Sub-sea tunnels and lake taps in Norway - a short overview



Similar documents
Coastal Highway Route E39 Project

Geology 200 Getting Started...

Høyanger Upper Secondary School

CROSSING THE OSLOFJORD - AN EARLY STRATEGIC ANALYSIS - Technical challenges and consideration of Feasible solutions

UPSTREAM OIL AND GAS INDUSTRY IN KENYA

Project Layout & Design Features of the Project

Oil and gas fields in norway Industrial Heritage plan

pumped storage power Of which: Energy intensive industry incl. pulp and paper

Wages and Working Conditions in Norway

PRELIMINARY REPORT ON THE NORTHSTAR #1 CLASS II INJECTION WELL AND THE SEISMIC EVENTS IN THE YOUNGSTOWN, OHIO AREA

Tunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr.

ASX ANNOUNCEMENT 17 JUNE 2014

UNDERGROUND THERMAL ENERGY STORAGE (UTES) WITH HEAT PUMPS IN NORWAY

3D MODELLING OF GEOLOGICAL STRUCTURES FOR UNDERGROUND CAVERNS : A NEW AND SIMPLE METHODOLOGY

Coastal Highway Route E39 Project Overview

Press Kit Jette Well PL 027D, PL 169C og PL 504 REV. : 01 DATE : PAGE : 2 of 6

Rocks & Minerals. 10. Which rock type is most likely to be monomineralic? 1) rock salt 3) basalt 2) rhyolite 4) conglomerate

Carbonate Rock Formation

Operations in the Arctic areas? New challenges: Exploration Development Production

Det norske oljeselskap - Our first diving operation. Annual Conference The Norwegian Oil and Gas Association Stavanger, Norway

Offshore Structures. Offshore Drilling Equipment

Water management and challenges in Norway

Preparing for the Fornebu Metro Line. Ingeborg Krigsvoll, Sporveien Oslo AS June 7, 2016

Pipelines and seabed intervention

WATERVIEW CONNECTION PROJECT. Ground Settlement WATERVIEW CONNECTION TEAM

Three Main Types of Rocks Igneous Rocks. Sedimentary Rocks Metamorphic Rocks. Made by Liesl at The Homeschool Den

Advanced Natural Gas Storage (ANGAS) Project and Verification Tests of Experimental Lined Rock Cavern in Japan

number 2) proposed well's type, location, elevation, total depth, etc. 3) site inspection, 2) assess the adequacy of the proposed engineering

SPECIALTY FIBER OPTIC CABLE. Downhole Sensing Subsea

Rocks and Minerals What is right under your feet?

Oil and Gas Exploration and Production Oil and gas exploration and production... 22a-472-1

What is a rock? How are rocks classified? What does the texture of a rock reveal about how it was formed?

OFFSHORE FIELD DEVELOPMENT

Engineering Geological Asset Management for Large Dams. Yasuhito SASAKI (1)

UNDERGROUND CONSTRUCTIONS FOR THE NORWEGIAN OIL AND GAS INDUSTRY

The Gotthard Base Tunnel

EIENDOMSVERDI. The housing market update April. Copyright Eiendomsverdi

WEATHERING, EROSION, AND DEPOSITION PRACTICE TEST. Which graph best shows the relative stream velocities across the stream from A to B?

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

(25) CONCEPT STUDY OSLO HUB A MEGA PROJECT Nina Tveiten Norwegian National Rail Administration

Investigation 1-Part 1: Investigating Mock Rocks. Geology: the scientific study of Earth s history and structure

The Technology Challenge. Agenda - The Technology Challenge

Revolutionary Inspection Technology by FORCE Technology

SECTION GRAVITY SANITARY SEWERS

Pre-Excavation Grouting in Rock Tunneling. Knut F. Garshol M.Sc. Engineering Geology

ARCTIC OIL & GAS CHALLENGES AND OPPORTUNITIES UNIS, LONGYEARBYEN, APRIL 12TH, 2016

Irresponsible of Statoil

Applications of Integrated Vessel-based LiDAR, Multibeam Bathymetry, and Geophysical Surveys for Geohazard Assessments and Site Characterization

The Competitive Edge. The Foundation For Competing

Deep Geothermal energy and groundwater in

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Worldwide Technip in Norway

EIENDOMSVERDI. The housing market update August. Copyright Eiendomsverdi

1 THE HISTORY OF TBM TUNNELLING IN NORWAY

WHAT YOU NEED TO KNOW ABOUT LIVING NEAR INDIANA COAL MINES

SAFARI An outcrop analogue database for reservoir modelling

hs2 Ground A non-technical guide

PRESS KIT IVAR AASEN DET NORSKE OLJESELSKAP ASA

Graduate Courses in Petroleum Engineering

NOTE. Note on the pumped storage potential of the Onslow-Manorburn depression, New Zealand

Granite. A Rocky Journey and Talking Rocks Role play and sorting clues.

