SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015



Similar documents
NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES CONSULTATION

STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited

SP Energy Networks Business Plan

RIIO-T1: Decision on fast-tracking for SP Transmission Ltd and Scottish Hydro Electric Transmission Ltd

Integrated Development and Assessment of New Thermoplastic High Voltage Power Cable Systems

SSE s criteria used for GHG emissions reporting

Executive summary 2. 1 Introduction 4

NIA Project Registration and PEA Document

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

Customer Engagement Plan Underground Cable Overlay Cost Reduction Project NIA_SSEPD_0014

Electrical Considerations for HVDC Transmission Lines. Joe Mooney, PE

EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION

Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems

National Grid Electricity Transmission RIIO-T1: Initial Proposals consultation response Supplementary information Strategic Spares

Financing New High Voltage Transmission Lines in Nepal Using HTLS Conductors Surendra Rajbhandari, Nepal Electricity Authority Zhang Lei, ADB South

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

RCP2 Portfolio Overview Document

Smarter Network Storage - business model consultation

SP Transmission RIIO-T1 Business Plan

PB POWER ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS

2012 San Francisco Colloquium

environment briefing02

Infrastructure in a low-carbon energy system to 2030: Transmission and distribution. Final report. for. The Committee on Climate Change

National Grid Electricity Transmission s RIIO-T1 business plan overview

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid

Summary of Electric Transmission Assessment Report

CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE

Overhead lines in Ireland

E-Highway2050 WP3 workshop April 15 th, 2014 Brussels

NEW CABLE? - Understanding the cost to connect renewable generation in Orkney

ASSET MANAGEMENT LCNI 2014 Wednesday 22 nd October. Jennifer Woodruff Innovation & Low Carbon Networks Engineer

AMSC s Superconductor Cable Technologies for Electric Utilities

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

factsheet High Voltage Direct Current electricity technical information

FIXED CHARGE: This is a cost that goes towards making the service available, including

BC Hydro. Electric Distribution System Cost of Service Study

FACT SHEET. BSES, Delhi - Distribution Network. Power Systems Consultancy from ABB

Modeling of Transmission Lines

Guideline for Energy Efficient Electrical systems for building. Presentation by TERI

RIIO T1 Business Plan Update January 2012

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

Integrated Offshore Transmission Project (East) Final Report. Conclusions and Recommendations. August 2015

Earthing Guidance Notes

Offshore wind farm electrical engineering (when considering the operation of array cabling at voltages of 66kV)

HIGH-CAPACITY HIGH TEMPERATURE SUPERCONDUCTING POWER CABLES

Size template. Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer

red zone management white paper Making the most of Distribution Use of System (DUoS) Charges

Innovation in Electricity Networks

Electricity Terminology. Simplifying energy management

INTRODUCTION TO HARMONIC ASSESSMENT IN POWER SYSTEMS

Estimation of electrical losses in Network Rail Electrification Systems

ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1

Engineering Recommendation G81 - Part 1: Design and Planning

National Grid EMR Electricity Capacity Report

The electrical energy produced at the gen

National Fund for Environmental Protection and Water Management. activities in climate protection

National Grid Transmission RIIO-T1: Initial Proposals consultation response Supplementary information Asset painting

Brochure Introducing HVDC

16 West Coast Regional Plan

SP Energy Networks Business Plan

A Review of Engineering Recommendations P15, P17 and P27 (Transformers, Cables and Overhead Lines)

POWER TRANSMISSION FROM OFFSHORE WIND FARMS

Power System review W I L L I A M V. T O R R E A P R I L 1 0,

A least-cost electrification proposal for Kisiizi, Uganda Sten Bergman Sr. Energy Specialist, The World Bank

factsheet High Voltage Direct Current Electricity technical information

Asset Management Plans

STATEMENT OF CHARGES FOR USE OF SP MANWEB s ELECTRICITY DISTRIBUTION NETWORK

ENERGY NETWORKS ASSOCIATION. Electricity Industry EMF Measurement Protocol for High Field Areas

Electricity settlement reform moving to halfhourly

APPLICATION NOTE. Increasing PV Hosting Capacity on LV Secondary Circuits with the Gridco System empower TM Solution

Helping you to understand your SSE bill

FACTS. Solutions to optimise network performance GRID

New range of special alloy conductors Advantages over ACSR & AAAC conductors

Power Voltage Transformers for Air Insulated Substations. THE PROVEN POWER.

