Join the UK Nuclear Renaissance. Procurement & Quality Process

Size: px
Start display at page:

Download "Join the UK Nuclear Renaissance. Procurement & Quality Process"

Transcription

1 Join the UK Nuclear Renaissance Procurement & Quality Process 1 AREVA NP UK Supplier Day, March 16th Birmingham EPR is a trademark of the AREVA Group 1

2 The Process: AREVA Supply Chain Strategy Didier David AREVA Production Purchasing Vice President 2 AREVA NP 2

3 UK nuclear new build is an opportunity for the UK supply chain To deliver multiple EPR new builds in UK, AREVA needs a strong UK supply chain Start UK, then go global as an AREVA supplier 3 AREVA NP 3

4 AREVA has a vision to share with more suppliers A new generation of suppliers for a new generation of reactor Purchasing Strategy AREVA continuously seeks to enrich, develop and optimize its worldwide panel of supplier partners in order to select the most competitive solutions with respect to both technical and financial requirements. Long-term partnerships will be developed with selected suppliers in order to Respond to local requirements DOMESTIC PROJECTS Offer competitive solutions worldwide to our customers INTERNATIONAL PROJECTS 4 AREVA NP 4

5 The AREVA Purchasing organization One face to suppliers A Corporate interface (Commodity Manager) Vision and strategy Supplier development & continuous improvement New business opportunities A Project interface (UK Project Procurement Manager) Specific project-related business = UK Supply Chain a supplier customer partnership relationship 5 AREVA NP 5

6 The AREVA UK purchasing organization UK AREVA dedicated team is in charge of all aspects of procurement from tender phase to the beginning of the warranty period in particular Suppliers selection Orders Follow up of deliveries (Expediting) Purchasing in UK project ensures that equipment or services are bought on time, within a defined budget, according to quality on technical specs, in respect of contractual obligations towards the final client 6 AREVA NP 6

7 Involve suppliers in a continuous improvement approach Stimulate supplier creativity with contracts stipulating quality, cost and delivery objectives Encourage active supplier participation in codevelopment initiatives Implement Sustainable Development Declaration for suppliers Develop and formalize long-term partnerships with written agreements 7 AREVA NP 7

8 AREVA Purchasing Scope of Supply»8 AREVA NP»8

9 AREVA Scope of supply: NI»Areva Scope of supply: NI 9 AREVA NP 9

10 EPR Project - Scope of supply EPR New Plants General Scope Sharing NI/TI AREVA is managing the scope related to Nuclear Island System Design, Concept Design, Basic Design, Detail Design Layout, all planning activities Procurement of all mechanical equipment (incl. piping), all electrical and I&C equipment, HVAC-equipment Installation of all equipment and commissioning as well as overall coordination of Plant commissioning BNI might be in customer s Scope (EDF) Turbine Island is managed by a partner (could be in a Consortium) Civil Works could be managed by Partners There are various Project Schemes which could be applied creating several potential Customers for UK Suppliers! 10 AREVA NP 10

11 Main activities for NI scope Design services Fabrication and delivery of materials (equipment, components) Erection & commissioning on the NPP site Project management and associated activities Identification of potential supplier partners as early as possible 11 AREVA NP 11

12 AREVA NP Quality Management Specification for the Supply chain In AREVA NP QA prescription to its suppliers: a graded approach For safety related product/services (mainly Class 1 & Class 2): Compliance with ISO additions based upon IAEA GS-R For non safety related product/services but important for installation (Class 3 & NC impacting schedule, cost, availability): Compliance with ISO For all products/services attention is drawn to: Environmental program (ISO14001) Safety program (OHSAS 18001) 12 AREVA NP 12

13 Procurement Methodology Definition of the request for tender file Qualification of potential suppliers (Approved Vendor List) Consultation and selection of Suppliers Definition of the contract to the selected Supplier(s) Implementation of the contract by the Supplier Delivery of the product manufactured by the Supplier to our Customer 13 AREVA NP 13

14 Typical Procurement Expediting Process 3 types of information to be followed up General data (from procurement activities) Dates (from Time Schedule) Performance indicators 4 consecutive phases for procurement of equipment Phase 1 Phase 2 Phase 3 Phase 4 Time Delivery of requisition Purchase Order passed Start of manufacturing Delivery to site 14 AREVA NP 14

