1 Filed: May, EB--00 Page of SUMMARY OF CAPITAL EXPENDITURES.0 SUMMARY OF CAPITAL BUDGET The proposed capital expenditures result from a rigorous business planning and work prioritization process that reflects risk-based decision-making to ensure that the appropriate, cost-effective solutions are put into place to meet Hydro One Transmission objectives. These processes are described in detail at Exhibit A, Tab, Schedules to Schedule. The capital expenditures proposed in this filing represent investments that will ultimately become in-service capital assets supporting the Hydro One Transmission business. Specifically, these expenditures include: a) design and development of specific assets providing future economic benefits; b) purchase, construction and commissioning of specific assets providing future economic benefits; c) additions to specific assets; and d) betterments that result in improvement of capacity, efficiency, useful life span, or economy of specific assets. As described in the following schedules of this Exhibit, the proposed capital programs address Hydro One Transmission s integrated set of asset replacement and expansion needs to meet its objectives of: public and employee safety; maintenance of transmission reliability at targeted performance levels; meeting system growth requirements; compliance with regulatory requirements (such as specified within the Transmission System Code); environmental requirements; and Government direction. The

2 Updated: August, EB--00 Page of development of these capital programs is based on comprehensive asset condition information, system loading versus capacity information and various studies. Hydro One Transmission's capital budget is grouped into four different investment categories: Sustaining, Development, Operations, and Shared Services Capital. Table provides a summary of Hydro One Transmission s capital expenditures for the historical, bridge and test years. Table Summary of Transmission Capital Budget ($ Million) Including Capitalized Overheads and Interest Capitalized* Description Historic Bridge Test 0 Sustaining Development Operations Shared Services Capital TOTAL ,.,. *AFUDC for the period 0 to The Transmission Capital requirements continue to grow over the to period to address asset replacement and refurbishment needs of Hydro One s aging system, and to expand the system for the purposes of load growth, accommodating a modified generation mix, and expanding access to interconnected electricity markets. The increase in Sustaining expenditures is primarily due to the continued growth in the number of assets that are beyond their expected service life and have been identified as either in poor condition and at end of life, obsolete with no spare parts available, or requiring replacement in order to satisfy changes in the regulations that govern the transmission business.

3 Filed: May, EB--00 Page of Investment Summary Documents in support of capital projects with cash flows in excess of $.0 million in either or are filed at Exhibit D, Tab, Schedule..0 SUSTAINING The Sustaining capital program includes the costs for investments required to replace or refurbish components to ensure that existing transmission system facilities function as originally designed. Hydro One Transmission manages its sustaining program within two program categories, namely stations and lines. Details of the expenditures under this program are provided at,, Schedule..0 DEVELOPMENT The Development capital program consists of the investments required to upgrade or enhance transmission system capabilities to address load growth, generation connection requirements and transmission congestion, and to ensure that the system is designed and operated in a safe, secure and reliable manner. Details of the expenditures under this program are provided at,, Schedule..0 OPERATIONS The Operations capital program represents investments in infrastructure required to sustain the Central Transmission Operations function, which is operated from Hydro One's Ontario Grid Control Centre. Details of the expenditures under this program are filed at,, Schedule.

4 Filed: May, EB--00 Page of.0 SHARED SERVICES AND OTHER CAPITAL Shared Services capital consists of the sustainment and enhancement of existing equipment and infrastructure, including computer-related hardware and software, facilities and transport and work equipment, as well as projects initiated to improve business support functions. Shared Services investments are described in detail at, Tab, Schedules through..0 COMPARISON OF CAPITAL COSTS TO BOARD APPROVED Table provides a comparison between the actual capital expenditures and the expenditures approved by the Board in its Decision on Hydro One Transmission s previous application in Proceeding EB Table Board Approved versus Actual Capital Expenditures Capital Category Board Actuals Variance Approved ($ million) ($ million) ($ million) Sustaining.. (.0) Development 0.. (.) Operations.. (.) Shared Services.. (.) Total,.. (.) Hydro One Transmission s capital expenditures in were approximately $ million lower than the level approved by the Board due to the following offsetting work program factors: The Sustaining under-expenditure was driven by delays in the System Re-investment program, due to the complexity of a number of projects resulting in more time

