RIIO-T1: Decision on fast-tracking for SP Transmission Ltd and Scottish Hydro Electric Transmission Ltd
|
|
|
- Augustus Golden
- 10 years ago
- Views:
Transcription
1 To generators, shippers, suppliers, network companies, consumers and their representatives, the sustainable development community, investors and other interested parties Promoting choice and value for all gas and electricity customers Our ref: 07/12 Direct Dial: Date: 23 January 2012 Dear colleague RIIO-T1: Decision on fast-tracking for SP Transmission Ltd and Scottish Hydro Electric Transmission Ltd The next transmission price control (RIIO-T1) is the first price control 1 to be conducted under our new RIIO (Revenue = Incentives + Innovation + Outputs) model. The price control is due to run from 1 April 2013 to 31 March The objective of RIIO is to encourage network companies to play a full role in the delivery of a sustainable energy sector, and to do so in a way that delivers value for money for existing and future consumers. This letter sets out the Authority s decision that the business plans of SP Transmission Ltd (SPTL) and Scottish Hydro Electric Transmission Ltd (SHETL) are of sufficient quality to be consulted upon through fast-tracking Initial Proposals with a view to reaching early settlement of their price controls, ie that their business plans are suitable for fasttracking. It provides a high-level summary of our assessment of the companies business plans. It also sets out the key components of their plans that will form our Initial Proposals for their price controls. Our decision to fast-track SPTL s and SHETL s plans, subject to consultation, reflects the significant improvement in the plans in both cases since their initial submission in July 2011, and the value that the plans provide to consumers and wider stakeholders. As set out in our October letter 2, in RIIO-T1 we have provided for greater iteration between the first business plan submission and our fast-track decision than we intend in the future, including in RIIO-GD1 and RIIO-ED1. As network companies learn what is expected from them under RIIO, for example in terms of a more joined up assessment, testing different options and employing long-term thinking across the whole plan, we do not consider there will be a requirement for significant iteration as the quality of the initial submissions should be higher. Importantly, this does not mean that we are lowering the bar for a company to be fast-tracked in RIIO-T1. SPTL and SHETL have published revised versions of their RIIO-T1 business plans. These will be available at the following links: 1 We are currently in the process of setting price controls for the gas distribution companies RIIO-GD1 but that process is being taking forward on a separate timetable. 2 Initial assessment of RIIO-T1 business plans and proportionate treatment
2 SPTL SHETL We intend to publish our consultation on Initial Proposals for both SPTL and SHETL on 6 February, and will seek views from stakeholders at that point. In the meantime, if you would like to discuss any aspect of this letter, please contact Grant McEachran on or by ing [email protected]. Background Under the RIIO process, network companies are required to take into account the needs and views of stakeholders in order to submit to us well-justified business plans. We are taking a proportionate approach to our scrutiny of companies plans, i.e. the level of our regulatory scrutiny varies according to the quality of plans. Companies that submit very high quality plans will be able to agree price controls early, i.e. achieving fast-tracking. In March 2011, we set out our Strategy Decision for RIIO-T1. 3 This set out decisions on the key aspects of the regulatory framework. It also set out what we expected to see in a welljustified business plan and the criteria against which we would assess such a plan. We used five broad criteria to assess the plans: Process: has the company followed a robust process? Outputs: does the plan deliver the required outputs? Resources (efficient expenditure): are the costs of delivering the outputs efficient? Resources (efficient financial costs): are the proposed financing arrangements efficient? Uncertainty/risk: how well does the plan deal with uncertainty and risk? We received the transmission owners (TOs) RIIO-T1 business plans at the end of July Our assessment in October concluded that none of the plans was suitable for fasttracking in their existing format. However, we also took into consideration that this was the first time any company had submitted a business plan under the RIIO framework and that the scale of the outstanding issues for SPTL and SHETL may allow them to resolve these in a timeframe consistent with fast-tracking. On this basis we retained SPTL and SHETL in the fast-tracking process. Our assessment outlined the issues SPTL and SHETL would need to address in order for us potentially to develop Initial Proposals in early We considered that the outstanding issues for National Grid Electricity Transmission plc (NGET) and National Grid Gas Transmission plc (NGG) were not resolvable in this timeframe. Consequently, NGET and NGG reverted to the non-fast-tracking process. SPTL and SHETL s revised business plans Following the publication of our initial assessment of the companies plans both SPTL and SHETL have undertaken a significant amount of further work to revise their plans. Both have undertaken more work in key areas, provided further supporting information and carried out further stakeholder engagement. Both companies have submitted revised versions of their business plans. Our updated assessment is based on all of the information provided to us as part of this process. It is also informed by responses to our October business plan assessment and views received from the Consumer Challenge Group (CCG) 4. 3 Decision on strategy for the next transmission price control: RIIO-T1 Ofgem, 31 March 2011 Ref:46/ The CCG comprises consumer and environmental experts acting as a critical friend to Ofgem in the RIIO-T1 and RIIO-GD1 processes. 2 of 6
