Montana Department Transportation



Similar documents
Montana Department Transportation

QUALITY ASSURANCE. and QUALITY CONTROL PROCESS GUIDE. for PROJECT MANAGERS

Montana Business Process to Link Planning Studies and NEPA/MEPA Reviews

DISTRICT 3 TRAFFIC MANAGEMENT PLAN CHECKLIST

WORK ZONE SAFETY & MOBILITY GUIDANCE DOCUMENT

Transportation Management Plan Overview. Module 3

Transportation Management Plan Template

Traffic Management Guidelines

12MAP-21, a funding and authorization bill to govern U.S. federal surface MONITORING IMPLEMENTATION AND PERFORMANCE

Impacts of Technology Advancement on Transportation Management Center Operations

Design-Build Process for Project Managers

Intersection Cost Comparison Spreadsheet User Manual ROUNDABOUT GUIDANCE VIRGINIA DEPARTMENT OF TRANSPORTATION

Idaho Transportation Department. Work Zone Safety and Mobility Program

Chapter Thirteen WORK ZONE TRANSPORTATION MANAGEMENT PLANS BUREAU OF DESIGN AND ENVIRONMENT MANUAL

8 IMPLEMENTATION PLAN. 8.1 Introduction

CHAPTER 20 Project Development Cost Estimates Table of Contents

Appendix. Change Management Plan. Communication Plan. QA/QC Plan. Transition and Closure Plan C-1

Alternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011

Developing and Implementing Mobility Management in Oregon. W.D. Baldwin OBDP/HDR TCM 2008 Orlando, Florida

SAN DIEGO GAS & ELECTRIC COMPANY SOUTH BAY SUBSTATION RELOCATION PROJECT TRAFFIC MANAGEMENT PLAN SEPTEMBER 2014

COST PROPOSAL BID SHEET Nebraska Department of Roads Excavating Services. DISTRICT 1-Superintendent Area 110 EST QTY COST PER HOUR

Implementation Strategy

SR 89/Fanny Bridge Community Revitalization Project. Draft Environmental Impact Report/ Environmental Impact Statement/ Environmental Assessment

LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL

Comprehensive Mobility Project Development Process Capital Metro ¼-Cent Fund Analysis

Activity Report for FY 2010 Real-time Traffic Signal Adjustments

Massachusetts Department of Transportation, Highway Division Ten Park Plaza, Boston, MA A Guide on Traffic Analysis Tools

CONTRACT TRAFFIC MANAGEMENT PLAN

MassDOT s Work Zone Transportation Management Procedures. By: Neil Boudreau, MassDOT and Michael Sutton, P.E., VHB

PROGRAM FOR ARTERIAL SYSTEM SYNCHRONIZATION (PASS) STANDARD SCOPE OF WORK, SCHEDULE AND BUDGET

Safe Transportation System. Tangible Result Driver Leanna Depue, Highway Safety Director

CAPACITY AND LEVEL-OF-SERVICE CONCEPTS

A Discussion on Developing Processes and Procurement Methods to improve Traveler and Worker Safety

Emergency Responder Safety Institute

South Carolina Multimodal Transportation Plan Vision, Goals, Objectives, and Performance Measures

FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005

MOVING FORWARD: TRAFFIC OPERATIONS AND SAFETY RESEARCH

MPO Staff Report MPO Technical Advisory Committee: March 13, 2013 MPO Executive Board: March 20, 2013

OHIO S SAFE ROUTES TO SCHOOL PROGRAM


Traffic Management Plan - Depot Procedure

National Traffic Incident Management Responder Training Nebraska Update. Nebraska Asphalt Paving Conference February 11-12, 2014

APPENDIX A Dallas-Fort Worth Region Transportation System Management Strategies and Projects

Traffic Volume Counts

Alternatives Evaluation Overview

Traffic Incident Management Where are we focused? Captain Mike Prochko Arizona Department of Public Safety Highway Patrol Division

DRAFT PLANNING THE OPENING OF A ROAD PROJECT GUIDELINE 1

Guidelines for Developing Traffic Incident Management Plans for Work Zones

Goals & Objectives. Chapter 9. Transportation

STANDARD OPERATING INSTRUCTION. Worksite Safety Traffic Management Procedure

Boston Traffic Management Center Activity Report for FY 2013 Real-time Traffic Signal Adjustments