5 Filed: May, EB--00 Page of required for planning and engineering as well as resolution of stakeholder issues (primarily Beck # SS); a Toronto underground cable replacement project due to unexpected difficulties with obtaining land easements; and the Protection & Control program, due to complexities encountered in several projects in the detailed engineering phase. This was partially offset by the acceleration of power transformer replacements due to unit failures and to mitigate the risk of further failures due to the poor condition of specific units. The Development program variance is primarily due to delays in customer projects, Tremaine and Barwick TS, delays in the Toronto Area projects, Leaside and Hearn due to outage scheduling and land acquisition issues, as well as several of the SVC projects coming into service under budget. The Operations program is under spent primarily due to delays in the Back-up Control Centre facility costs and the Wide Area Network (WAN) program costs. Shared Services actual capital expenditures were lower than approved primarily due to lower Facilities and Real Estate and fleet spending initially planned for that was ultimately deferred. This is partially offset by the shift of Cornerstone savings which were netted out against the Cornerstone spend in Board approved; the actuals reflect the Cornerstone savings within Sustaining, Development and Operations as well as Shared Services program/project spending. Table provides a comparison between the projected capital expenditures and the expenditures approved by the Board in their Decisions in Proceedings EB and EB--0.

6 Updated: August, EB--00 Page of Table Board Approved versus Projected Capital Expenditures Capital Category Board Bridge Year Approved ($ million) ($ million) Variance ($ million) Sustaining... Development.. (.) Operations.. (0.) Shared Services... Total. 0.0 (.) Hydro One Transmission s projected capital expenditures in are $ million below the expenditure levels approved by the Board in EB--000 and EB--0 due to the following work program factors. The Sustaining over-expenditure is primarily due to the continued acceleration of the power transformer replacements to mitigate the risk of failures due to the poor condition of specific units. This is partially offset by Cornerstone savings and further delays in the System Re-investment program. The Development program is under spent primarily due to the new Bruce to Milton project coming into service under budget, the impact of the load and generation related project delays cascading into, as well as the suspension of some of the Green Energy projects identified in proceeding EB The Operations program is under spent primarily due to the delays in the Back-up Control Centre and the WAN project. The WAN implementation is underway but will have lower spending in than originally forecast. The increased Shared Services capital costs are due to the shift of Cornerstone savings which were netted out against the Cornerstone spend in Board Approved; the bridge year forecast reflects the Cornerstone savings within Sustaining, Development and Operations as well as Shared Services program/project spending.

7 Updated: August, EB--00 Page of.0 STATUS OF NIAGARA REINFORCEMENT PROJECT (NRP) As of the summer of 0, completion of the project has been indefinitely delayed due to unforeseen circumstances which are out of the control of Hydro One Transmission. Expenditures to date are $ million. In its Decision with Reasons in EB-0-00, the Board decided to allow Hydro One Transmission to expense rather than capitalize the AFUDC¹ associated with the project based on the actual expenditures made to date, effective January, 0 with no explicit time limit as it remains uncertain when the Caledonia dispute will be resolved. As a result, through the current Ontario Uniform Transmission Rates, Hydro One is recovering the AFUDC¹ associated with NRP. Hydro One Transmission is continuing to apply this OEB directive and as such the interest capitalized associated with NRP has been included in the and Revenue Requirement (as referenced in Exhibit E, Tab, ). In its EB-0-00 Decision, the Board also stated that if Hydro One requires additional relief prior to the project being completed and in-service, it is free to bring an application seeking such further relief. Hydro One Transmission remains hopeful that at some point it will be able to complete the NRP and is not seeking further relief at this time. ¹ As of January,, no allowance for funds used during construction (AFUDC) rate is specified for use by Hydro One, consistent with the OEB s decisions in EB See, Tab, for details.