3 Assessment of revised business plans This section summarises our updated assessment of each of SPTL s and SHETL s revised business plans. This covers the five criteria we used in the initial assessment. SPTL and SHETL have taken different approaches to their business plans. In taking a decision on fasttracking we have therefore assessed each plan as a package. We are satisfied that both packages as a whole provide value for money to both existing and future consumers and demonstrate how they will meet the challenges associated with facilitating the move to a low carbon economy. SP Transmission Ltd (SPTL) In relation to its process SPTL has addressed our key concerns. It has undertaken further stakeholder engagement and increased its stakeholder database. It has also provided information in relation to omissions from the key content in its July business plan. SPTL has made changes to a number of its output and incentive parameters which provide better value to customers. In particular, it has changed its proposals in relation to the primary outputs for reliability and connections which bring it into line with the positions set out in our Strategy Decision document. It has provided more information in relation to its processes for developing a network availability policy and customer satisfaction survey. It has also provided more information on their environmental outputs and recognises there is room to refine these further. The area where SPTL has made most progress since October is in relation to its justification around cost efficiency. It has provided a wide range of additional material including evidence of the robustness of its processes to ensure efficiency, shown that a large proportion of its cost base is subject to competitive tenders and provided additional information to demonstrate how it will deliver its plan. SPTL s unit costs are comfortably within our consultants range. SPTL has revised elements of its financial proposals. It has reduced its cost of equity assumption, increased notional gearing and introduced a fixed rate of totex capitalisation. SPTL has made revisions to its approach to dealing with risk and uncertainty. It has proposed volume drivers that are tightly defined both in terms of scope and unit costs and set out a similarly well defined mechanism for wider works. Scottish Hydro Electric Transmission Ltd (SHETL) In relation to its process SHETL has undertaken further stakeholder engagement and increased its stakeholder database. It has also provided information in relation to omissions from the key content in their July business plan. SHETL has made changes to a number of its output and incentive parameters. Several of these, including its environmental outputs, network availability policy and customer satisfaction, will be strengthened by further detail in the coming months. SHETL has provided more information and revised plans in relation to both its costs and risk and uncertainty to address our concerns that its July plan transferred a disproportionate risk onto consumers. SHETL has made substantial changes to its financial package since the July plan, bringing it in line with our policies and ranges. Among the key changes it has made are applying straight line depreciation to new assets, with a 16-year transition; reducing the assumed cost of equity from 8.25% over the first four years of the RIIO-T1 period and 7.5% thereafter to 7% throughout the RIIO-T1 period; increasing notional gearing from 50% in the first four years of the RIIO-T1 period and 55% thereafter to 55% throughout the RIIO- 3 of 6
4 T1 period; removing the uplift to the cost of debt index; and applying a fixed totex capitalisation rate. Decision on fast-tracking and proportionate treatment SPTL SPTL has addressed the key outstanding issues we had with their July business plan. In a wide range of areas it has provided more detail and in a number of areas it has changed its proposals. We note there are areas where SPTL could improve and we are outlining below some areas in relation to stakeholder engagement and outputs where we expect further work to be undertaken. Overall we consider the package put forward by SPTL provides good value for consumers. On this basis, we are putting forward SPTL s business plan for fast-tracking and intend to publish Initial Proposals shortly. SHETL SHETL has made significant progress in addressing the outstanding issues we had with its July business plan. It has provided more detail in various areas of the plan and put forward innovative proposals in a number of areas. Most notably SHETL has proposed significant changes to its financial package. As with SPTL there are areas where SHETL could improve. We outline below some areas in relation to stakeholder engagement and outputs where we expect further work to be undertaken. Overall we consider the package put forward by SHETL provides good value for consumers. On this basis, we are putting forward SHETL s business plan for fast-tracking and intend to publish Initial Proposals shortly. Summary of SPTL and SHETL s business plans The fast-tracking Initial Proposals for SPTL and SHETL will be developed and published shortly, based on the information set out in their business plans. The key elements of those plans are summarised in Table 1 below. 4 of 6