15 How to become an EPR UK supplier: Respect Sustainable Development Sign AREVA Sustainable Development Charter Target the right product Supplier should have the required technical capabilities With the right quality requirement Supplier & product should be qualified At the right cost Supplier should be competitive Be on-time Supplier should have a proven reputation for on-time delivery Be able to supply a fleet of EPR reactors The Supplier should have project management capabilities for the scope of supply 15 AREVA NP 15

16 EPR reactor Scope of Equipment Supplies & Erection Services»16 AREVA NP»16

17 Scope of External Procurement (1) Mechanical Equipment Fuel Handling Equipment Polar Crane All Pumps (excluding Main Coolant Pump) All Valves All Pressure Vessels (excluding Pressurizer and RPV) All Heat Exchangers (excluding Steam Generators) All Filters / Process Components All Waste Components Fire Fighting Equipment Physical Plant Protection Equipment Special Devices, e.g. Filter Changing Machine, Multi-Stud Tensioning Device, Core Catcher, Airlocks, Liner, etc.) 17 AREVA NP 17

18 Scope of External Procurement (2) Piping and Support Materials Supplies All piping material (excluding Primary Loop) All fittings, forgings, elbows, flanges, compensators All support material incl. steel structures Piping prefabrication and installation works (including design for layout, detailed isometrics and spooling) 18 AREVA NP 18

19 Scope of External Procurement (3) Heating / Ventilation / Air Conditioning (HVAC) Refrigeration Units / Chillers Containment Isolation Dampers Gas-Tight Dampers, Isolation Dampers, Non-Return Dampers Fire Dampers/Smoke Relief Dampers Fans (Ventilators) Heaters, Air Heating Unit, Humidifiers Silencers Filters Other HVAC-Equipment (Blast Valves, Black Box Systems) Waste Management Equipment (starting from Conceptual Design, provided by AREVA including Installation) 19 AREVA NP 19

20 Scope of External Procurement (4) Components for Electrical Equipment Diesel Generators (EDG and SBO) MV-Switchgears, LV-Switchgears Batteries, UPS Containment Cable Penetrations Transformers, AC/DC Converters, DC/AC Inverters Cables (LOCA Cables and Non-LOCA Cables) Cable Trays including Support Structures Cable Seals, Junction Boxes Building Technology Equipment for complete electrical infrastructure Installation Services for all Electrical Equipment 20 AREVA NP 20

21 Scope of External Procurement (5) Components for I&C Equipment I&C equipment will be procured externally: All Radiation Monitoring Systems Dosimetry Equipment Physical Health Stationary Equipment Sensors & Instrument Tubing Instrumentation Sensors (Flow, level, pressure, temperature, chemical, ) Instrumentation Tubing Instrumentation Frames 21 AREVA NP 21

22 Scope of External Procurement (6) Electrical Infrastructure including systems such as: Telephone, LAN/WAN, Intercommunication Systems Public Address & Alarm Systems Clock Systems CCTV Systems Lighting Systems and small power systems Fire Alarm systems and fire damper control And Electrical Physical Protection Systems such as: Specific Power Supply Intercommunications CCTV Access Control Security Alarms and associated control stations & desks 22 AREVA NP 22

23 UK Orders & How to start process Majority POs starting / 2010 to be qualified Next steps: RFI in Q2/2009 Suppliers Selection Pre assessment visits 23 AREVA NP 23

24 Nuclear Quality Supplier Qualification Process Thierry Zumbihl Vice President, Quality-Plants Sector 24 AREVA NP 24

25 Quality requirements in UK HSE requirements are expressed in the Safety Assessment Principles (2006 edition - revision1) Leadership and management for safety (SAP MS.1) quality management system shall be used to ensure that safety is being maintained and improved reference to international standards HSE expectations are QA arrangements from licensees and vendors to cover IAEA GS-R-3 and ISO-9001 requirements graded approach = application of controls proportional to safety significance The IAEA safety guide GS-R-3 = The Management System for Facilities and Activities released in AREVA NP 25

26 AREVA NP Quality organization: international approach adapted to UK expectations The AREVA NP quality system is based on international nuclear quality standard (IAEA GS-R-3) industry consensus quality standard (ISO-9001) graded application General AREVA NP quality approach covers UK requirements and regulator expectations addresses requirements in most of the countries global market 26 AREVA NP 26