ASSET MANAGEMENT PLANNING PROCESS

ASSET MANAGEMENT PLANNING PROCESS Filed: -0- EB--0 Tab Page of ASSET MANAGEMENT PLANNING PROCESS.0 INTRODUCTION Hydro One s Asset Management Plan is a systematic approach to determine and optimize on-going operating and maintenance expenditures

More information

OPERATIONS CAPITAL. The Operations Capital program for the test years is divided into two categories:

OPERATIONS CAPITAL. The Operations Capital program for the test years is divided into two categories: Filed: September 0, 00 EB-00-0 Tab Schedule Page of OPERATIONS CAPITAL.0 INTRODUCTION Operations Capital funds enhancements and replacements to the facilities required to operate the Hydro One Transmission

More information

Attachment 2-1 Distribution System Plan Attachment 2-2 OEB Appendix 2-FA and 2-FC REG Expansion Investment

Attachment 2-1 Distribution System Plan Attachment 2-2 OEB Appendix 2-FA and 2-FC REG Expansion Investment Waterloo North Hydro Inc. EB-2015-0108 Exhibit 2 Page 1 of 95 Filed: May 1, 2015 TABLE OF CONTENTS 2.5 EXHIBIT 2 - RATE BASE.... 2 2.5.1 Rate Base...2 2.5.1.1 Overview... 2 2.5.1.2 Gross Assets Property

More information

COST EFFICIENCIES/PRODUCTIVITY

COST EFFICIENCIES/PRODUCTIVITY Updated: 0-0-0 EB-0-0 Schedule Page of 0 COST EFFICIENCIES/PRODUCTIVITY.0 INTRODUCTION Hydro One has updated this exhibit to improve the information on Cost Efficiencies and Productivity initiatives and

More information

SUPPLY CHAIN SERVICES

SUPPLY CHAIN SERVICES EB-0-0 Exhibit F Schedule Page of SUPPLY CHAIN SERVICES INTRODUCTION Supply Chain supports THESL asset management plans by ensuring that all required goods and services are available when needed. Strong

More information

HYDRO ONE LIMITED REPORTS FOURTH QUARTER 2015 RESULTS

HYDRO ONE LIMITED REPORTS FOURTH QUARTER 2015 RESULTS HYDRO ONE LIMITED REPORTS FOURTH QUARTER 2015 RESULTS Quarterly results reflect a number of timing, unusual and unseasonal weather related items while core operations remain strong; Board declares first

More information

SHARED SERVICES CAPITAL - CORNERSTONE

SHARED SERVICES CAPITAL - CORNERSTONE Filed: May, 0 EB-0-00 Exhibit D Schedule Page of SHARED SERVICES CAPITAL - CORNERSTONE.0 OVERVIEW The Cornerstone Project is part of the overall information technology ( IT ) strategy to replace several

More information

INTRODUCTION AND SUMMARY OF O&M COSTS

INTRODUCTION AND SUMMARY OF O&M COSTS EB-00-0 Exhibit F Tab Schedule Page of CUSTOMER SERVICES INTRODUCTION AND SUMMARY OF O&M COSTS The Customer Services division performs activities that are required to provide services to customers connected

More information

COMMON CORPORATE COSTS CAPITAL - INFORMATION TECHNOLOGY

COMMON CORPORATE COSTS CAPITAL - INFORMATION TECHNOLOGY Updated: 0-0-0 EB-0-0 Tab Page of COMMON CORPORATE COSTS CAPITAL - INFORMATION TECHNOLOGY.0 OVERVIEW 0 Information Technology ( IT ) refers to computer systems (hardware, software and applications) that

More information

2012 Capital Expenditure Status Report NP 2013 CBA. 2012 Capital Expenditure Status Report

2012 Capital Expenditure Status Report NP 2013 CBA. 2012 Capital Expenditure Status Report NP 2013 CBA June 2012 NP 2013 CBA Newfoundland Power Inc. 2012 Capital Expenditure Status Report Explanatory Note This report is presented in compliance with the directive of the Board of Commissioners

More information

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 SHE Transmission 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 Summary This paper presents SHE Transmission s views and approach on the impact of transmission losses on the transmission