5 Table 1: Summary of SPTL and SHETL s business plans Area SPTL SHETL Outputs Complete range of RIIO outputs including baseline deliverables and the strength of the financial incentives Complete range of RIIO outputs including baseline deliverables and the strength of the financial incentives Environmental strategy Expenditure (nominal prices) Baseline capex Capex subject to uncertainty mechanisms Controllable Opex Financial parameters Cost of equity (post-tax real) Notional gearing Cost of debt (pre-tax real) Depreciation profile Some areas of best practice in its environmental outputs i.e. baseline for SF 6 emissions and commitment to mitigation measures for visual amenity 1.8bn 0.7bn (SPTL best view) 0.3bn Some areas of best practice in its environmental outputs i.e. transmission losses and a visual amenity statement 1.1bn 4.0bn (SHETL best view) 0.4bn 7% 7% 55% 55% Indexed using 10 year simple trailing average Straight line: 20 years on existing assets, 45 years on new assets Indexed with bespoke weightings tracking Totex profile Straight line: 20 years on existing assets, 45 years on new assets one price control period two price control periods Asset life transition Totex capitalisation rate 90% 90% Efficiency incentive rate 50% 50% Uncertainty mechanisms Including, but not limited to, Including, but not limited to, a volume driver for volume drivers for generation connections, a generation connections, within-period revenue within-period revenue determination for specified determinations for specified large overhead line large wider reinforcement replacement projects and projects including where wider reinforcement works. possible costs associated with visual amenity. Innovation Set out an innovation strategy and requested an Innovation Allowance of 0.75% Set out an innovation strategy and requested an innovation allowance of 1% and a reprofiling of the allowance over the period. SPTL and SHETL s proposals are set out in more detail in their revised business plans which are published on their websites. Areas for further work While we consider both SPTL and SHETL s plans are suitable to be put forward for fasttracking we recognise there are areas for further work in both plans. Under RIIO, we expect significant changes from network companies in terms of the way they operate and engage with consumers. While both companies have made considerable strides forward over the last year, there is inevitably more that they could do. 5 of 6
6 The areas where we will be expecting both SPTL and SHETL to undertake further work are: Environmental strategy While both plans set out baselines for some of the environmental outputs required in the RIIO-T1 strategy, both have further work to do to firm up the performance levels they will deliver across all of the environmental outputs. We expect the companies to provide more detail on their processes to finalise the outstanding areas to inform our decisions on Final Proposals. Stakeholder engagement We note the significant progress both companies have made in this area and welcome their commitments to do more going forward. Network availability and customer satisfaction These are areas where all of the TOs continue to work together to further develop the outputs. We expect that work to continue over the coming months to ensure the new arrangements are in place for the start of RIIO-T1. Both companies requested network innovation allowances of greater than the minimum which was provided for in the March strategy document. Having reviewed the companies innovation strategies, we do not consider that either company has yet provided sufficient justification for their proposed allowance. However, if either company considers that they can justify a higher level of allowance then they may put forward further evidence. We will consider that evidence, alongside any consultation feedback, in setting the Final Proposals. Next steps In light of our assessment we will consult on Initial Proposals for SPTL and SHETL. We intend to publish those proposals along with further detail on our assessment of the revised plans on 6 February We will provide a six week consultation period and will require responses by 19 March. We will set out our final decision on fast-tracking and, if appropriate, Final Proposals for one or both companies in April If, in light of feedback to our Initial Proposals, we decide not to fast-track SPTL and/or SHETL then they will revert to the non fast-track process. Alongside our Initial Proposals we also intend to consult on additional financial incentives to sharpen the environmental considerations demonstrated by the transmission companies throughout the RIIO-T1 period. We had set out our intention to consult in this area in our March 2011 Strategy Decision document. The proposal set out in this document would apply to NGET as well as SPTL and SHETL. We will also publish our Final Proposals in this area in April NGET and NGG are required to resubmit their business plans by 5 March We will consult on Initial Proposals for NGET and NGG in July Yours sincerely Hannah Nixon Acting Senior Partner, Smarter Grids and Governance: Transmission 6 of 6
RIIO-T1 business plan submission London Tuesday 6 September 2011
RIIO-T1 business plan submission London Tuesday 6 September 2011 Cautionary statement This presentation contains certain statements that are neither reported financial results nor other historical information.