HV Submarine Cable Systems Design, Testing and Installation

Asset Management Strategy

VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES

Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives. Final Report

Viking Link Interconnector

ABB PSPS Erich Steinmann; Generator control-2013

ENA Submission to the Parliamentary Renewable and Sustainable Energy Group Inquiry into the access and management of renewables and the Grid

SUMMARY OF CAPITAL EXPENDITURES

Actual capital expenditure during the current regulatory period. Project summary

Good Industry Best Practice Safety Co-ordinator ordinator Guide

ENERGY SAVINGS ACTION PLAN

About electricity distribution networks: now and in the future

Energy Networks Association. Electricity Demand Side Response Working Group. Demand Side Response Shared Services Framework Concept Paper

Transcription:

SHE Transmission 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

Summary This paper presents SHE Transmission s views and approach on the impact of transmission losses on the transmission system. While every measure is taken to minimise transmission losses, there are a number of factors which must be taken into account when making investment decisions and not all of these result in a reduction of transmission losses. All investment planning studies carried out by SHE Transmission take account of transmission system losses to ensure compliance of the transmission system with the National Electricity Transmission System Security and Quality of Supply Standard (NETS SQSS) as required under Standard Licence Condition D3 and section 9(2) of the Electricity Act. In addition, selection and purchase of new transmission plant requires an evaluation of the asset lifetime costs, an important part of which includes the assessment of the capitalised cost of losses. As a Transmission Owner (TO) we do not measure actual losses on the system throughout the year, however our investment planning process does take into account the impact of electrical losses in our network development plans. Our focus is therefore on modelled losses which are assessed against a predefined generation and demand background in accordance with the NETS SQSS. SHE Transmission also considers the impact of losses when undertaking cost-benefit analysis on network expansion and reinforcement options. Losses occur in the transmission system due to the heating of conductors in transmission lines and the heating of transformer windings. Transmission losses also occur due to the magnetisation of overhead line conductors and iron core in transformers. Losses can be reduced through existing overhead line reconductoring, voltage conversion, flexible AC transmission system, HVDC and use of low-loss transformers. Loss reduction strategies are rarely cost-effective when based on the loss reduction alone, however, strategies like reconductoring or voltage upgrade to increase transfer capacity can include loss reduction (savings) as part of a costbenefit analysis to justify the investment. During the RIIO-T1 price control period, SHE Transmission proposes a number of key transmission developments to accommodate the rapid growth in renewable generation in the north of Scotland. These developments include various conventional reinforcement works such as new overhead lines and substations, re-insulation and re-profiling of existing overhead lines as well as new technology such as HVDC links and Static Var Compensators. While all these have a beneficial impact on transmission losses, the rapidly increasing power exports through the network means that overall losses could remain flat or increase slightly over time. Introduction As part of its statutory and Transmission Licence obligations, SHE Transmission has a number of duties including the obligation to publish annual Transmission Losses report for the previous relevant year on or before 31 October 2014 and for each subsequent year, unless the Authority directs otherwise, in accordance with the requirements of the Special Condition 2K of our licence conditions. Losses occur in a transmission system when power is transported from the power generating stations to the grid supply points. There are two main components of losses in a transmission system: fixed losses and variable losses, also classified as no-load Revision 2.0 October 2015 Page 1