More information

PROJECT PROCUREMENT PROCEDURES AND GUIDELINES

PROJECT PROCUREMENT PROCEDURES AND GUIDELINES CAPITAL ASSET MANAGEMENT PROJECT PROCUREMENT PROCEDURES AND GUIDELINES June 2003 Updated June 20, 2003 Ministry of Education Province of British Columbia TABLE OF CONTENTS EXECUTIVE SUMMARY... iii 1.0

More information

PROJECT AND PORTFOLIO MANAGEMENT - NUCLEAR

PROJECT AND PORTFOLIO MANAGEMENT - NUCLEAR Page 1 of 5 PROJECT AND PORTFOLIO MANAGEMENT - NUCLEAR 1.0 PURPOSE This evidence provides an overview of the nuclear operations project portfolio and other related project work. The project portfolio includes

More information

TRANSMISSION BUSINESS PERFORMANCE

TRANSMISSION BUSINESS PERFORMANCE Filed: 0-0- Tx 0-0 Rates Tab Schedule Page of TRANSMISSION BUSINESS PERFORMANCE.0 INTRODUCTION 0 Hydro One is focused on the strategic goals and performance targets in the area of safety, customer satisfaction,

More information

2015 ANNUAL OPERATING AND FINANCIAL PLAN

2015 ANNUAL OPERATING AND FINANCIAL PLAN 2015 ANNUAL OPERATING AND FINANCIAL PLAN TABLE OF CONTENTS 2015 ANNUAL OPERATING AND FINANCIAL PLAN Executive Summary... 3 Summary... 7 Revenue and Expenditure Overview... 15 2015 Enterprise Financial

More information

FUNCTIONAL AREA 12. Network Administration (NET)

FUNCTIONAL AREA 12. Network Administration (NET) FUNCTIONAL AREA 12 Network Administration (NET) Incumbents in this functional area address interoperability issues related to hardware, software, and connectivity of communications such as cable, fiber

More information

APPENDIXB ONTARIO ENERGY BOARD GUIDELINES FOR ASSESSING AND REPORTING ON NATURAL GAS SYSTEM EXPANSION IN ONTARIO

APPENDIXB ONTARIO ENERGY BOARD GUIDELINES FOR ASSESSING AND REPORTING ON NATURAL GAS SYSTEM EXPANSION IN ONTARIO Was Appendix, preliminary page 2 247 APPENDIXB ONTARIO ENERGY BOARD GUIDELINES FOR ASSESSING AND REPORTING ON NATURAL GAS SYSTEM EXPANSION IN ONTARIO 1998 248 CONTENTS Was Appendix, preliminary page 3

More information

Disaster Recovery Plan Test. Audit Report

Disaster Recovery Plan Test. Audit Report ATTACHMENT 4 Disaster Recovery Plan Test Audit Report Internal Audit Report TABLE OF CONTENTS Section Page No. 1.0 MANAGEMENT SUMMARY...2 2.0 INTRODUCTION...2 3.0 OBJECTIVES AND SCOPE...3 4.0 METHODOLOGY...3

More information

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date

More information

New York State 2100 Commission Report: Energy

New York State 2100 Commission Report: Energy New York State 2100 Commission Report: Energy Improving Strength and Resilience Phil Mihlmester New York Bar Association Columbia University Law School New York, NY May 14, 2014 Context: Aftermath of Hurricane

More information

Managing Utility Capital Projects Using Enterprise Project Portfolio Management Solutions

Managing Utility Capital Projects Using Enterprise Project Portfolio Management Solutions An Oracle White Paper January 2012 Managing Utility Capital Projects Using Enterprise Project Portfolio Management Solutions Executive Overview Utility executives worldwide face a precarious balancing

More information

How To Plan For A New Power Plant In Manitoba

How To Plan For A New Power Plant In Manitoba Meeting Manitobans Electricity Manitoba is growing and is expected to continue doing so. Over the last years the province has enjoyed an expanding population and economy. These increases have led to many

More information

So, What Exactly is Risk Management?

So, What Exactly is Risk Management? So, What Exactly is Risk Management? By Paul Wielgus, Managing Director, GDS Associates, Inc. Buyers, sellers, and others in the energy business need to understand the risks in this very uncertain environment

More information

We are working hard to help Ontario businesses manage their electricity costs.

