GHD EPCM Standard operating procedure Working at height May 2013 v1

Similar documents
PORT HEDLAND PORT AUTHORITY

SECTION 2 HAZARDOUS WORK. CLASSIC STANDARD 2.04 Working at Heights

Document ref: MG(M)201 Version no: 01 Page no: 1 / 12. Contractor rules

THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY

RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager

WORK AT HEIGHT UNIT 4

Scaffold Standard (Standard to Managing and Appointing Scaffolding Contractors on University College London (UCL) Projects) Management Standard

COURSE INFORMATION SHEET

Good Practice Guide. The Selection of Access Methods to Install and Dismantle Safety Netting

Work at Height. John Frontczak Construction Manager Facilities Engineering Chevron Corporation. All rights reserved.

Safety Systems Review Facilities Management Guidance and specification Version

WORKING IN CONFINED SPACES GUIDELINES

WORKING AT HEIGHT GUIDELINES. Version II

Golden Safety Rules booklet. No one gets hurt, no incidents

Working at Height. Procedure

68 Metal Industry Guidelines for Safe Work

SAFE WORK ON ROOFS PART 1: COMMERCIAL AND INDUSTRIAL BUILDINGS. making a difference CODE OF PRACTICE New South Wales Government

WORKPLACE INDUCTION FOR CONSTRUCTION WORKPLACES INFORMATION SHEET 1

WORK AT HEIGHT. STFC Safety Code No 9. Rev. 1.4, Issued April, 2015

Tremline Pty Ltd trading as The Hills Bark Blower

Fall Protection, Title 29 Code of Federal Regulations (CFR) Part 45, Subpart M, Fall Protection, , , , and1926.

WHS Contractor Management Procedure

WHS Contractor Management Procedure

Procedural Guidance for Roof Access/Roof Work

HEALTH AND SAFETY POLICY LEWIS & RABY ENGINEERS LTD

Working at height A brief guide

NZQA registered unit standard version 4 Page 1 of 6

Working at a height of two metres or more while carrying out general work activities or construction works

Programme-Based Engagement (ProBE) for Fall From Heights. Statistics

CONTRACTOR SAFETY MANAGEMENT PROCEDURE

WHS CONTRACTOR MANAGEMENT PROCEDURE

Names and Contact Numbers of Competent Rescuers Assigned to Job (Please print)

Hazard Identification, Risk Assessment And Control Procedure

Pre-Qualification Questionnaire Checklist

WHS CONTRACTOR MANAGEMENT PROCEDURE

Eskom Life Saving Rules Implementation of the Eskom Life Saving Rules

OCCUPATIONAL HEALTH AND SAFETY RISK ASSESSMENT PROGRAM FOR AGRICULTURE

Confined Space Management Procedure

Fall Protection Guidelines

Method Statement. Risk Assessment

Working at Height. A printed or saved copy is an UNCONTROLLED copy. Check that it is the latest available version before use.

Asbestos Policy ASBESTOS POLICY. Version 2 / Jun 2015 Page 1 of 11 Asbestos Policy

WorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

FALL PROTECTION WORK PLAN

HEALTH & SAFETY HANDBOOK. No Body GetsHurt. Our Safety Slogan is:

Approved Contractor Application (SAFE Form B)

SITE SPECIFIC FALL PROTECTION PLAN

CONTRACTOR INDUCTION HANDBOOK

Cristal Mining East. Mine Safety Management Plan

SG19:10 NASC. A Guide to Formulating a Rescue Plan. NOTE: Scaffolders who need to use a harness should never work alone. 1 of 8 1.

