Technologies & Management Systems that Work: Current Best Practice in Nuclear New Build

Similar documents
Lessons Learned from past NPP Construction Technology/Management

UAE Nuclear Power Programme : Status and Update

Hitachi s Involvement in Nuclear Power Plant Construction in Japan

Advanced Construction Methods for New Nuclear Power Plants

Olkiluoto 3 Experience

Westinghouse AP1000 PWR and the Growing Market for New Nuclear Power Plants

Building New Generation Nuclear Plants Worldwide : AREVA's Experience

The ABWR Project at Shimane-3, Japan

1.040 Project Management

The World Nuclear Supply

Olkiluoto 3 Project. AREVA Suppliers Day Warsaw October 4, 2011

The ACR : Advanced Design Features for a Short Construction Schedule

Engineering, Procurement and Construction (EPC) Projects

Auditing Capital Projects and Project Controls. March 2013

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3

Russian approach to organization of international cooperation in the field of nuclear infrastructure (NI)

AP1000 Technology: Passive & Proven

Accenture Management Consulting. Open Roles

Ensuring Quality Going Down the Supply Chain

C-41 (May 13) Procurement Engineering and Supply Chain Guidelines in Support of Operation and Maintenance of Nuclear Facilities

CONSTRUCTION EXPERIENCE FROM MODULAR NUCLEAR POWER PLANTS

ROK s Assistance Programs for New comers

Planning, Organisation and Control of Resources in Construction and the Built Environment

Best Practices and Approaches to Supply Chain Management

ENEC Management System and Quality Assurance Program

VENDOR PREQUALIFICATION QUESTIONNAIRE

DOE O 226.1A, IMPLEMENTATION OF DEPARTMENT OF ENERGY OVERSIGHT POLICY CONTRACTOR ASSURANCE SYSTEMS CRITERIA ATTACHMENT 1, APPENDIX A

Financing Nuclear Power Projects: Challenges and IAEA Assistance in Capacity Building

Introduction to Social Compliance & Its Business Benefits

Technical Meeting on Fire Protection Approaches and Experiences in Nuclear Power Plants

Vogtle. Twelfth Semi-annual Vogtle Construction Monitoring Report. units 3 & 4. February 2015 Docket No

R000. Revision Summary Revision Number Date Description of Revisions R000 Feb. 18, 2011 Initial issue of the document.

IAEA Safety Standards for Regulatory Activities

Materials Management:

REPORT 2016/035 INTERNAL AUDIT DIVISION

POWER & RENEWABLE ENERGY SERVICES

MISSION REPORT ON THE INTEGRATED NUCLEAR INFRASTRUCTURE REVIEW (INIR)

How to successfully manage your mega-project

MANAGEMENT SYSTEM FOR A NUCLEAR FACILITY

POWER & RENEWABLE ENERGY SERVICES

Experience and Qualifications of PROCESS PLANTS CORPORATION

MNLARS Project Audit Checklist

QUALITY ASSURANCE GUIDE FOR PROJECT MANAGEMENT

Capacity Building and Human Resource Development for Nuclear Power Programmes

& Start-up Directory

Quality Management Plan

Global Nuclear Power Developments Asia Leads The Way


PROJECT AND PORTFOLIO MANAGEMENT - NUCLEAR

The Role of Nuclear Knowledge Management

Engineering Procurement Construction Quality Plan

Nuclear Consultancy & Engineering Services

DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM

PROCUREMENT OF MAINTENANCE SERVICES AND HEALTH AND SAFETY AT WORK

September 20, 2011 SUBJECT: NRC INSPECTION REPORT NO / AND NOTICE OF NONCONFORMANCE

The Comprehensive Coatings Service Provider to Industry

QUALITY MANAGEMENT SYSTEM REVIEW AND APPROVAL TEMPLATE (DOE G A, Appendix A, )

Quality Assurance QUALITY ASSURANCE PLAN

AREVA: supply chain network principles and company s vision

Industry Solutions Oil and Gas Engineering Document Control and Project Collaboration Solutions for Oil and Gas