We are working hard to help Ontario businesses manage their electricity costs. Ontario Minister of Energy Meets with Chamber Network, Addresses Key Concerns In August 2015, the Ontario Chamber of Commerce released Empowering Ontario, a comprehensive report that takes a look at the

More information

Scorecard MD&A - General Overview

Scorecard MD&A - General Overview Scorecard MD&A - General Overview In 2014, Essex Powerlines Corporation has exceeded all performance targets except for the Net Annual Peak Demand Savings. Essex has seen improvement in some areas from

More information

16 West Coast Regional Plan

16 West Coast Regional Plan 16 West Coast Regional Plan 16.1 Regional overview 16.2 West Coast transmission system 16.3 West Coast demand 16.4 West Coast generation 16.5 West Coast significant maintenance work 16.6 Future West Coast

More information

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15 (Schedule B);

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15 (Schedule B); Ontario Energy Board Commission de l énergie de l Ontario EB-2007-0063 IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15 (Schedule B); AND IN THE MATTER OF applications by electricity

More information

Toronto Hydro-Electric System Limited ( THESL ) 2011-2020 Electrical Distribution Capital Plan

Toronto Hydro-Electric System Limited ( THESL ) 2011-2020 Electrical Distribution Capital Plan Toronto Hydro-Electric System Limited EB-2010-0142 Exhibit D1 Tab 8 Schedule 10 ORIGINAL (33 pages) Toronto Hydro-Electric System Limited ( THESL ) 2011-2020 Electrical Distribution Capital Plan June 2010

More information

Written Direct Evidence. Filed: April 24, 2008 EB-2007-0050 Exhibit A Tab 5 Schedule 3 Page 1 of 12

Written Direct Evidence. Filed: April 24, 2008 EB-2007-0050 Exhibit A Tab 5 Schedule 3 Page 1 of 12 Written Filed: April 24, 2008 Page 1 12 Page 2 12 Robert Chow Leave to Construct Application Bruce-Milton Transmission Reinforcement Project 2 A.1 My name is Mr. Robert Chow and my business address is

More information

Project Name 2012 2013 2014 Engineering Capital 9.50 9.50 9.50 Worst Performing Feeder 6.10 24.50 24.50 Customer Connections (net of Customer

Project Name 2012 2013 2014 Engineering Capital 9.50 9.50 9.50 Worst Performing Feeder 6.10 24.50 24.50 Customer Connections (net of Customer EB 0 00 Tab Schedule C Page of I OPERATIONS PORTFOLIO CAPITAL OVERVIEW THESL s Operations Portfolio Capital is made up of the following components: Engineering Capital Worst Performing Feeder Capital Customer

More information

ONTARIO ENERGY BOARD AFFIDAVIT OF TODD WILLIAMS

ONTARIO ENERGY BOARD AFFIDAVIT OF TODD WILLIAMS File No. EB-2005-0523 ONTARIO ENERGY BOARD IN THE MATTER OF the Ontario Energy Board Act, 1988, S.O. 1998, C.15, Schedule B. AND IN THE MATTER OF a proceeding initiated by the Ontario Energy Board to make

More information

Asset Management Plan

Asset Management Plan Asset Management Plan Final Report May 2014 EXECUTIVE SUMMARY Adequate municipal infrastructure such as roads, bridges, and underground water and sewage pipes are essential to economic development, citizen

More information

Addressing Barriers to Renewable Energy Procurement. In association with the EPA Green Power Partnership

Addressing Barriers to Renewable Energy Procurement. In association with the EPA Green Power Partnership Addressing Barriers to Renewable Energy Procurement In association with the EPA Green Power Partnership September 19, 2012 CORPORATE GOALS Corporations are increasingly interested renewable energy. The

More information

DRAFT TECHNICAL REPORT AND BUSINESS CASE FOR THE CONNECTION OF REMOTE FIRST NATION COMMUNITIES IN NORTHWEST ONTARIO FOR

DRAFT TECHNICAL REPORT AND BUSINESS CASE FOR THE CONNECTION OF REMOTE FIRST NATION COMMUNITIES IN NORTHWEST ONTARIO FOR DRAFT TECHNICAL REPORT AND BUSINESS CASE FOR THE CONNECTION OF REMOTE FIRST NATION COMMUNITIES IN NORTHWEST ONTARIO FOR NORTHWEST ONTARIO FIRST NATION TRANSMISSION PLANNING COMMITTEE AUGUST, 0 Page of