Interaction between business context and an appropriate WACC for ESBN
Interaction between business context and an appropriate WACC for ESBN A REPORT PREPARED FOR ESB NETWORKS September 2013 Frontier Economics Ltd, London. Confidential July 2013 Frontier Economics i Interaction
The Implementation of the RIIO Framework
The Implementation of the RIIO Framework EPRG Winter Conference James Grayburn December 2014 Cambridge This presentation assesses Ofgem s implementation of RIIO framework following introduction of new
National Grid Electricity Transmission s RIIO-T1 business plan overview
MARCH 2012 National Grid Electricity Transmission s RIIO-T1 business plan overview Connecting a sustainable future UK ELECTRICITY TRANSMISSION Contents 01 Introduction 02 The structure of our plan 03 Context
SP Energy Networks 2015 2023 Business Plan
Environmental Discretionary Reward Scheme 1 SP Energy Networks 2015 2023 Business Plan Executive summary SP Distribution Ltd SP Manweb plc July 2013 RIIO ED1 Business Plan 2015 to 2023 2 A Message from
Duncan Burt Head of Commercial Operation National Grid. The Office of Gas and Electricity Markets 9 Millbank London SW1P 3GE
National Grid House Warwick Technology Park Gallows Hill, Warwick CV34 6DA The Office of Gas and Electricity Markets 9 Millbank London SW1P 3GE 16 June 2015 Duncan Burt Head of Commercial Operation National
Glossary of terms: RIIO-T1 and GD1 review
Glossary of terms: RIIO-T1 and GD1 review A Administrative burden Things that business must do or other administrative costs that businesses sustain due to a requirement from regulation. This may include
Dear Colleague, Summary
System Operators, Transmission and Transportation System Owners, Generators, Shippers, Suppliers, Customers, Investors and other interested parties Date: 20 December 2013 Dear Colleague, Consultation on
RIIO T1 Business Plan Update January 2012
UPDATE RIIO T1 Business Plan Update January 2012 Executive Summary Purpose of this Document In accordance with Ofgem s fast-track process, this updated Executive Summary sets out SP Transmission Limited
National Grid Gas Transmission s RIIO-T1 business plan overview
MARCH 2012 National Grid Gas Transmission s RIIO-T1 business plan overview Connecting a sustainable future UK GAS TRANSMISSION Contents 01 Introduction 02 The structure of our plan 03 Context 05 Our key
We hope all the questions are understandable, If you have any difficulties please email
Appendix 2- FEEDBACK QUESTIONNAIRE (word format) Thank you for taking the time to respond to our questions We hope all the questions are understandable, If you have any difficulties please email Once the
SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015
SHE Transmission 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 Summary This paper presents SHE Transmission s views and approach on the impact of transmission losses on the transmission
RIIO-T1 & RIIO-GD1: UNCERTAINTY ISSUES
RIIO-T1 & RIIO-GD1: UNCERTAINTY ISSUES A REPORT FOR CENTRICA February 2011 Final report - for publication Submitted by: CEPA LLP CONTENTS Executive Summary... i 1. Introduction... 1 1.1. Purpose... 1 1.2.
SP Transmission RIIO-T1 Business Plan
SP Transmission RIIO-T1 Business Plan July 2011 Contents Context Executive summary 1 1. Overview 3 1.1 Energy Market Reform 3 2. Capital investment, deliverability and associated outputs 4 2.1 Load Related
National Grid Gas plc Annual Report and Accounts 2015/16. Company number 2006000
National Grid Gas plc Annual Report and Accounts 2015/16 Company number 2006000 National Grid Gas plc Annual Report and Accounts 2015/16 Contents National Grid Gas plc Annual Report and Accounts 2015/16
NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited
NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2 2.0
ANNEX 27: CORPORATE GOVERNANCE, COMPLIANCE AND DATA ASSURANCE BUSINESS PLAN ANNEX
ANNEX 27: CORPORATE GOVERNANCE, COMPLIANCE AND DATA ASSURANCE BUSINESS PLAN ANNEX Electricity North West Limited Registered Office: 304 Bridgewater Place, Birchwood Park, Warrington, Cheshire. WA3 6XG.
NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited
NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2
Transmission Price Control Review: Updated Proposals and Smithers & Co. Ltd.: Report on the Cost of Capital. Response to consultation
Transmission Price Control Review: Updated Proposals and Smithers & Co. Ltd.: Report on the Cost of Capital Response to consultation Prepared by Ian Rowson, IMR Solutions On behalf of: BG Gas Services
Data Communications Company (DCC) price control guidance: process and procedures
Guidance document Contact: Tricia Quinn, Senior Economist Publication date: 27 July 2015 Team: Smarter Metering Email: [email protected] Overview: The Data and Communications Company (DCC) is required
RULE DETERMINATION Rule Proponents
RULE DETERMINATION National Electricity Amendment (Economic Regulation of Network Service Providers) Rule 2012 National Gas Amendment (Price and Revenue Regulation of Gas Services) Rule 2012 Rule Proponents
Electricity Market Reform:
Electricity Market Reform: Consultation on Low Carbon Contracts Company s and Electricity Settlements Company s operational costs 2015/16 Government Response January 2015 Crown copyright 2015 URN 15D/001
https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework
All interested parties Direct Dial: 020 7901 1849 Email: [email protected] Date: 17 November 2015 Dear Colleague EPC Contract Principles for OFTO Build Tenders This letter provides guidance
Report on the EMR Delivery Body s performance of its functions in relation to the Capacity Market
Report on the EMR Delivery Body s performance of its functions in relation to Report Publication date: 19 June 2015 Team: EMR Team Contact: Sujitra Krishnanandan; Matthew Pearson Tel: 020 3263 9832; 020
The Levy Control Framework
Report by the Comptroller and Auditor General Department of Energy & Climate Change The Levy Control Framework HC 815 SESSION 2013-14 27 NOVEMBER 2013 4 Key facts The Levy Control Framework Key facts 2bn
Consultation on United Utilities statement of risks, strengths and weaknesses 2015/16 Our 2015-20 annual performance reporting
Consultation on United Utilities statement of risks, strengths and weaknesses 2015/16 Our 2015-20 annual performance reporting United Utilities performance reporting Consultation on our statement of risks,
PROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
NETWORK OUTPUT MEASURES CONSULTATION
NETWORK OUTPUT MEASURES CONSULTATION Great Britain s electricity transmission network transmits high-voltage electricity from where it is produced to where it is needed throughout the country. It broadly
UNSOLICITED PROPOSALS
UNSOLICITED PROPOSALS GUIDE FOR SUBMISSION AND ASSESSMENT January 2012 CONTENTS 1 PREMIER S STATEMENT 3 2 INTRODUCTION 3 3 GUIDING PRINCIPLES 5 3.1 OPTIMISE OUTCOMES 5 3.2 ASSESSMENT CRITERIA 5 3.3 PROBITY
Value for Money Assessment Guidance: Capital Programmes and Projects
Value for Money Assessment Guidance: Capital Programmes and Projects October 2011 Value for Money Assessment Guidance: Capital Programmes and Projects Foreword This guidance has been prepared and issued
Offshore Transmission: Guidance for Cost Assessment Guidance Document
Promoting choice and value for all gas and electricity customers Offshore Transmission: Guidance for Cost Assessment Guidance Document Reference: 183/12 Contact Roger Morgan, Senior Manager Publication
Project Assessment Framework Establish service capability
Project Assessment Framework Establish service capability July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below.
Innovation in Electricity Networks
OPPORTUNITIES IN ENERGY SG2 Innovation in Electricity Networks physical & digital network security Contents Introduction... 1 Innovation in electricity networks... 1 The smart grid opportunity... 2 Physical
Information Requirements: Business Plan. Trinidad & Tobago Electricity Commission
Information Requirements: Business Plan June 01, 2011 May 31, 2016 Trinidad & Tobago Electricity Commission November 2010 This document is one of a series of discussion papers exploring a specific aspect
This document outlines Wales & West Utilities Business Plan for the next regulatory period from 2013-2021.