Managing Special Education User Guide Version 2.11

Chapter 7 PURPOSE AND NEED MDT ENVIRONMENTAL MANUAL

Quick-Starting Your. Regional ITS Architecture Update

Bicycle Safety Program Plan

FINAL Cost Estimate Report

Multi-Modal Corridor Degree of Complexity: High Cost/Benefit: High

Cost Estimating Guideline December, 2015

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A

Guidelines. Motorcycle and Bicycle Work Zone Safety

Near Westside Neighborhood and University Avenue Corridor Transportation Study. Public Workshop #2. September 12 and 23, 2013

Safety Engineering Policy Memorandum

Project Management On-line Guide

North Carolina Department of Transporta on. Guidelines. Transporta on Management Plan Development

Improving Access in Florida International University Biscayne Bay Campus Executive Summary

GENERAL. This manual addresses five local programs that are funded under the current Highway Act:

SAMPLE TRANSPORTATION MANAGEMENT PLANS AND TEMPLATES. U.S. Department of. Transportation. Federal Highway Administration Office of Operations

Chapter 22. Lump Sum Project Guidelines

CITY OF SUN PRAIRIE NEIGHBORHOOD TRAFFIC MANAGEMENT PROGRAM

Traffic Management App. User Guide

MAP 21 themes. Strengthens America s highway and public transportation systems. Supports the Department s aggressive safety agenda

How To Design A Crash Investigation Site

Mainstreaming Incident Management in Design-Build: The T-REX Experience

Basic Pivot Tables. To begin your pivot table, choose Data, Pivot Table and Pivot Chart Report. 1 of 18

` MOBILITY PROCEDURES MANUAL

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS

SAN DIEGO - A BICYCLE FRIENDLY CITY

2014 TRANSPORTATION SAFETY SUMMIT LOUISIANA STATE POLICE & LADOTD TIM INITIATIVE

North Avenue Corridor Study. Advisory Committee Meeting #5 June 11, 2014

Bicycle Safety Enforcement Action Guidelines

Welcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU

Crash Analysis. Identify/Prioritize. Gather Data. Analyze Crashes and Identify Improvements. Review Funding Options. Implement Improvements

TEMPORARY TRAFFIC CONTROL SAFETY

Tier 1 Strategies. WV Route 14 Corridor Management Plan

I-95 Corridor Coalition. Best Practices for Border Bridge Incident Management Executive Summary

Construction Business Continuity Management Plan. City Centre Revitalization and Redevelopment Project

Design Guidelines for School Site and Adjacent Lands Planning

Chapter 2. Project Development. 2 Project Development

Section 6 Traffic Analysis

CALTRANS PROJECT MANAGEMENT HANDBOOK

MSP How to guide session 2 (Resources & Cost)

C PTMS Vendor

State of California Department of Transportation. Transportation System Data Business Plan

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS

Safe and Effective Work Zone Inspections

New Jersey SRTS Travel Plan Guide

California PATH, University of California at Berkeley, Building 452, Richmond Field Station 1357 South 46 th Street, Richmond, CA 94804

Background and Goals for the Project

Draft Transportation Management Plan for Via Verdi Repair Project

Project Delivery Process Overview

Transcription:

