-Water VAV Systems discusses the advantages and drawbacks of the system, reviews the various components that make up the system, proposes solutions to common design challenges, explores several system variations, and discusses systemlevel control. (SYS-APM008-EN, updated May 2012) Water-Source and Ground-Source Heat Pump Systems examines chilled-watersystem components, configurations, options, and control strategies. The goal is to provide system designers with options they can use to satisfy the building owners desires. (SYS-APM010-EN, updated November 2013) Trane, A business of Ingersoll Rand For more information, contact your local Trane office or us at [email protected] Trane believes the facts and suggestions presented here to be accurate. However, final design and application decisions are your responsibility. Trane disclaims any responsibility for actions taken on the material presented. 6 Trane Engineers Newsletter volume 43 2 ADM-APN051-EN (May 2014)
*At the AHRI Standard flow rate of 3 gpm/ton, using today s efficient chillers, the ΔT is 9.3 F rather than the 10 F often assumed.
providing insights for today s hvac system designer Engineers Newsletter volume 41 3 Condenser Water System Savings Optimizing flow rates and control Optimized flow rates in the condenser water system
Commissioning - Construction Documents (Page 1 of 6)
Commissioning - Construction Documents (Page 1 of 6) A. General Information Climate Zone: Building Type: Conditioned Area (sf): Reviewer's Name: Reviewer's Agency: Note: Design Review for each system/subsystem
newsletter engineers energy-saving strategies for Water-Source Heat Pump Systems volume 36 2 providing insights for today s hvac system designer
engineers volume 36 2 newsletter providing insights for today s hvac system designer energy-saving strategies for Water-Source Heat Pump Systems from the editor... Water-source heat pump (WSHP) systems
Life Cycle Costing Analysis of Water-cooled Chillers. Chillventa Nuremburg, Germany
Life Cycle Costing Analysis of Water-cooled Chillers Chillventa Nuremburg, Germany Spring 2012 Description Life Cycle Cost Analysis is a method of determining and comparing the total costs of investment
HIGH PERFORMANCE CHILLED WATER SYSTEMS. EarthWise HVAC. EarthWise HVAC High Performance CHW Plants
HIGH PERFORMANCE CHILLED WATER SYSTEMS EarthWise HVAC Simon Ho e: [email protected] 2012 EarthWise HVAC High Performance CHW Plants Low Flow Low Temperature Systems Variable Flow Systems Variable CHW Variable
Air Conditioning Clinic
Air Conditioning Clinic Introduction to HVAC Systems One of the Systems Series February 2012 TRG-TRC018-EN Introduction to HVAC Systems One of the Systems Series A publication of Trane Preface Introduction
COMMERCIAL HVAC CHILLER EQUIPMENT. Air-Cooled Chillers
COMMERCIAL HVAC CHILLER EQUIPMENT Air-Cooled Chillers Technical Development Programs (TDP) are modules of technical training on HVAC theory, system design, equipment selection and application topics. They
Calculating System Flow Requirements
Calculating System Flow Requirements To select a pump, we need to know the flow rate (the amount of fluid to be pumped) and the system resistance or head. In the U.S., flow rates are given in gallons per
Engineers Newsletter. Understanding Single-Zone VAV Systems. providing insights for today s hvac system designer. volume 42 2
providing insights for today s hvac system designer Engineers Newsletter volume 42 2 Understanding Single-Zone VAV Systems Single-zone variable-air-volume (VAV) is not a new concept, but due to new energy
HEAT RECOVERY FROM CHILLED WATER SYSTEMS. Applications for Heat Reclaim Chillers
HEAT RECOVERY FROM CHILLED WATER SYSTEMS Applications for Heat Reclaim Chillers April 2008 TABLE OF CONTENTS INTRODUCTION... 3 WASTE HEAT SOURCES... 3,4 Capturing Sufficient Heat for Useful Purposes...