This document outlines Wales & West Utilities Business Plan for the next regulatory period from 2013-2021. It has been prepared following extensive consultation with a wide range of stakeholders and reflects
Private Health Insurance Ombudsman
Private Health Insurance Ombudsman Health and Ageing Portfolio Agency Section 1: Overview...448 Section 2: Resources for 2006-07...449 2.1: Appropriations and Other Resources...449 2.2: 2006-07 Budget
Water Charges Plan Decision Paper (Executive Summary)
Water Charges Plan Decision Paper (Executive Summary) DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: QUERIES TO: Decision Paper CER/14/746 30 September 2014 [email protected] The Commission for Energy
The Transport Business Cases
Do not remove this if sending to pagerunnerr Page Title The Transport Business Cases January 2013 1 Contents Introduction... 3 1. The Transport Business Case... 4 Phase One preparing the Strategic Business
UTILITY REGULATOR WATER. Water & Sewerage Services Price Control 2015-21
Water & Sewerage Services Price Control 2015-21 Final Determination Annex A Financing Investment December 2014 Contents Page Water and Sewerage Services Price Control 2015-21 Final Determination Annex
UK Power Networks Business plan (2015 to 2023) Executive summary
UK Power Networks Business plan (2015 to 2023) Executive summary July 2013 The most reliable, most innovative, lowest price electricity distribution group. ukpowernetworks.co.uk Foreword 1 2 3 4 5 6 7
REGULATORY ACCOUNTING GUIDELINES FOR TRINIDAD AND TOBAGO ELECTRICITY COMMISSION DRAFT FOR CONSULTATION
REGULATORY ACCOUNTING GUIDELINES FOR TRINIDAD AND TOBAGO ELECTRICITY COMMISSION DRAFT FOR CONSULTATION January 2008 C O N T E N T S Page No. 1. Overview 1 2. Introduction 3 3. RIC s Regulatory Framework
Retained Fire Fighters Union. Introduction to PRINCE2 Project Management
Retained Fire Fighters Union Introduction to PRINCE2 Project Management PRINCE2 PRINCE stands for: PRojects IN Controlled Environments and is a structured method which can be applied to any size or type
PRELIMINARY DECISION CitiPower distribution determination 2016 20
PRELIMINARY DECISION CitiPower distribution determination 2016 20 Attachment 8 Corporate income tax October 2015 8-0 Attachment 8 Corporate income tax CitiPower determination 2016 20 Commonwealth of Australia
RII0-GD1. Business Plan
RII0-GD1 Business Plan A guide to this document This document is the business plan of Northern Gas Networks (NGN) for the period from April 2013 to March 2021. Its primary purpose is to demonstrate to
december 08 tpp 08-5 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper
december 08 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper Preface The NSW Government is committed to the ongoing improvement of public services by ensuring
A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM)
A new electricity market for Northern Ireland and Ireland from 2016 - Integrated Single Electricity Market (I-SEM) Non-technical summary High level design Draft Decision Paper SEM -14-047 June 2014 1 INTRODUCTION
Reorganising central government. Synergy reporting for Mergers and Acquisitions
Reorganising central government Synergy reporting for Mergers and Acquisitions MARCH 2010 Contents Drawing parallels with the private sector National Audit Office Synergy reporting for Mergers and Acquisitions
Thames Tideway Tunnel Cost of capital
Thames Tideway Tunnel Cost of capital CEPA briefing note 25 th August 2015 Introduction Thames Water over the past nine months has run a competitive licence application to appoint the Infrastructure Provider
Smart metering A REPORT PREPARED FOR CENTRICA. October 2007. Frontier Economics Ltd, London.
Smart metering A REPORT PREPARED FOR CENTRICA October 2007 Frontier Economics Ltd, London. i Frontier Economics October 2007 Smart metering Executive summary...1 1.1 Introduction...1 1.2 The case for
Synergies and Conflicts of Interest arising from the Great Britain System Operator delivering Electricity Market Reform
Synergies and Conflicts of Interest arising from the Great Britain System Operator delivering Electricity Market Reform Final report URN: 13D/088 Department of Energy and Climate Change 3 Whitehall Place
Proposed debt assignment protocol for prepayment customers. A consultation document
Proposed debt assignment protocol for prepayment customers A consultation document Summary Ofgem is committed to removing any unnecessary barriers preventing customers from switching suppliers. This document
2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology
2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology Version Number 1 26 June 2015 Tasmanian Networks Pty Ltd (ACN 167 357 299) Table of contents 1 Introduction... 1 2 Meeting our
15 April 2011 Re: Expansion of the Victorian Energy Efficiency Target
Mr Anthony Williamson Principal Policy Officer, Energy Sector Development Division Department of Primary Industries Email: [email protected] 15 April 2011 Re: Expansion of the Victorian
Annex A Feed-in Tariff with Contracts for Difference: Operational Framework
Annex A Feed-in Tariff with Contracts for Difference: Operational Framework November 2012 Contents Executive Summary... 5 Document Overview... 9 1. Introduction... 10 The Energy Bill: The Legal Framework
Network Rail Infrastructure Projects Joint Relationship Management Plan
Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf
Project Management Guidebook
METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple
Accessing finance. Developing a business case for your resource efficiency projects
Accessing finance Developing a business case for your resource efficiency projects Developing a business case for your resource efficiency projects 2 Contents 1 Planning a resource efficiency project?