Montana Department Transportation Work Zone Safety and Mobility Transportation Management Plan Development Process 2015 Background Montana Department of Transportation s WZSM policy and guidance is predicated on the FHWA requirement to include a Transportation Management Plan (TMP) for every project. In most cases, the TMP will consist of a Traffic Control Plan (TCP) only. Many projects will include a Traffic Operations (TO) and Public Involvement (PI) component as well. Significant, or Level 1, projects require that the TCP, TO, and PI are all included in the TMP. TMP Process Ideally, the TMP process should start with the Preliminary Field Review. The Project Design Manager (PDM) is responsible to ensure that the TMP is developed for each project and to ensure that the components of the TMP are incorporated into the project design and plans package as appropriate. A worksheet and a help guide have been developed to facilitate the process. All of the WZSM tools and guidelines are available in the MDT Work Zone Safety and Mobility Toolbox. Depending on the complexity and level of significance for any given project, the PDM is encouraged to enlist members of the design team to help with the TMP development. Headquarters and district construction staff are a critical part of the TMP team for most projects. In addition, the District Construction Operations Engineer has been assigned the role of TMP Coordinator for all projects. This means that he/she will be involved in project design decisions through all phases of design, by participating in project meetings and plan reviews, and in construction decisions including those involving the TMP components. Tasks for a successful TMP: Design stage Staff Tasks responsible Nomination Nominator Review Impact Level Checklist to determine project WZSM significance If significant, check the Significant Work Zone Project box in PPMS Review Appendices TMP Worksheet and Help Guide for potential WZSM strategies; include additional costs in nomination as necessary Preliminary Field Review (PFR) PDM, designer Confirm project WZSM significance If significant, check the Significant Work Zone Project box in PPMS Start the TMP worksheet and save to DMS Review TMP worksheet with design team during PFR Alignment and Grade Review (AGR) PDM, TMP team* Document decisions and estimated costs in PFR report Determine level of TMP necessary for project Identify internal and external stakeholders Fill out or update TMP worksheet to identify applicable strategies to reduce WZSM impacts during construction Focus on traffic management issues and begin drafting Traffic Control and Sequence of Operations special provision. Discuss: Specific treatments for addressing roadside construction hazards Sequencing activities for realistic and efficient construction schedules 1

Scope of Work (SOW) Plan-In-Hand (PIH) Final Plan Review (FPR) PDM PDM, Design team, TMP team* PDM, Design team, TMP Coordinator * See list below for suggested TMP members Signing and delineation during different stages of construction Hauling and roadway crossing operations Temporary advisory, regulatory, and warning signs Needs for requesting project level law enforcement Pedestrian, bicycle, and ADA accommodations Traffic control and construction limitations during community events Acceptable Level of Service (LOS), travel time delay goals and the acceptable queue lengths Need to accommodate wide or oversized loads Document traffic control, sequencing, detour proposals Request traffic information or modeling to determine LOS impacts for strategies such as lane closures Document feedback from public involvement information gathered Review TMP worksheet Discuss and resolve issues related to WZSM strategies Review Special Provisions related to traffic control, sequencing, detours, night time work provisions/requirements, constructability Discuss wide load restrictions and placement of signing Define peak hours, allowed lane or road closures, LOS issues Address safety concerns related to construction work in High Crash Corridors or at locations with recorded crash incidents Address railroad involvement related to WZSM strategies Focus on construction zone issues, safety concerns, traffic control and sequencing Ensure all identified strategies are included in the design or addressed specifically with Special Provisions or notes Ensure WZSM strategies are included in the bid items, as appropriate Contact MCS to ensure oversized loads are appropriately accommodated Answer the following questions: Are the Special Provisions adequate? Is adequate signing provided? Is the appropriate traffic control included? Is a public involvement plan included if necessary? Does the plan set incorporate all of the construction strategies identified in the TMP Worksheet? TMP Team Members for Significant Projects Project Design Manager - required Road plans designer (or consultant designer) Construction Operations Engineer (TMP Coordinator) required Construction Traffic Control Engineer District Construction Engineer, Operations Engineer, or Engineering Project Manager District Engineering Services Engineer, Projects Engineer, or Traffic Engineer Traffic Project Engineer if necessary for capacity issues, safety accommodations such as traffic signals, or signing issues MDT Maintenance Superintendent or Chief FHWA Operations Engineer or Safety/Traffic Design Engineer (required for Projects of Division Interest) City officials for urban projects Emergency Response officials (may be volunteers) 2