Excavation & Trenching Procedure

Fall Protection. Office of Risk Management. uottawa.ca. Guide

Procedure. Working at Heights. 1. Purpose. 2. Scope. 3. Definitions. 4. Planning QUT risk check Work at Height permit

HEIGHT SAFETY EQUIPMENT MAINTENANCE, INSPECTION, RECERTIFICATION & TRAINING GUIDANCE

FALL PREVENTION PLAN FPP. Sharing of Safe Work at Height

Managing the risk of falls while working on roofs in housing construction

The Work at Height Regulations 2005 (as amended) A brief guide

Five Star Occupational Health and Safety Audit Specification document 2013

FALL PROTECTION PROGRAM RESCUE PLAN

Part of the Arco family

Question and answer brief for the construction industry on the Work at Height Regulations 2005

CONFINED SPACE PROCEDURE

Level 1 Award in Health and Safety in a Construction Environment

FALL PROTECTION PROGRAM

Guide to manual tasks high impact function (HIF) audit 2010 March 2010

FALLING OBJECTS EXCESSIVE NOISE CHAINSAW & CHIPPER WORK AT HEIGHTS MANUAL HANDLING

Guidance Note GN049. Using portable ladders safely. WorkSafe Tasmania Department of Justice. Introduction and purpose

Accident/Incident Investigation & Reporting Procedure

Generic Risk Assessment: Working on Roofs (FMRA 0006)

Hazard Identification, Risk Assessment and Control (HIRAC) for Work at Height Risk, Health and Safety

Contractor s Safe Working Agreement

PreventING falls from height Introduction How will worksites be targeted? Approach Who will be targeted?

Work Health & Safety Policy Document Number: WH&S Ver 1

HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM

Quantum Risk Management Ltd t/a Quantum Compliance 23 Hanover Square, London W1S 1JB 34 Greenbox, Westonhall Road, Stoke Prior B60 4AL T:

SITE CONTRACTOR PROCEDURES

Corporate Health and Safety Policy

No. Name of Legislation Applicable Issues and Requirements Demonstration of Compliance 1. Health and Safety at Work Act 1974

Contractor Safety Management

SUPPLY CHAIN PREQUALIFICATION PACKAGE

Release 1. BSBWHS508A Manage WHS hazards associated with plant

Life Saving Rules SAFETY BY CHOICE, NOT BY CHANCE

Sample Checklist for Permit Required Confined Spaces Program

Fall Protection System: A system put in place to protect workers from falling. (i.e. installation of guardrails, fall arrest, fall restraint, etc.

SAFE WORK PROCEDURE SWP 015 WORKING AT HEIGHT SEPTEMBER 2013 DOC. NO. D13/248399

RESTRICTED ACCESS AND CONFINED SPACES

OAKPARK SECURITY SYSTEMS LIMITED. Health & Safety Policy. Requests or suggestions for amendment to this procedure

OH&S Management Systems Audit Checklist (NAT, E3)

The Tomato Plant Company Ltd. Method Statement and Risk Assessment Loads requiring lifting

CHAPTER 10. FALL PROTECTION PROGRAM

ELECTRICAL SAFETY & ARC FLASH Handbook

WHS CONTRACTOR MANAGEMENT PROCEDURE

The Work At Height Safety Association

CONTRACTOR S MANAGEMENT PROCEDURE

Event Management Guidelines. Month Event Management Guidelines (Month, 2011)

WHS Policies and Procedures Package

TEMPLATE -PRINCIPAL CONTRACTOR CONSTRUCTION SAFETY & ENVIRONMENT MANAGEMENT PLAN

Life Saving Rules. Working Safely at EPCOR

Working on roofs. Planning roof work

Transcription:

GHD EPCM Standard operating procedure Working at height May 2013 v1

Table of contents 1. Purpose 2. Scope 3. Duty of care 4. Lifesaving rules; An overview 5. Roles and responsibilities 4.1 Operating centre manager (OCM) 4.2 Project director (PD) 4.3 Job manager (JM) 4.4 Staff 6. Procedures 7. References 8. Definitions