Long term operation integrated processes for delivering extended asset performance

Join the UK Nuclear Renaissance. Procurement & Quality Process

TOSHIBA s Nuclear Energy Activities

AP1000 European 18. Human Factors Engineering Design Control Document

NOT PROTECTIVELY MARKED

Executive Development Workshop. A Systems Approach to Inventory Management

JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013

Qualification of In-service Inspections of NPP Primary Circuit Components

WORK SCOPE. Domains in which we work:

Cyber Security and the Canadian Nuclear Industry a Canadian Regulatory Perspective

SUPPLIER QUALITY MANAGEMENT SYSTEM QUESTIONNAIRE

ABSTRACT. The Guidelines Section F is related to the Purchasing requirements of NSQ100 (Chapter 7.4). Summary

NZQA registered unit standard version 2 Page 1 of 5. Develop and implement a project plan to deliver on an Infrastructure works contract

MSD Supply Chain Programme Strategy Workshop

How to successfully manage your mega-project. Part III Continuously improve your chances for project success. kpmg.com

JOINT INTEGRITY MANAGEMENT SOLUTIONS

Part 1 General and Administrative Information. Part 3 Applicant s Environmental Report Combined License Stage

ALL PRODUCTS MFG & SUPPLY

AREVA, an unparalleled experience in building nuclear reactors

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

APPENDIX B SUPPLEMENTAL INSPECTION PROGRAM A. OBJECTIVES AND PHILOSOPHY OF THE SUPPLEMENTAL INSPECTION PROGRAM

Quality Management System

PM in construction industry

INSPECTION AND CONSTRUCTION MANAGEMENT CAPABILITIES

Introduction Building project management

Rev: Issue 4 Rev 4 Quality Manual AOP0101 Date: 10/07/13. Quality Manual. CBT Technology, Inc. 358 North Street Randolph, MA 02368

Bogue Machine Company, Inc. Business Instruction

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

AS9100 Quality Manual

EXHIBIT 2-2-C PROGRESS SCHEDULES

CHARACTERISTICS OF SUCCESSFUL MEGAPROJECTS

Quality Assurance Manual ISO 9001:2000. Uncontrolled copy

Title: Rio Tinto management system

3.03 College Board Advanced Placement Test means the Advanced Placement test administered by the College Board and Educational Testing Service.

COMPARISON OF ELECTRICITY GENERATION COST OF NPP WITH ALTERNATES IN PAKISTAN

Transcription:

Technologies & Management Systems that Work: Current Best Practice in Nuclear New Build John H. Moore Nuclear Power Division j.h.moore@iaea.org Paris, France March 11, 2014 (OECD Workshop) International Atomic Energy Agency

Exciting Times! International Atomic Energy Agency

Barakah-Unit 1, UAE July 20 2012 Concrete pouring after approval of PSAR. Unit 2 followed May 2013. The United Arab Emirates is the first country to start the construction of its first nuclear power plant in 27 years, since construction was started on China's first plant in 1985.

Sanmen, China Jan 29, 2013 AP-1000 Containment vessel top head placement; Sanmen, China

VC Summer Unit 2, USA March 10/11, 2013 First concrete pour of a new NPP in North America in three decades. Followed closely followed by concrete pours at Vogtle Unit 3 (and later by Summer 3 and Vogtle4)

Other recent starts (2013 and 2014) Belarus; China (3); South Korea; Argentina.

Current status 18 Construction Starts 80 Under Construction 16 14 12 10 8 6 4 2 0 70 60 50 40 30 20 10 0 Europe-Western Europe-Central & East Asia-Middle East & South Asia-Far East America-North America-Latin Source: PRIS 05-Mar-2014

NPP Guidance Nuclear Facility Guidance Safety Requirements MANAGEMENT SYSTEM GUIDANCE

GS-G-3.5 Mgmt System for Nuclear Installations - Appendix V Construction Things to do: Define roles and interfaces; Grade requirements based on safety significance; Have well defined processes; Define handover and responsibility transfer processes; Plan activities;

GS-G-3.5 Mgmt System for Nuclear Installations - Appendix V Construction Things to do (continued): Have kick off meetings; Control design information; Maintain cleanliness; Maintain control of material; Prevent damage during storage and handling; Verify construction work.