losses and load losses respectively. Fixed losses occur in a transmission system by virtue of it being energised and are independent of loading conditions. The fixed losses are made up of corona losses in overhead lines and iron losses in transformers. Variable losses occur due to the loading of the transmission system and are proportional to the load squared. The variable losses are heating losses due to the resistance of the conductor in overhead lines and the resistance of copper in the HV and LV windings of the transformers. Losses can be reduced through existing overhead line reconductoring, bundling of phase conductors, raising nominal voltage, voltage conversion (HVDC), flexible AC transmission system, and use of low-loss transformers, among others. This paper presents our approach to minimise the level of transmission losses on the SHE Transmission system in respect of section 9(2) of the Electricity Act to develop and maintain an efficient, co-ordinated and economical system of electricity transmission. Methodologies As a Transmission Owner (TO) we do not measure actual losses on the system; that is a function of how the system is operated and, hence, is monitored by National Grid as System Operator (SO). Our focus is on modelled losses which are assessed against a predefined generation and demand background. SHE Transmission s investment planning studies are carried out against GB generation and demand backgrounds provided to SHE Transmission by National Grid, the National Electricity Transmission System Operator. Generation backgrounds are based on a future energy scenario approach that has been developed by NGET. Demand and small embedded generation figures are based on the Grid Code week 24 submissions from the local Distribution Network Owner (Scottish Hydro Electric Power Distribution) and any directly connected transmission users. The subsequent system power flow studies used for transmission investment planning and for the assessment of new connections include the assessment for transmission losses. Transmission losses are determined from power load flows under different generation and demand background scenarios using PSS/E power load flow software. Load Related Reinforcement Projects Power flow studies are used to determine the impact of the proposed load related reinforcement projects on transmission losses against generation background at system peak demand in the completion year of the project. Non-load Related Asset Replacement Projects Power flow studies are used to determine the impact of the proposed non-load related asset replacement projects on transmission losses against generation background at system peak demand in the completion year of the project. Material and Equipment Specifications The procurement of materials and equipment (for example, transformers, static VAr compensators and High Voltage Direct Current links) takes account of the whole lifetime costs including transmission losses. Suppliers are provided with a capitalized loss value in /kw to enable the optimum design to be established. Revision 2.0 October 2015 Page 2

Transformers / HVDC Within our tenders for transmission, we consider whether capitalised system losses are a valid criteria to include within our commercial evaluation (these are typically included for tenders for transformers, SVC and HVDC links). Consideration is also given to the inclusion of post completion performance tests to demonstrate losses are no different to loss values given in the tender. Conductors When replacing overhead conductors, an assessment of suitable replacements consistent with the capability of the existing tower structures is undertaken. Where appropriate, this can include a review of the conductor size versus cost, and replacing conventional ACSR conductors with AAAC conductors or new technology conductors which have a lower resistivity. Cables When selecting underground cables for asset replacement or reinforcement projects, consideration is taken on the type of conductor, dielectric material and sheath of the cable in order to select cables that provide optimum solution in terms of installation costs and losses. Annual Reporting To provide a consistent and coordinated approach to the measurement of Transmission Losses for each TO, a joint methodology was agreed between the respective TOs and SO to utilise the existing metering on the National Electricity Transmission System and the apportionment of losses for each respective TO licencee`s system. This methodology sets out principles and assumptions for this calculation to allow each TO to report on their metered Transmission Losses as per the TOs Special Condition 2K.4 (a). (see Appendix 1) Approach to new and alternative technologies SHE Transmission s approach to new and alternative technologies is to apply solutions that offer the greatest potential benefit for transmission customers and our wider stakeholder groups. Our stakeholderled priorities within this approach are to maintain security of supply and to keep costs down. In order to keep costs down and reduce the environmental impact of our activities, we are pursuing opportunities to reduce losses through new technologies. These include the following key examples: ACCC overhead conductor (Project: IFIT 2010_01) We have completed the assessment and trial installation of an Aluminium Conductor Composite Core (ACCC) conductor on a 132kV wood pole transmission line. The design of the ACCC maximises the area of conductive material in the conductor, providing the same power-carrying capacity at a lower operating temperature than in conventional conductor designs. The lower comparative operating temperature leads to reduced losses, as well as a high current-carrying capacity that can defer or avoid the requirement for more costly conventional network reinforcement. We are currently undertaking analysis of the trial results prior to potential transfer to business-as-usual in RIIO-T1. We will also continue to explore conductor opportunities other than the ACCC conductor which offer further opportunities to reduce losses as well as increasing capacity. Revision 2.0 October 2015 Page 3