Presentation Outline. Common Terms / Concepts HVAC Building Blocks. Links. Plant Level Building Blocks. Air Distribution Building Blocks
Presentation Outline Common Terms / Concepts HVAC Building Blocks Plant Level Building Blocks Description / Application Data Green opportunities Selection Criteria Air Distribution Building Blocks same
Optimization of Water - Cooled Chiller Cooling Tower Combinations
Optimization of Water - Cooled Chiller Cooling Tower Combinations by: James W. Furlong & Frank T. Morrison Baltimore Aircoil Company The warm water leaving the chilled water coils is pumped to the evaporator
Building Performance With District Cooling
Reprinting this proof for distribution or posting on web sites is not permitted. Authors may request permission to reprint or post on their web site once the fi nal version has been published. A reprint
Chilled Water System Commissioning: Variable Primary Flow. John D. Villani, P.E. Associate Grumman/Butkus Associates
Chilled Water System Commissioning: Variable Primary Flow John D. Villani, P.E. Associate Grumman/Butkus Associates AIA Quality Assurance Learning Objectives 1. History of chilled water system configurations
3/29/2012 INTRODUCTION HVAC BASICS
INTRODUCTION HVAC BASICS AND HVAC SYSTEM EFFICIENCY IMPROVEMENT SECTION O HVAC systems or Heating, Ventilating and Air-Conditioning systems control the environment for people and equipment in our facilities.
Advanced Energy Design Guide LEED Strategies for Schools. and High Performance Buildings
Advanced Energy Design Guide LEED Strategies for Schools and High Performance Buildings Today s Presenters Stephen Koontz, LEED AP Energy Services Leader Tampa Bay Trane Allen Irvine General Sales Manager
Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia
Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia Prepared for the U.S. Department of Energy s Federal Energy Management Program
As we will see, some metrics function better as one dependency type over another.
providing insights for today s hvac system designer Engineers Newsletter volume 43 3 FANtastic! A Closer Look At Fan Efficiency Metrics This EN will explore two of the most talked-about fan efficiency
Digital Realty Data Center Solutions Digital Chicago Datacampus Franklin Park, Illinois Owner: Digital Realty Trust Engineer of Record: ESD Architect
Digital Realty Data Center Solutions Digital Chicago Datacampus Franklin Park, Illinois Owner: Digital Realty Trust Engineer of Record: ESD Architect of Record: SPARCH Project Overview The project is
Data Realty Colocation Data Center Ignition Park, South Bend, IN. Owner: Data Realty Engineer: ESD Architect: BSA LifeStructures
Data Realty Colocation Data Center Ignition Park, South Bend, IN Owner: Data Realty Engineer: ESD Architect: BSA LifeStructures Project Overview Data Realty is a data center service provider for middle
ASHRAE Boston Chapter Meeting Designing AC Refrigeration Systems Lessons Learned February 11, 2014
ASHRAE Boston Chapter Meeting Designing AC Refrigeration Systems Lessons Learned February 11, 2014 Explanation of the refrigeration cycle. Compressors. Benefits and operating characteristics. -Reciprocating
By Steven C. Severini, P.E., Member ASHRAE
The following article was published in ASHRAE Journal, July 2004. Copyright 2004 American Society of Heating, Refrigerating and Air- Conditioning Engineers, Inc. It is presented for educational purposes
Design Guide. Retrofitting Options For HVAC Systems In Live Performance Venues
Design Guide Retrofitting Options For HVAC Systems In Live Performance Venues Heating, ventilation and air conditioning (HVAC) systems are major energy consumers in live performance venues. For this reason,
HVAC Systems: Overview
HVAC Systems: Overview Michael J. Brandemuehl, Ph.D, P.E. University of Colorado Boulder, CO, USA Overview System Description Secondary HVAC Systems Air distribution Room diffusers and air terminals Duct
How To Design A Building In New Delhi
ENERGY EFFICIENT HVAC DESIGN FOR COMPOSITE CLIMATE Overview of Design Conditions: Air conditioning system consumes most of the energy that a building needs in its operation. In order to reduce energy consumption
SECTION 5 COMMERCIAL REFRIGERATION UNIT 22 CONDENSERS
SECTION 5 COMMERCIAL REFRIGERATION UNIT 22 CONDENSERS UNIT OBJECTIVES After studying this unit, the reader should be able to explain the purpose of the condenser in a refrigeration system. describe differences
Heat Recovery In Retail Refrigeration
This article was published in ASHRAE Journal, February 2010. Copyright 2010 American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. Posted at www.ashrae.org. This article may not
ENERGY EFFICIENT HVAC DESIGN FOR WARM-HUMID CLIMATE CLIMATE
ENERGY EFFICIENT HVAC DESIGN FOR WARM-HUMID CLIMATE CLIMATE Overview of Design Conditions: Air conditioning system consumes most of the energy that a building needs in its operation. In order to reduce
Tips to Reduce Chilled Water Plant Costs
This article was published in ASHRAE Journal, October 2013. Copyright 2013 ASHRAE. Posted at www.ashrae.org. This article may not be copied and/or distributed electronically or in paper form without permission
IDEA Presentation SMALL CAMPUS CHILLED WATER PLANT OPTIMIZATION.