More information

Recommended Practice for Software Acquisition

Recommended Practice for Software Acquisition Recommended Practice for Software Acquisition PSIG 003/2000 Objective: To develop a set of practices that may be used in the acquisition of pipeline simulation software. Pipeline Simulation Interest Goup,

More information

DISASTER RECOVERY PLANNING FOR CITY COMPUTER FACILITIES

DISASTER RECOVERY PLANNING FOR CITY COMPUTER FACILITIES APPENDIX 1 DISASTER RECOVERY PLANNING FOR CITY COMPUTER FACILITIES March 2008 Auditor General s Office Jeffrey Griffiths, C.A., C.F.E. Auditor General City of Toronto TABLE OF CONTENTS EXECUTIVE SUMMARY...1

More information

CITY OF GLENDALE CALIFORNIA REPORT TO CITY COUNCIL

CITY OF GLENDALE CALIFORNIA REPORT TO CITY COUNCIL FORM CM-36 CITY OF GLENDALE CALIFORNIA REPORT TO CITY COUNCIL February 7,2012 AGENDA ITEM Request for Approval to Issue a Request for Qualification (RFQ) of Firms, and Request for Proposal (RFP) to Engineer,

More information

NETWORK OUTPUT MEASURES CONSULTATION

NETWORK OUTPUT MEASURES CONSULTATION NETWORK OUTPUT MEASURES CONSULTATION Great Britain s electricity transmission network transmits high-voltage electricity from where it is produced to where it is needed throughout the country. It broadly

More information

Scorecard - Oakville Hydro Electricity Distribution Inc.

Scorecard - Oakville Hydro Electricity Distribution Inc. Scorecard - Oakville Hydro Electricity Distribution Inc. 9/24/215 Performance Outcomes Performance Categories Measures 21 211 212 213 214 Trend Industry Distributor Target Customer Focus Services are provided

More information

PUBLIC UTILITIES COMMISSIO~t~ Docket No. DE 15-

PUBLIC UTILITIES COMMISSIO~t~ Docket No. DE 15- Th~NALZZ~ Exhibit STATE OF NEW HAMPSHIRE t~~eeee BEFORE THE FROM FILE PUBLIC UTILITIES COMMISSIO~t~ Liberty Utilities (Granite State Electric) Corp. dibla Liberty Utilities Calendar Year 2014 Reliability

More information

UPTIME MAGAZINE. june/july15 JUNE/JULY 2015. uptimemagazine.com

UPTIME MAGAZINE. june/july15 JUNE/JULY 2015. uptimemagazine.com june/july15 UPTIME MAGAZINE JUNE/JULY 2015 uptimemagazine.com AM Developing Plans Creating Value From Physical Assets by Mark Ruby 46 june/july 15A sset management plans form the cornerstone of an effective

More information

New York s Transmission Challenges and Opportunities: An Overview

New York s Transmission Challenges and Opportunities: An Overview New York s Transmission Challenges and Opportunities: An Overview By: Dr. Matthew Cordaro 2012 is shaping up to be the year of the grid. Governor Cuomo has proposed an energy highway aimed at finding ways

More information

Post-Sandy Municipal Needs Assessment for Long-Term Recovery and Resiliency Planning EXECUTIVE SUMMARY

Post-Sandy Municipal Needs Assessment for Long-Term Recovery and Resiliency Planning EXECUTIVE SUMMARY Post-Sandy Municipal Needs Assessment for Long-Term Recovery and Resiliency Planning EXECUTIVE SUMMARY Prepared by Nathaly Agosto Filión, Resiliency Manager for the New Jersey Resiliency Network, a program

More information

Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy

Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy Network Program Deliverability Strategy 2015-20 Regulatory Control Period SA Power Networks www.sapowernetworks.com.au Internal