Questions & Answers Proposed for Exam #3

Metamorphic rocks are rocks changed from one form to another by intense heat, intense pressure, and/or the action of hot fluids.

Norsk Naturskadepool

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

1. Base your answer to the following question on on the photographs and news article below. Old Man s Loss Felt in New Hampshire

PORTS OF. sh i p to no r way

Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES

PROPOSAL FOR CONTRACTORS ALL RISKS

Havbunnsproduksjon. NTNU, 15 april 2013 Eldar Lundanes System Responsible for Controls and Data Management, Eastern Region.

ADX ENERGY. Sidi Dhaher Well test Briefing Live Webcast, 4 July Wolfgang Zimmer, Paul Fink

QUESTIONNAIRE AND PROPOSAL FOR CONTRACTORS ALL RISK INSURANCE

Beacon Hill Sewer District Standard Specifications

HEAT PUMP FOR DISTRICT COOLING AND HEATING AT OSLO AIRPORT, GARDERMOEN

PRESS KIT PL 553 KVITVOLA. Exploration well 34/7 36 S

Statoil s Arctic program, Bear Island nature reserve and the ice edge May 12, 2014

Multisensor Data Integration in O&G Business Lutz Petrat Hélène Lemonnier Michael Hall

Layers of the Earth s Interior

Total Subsea Services

Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle

Full scale tunnel fire tests of VID Fire-Kill Low Pressure Water Mist Tunnel Fire Protection System in Runehamar test tunnel, spring 2009

World Leader of Subsea Systems

THE TRANSITION FROM OPEN PIT TO UNDERGROUND MINING: AN UNUSUAL SLOPE FAILURE MECHANISM AT PALABORA

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

Taking a Giant Leap in Subsea Technology

How to strengthen business ties between Norway & China?

Permits to Dig / Permits to Excavate / Permits to work near underground services

THE BALTIC SEA OFFSHORE PROJECTS

DEVELOPMENT OF THE PATHFINDER FOAM CALIPER PIG. By: Peter Ward, Pipeline Innovations Ltd, UK

CCS Risk Analysis. Vanessa Nuñez Lopez. CEPAC - CSLF Capacity Building Workshop Porto Alegre, Brazil July 30 Aug 3, 2012

Monetary policy and the economic outlook Governor Svein Gjedrem SR-banken, Stavanger 19 March 2004

Exploration for natural gas

ources of Drinking Water

Transcription:

Reference: www.rockmass.net Sub-sea tunnels and lake taps in Norway - a short overview Arild Palmström, Ph.D. (May 2002) Sub-sea tunnels are those tunnels, which pass beneath the sea or a lake bottom; where the geology is hidden by water, see Figure 1. They are more affected by geological uncertainties and risks than most other tunnel projects because of the limited geological information and the close proximity of large amounts of water. 0 1 2 3 4km 0-100 max gradient soil max gradient min. rock cover -200 min. rock cover FIGURE 1 MAIN FEATURES DETERMINING THE ALIGNMENT OF A SUB-SEA TUNNEL Looking back on earlier tunnel projects in Norway, there are many tunnels, especially in conjunction with hydropower projects, which pass under rivers and lakes and which may be classified as sub-sea tunnels. Specially in this connection are the intakes to reservoirs consisting of submerged bottom piercings or "lake taps", a specialty in Norwegian tunnel construction, see Figure 2. More than 500 of these have been constructed over the years, and more than 70 have been made since 1980. A list of some lake taps/tunnel piercings is shown in Table 3. LAKE headrace tunnel The total length of all sub-sea tunnels constructed in Norway during the last 75 years is not known, but is crudely estimated at 100km. The first sub-sea road tunnel was constructed in 1982, see Table 1. Since then, more than 85km of such tunnels have been excavated. Their locations are shown in Figure 4. final rock plug to be blasted 4-5 m BEFORE FINAL BLAST AFTER FINAL BLAST FIGURE 2 PRINCIPLES IN THE NORWEGIAN LAKE TAP METHOD From Table 1 it can be seen that the deepest sub-sea tunnel in Norway - the Hitra tunnel - was constructed in 1994. It has 40m rock cover at its deepest point 267m below sea level. All sub-sea tunnels in Norway have been excavated by the drill and blast method. Lake taps have also been performed by blasting the final rock plug, except for some of the piercings made for the oil-/gas pipe landfalls for which the final holes through have been made by the reaming method (not shown in this article).