IDEA Presentation SMALL CAMPUS CHILLED WATER PLANT OPTIMIZATION. Pre-Project Details Hawaiian Community College Campus consisting of 16 individual buildings totaling 308,000 sq.ft of conditioned space.
Ener.co & Viridian Energy & Env. Using Data Loggers to Improve Chilled Water Plant Efficiency. Randy Mead, C.E.M, CMVP
Ener.co & Viridian Energy & Env. Using Data Loggers to Improve Chilled Water Plant Efficiency Randy Mead, C.E.M, CMVP Introduction Chilled water plant efficiency refers to the total electrical energy it
Heating & Cooling Efficiency
Heating & Cooling Efficiency Advantages of Geothermal HVAC Efficiency Keith Swilley Gulf Power Company Why Gulf Power Promotes Energy Efficiency? Customer Satisfaction Education Help Customers Make Smart
Water Fired Chiller/Chiller-Heater. WFC-S Series: 10, 20 and 30 RT Cooling
Water Fired Chiller/Chiller-Heater WFC-S Series: 1, 2 and 3 RT Cooling W E A R E F R I E N D L Y T O T H E E A R T H Water Fired SINGLE-EFFECT Chiller or Chiller-Heater Absorption Principle Cooling Cycle
Modeling and Simulation of HVAC Faulty Operations and Performance Degradation due to Maintenance Issues
LBNL-6129E ERNEST ORLANDO LAWRENCE BERKELEY NATIONAL LABORATORY Modeling and Simulation of HVAC Faulty Operations and Performance Degradation due to Maintenance Issues Liping Wang, Tianzhen Hong Environmental
Secondary Loop Chilled Water In Super High-Rise
The following article was published in ASHRAE Journal, May 2008. Copyright 2008 American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. It is presented for educational purposes
Analysis of data centre cooling energy efficiency
Analysis of data centre cooling energy efficiency An analysis of the distribution of energy overheads in the data centre and the relationship between economiser hours and chiller efficiency Liam Newcombe
Chilled Water HVAC Systems
Chilled Water HVAC Systems By Ron Prager, Brinco Mechanical Services, Inc. Types of water based systems: There are three types of HVAC systems that utilize water as a heat transfer medium. The first system,
Maximize energy savings Increase life of cooling equipment More reliable for extreme cold weather conditions There are disadvantages
Objectives Increase awareness of the types of economizers currently used for data centers Provide designers/owners with an overview of the benefits and challenges associated with each type Outline some
How To Use A Water Source Heat Pump
Geothermal Energy Using Water-Source Heat Pumps By VIRSTAR Corporation Geothermal Expertise Since 1978 All information contained herein is the exclusive property of VIRSTAR Corporation, all rights reserved.