Multi-terminal test environment for HVDC systems (Project: SSEEN01) A key aspect of SHE Transmission s longer-term strategy to reduce losses is the deployment and optimisation of high voltage direct current (HVDC) systems. HVDC systems are applicable to transmission over longer distances (i.e. greater than 60-70km), where the lower losses exhibited by HVDC systems make them a more economically viable solution than conventional alternating current (AC) systems. SHE Transmission is proposing to establish a collaborative facility which will enable the planning and optimisation of future HVDC systems in GB. This proposal was submitted to Ofgem in August 2013 for consideration as part of the Electricity Network Innovation Competition (NIC). This facility is known as the Multi-Terminal Test Environment (MTTE). It would allow detailed study of the interaction between new HVDC and existing AC networks as well as modelling of operational approaches to optimise DC and AC system performance, potentially leading to reduced losses. The outputs of the MTTE could potentially contribute to reducing losses in the latter years of RIIO-T1. Further information about these priorities and how we apply them in our innovation programme is provided in SHE Transmission s Innovation Strategy submission for RIIO-T1 (p.1, Keeping the lights on and supporting growth: Our strategy for a smarter network, January 2012) at, http://www.ssepd.co.uk/uploadedfiles/controls/lists/resou rces/compliance_report(1)/shetl_innovationstrategyupd atejanuary2012.pdf In addition to these technologies, we are assessing new technologies related to reactive power compensation on the transmission network. While we are at an earlier stage in assessing these technologies, they offer the potential to further reduce losses. A further important aspect of keeping costs down is to maximise the use of existing infrastructure to provide the capacity required by our customers. Our stakeholders have emphasised this as a specific objective for innovation in RIIO-T1 (Ibid., p.7). The new technologies which we are assessing to support delivery of this objective including the following: Maximising the use of existing infrastructure through new technologies: 132kV Crossarm Trial (Project: NIA_SHET_0007) We are trialling innovative insulated crossarms on the towers of an operational 132kV circuit. The purpose of crossarms is to hold the wires clear of the tower body. Retrofitting the innovative crossarms to existing towers can enable the upgrading of existing lines to a higher voltage to enable higher power flows as well as reduce losses. This avoids the higher cost and greater environmental impact of rebuilding the affected lines to provide additional capacity. We are currently undertaking analysis of the trial results prior to potential transfer to business-as-usual in RIIO-T1. We believe the set of new technologies described in this section address the need to reduce losses on our network as well as delivering our priority to deploy solutions which deliver the greatest net benefit for transmission customers and our wider stakeholder groups. Impact of future developments on losses During the RIIO-T1 price control period, SHE Transmission proposes a number of key transmission developments to accommodate the rapid growth in Revision 2.0 October 2015 Page 4

renewable generation in the north of Scotland. These developments include various conventional asset replacement and reinforcement works such as transformer replacements, new overhead lines and substations, re-insulation and re-profiling of existing overhead lines as well as new technology such as HVDC links and Static Var Compensators. While all these have a beneficial impact on transmission losses, the rapidly increasing power exports through the network means that overall losses could remain flat or increase slightly over time. Figure 1 below gives a forecast of the losses in the SHE Transmission network at the time of system peak demand over the next eight years. The figure reflects the relative improvement works against a background of increasing power exports from north to south. Figure 1: SHE Transmission Planned Transfers vs Transmission Losses Transfer (MW) Planned Transfers and Transmission Losses 8000 Gone Green Transfer 500 7000 Transmission Losses 400 6000 5000 300 4000 3000 200 2000 100 1000 0 0 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Year Losses (MW) Revision 2.0 October 2015 Page 5

Issue Revision (no 2.0 October 2015) Scottish and Southern Energy Power Distribution is a trading name of: Scottish and Southern Energy Power Distribution Limited Registered in Scotland No. SC213459; Scottish Hydro Electric Transmission plc Registered in Scotland No. SC213461; Scottish Hydro Electric Power Distribution plc Registered in Scotland No. SC213460; S+S Limited Registered in Scotland No. SC214382 (all having their Registered Offices at Inveralmond House 200 Dunkeld Road Perth PH1 3AQ); and Southern Electric Power Distribution plc Registered in England & Wales No. 04094290 having its Registered Office at 55 Vastern Road Reading Berkshire RG1 8BU which are members of the SSE Group www.ssepd.co.uk