2 Alignment of a sub-sea tunnel is determined by geological and topographical conditions as well as the tunnel's maximum gradient requirement (see Figure 1). The minimum distance for safety between the tunnel roof and the rock surface under the sea, otherwise known as the rock cover, is a crucial dimension for locating a sub-sea tunnel, Figure 3. Figure 4 shows the minimum rock cover used in Norwegian sub-sea tunnels. Although there has been a continuous development in sub-sea tunnel construction TUNNEL since the start of lake taps in 1905, more 400 systematic improvements have taken place LAKE TAP during the last 20 years due to the increase in 300 sub-sea tunnelling activity. Here, the improvements in geophysical site investigation techniques have been important. Results 200 from acoustic profiling and refraction seismic measurements are vital for tunnel alignment planning. A map of the sea bottom is 100 obtained from the acoustic profiling which gives the distribution and thickness of loose WATER DEPTH (m) 0 FIGURE 3 conditions good rock poor rock conditions 0 10 20 30 40 50 60 70 ROCK COVER (m) NORWEGIAN PRACTICE REGARDING MINIMUM ROCK COVER deposits (soil). The refraction seismic measurements give additional information on the rock mass quality and a more accurate location of the rock surface. Developments in equipment have also resulted in a faster execution of field investigations, better data processing, and consequently, a reduction of investigation cost, which now, for sub-sea tunnels amounts to 2.5-7% of the total construction cost. In addition to the use of advanced field investigation methods, the special challenges of sub-sea tunnelling require thorough planning and execution of the excavation works. The following safety measures, important for safe tunnel construction, are standard today in sub-sea tunnelling: - Systematic 20-30m long exploratory drill holes ahead of the tunnel working face. - Additions, longer exploratory core drill holes where possible poor quality rock masses can be expected. - High pressure pre-grouting if water bearing zones and/or poor rock mass qualities have been detected in the exploratory holes. - A high pumping capacity for de-watering the tunnel in case of unforeseen water ingress. - High capacity application of fibrecrete quickly after blasting in order to support poor stability rock masses of short stand-up time. These measures reduce the possibility of tunnelling problems caused by unforeseen ground conditions. In addition, a continuous exchange of experience and a close cooperation between engineering geologists, planners and contractors has been the key to the successful constructions. A good number of studies have been made for possible sub-sea tunnels in the last 20 years, amongst which are 60km long tunnels from the Norwegian mainland to some of the nearer offshore oil fields and a 45km long railway tunnel beneath a deep fjord. Several other sub-sea projects are at the planning stage. A list of planned sub-sea road tunnels is shown in Table 2.