Maintenance for Energy Efficiency
Maintenance for Energy Efficiency Institute of Hospital Engineering, Australia (IHEA) Seminar Asset Management & Energy Efficiency Exclusive Trane distributor Australia/New Zealand. The TRANE trade mark
POLK STATE COLLEGE CHILLER PLANT EVALUATION WINTER HAVEN, FLORIDA APRIL 2, 2014. C arastro & A ssociates, C&A# 5747
POLK STATE COLLEGE WINTER HAVEN, FLORIDA CHILLER PLANT EVALUATION APRIL 2, 2014 C&A# 5747 C arastro & A ssociates, c o n s u l t i n g e n g i n e e r s inc. 2609 W. De Leon Street, Tampa, Florida 33609
ADVANCES IN SUPERMARKET REFRIGERATION SYSTEMS
ADVANCES IN SUPERMARKET REFRIGERATION SYSTEMS Van D. Baxter, Oak Ridge National Laboratory, Oak Ridge, TN 37831-6070 ABSTRACT Present supermarket refrigeration systems require very large refrigerant charges
CHILLED WATER PLANT PUMPING SCHEMES. James J. Nonnenmann, PE Stanley Consultants, Inc. Muscatine, Iowa
CHILLED WATER PLANT PUMPING SCHEMES James J. Nonnenmann, PE Stanley Consultants, Inc. Muscatine, Iowa ABSTRACT From the advent of central chilled water plants, the system for delivering chilled water to
Creating Efficient HVAC Systems
Creating Efficient HVAC Systems Heating and Cooling Fundamentals for Commercial Buildings Heating, ventilating, and air conditioning (HVAC) systems account for nearly half of the energy used in a typical
CHILLER PLANT CONTROL MULTIPLE CHILLER CONTROLS
CHILLER PLANT CONTROL MULTIPLE CHILLER CONTROLS By: Michael J. Bitondo, Mark J. Tozzi Carrier Corporation Syracuse, New York August 1999 INTRODUCTION In December of 1998, the American Refrigeration Institute
EnergyPro Building Energy Analysis. Assisted Living Building
EnergyPro Building Energy Analysis Assisted Living Building EnergyPro Building Energy Analysis for an assisted living building Project Scope The purpose of the EnergyPro energy model was to evaluate the
COMMERCIAL HVAC EQUIPMENT. Condensers and Cooling Towers
COMMERCIAL HVAC EQUIPMENT Condensers and Cooling Towers Technical Development Programs (TDP) are modules of technical training on HVAC theory, system design, equipment selection and application topics.
Advanced Heat Reclaim Systems. Harrison Horning, PE, CEM Delhaize America - Hannaford
Advanced Heat Reclaim Systems Harrison Horning, PE, CEM Delhaize America - Hannaford Outline Basic refrigeration cycle Conventional series heat reclaim Full-condensing parallel heat reclaim Direct Hydronic
for K-12 School Buildings
Advanced Energy Design Guide for K-12 School Buildings HVAC Section John Murphy Applications Engineer, LEED AP Trane La Crosse, Wisconsin [email protected] www.trane.com AEDG-K12 HVAC Subcommittee John
DATA CENTER COOLING INNOVATIVE COOLING TECHNOLOGIES FOR YOUR DATA CENTER
DATA CENTER COOLING INNOVATIVE COOLING TECHNOLOGIES FOR YOUR DATA CENTER DATA CENTERS 2009 IT Emissions = Aviation Industry Emissions Nations Largest Commercial Consumers of Electric Power Greenpeace estimates
State of the Art Energy Efficient Data Centre Air Conditioning
- White Paper - State of the Art Energy Efficient Data Centre Air Conditioning - Dynamic Free Cooling - Release 2, April 2008 Contents ABSTRACT... 3 1. WHY DO I NEED AN ENERGY EFFICIENT COOLING SYSTEM...
Low GWP Replacements for R404A in Commercial Refrigeration Applications
Low GWP Replacements for R404A in Commercial Refrigeration Applications Samuel YANA MOTTA, Mark SPATZ Honeywell International, 20 Peabody Street, Buffalo, NY 14210, [email protected] Abstract
Principals of Condensing Boiler System Design
Principals of Condensing Boiler System Design Dennis Jones, P.E. Member ASHRAE ABSTRACT Condensing boilers can provide significant energy savings due to operating efficiencies as high as 98% as compared
Tim Sisson - Trane HVAC OVERVIEW
Tim Sisson - Trane HVAC OVERVIEW HVAC Systems System Types Acoustics Controls Modernization more than one Down to the Studs Opportunity for new System Type Renovation Possible opportunity for new System
HVACPowDen.xls An Easy-to-Use Tool for Recognizing Energy Efficient Buildings and HVAC Systems
HVACPowDen.xls An Easy-to-Use Tool for Recognizing Energy Efficient Buildings and HVAC Systems Fundamental Principles of Environmentally Responsible, Energy Efficient Buildings 1. Energy efficiency is
MAC-120HE-01 Air-Cooled Chiller
MAC-120HE-01 Air-Cooled Chiller 10 Ton / 120,000 BTUH Air-Cooled Chiller 208/230-1-50/60 1 HVAC Guide Specifications Air-Cooled Liquid Chiller Nominal Size: 10 Tons Multiaqua Model Number: MAC-120HE-01
In the compression-refrigeration loop (air conditioning), which is likely to be warmer? 1. Condenser coil 2. Evaporator coil
In the compression-refrigeration loop (air conditioning), which is likely to be warmer? 1. Condenser coil 2. Evaporator coil Answer: (1) Condenser coil See the video. A.R.E. Building Systems Study Guide
VARIABLE VOLUME / VARIABLE SPEED SYSTEMS APPLICATIONS
Bulletin D-120B Pages D120-115 to D120-118 VARIABLE SPEED PRIMARY CHILLED WATER PUMP CONTROL WITH TWO WAY VALVE DIRECT RETURN SYSTEM DESCRIPTION: The volume of water supplied to the system is varied in
Heating, Ventilation & Air Conditioning Equipment
FinAnswer Express Utah Incentive Catalog Effective as of May 19, 2012 Heating, Ventilation & Air Conditioning Equipment Rocky Mountain Power provides incentives for many types of energy-efficient technologies.