On-line Tools and Resources: MDT Work Zone Safety and Mobility Toolbox Impact Level Checklist The Impact Level Checklist is to be used for all projects that have the potential to cause a significant impact to the travelling public during construction. The checklist will assist the nominator or PDM in determining whether or not a project qualifies as a significant, or Level 1, project. TMP Worksheet and Help Guide The worksheet and help guide are meant to be used together. If possible, use the most recent version of the documents from the toolbox, and fill out the worksheet electronically. The help guide will step you through the process of filling out the worksheet. In addition, it contains explanations and definitions for all of the strategies identified in the worksheet as well as considerations to think about before using some of the strategies. The TMP Worksheet has multiple sheets, each with a tab at the bottom of the spreadsheet: 1. Project Background 2. TMP Elements Table 3. Comments & Revisions 4. TMP Issues & Action Items 5. Options Analyses 6. Work Type Codes 7. Work Type Definitions 1. Project Background The first sheet of the worksheet contains project information, project design staff information, and a cost summary. Document as much as possible for easy future reference. Refer to the help guide for instructions on filling out this sheet. 2. TMP Elements Table The second section of the worksheet is used to identify and document potential strategies and associated costs for mitigating work zone safety and mobility impacts. The strategies have been customized to MDT construction practices and follow those listed in the WZSM Guidelines. They are described in more detail in the TMP Help Guide. Each checkbox has a drop-down menu. An X signifies that the TMP team has selected the strategy to be included in the project design and/or plan package. A? means that the strategy may be used. A blank means that the particular strategy will not be used for the project. Costs can be entered when a strategy is selected. Currently, MDT has not started tracking costs for most of the strategies. However, there are some strategies and traffic control devices that have known costs and these should be entered in the worksheet to ensure that the project cost estimate accounts for WZSM items. The TMP Elements Table should be updated as the plan package develops. By Final Plan Review, there shouldn t be any? left in the worksheet. All construction-related strategies that were marked with an X must be included in the final PS&E as appropriate (design details, Special Provisions, bid items, etc.). 3

3. Comments & Revisions Documentation is very important in the TMP process. At a minimum, the TMP will be updated at the various milestones of the project (AGR, SOW, PIH, etc.). Anytime a major element is added or removed, this should be documented as a revision. Questions will come up later in the design process or during construction, and the TMP Worksheet can serve as the one place to track the decisions made regarding specific TMP strategies. The final worksheet, including the comments page, should be provided to the TMP Coordinator. The TMP worksheet will serve as a good reminder for the TMP Coordinator, since he/she should have been involved in all of the major decisions during the design process. 4. TMP Issues & Action Items The TMP Issues & Action Items list can serve as a tracking document for the PDM to document issues that are brought up during discussions with external stakeholders (emergency services, City/County, Highway Patrol, businesses) and during TMP or plan review meetings. For each item, the PDM and team should clearly describe the issue or concern; provide a solution; and list an action item and person responsible. When items are completed, note the completion date in the action column. When items are incorporated into a TMP strategy, describe the action in the action column or on the Comments & Revisions sheet, whichever is more appropriate. 5. Options Analysis The Options Analysis sheet is available to help document and decide between different strategies. For example, one possible scenario may be to shift the alignment to allow traffic to stay on the existing roadway, while another option is to incorporate various design and traffic control strategies. This type of documentation and organized analysis process can help the team, especially when external stakeholders are involved. 6. Project Work Type Codes MDT code numbers assigned to construction work. 7. Work Type Definitions Descriptions of the construction work types to assist with determining the work type code. Additional Information Training presentations and internet resources are available. Work zone related Standard Special Provisions can be accessed through the MDT Standard Specifications link. http://www.mdt.mt.gov/business/contracting/standard_specs.shtml Relevant topics include: Contract Time Detour Construct and Maintain Dust Control Public Advisory Public Relations Incentive, Disincentive Traffic Control and Sequence of Operations Traffic Control Lump Sum Motorcycle Advisory Signs FHWA and Workzonesafety.org have developed on-line clearinghouses for information related to work zone safety and mobility. FHWA has compiled research reports, case studies, state DOT examples and best practices, along with publications that help clarify and guide the Work Zone Safety and Mobility rule. Links are provided on the Highways Bureau work zone safety web page. 4

PPMS Identification There is a Significant Work Zone Project check box on the Header-Nomination page in PPMS. Significant projects can be tracked through OPX2 and PPMS when the check box is used. Both the nominator and the PDM can perform this task. For Level 1 projects, the PDM is expected to check the box when updating cost estimates in PPMS. Conclusion Other tools and resources can be used as needed. Remember, the TMP will continue to evolve and develop over the life of a project. Plan adjustments and the creation of special provisions will help incorporate strategies that were identified using the TMP worksheet. No single person is expected to develop the TMP alone. Input is needed from many disciplines from Design to Construction to Maintenance as well as from external stakeholders. This is intended to be a team-oriented process. 5