1. Purpose The purpose of this document is to set out the minimum requirements for GHD staff, visitors and contractors engaged on behalf of GHD to safely assess and manage works at height. Consideration must be given to existing client measures for controlling work at height when visiting any site which is controlled by another party. 2. Scope This procedure applies to all GHD employees, contractors and visitors for the purpose of carrying out work activities sanctioned by the practice management group where GHD is engaged in the role of engineering, procurement and construction management. GHD has a duty to provide a safe work place and protect life and property to all staff requiring access to or entering a GHD controlled site or office. 3. Duty of care GHD has a duty of care to control any risks associated with work at height under the Model work health and safety Act: 2011. As such, GHD shall aim to eliminate risks from work at height wherever possible. Where this is not possible, GHD shall aim to minimise risks so far as is reasonably practicable. 4. Lifesaving Rules; An overview The aim of this procedure is to control the risks associated with hot work in the workplace. It aims to identify controls which can assist to identify, eliminate, control and otherwise minimise risks to people, premises and the environment which may arise from hot works. 1. Avoid hot works as the first option 2. Anyone undertaking or supervising hot works must be trained to do so 3. An emergency response plan must be in place 4. A safety plan must detail controls for the works being undertaken 5. The environment will be checked before work and monitored during work 6. No works shall take place where oxygen levels are outside of 19.6%- 22.8% in the atmosphere. 7. The smallest possible quantities of hazardous substances shall be used to perform the task 8. Fire resistant barriers shall be in place 9. Permit to work must be implemented 10. Where isolation of services or equipment is needed, a lock out/tag out system shall be implemented 11. All affected parties shall attend a pre start meeting 12. The GHD job manager shall act as coordinator of activities 13. Barriers and signage must be in place 14. Health monitoring shall be in place where there is any risk of exposure 15. PPE shall be provided relevant to identified risks

Work at height permit process Does the proposed job involve: Works which present the risk of a fall between levels, or objects falling between levels Yes No Not work at height Access equipment required? No Yes Permit to work required Does the contractors safety plan meet the requirements of all SOP minimum standards? Yes implement pre work controls No Contractor to review and resubmit safety plan Are barriers in place? Fixed scaffold verified as safe by a licensed contractor? OR Access equipment fit for purpose and in place? Emergency procedures (including rescue plan) in place? Issue work at height permit alongside other permits required Pre start meeting all site made aware of no go zone Go to work Changed condition STOP WORK and surrender permit Works complete Make safe and surrender permit

5. Roles and responsibilities OC manager Support the project director to resource the works Project director Ensure funds and preliminary information is gathered with support of the client. Implementation of the HSE project systems. Ensure that staff are trained and competent for their roles Development of permit to work system, Job manager Review of contractors Safe systems of work Implement Lock out/ Tag out system Inducting new staff, visitors and contractors to project hazards Act as liaison to all trades affected by hot works Pre start briefings Issue of permit to work Undertake pre work assessment of hot work risks Contractor Implement emergency procedures Submission of documentation to GHD. Ability to prove the use of only competent staff. Select smallest quantities of hazardous substances needed to complete the task Monitor exposure levels in the workplace Arrange for health monitoring Supply of PPE Incorporation into the GHD permit to work system Be inducted project Staff Attend pre start meetings Assist in creation of safety plans Only operate in areas where they are trained Creation of the permit to work and lock out / tag out system HSE function Review safe systems of work as required Attend pre start meetings as required 6. Procedures This standard operating procedure draws guidance from http://www.safeworkaustralia.gov.au/sites/swa/about/publications/documents/632/mana ging_the_risk_of_falls_at_workplaces.pdf. When operating on a GHD site, the Job manager shall first establish if the need for work at height can be eliminated. GHD shall aim to eliminate work at height wherever reasonably practicable. When any work at height is being conducted on a GHD managed or operated site, the GHD Job manager shall first consider the hierarchy of controls when assessing any contractor safety plan. Where it is deemed that any work at height must take place which involves the use of equipment or plant to reach the working height, or where there is a risk of falls to a hazardous area, a permit to work shall be issued. Any site or project controlled and operated by GHD shall relay all known hazardous conditions to any sub-contractor prior to any work at height taking place. The project manager shall provide this information through induction to the project. This shall include