Enclosed Football Stadium Design History and Lessons Learned
Enclosed Football Stadium Design History and Lessons Learned Robert L. Towell, P.E., LEED AP, QCxP [email protected] CxE Group LLC St. Louis, Missouri 314-436-6543 With thanks to the St. Louis Convention
Example Retrocommissioning Measure: Opening Throttled Discharge Valves
Opening Throttled Discharge Valves This 21-story building, constructed in 1997, is located in Oregon and contains 589,000 gross square feet of mostly office occupancy. The HVAC system includes six large
Large Energy Savings Per Installation VFDs for Large Chillers
This article was published in ASHRAE Journal, June 2010. Copyright 2010 American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. Reprinted here by permission from ASHRAE at www.tiaxllc.com.
Basic Design Considerations for Geothermal Heat Pump Systems
Basic Design Considerations for Geothermal Heat Pump Systems 2005 Tri-Service Infrastructure Systems Conference and Exhibition Gary Phetteplace US Army Engineer Research and Development Center Cold Regions
CURBING THE COST OF DATA CENTER COOLING. Charles B. Kensky, PE, LEED AP BD+C, CEA Executive Vice President Bala Consulting Engineers
CURBING THE COST OF DATA CENTER COOLING Charles B. Kensky, PE, LEED AP BD+C, CEA Executive Vice President Bala Consulting Engineers OVERVIEW Compare Cooling Strategies in Free- Standing and In-Building
Engineering White Paper UTILIZING ECONOMIZERS EFFECTIVELY IN THE DATA CENTER
Engineering White Paper UTILIZING ECONOMIZERS EFFECTIVELY IN THE DATA CENTER SUMMARY A proper balance of temperature and humidity control is essential for efficient data center operation, and integral
The main steam enters the building in the basement mechanical room; this is where the condensate line also leaves the building.
MSV: Square Footage: 24,844 No. of Floors: 1 Year Built: 1963 Type of Use: Lounge and dining area open all night for snacks Steam Water-cooled condenser, 50-Ton York unit with a 6 cylinder-reciprocating
Chapter 3.4: HVAC & Refrigeration System
Chapter 3.4: HVAC & Refrigeration System Part I: Objective type questions and answers 1. One ton of refrigeration (TR) is equal to. a) Kcal/h b) 3.51 kw c) 120oo BTU/h d) all 2. The driving force for refrigeration
The ASHRAE HQ Building Can the energy efficiency of the different mechanical systems really be compared? RESIDENTIAL LIGHT COMMERCIAL COMMERCIAL
The ASHRAE HQ Building Can the energy efficiency of the different mechanical systems really be compared? RESIDENTIAL LIGHT COMMERCIAL COMMERCIAL Technical Article April 2013 The ASHRAE HQ Building Can
2B.1 Chilled-Water Return (and Supply) Temperature...119. 2B.3 Cooling-Water Supply Temperature / Flow... 124
Appendix 2B: Chiller Test Results...119 2B.1 Chilled-Water Return (and Supply) Temperature...119 2B.2 Chilled-Water Flow... 122 2B.3 Cooling-Water Supply Temperature / Flow... 124 2B.4 Pressure/Temperature...