Verification of Construction Work Need to have: Methods/schedules for verification that specify levels of inspection & verification required; Suppliers must verify all procurement requirements have been satisfied; Construction activities should follow inspection and test plans (ITPs) approved by organization (Owner);

Verification of Construction Work ITPs should have appropriate hold / witness points for owner to verify acceptability; Plan to be prepared to ensure design and regulatory requirements met; Process required to verify construction activities; Verification normally documented via check sheets or similar means to record that SSCs have been constructed and installed to specified requirements.

Example quality issues (Sanman, China) RCP impeller : Irregularities welded without documentation; Squib Valve : Manufacturer used components and subcontractor without proper equipment qualification.

BEST PRACTICE PUBLICATIONS

Project Management in NPP Construction Construction management Preparatory phase; Construction phase (after concrete pouring); Commissioning phase; Main issues and lessons learned Selection of local suppliers; Bulk material management; Worker turnover; Construction equipment; Massive movements of people and material; Public perception; Construction phase closure activities; Country specific lessons learned

Construction Technologies for New NPPs Goal: Achieving optimum construction schedule for future NPP construction projects. Content: Comprehensive descriptions of all construction methods; Advantages / disadvantages; Best practices; Lessons learned.

Some sample beneficial technologies Early engineering / front end planning; Site construction management support systems Modularization and open top construction; Advanced welding; 4 season construction.

Early Engineering Reduce Site Manpower by 40% Previous Design Process Basic Design Detailed Design Construction Construction Engineering Front-Loaded Construction Engineering Basic Design Requirements from Construction Engineering Detailed Design Inputs from Plant Design (BOQ, Composite Design, etc.) Construction Construction Engineering Source : From Hitachi construction experience

Issues with a Gen 3+ project 18000 design changes by end of 2013; Lead time for nuclear side design change approvals from one month to six months; Engineering completion behind schedule; Insufficient support for regulatory review from off-shore team. Should improve for nth of a kind

Site construction management support 建 設 工 程 3D-model linked to schedule

6D construction schedules 3D model + Quantities + Resources + Time = 6D database Develop detailed construction schedule by area based on quantities and labour resources; Simulate schedule with 3D-model. 3D-model by construction area Quantities based on 3D-model Schedule loaded with quantities and resources Assign labour resource

Modularization Upper Drywell Module RPV RCCV Top Slab Stator (650 ton) (900 ton) (550 ton) (420 ton) RCCV Lower Liner Module Upper Condenser Module 630 ton) (270 ton) RPV Pedestal Module Base Mat Module HPU Module Lower Condensor Unit (410 ton) (460 ton) (270 ton) (260 ton)

Sep 27, 2010 Unit 1 CA01 lifting.

Man Power (arb.) Manpower Peak Reduction Effort - Construction & Module Experience- 4 Based on previous ABWR (Conventional Method) 3 Level-off Manpower Peak 2 1 Manpower Distribution 1 6 11 16 21 26 31 36 41 Construction Progress Based on Latest ABWR (month)

Advanced Welding Techniques Quality welding is crucial and time consuming; Advanced Techniques Metal Arc Welding; Gas Tungsten Arc Welding; Submerged Arc Welding; Automatic welding equipment is very effective; Maintains high quality; Improves work environment in narrow spaces.

Automatic Welding Machine Automatic Welding Machine for RCCV Liner Automatic Welding for Large Bore Piping Automatic Welding for Small Bore Piping (CRD piping)

Four season construction Provides factory-like environment for construction during winter; Secures environment for: Welding; Concrete pouring & curing; Protection from equipment; Allows around the clock work.