3 Table 1 Sub-sea tunnels constructed in Norway after 1975 Year completed Tunnel name Type Length ( km ) Deepest point (m) Cross section ( m 2 ) Rocks encountered 1976 Frierfjord O 3.6-253 16 gneiss, claystone 1976 Vollsfjord W 1.5-80 8 / 16 gneiss 1980 Slemmestad W 1.0-93 10 claystone, limestone 1982 Vardö R 2.6-88 46 slate and sandstone 1983 Kårstö I W 0.4-58 20 phyllite 1983 Kårstö II W 0.3-30 20 phyllite 1984 Karmsund O 4.7-180 26 gneiss, phyllite 1984 Fördesfjord O 3.4-160 26 gneiss 1984 Förlandsfjord O 3.9-170 26 gneiss, phyllite 1987 Ellingsöy R 3.5-140 68 gneiss 1987 Valderöy R 4.2-137 68 gneiss 1987 Hjartöy O 2.3-110 26 gneiss 1987 Alvheimsund O 1.3-60 20 gneiss 1988 Kvalsund R 1.5-56 43 gneiss 1989 Godöy R 3.8-153 48 gneiss 1989 Flekkeröy R 2.3-101 46 gneiss 1989 Hvaler R 3.8-120 45 gneiss 1990 Nappstraum R 1.8-60 55 gneiss 1990 Maursundet R 2.3-93 43 gneiss 1990 Fannefjord R 2.7-100 43 gneiss 1991 IVAR, Jaeren W 1.9-80 20 phyllite 1991 Kalstö O 1.2-100 38 greenstone 1992 Byfjord R 5.8-223 70 phyllite 1992 Mastrafjord R 4.4-132 70 gneiss 1992 Freifjord R 5.2-130 70/54 gneiss 1994 Tromsöysund (two tubes) R 3.4-101 2 x 57 dioritic gneiss 1994 Hitra R 5.3-267 70 gneiss 1995 Troll O 3.8-260 66 gneiss 1996 Bjoröy R 2.0-88 43 gneiss 1997 Slöverfjord R 3.3-120 55 gneiss, mangerite 1997 Lysaker W 0.6-73 19 claystone 1999 Nordkapp (Magerøysund) R 6.9-150 43 mica schist, quartzite 1999 Kårstö III W 3.0-60 22 phyllite 1999 Kårstö IV W 0.6-10 22 phyllite 2000 Fröya R 5.3-164 43 gneiss 2000 Oslofjord R 7.3-120 70 gneiss, amphibolite 2000 Ibestad R 3.4-112 43 gneiss 2000 Bömlafjord R 7.9-263 70 greenstone, gneiss 2002 Skatestraum R 1.9-80 43 gneiss R = SUB-SEA ROAD TUNNEL W = SUB-SEA WATER TUNNEL O = SUB-SEA TUNNEL FOR OIL / GAS PIPELINE Table 2 Some planned Norwegian sub-sea road tunnels Tunnel name County Length (km) Rocks Björvika - Bispevika Oslo 0.7 claystone Hadselfjorden Nordland 9.0 gneiss Eiksund Möre og Romsdal 7.8 gneiss Averöy Möre og Romsdal 5.8 gneiss Ryfast Rogaland 13.0 gneiss Finnfast Rogaland 5.0-6.0 gneiss Hidrasundet Vest-Agder 2.6 gneiss Boknafjorden Rogaland 24.5 gneiss

4 Vadsö Tromsö RUSSIA FINLAND N Narvik Bodö SWEDEN Molde Ålesund Trondheim Kristiansund NORWAY Bergen Oslo Stavanger Kristiansand 0 100 km FIGURE 3 NORWEGIAN SUB-SEA TUNNELS

5 Table 3 Some lake taps/tunnel piercings performed in Norway after 1980 Year Project Type Number of Water depth piercings (m) Rocks 1980 Aurland H 4 15-22 gneiss 1980 Kjela H 1 48 gneiss 1980 Holen H 1 45 gneiss 1980 Vangen H 2 21-22 gneiss 1980 Oksla H 1 85 gneiss, granite 1980 Eidfjord H 5 9-52 gneiss 1980 Slemmestad W 1 40 claystone 1981-83 Reppa H 2 10-15 phyllite 1981-84 Aurland II H 10 10-30 gneiss, phyllite 1982 Sörfjord H 1 70 mica schist 1983 Lomen H 2 20 phyllite 1983 Mosvik H 1 40 amphibolite, mica gneiss 1984 Tjodan H 4 15-25 gneiss 1984 Bergsbotn H 1 12 granitic gneiss 1986 Ulla Förre H 8 36-101 gneiss, phyllite 1986 Skarje H 2 6-20 gneiss 1986 Eikelandsosen H 1 60 granitic gneiss, phyllite 1986 Kobbelv H 7 5-120 gneiss, mica schist 1986-89 Jostedal H 6 16-73 gneiss 1987 Hjartöy O 1 80 gneiss 1989 Mel H 4 30-90 gneiss 1986 Nyset-Steggje H 2 10-17 gneiss 1991 IVAR, Jaeren W 2 40-80 phyllite 1991 Kalstö O 1 60 gneiss 1995 Troll O 2 250 gneiss 1999 Kaarstö O 2 20 / 60 phyllite H = LAKE TAP/TUNNEL PIERCING FOR HYDROPOWER DEVELOPMENT W = TUNNEL PIERCING FOR SEWERAGE OUTLET O = TUNNEL PIERCING FOR SHORE APPROACH OF GAS/OIL PIPELINE