Reforming the business energy efficiency tax landscape
Reforming the business energy efficiency tax landscape Consultation response from: Emission Trading Group (ETG) Contact details: John Craven, [email protected] ETG welcomes this review of the business
Accessing finance. Developing a business case for your resource efficiency projects
Accessing finance Developing a business case for your resource efficiency projects Developing a business case for your resource efficiency projects 2 Contents 1 Planning a resource efficiency project?
National Grid Electricity Transmission RIIO-T1: Initial Proposals consultation response Supplementary information Strategic Spares
National Grid Electricity Transmission RIIO-T1: Initial Proposals consultation response Supplementary information Strategic Spares Table of contents Executive summary... 2 Introduction... 4 Replenishment
Government response: EMR consultation on industry code and licence modifications
Government response: EMR consultation on industry code and licence modifications June 2014 Crown copyright 2014 Copyright in the typographical arrangement and design rests with the Crown. This publication
Electricity settlement reform moving to halfhourly
Electricity settlement reform moving to halfhourly settlement Launch Statement Publication date 4 April 2014 Contact: Jonathan Amos and Jeremy Adams- Strump Team: Smarter Markets Tel: 0207 901 7000 Email:
Appendix 5 Oadby and Wigston Borough Council: HRA self-financing business plan model
Appendix 5 Oadby and Wigston Borough Council: HRA self-financing business plan model As we enter the final quarter of 2013/14, the HRA business plan model has been updated to reflect activity in 2013/14
Financeability and financing the asset base a discussion paper
Water today, water tomorrow Financeability and financing the asset base a discussion paper www.ofwat.gov.uk About this document This document focuses on two of our primary duties, which are to: further
Wholesale power market liquidity: consultation on a Secure and Promote licence condition
Promoting choice and value for all gas and electricity customers Wholesale power market liquidity: consultation on a Secure and Promote Consultation Reference: 163/12 Contact: Phil Slarks, Senior Economist
Financial Settlement Strategy
Financial Settlement Strategy We are seeking stakeholders views on the questions set out in this consultation document. If you have any comments on the paper please contact: [email protected]
Monitoring Highways England The monitoring framework
Monitoring Highways England The monitoring framework October 2015 Contents Executive summary 4 Roads reform 4 ORR s role in monitoring Highways England 5 What we will do next 10 1. Overview of this document
EXPLANATORY MEMORANDUM TO THE CONTRACTS FOR DIFFERENCE (ELECTRICITY SUPPLIER OBLIGATIONS) REGULATIONS 2014. 2014 No. [XXXX]
EXPLANATORY MEMORANDUM TO THE CONTRACTS FOR DIFFERENCE (ELECTRICITY SUPPLIER OBLIGATIONS) REGULATIONS 2014 2014 No. [XXXX] 1. This explanatory memorandum has been prepared by the Department for Energy
Annual EMR Compliance Report. National Grid Electricity Transmission plc
Annual EMR Compliance Report National Grid Electricity Transmission plc Prepared pursuant to paragraphs 2N.25 and 2N.26 of Special Condition 2N of the Electricity Transmission Licence granted to National
Manchester City Council
Manchester City Council Accounts Audit Plan 2009/10 18 December 2009 Contents Page 1 Introduction 2 2 Approach and audit risks 3 3 Administration 13 4 Planned outputs 16 Appendices A B IFRS Action Plan
Contract and Vendor Management Guide
Contents 1. Guidelines for managing contracts and vendors... 2 1.1. Purpose and scope... 2 1.2. Introduction... 2 2. Contract and Vendor Management 2.1. Levels of management/segmentation... 3 2.2. Supplier
NEW CABLE? - Understanding the cost to connect renewable generation in Orkney
New Holland, Holm 500kW Partner of Choice in Mid-Size Wind NEW CABLE? - Understanding the cost to connect renewable generation in Orkney Hammer, Westray 500kW Colin Risbridger Windflow UK Development Manager