Heating, ventilation and air conditioning equipment. A guide to equipment eligible for Enhanced Capital Allowances
Heating, ventilation and air conditioning equipment A guide to equipment eligible for Enhanced Capital Allowances 2 Contents Introduction 03 Background 03 Setting the scene 03 Benefits of purchasing ETL
VE 6.4.0.5: Thermal / Systems Pack. 1. Tabular Room Data editing for thermal properties
VE 6.4.0.5: Thermal / Systems Pack 1. Tabular Room Data editing for thermal properties There is a new button in Apache, UK Part L2, and PRM Tabular Room Data. This tool represents a real productivity enhancement
STULZ Water-Side Economizer Solutions
STULZ Water-Side Economizer Solutions with STULZ Dynamic Economizer Cooling Optimized Cap-Ex and Minimized Op-Ex STULZ Data Center Design Guide Authors: Jason Derrick PE, David Joy Date: June 11, 2014
Rittal White Paper 508: Economized Data Center Cooling Defining Methods & Implementation Practices By: Daniel Kennedy
Rittal White Paper 508: Economized Data Center Cooling Defining Methods & Implementation Practices By: Daniel Kennedy Executive Summary Data center owners and operators are in constant pursuit of methods
KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM
KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM AIR HANDLING UNITS... 1 CHILLERS... 2 COOLING TOWERS... 2 CLOSED LOOP COOLERS... 2 MISCELLANEOUS SUPPLY FANS...
How Ground/Water Source Heat Pumps Work
How Ground/Water Source s Work Steve Kavanaugh, Professor Emeritus of Mechanical Engineering, University of Alabama Ground Source s (a.k.a. Geothermal s) are becoming more common as the costs of energy
Defining Quality. Building Comfort. Precision. Air Conditioning
Defining Quality. Building Comfort. Precision Air Conditioning Today s technology rooms require precise, stable environments in order for sensitive electronics to operate optimally. Standard comfort air
Building Energy Systems. - HVAC: Heating, Distribution -
* Some of the images used in these slides are taken from the internet for instructional purposes only Building Energy Systems - HVAC: Heating, Distribution - Bryan Eisenhower Associate Director Center
9. ENERGY PERFORMANCE ASSESSMENT OF HVAC SYSTEMS
9. ENERGY PERFORMANCE ASSESSMENT OF HVAC SYSTEMS 9.1 Introduction Air conditioning and refrigeration consume significant amount of energy in buildings and in process industries. The energy consumed in
Free Cooling in Data Centers. John Speck, RCDD, DCDC JFC Solutions
Free Cooling in Data Centers John Speck, RCDD, DCDC JFC Solutions Why this topic Many data center projects or retrofits do not have a comprehensive analyses of systems power consumption completed in the
7 Best Practices for Increasing Efficiency, Availability and Capacity. XXXX XXXXXXXX Liebert North America
7 Best Practices for Increasing Efficiency, Availability and Capacity XXXX XXXXXXXX Liebert North America Emerson Network Power: The global leader in enabling Business-Critical Continuity Automatic Transfer
Heating, Ventilation & Air Conditioning Equipment
FinAnswer Express Wyoming Incentive Catalog Effective as of October 1, 2011 Heating, Ventilation & Air Conditioning Equipment Rocky Mountain Power provides incentives for many types of energy efficient
Data Center Energy Profiler Questions Checklist
Data Center Energy Profiler Questions Checklist Step 1 Case Name Date Center Company State/Region County Floor Area Data Center Space Floor Area Non Data Center Space Floor Area Data Center Support Space
Economizer Fundamentals: Smart Approaches to Energy-Efficient Free-Cooling for Data Centers
A White Paper from the Experts in Business-Critical Continuity TM Economizer Fundamentals: Smart Approaches to Energy-Efficient Free-Cooling for Data Centers Executive Summary The strategic business importance
HEAT PUMPING AND REVERSIBLE AIR CONDITIONING; RETROFIT OPPORTUNITIES IN A LABORATORY BUILDING. Campus du Sart Tilman, B49, B-4000 Liège, Belgium
HEAT PUMPING AND REVERSIBLE AIR CONDITIONING; RETROFIT OPPORTUNITIES IN A LABORATORY BUILDING Cleide Aparecida Silva 1, [email protected] Stéphane Bertagnolio 1, [email protected]
TRAINING. Commercial HVAC Systems. 2014 Fall Training Schedule. Energy Engineering Systems Technical. Classes in. What s Inside
www.damuth.com 2014 Fall Training Schedule Classes in Commercial HVAC Systems Energy Engineering Systems Technical TRAINING What s Inside Damuth Trane 757-558-0200 main 757-558-9715 fax Trane HVAC Parts
Ground Source Heat Pumps The Fundamentals. Southington, Connecticut 860 628 4622 John F. Sima III P.E.