冬 期 稼 働 率 [%] Four season construction Buildings with the All-Weather Structure (Steel and Temporary cover) Movable Temporary Roof 100 95 90 85 Improvement of Work Productivity during winter 80 75 70 個 別 養 生 耐 候 工 法 全 天 候 耐 候 工 法

CONSTRUCTION READINESS REVIEW SERVICE

REVIEW SERVICES Phase 1 Phase 2 Phase 3 NPP site review mission IPPAS mission INSSERV mission SCART mission Pre- OSART mission ISSAS mission EPREV mission INIR mission Milestone 1 Milestone 2 NPP construction review mission INIR mission Milestone 3 30

Construction Readiness Reviews Focus is on a specific NPP construction project (new build or refurbishment), not the overall programme. Must have design chosen and construction preparations underway at a very detailed level. Guidelines finalized and published. Service available now!

REVIEW SERVICES Phase 1 (commit to programme) Phase 2 (invite bids) Phase 3 (commission and operate) NPP site review mission IPPAS mission Stage 1 Construction INSSERV Preparation. mission SCART mission Pre- OSART ISSAS mission Stage 2 EPREV Construction Execution. mission INIR mission INIR mission NPP construction review mission INIR mission Milestone 1 Milestone 2 Milestone 3 32

Construction readiness reviews Areas Reviewed: Project Management; Engineering Readiness; Procurement / Material / Supply Chain Readiness; Quality Management and Records; Human Resources and Training; Construction Readiness; Construction Installation Completion Assurance; Targeted Reviews (as requested by customer).

Project management area Scope control; Front end planning; Risk management; Project oversight; Project scheduling; Contract & Estmating; procurement Metrics; strategies; Alignment; Change control; Community support; Delay/suspension provisions. Roles & responsibilities;

Engineering readiness area Documentation; Feedback incorporation; Design change process; Planning; Configuration mgmt, controlled docs & records; Computer & cyber security; Review of previous work (if delayed project); Eng. Programmes; Eng. quality (Ph2 review).

Procurement / material / supply chain readiness Equip./material availability; Procurement procedures and plans; Packaging, warehousing, & transport; Material inspection; Risk management; Quality assurance / quality surveillance.

Quality management and records Quality assurance & controls; Independent assessments; Non-conformance / corrective action programmes; Construction experience; Quality surveillance and construction inspection; Controlled documentation and records.

Human resources and training Hiring, development, and training; Personnel qualification; Human performance; Health and safety training; Personnel availability; First line supervision and management.

Construction readiness Site infrastructure requirements; Regulatory requirements; Tools availability; Construction sequencing; Security and safeguards requirements; Construction execution plans and procedures; Safety management; Environmental management; New construction practices / technologies.

Construction completion assurance Process defined; Walkdown processes; Hold points; Open item tracking; Labelling and control of boundaries; Inaccessible items; Interim maintenance during construction.

Targeted reviews (upon request) Completed activities and expenditures; Detailed as-experienced schedule review; Variance review; Significant events of interest; Corrective action review; Other areas.

E-LEARNING

Construction e-learning module Part of a series targeted at newcomer countries, at both senior leader and project team member levels. Topics covered in Construction Module: What makes nuclear construction unique; Important considerations for projects and programmes; How to achieve excellence; Key site considerations. Now available!

SOME LESSONS LEARNED

Elements needed for successful NPP Health, environment and safety Communicate with regulator and public as early as possible and as much as possible; Quality Quality surveillance of sub-contractors (engineering, construction etc.) should start early; Cover both domestic and foreign vendors; Schedule Level 2 for management; monitor at level 3; Ensure sufficient resources, support contractors; Financial Risk funding needed. Only 25 % NPP projects in China were completed with planned budget.

Project management lessons Clearly define roles of Owner and EPC contractor ; Set up PM organization early; Ensure Owner has appropriate contingency funding and risk allocated for unforeseens; Perform surveillance of quality during manufacturing; Need strong site centred PM for EPC and Suppliers;

Project management lessons (cont. d) Off-site team should support fully, but not manage site team; Include incentives for on/off site team; Authorized to proceed (ATP) for long lead items equally important with first concrete pour date (FCD); Lead time typically 3 years between ATP and FCD in recommended (China).

Thank you for your attention! Follow Nuclear Energy on Twitter @NE