More information

INVESTMENT SUMMARY FOR PROGRAMS/PROJECTS IN EXCESS OF $3 MILLION

INVESTMENT SUMMARY FOR PROGRAMS/PROJECTS IN EXCESS OF $3 MILLION Filed: September 30, 2008 EB-2008-0272 Exhibit D2 Tab 2 Schedule 3 Page 1 of 80 1 2 INVESTMENT SUMMARY FOR PROGRAMS/PROJECTS IN EXCESS OF $3 MILLION 3 4 5 6 7 8 Sustaining Capital S1 to S36 Development

More information

APPENDIX D DISTRIBUTION WIRES ONLY RATE BASE

APPENDIX D DISTRIBUTION WIRES ONLY RATE BASE APPENDIX D PAGE 1 APPENDIX D DISTRIBUTION WIRES ONLY RATE BASE This appendix is composed of the following three parts: 1. Part I - Guidelines for determining the distribution or wires only assets and activities;

More information

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology 2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology Version Number 1 26 June 2015 Tasmanian Networks Pty Ltd (ACN 167 357 299) Table of contents 1 Introduction... 1 2 Meeting our

More information

Township of Terrace Bay Drinking Water System Financial Plan

Township of Terrace Bay Drinking Water System Financial Plan Township of Terrace Bay Drinking Water System Financial Plan August 2014 Introduction Municipalities in Ontario recently adopted a full accrual accounting approach to tangible municipal assets in accordance

More information

Energy Management System (EMS) 3.0 Implementation Overview for BRP Consultation. July 2015

Energy Management System (EMS) 3.0 Implementation Overview for BRP Consultation. July 2015 Energy Management System (EMS) 3.0 Implementation Overview for BRP Consultation July 2015 Background Energy Management System EMS - Used by System Controllers to monitor, control and optimize the performance

More information

Q2 2014 Earnings Presentation July 30, 2014

Q2 2014 Earnings Presentation July 30, 2014 Q2 2014 Earnings Presentation July 30, 2014 1 Safe Harbor Statement Certain statements in the Business Update and Order Backlog sections contain forward-looking statements within the meaning of the safe

More information

Auditor General of Canada to the House of Commons

Auditor General of Canada to the House of Commons 2010 Report of the Auditor General of Canada to the House of Commons FALL Chapter 1 Canada s Economic Action Plan Office of the Auditor General of Canada The Fall 2010 Report of the Auditor General of

More information

ACQUISITION AND PROCUREMENT: NEW JERSEY HIGH-SPEED RAIL IMPROVEMENT PROGRAM HAS COST AND SCHEDULE RISKS

ACQUISITION AND PROCUREMENT: NEW JERSEY HIGH-SPEED RAIL IMPROVEMENT PROGRAM HAS COST AND SCHEDULE RISKS ACQUISITION AND PROCUREMENT: NEW JERSEY HIGH-SPEED RAIL IMPROVEMENT PROGRAM HAS COST AND SCHEDULE RISKS Audit Report OIG-A-2015-012 June 17, 2015 DRAFT REPORT Page intentionally left blank NATIONAL RAILROAD

More information

Ontario s s Water and Wastewater Energy Management Best Practices

Ontario s s Water and Wastewater Energy Management Best Practices Ontario s s Water and Wastewater Energy Management Best Practices Erin Cain February 27 th, 2007 AWWA/WEF Joint Management Conference February 25-28, 2007 Introduction What can I take back and apply? Energy

More information

Overview of the IESO-Administered Markets. IESO Training. Updated: January, 2014. Public

Overview of the IESO-Administered Markets. IESO Training. Updated: January, 2014. Public Overview of the IESO-Administered Markets IESO Training Updated: January, 2014 Public Overview of the IESO-Administered Markets AN IESO TRAINING PUBLICATION This guide has been prepared to assist in the

More information

GRAND ERIE DISTRICT SCHOOL BOARD

GRAND ERIE DISTRICT SCHOOL BOARD D-2-c GRAND ERIE DISTRICT SCHOOL BOARD TO: FROM: RE: John Forbeck, Director of Education & Secretary David Abbey, Assistant Superintendent of Education Information Technology Services Annual Report DATE:

More information