Ground Source Heat Pumps The Fundamentals Southington, Connecticut 860 628 4622 John F. Sima III P.E. Winter/Spring 2010 Ground Source Heat Pumps The Fundamentals TOPICS: Heat Pump Terminology Basic Physics
2A.1 Features of Chiller Control Components... 104. 2A.3 Chilled-Water Supply Temperature Control... 107. 2A.4 Cooling-Water Supply Control...
Appendix 2A: Chiller Control Principles... 104 2A.1 Features of Chiller Control Components... 104 2A.2 Start-up and Shutdown... 105 2A.2.1 Start-up...105 2A.2.2 Shutdown...106 2A.3 Chilled-Water Supply
HVAC Simplified Approach Option
HVAC Simplified Approach Option Part I Project Address: City: HVAC System Designer of Record: Date: Zip: Qualification The building is 2 stories or less in height and has a gross floor area is less than
How to Reduce Energy Costs in Your Commercial Building
How to Reduce Energy Costs in Your Commercial Building Mark Steinmetz, Energy Advisor, GDS Associates, Inc., an ActOnEnergy Partner Mary Bentsen, Education and Training Coordinator SAIC, an Ameren Illinois
HVAC Processes. Lecture 7
HVAC Processes Lecture 7 Targets of Lecture General understanding about HVAC systems: Typical HVAC processes Air handling units, fan coil units, exhaust fans Typical plumbing systems Transfer pumps, sump
HEATING, VENTILATION & AIR CONDITIONING
HEATING, VENTILATION & AIR CONDITIONING as part of the Energy Efficiency Information Grants Program Heating and cooling can account for approximately 23 % of energy use in pubs and hotels 1. Reducing heating
Flexibility, Efficiency In San Antonio Arena
2005, American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. (www.ashrae.org). Reprinted by permission from ASHRAE Journal, (Vol. 47, No. 9, September 2005). This article may not
The Different Types of Air Conditioning Equipment for IT Environments
The Different Types of Air Conditioning Equipment for IT Environments By Tony Evans White Paper #59 Executive Summary Cooling equipment for an IT environment can be implemented in 10 basic configurations.
UA-NJ Air Conditioning & Refrigeration Division Training Curriculum
UA-NJ Air Conditioning & Refrigeration Division Training Curriculum 1st Year Basic Mathematics for HVAC Using formulas as an expression of logical sequence in solving problems. Measuring using a ruler
Data Center Planning. PUE Overview
Data Center Planning PUE Overview Steve Carter, Americas Managing Principal Charles Prawdzik Jr., Project Manager HP Critical Facility Services delivered by EYP Mission Critical Facilities, Inc. 2008 Hewlett-Packard
OPTIMIZING CONDENSER WATER FLOW RATES. W. A. Liegois, P.E. Stanley Consultants, Inc. Muscatine, Iowa
OPTIMIZING CONDENSER WATER FLOW RATES W. A. Liegois, P.E. Stanley Consultants, Inc. Muscatine, Iowa T.A. Brown, P.E. Thermal Energy Corporation Houston, Texas ABSTRACT Most chillers are designed for a
Using Time-of-Day Scheduling To Save Energy
The following article was published in ASHRAE Journal, May 29. Copyright 29 American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. It is presented for educational purposes only.
Guidelines for energy efficient heating, ventilation and air conditioning (HVAC) systems
Guidelines for energy efficient heating, ventilation and air conditioning (HVAC) systems If you're a designer or a BCA, this guidance on the energy efficiency of HVAC systems in commercial buildings may