high risk areas which have previously been identified from site establishment and are deemed No go areas. From this, a safe system of work (or safe work method statement for high risk works as described in the Model WHS act) shall be established to complete the task by the person responsible for undertaking the works and their supervisor. In the case of a GHD undertaking works on a GHD site, the safe system of work shall be developed by the employee undertaking. Safe systems of work shall be in the form of a task specific risk assessment. Any safe system of work involving work at height shall list controls for; Safe access (This shall include selection of access equipment) Competency required for operators (Licensed scaffolder MANDATORY FOR SCAFFOLDS OF 4M AND OVER, plant operator) Monitoring of work conditions (Scaffold checks pre work, after changes and periodic, equipment checks) Isolation of other parties from height risks (See barriers ) Emergency planning (In line with site emergency plans ) Safe egress from the area Communication methods Any safety plans shall also list controls relating specifically to the task to be performed, including measures to protect workers and all other parties from associated risks. Any operative involved in work at height activities must have specific training and licensing to their role. The GHD job manager shall consult all effected workers through a pre start meeting. This shall highlight the hazards associated with the task, and the controls in place. As a minimum standard, when any work at height is to be undertaken, the area below shall have a barrier in place to restrict access by non-essential workers. When undertaking work at height to complete an associated high risk activity, a separate permit shall be issued in line with the relevant SOP. Any work at height which also involves hot work as a minimum standard must take place from a fixed stationary platform. Review of contractors risk assessment Before any works may begin, or any permit to work issued, the GHD job manager shall review the contractors proposed methodology. When work at height is involved, the following controls shall be implemented as a minimum standard. Where work can be performed at ground level, this shall be the first option. If part of the task can be performed at ground level to minimise work at height, this shall be implemented. A fixed platform shall be the first consideration as a working platform. Any fixed platform shall be erected and maintained by a licensed scaffolder. Forms of access to be considered as preferable shall be, Elevated work platforms, mobile tower scaffolds, enclosed work baskets. Ladders shall be used as a means of access and egress only and must be secured. Any work platform shall be enclosed by a fixed top and middle rail with a toe board in line with local standards.

The use of fall restraint systems shall be used for any works involving a risk of falling of 3 metres or below, and only when other options have been deemed reasonably impracticable. Fall arrest systems shall be used only as a final resort and must have a provision of rescue in the event of falls in the contractor safety plan. Any fall rescue plan must provide trained and competent people to perform the task. Where plant is to be brought onto site, it must conform to the requirements set in the Contractor, plant and equipment selection SOP alongside any requirements of the Environment SOP. Any anchor points or lifting equipment (Including harnesses, lanyards and anchor points must meet the criteria stated in the SOP Lifting equipment. When working in an area where work at height is being undertaken, all workers shall wear a safety helmet and safety capped boots as a minimum requirement. Where there is a risk to existing plant, equipment or facilities resulting from objects falling from height, all tools and equipment shall be secured to an anchor point capable of supporting them in the event of them falling from the work platform. This may be secured to a worker in the case of hand tools, on the provision that it would not impact upon the restraint system in place. In the event of any incident or injury to a field operative, GHD incident reporting procedures will be followed. 7. References Model work health and safety Act: 2011 http://www.safeworkaustralia.gov.au/sites/swa/about/publications/documents/634/confi ned_spaces.pdf Model Code of Practice Managing the risks of falls at workplaces http://www.safeworkaustralia.gov.au/sites/swa/about/publications/documents/632/mana ging_the_risk_of_falls_at_workplaces.pdf GHD documents and forms: Standard operating procedure Permit to work Standard operating procedure Barriers Standard operating procedure Emergency plans Standard operating procedure Contractors, plant and equipment selection Standard operating procedure Environment Standard operating procedure Lifting equipment

8. Definitions Work at height Works which present the risk of a fall between levels, or objects falling between levels Emergency plan: Arrangements for assistance in the event of an emergency, in this case, recovery of a person and arrangements for treatment following injury or exposure. Lock out/ Tag out; A system of isolating services of equipment which prevents accidental re activation Permit to work; A system which imposes controls and conditions for completion of a task, specifically related to high risk works.