27 How do these requirements apply to component and service suppliers? 27 AREVA NP 27

28 AREVA NP Quality requirements Quality requirements based on component or service importance to safety 28 AREVA NP 28

29 Nuclear quality specific requirements Defined in a generic AREVA NP specification (Q-N-100) Complement ISO-9001 requirements Nuclear specific requirements (examples) Activities important for safety: refer to activities performed during purchase order performance and where failure may lead to a non-conformance regarding requirements linked to safety notified by AREVA NP. Safety Culture: measures are required from the supplier management system to promote and support a strong safety culture. 29 AREVA NP 29

30 Nuclear quality specific requirements Nuclear specific requirements (examples) Grading the application of the quality management system: for the performance of the purchase order, identification of the activities important for safety Documentation: a quality management plan is required from the supplier Control of the design documentation: Design/Engineering activities are verified by individuals competent and other than those who carried them out Inspection: inspection is carried out by individuals competent and not involved in carrying out the activity. The conditions of this inspection are described and justified Purchasing: the purchasing data are verified by individuals competent and other than those who prepared them 30 AREVA NP 30

31 Qualification of the suppliers How to proceed?»areva NP»31 AREVA NP 31

32 Purpose of supplier qualification process Why? To assess the capability of a supplier to fulfill AREVA requirements applicable to products and services for nuclear power plants A prerequisite to product qualification and for placing purchase order Part of a global process involving technical, commercial, financial and quality 32 AREVA NP 32

33 Quality supplier qualification process (new suppliers) STEP 1»Pre-selection Review based on supplier s answer to our questionnaire STEP 2»On-site assessment Assessment by AREVA NP QA team STEP 3»Supplier s Improvement measures Supplier proposes improvement action plan STEP 4»Review by AREVA NP Implementation reviewed by AREVA NP Approved vendor list TOTAL DURATION : 6 to 12 Months for safety grade qualification 33 AREVA NP 33

34 A cooperative attitude AREVA NP offers support to the supplier during qualification process Provides materials for employees awareness and training Organization of advanced technical training Assessment with identification of improvement axis 34 AREVA NP 34

35 Summary Success is in your hands Company management commitment Disseminate safety culture to employees No compromise on quality requirements Relation based on trust and transparency For further questions contact us: 35 AREVA NP»35

36 AREVA NP Equipment / Supplier Qualification Process Yves Robin Senior Sourcing Manager 36 AREVA NP 36

37 Table of contents The Nuclear Island Context A search to match Equipment & Supplier A set of specifications A reference to Codes & Standards The Qualification Process A need for project risk management A successful experience A running process 37 AREVA NP 37

38 The context Safe and reliable NPPs worldwide require the selection of the right match of Equipment and Supplier Nuclear Island Equipment, Some for safety related systems Some non related to safety functions Nuclear Island Suppliers Quality management ability is a pre-requisite Capability to design and manufacture equipment Capacity to supply on time Competitiveness AREVA qualification process is structured to secure a match between Equipment and a Supplier for long term & worldwide partnership 38 AREVA NP 38

39 Equipment specifications Technical Codes & Standards: ASME, RCCM, KTA Pumps Valves etc. Piping Vessels/Exchangers Table of Contents Introduction 1. Scope 2. Definitions 3. Documentation 4. Design 5. Materials 6. Manufacturing 7. Operability 8. Requirements for Auxiliary Systems, Venting, Drains, Integral Supports Quality Requirements With modulation according to Safety Class and National Regulations - Quality Management - Documentation - Inspection 39 AREVA NP 39

40 Quality requirements Rules depend upon the safety level and public safety impact of the equipment: International IAEA rules National laws Owner s own Quality & Inspection requirements AREVA s QM requirements & Surveillance requirements of detailed design and manufacturing Surveillance intensity of AREVA depends on The safety level and complexity of the equipment The experience of the supplier and feedback of previous contracts 40 AREVA NP 40

41 Codes & Standards: RCC-M or ASME III RCC-M Code ASME Code Section 1 Nuclear Island Components Section III A General requirements NCA B Class 1 components NB C Class 2 components NC D Class 3 components ND E Small components None G Core support structures NG H Supports NF J Storage tanks NC/ND P Containment penetrations NE Z Technical appendices Appendices Section 2 Materials Section II Section 3 Examination methods Section V Section 4 Welding Section IX (Qualifications) Section 5 Fabrication Various parts of Sect. III 41 AREVA NP 41

42 General view for EPR Reactor Codes and Standards selection Classification EPR Reactor Global Application Class 1 ASME Sect.III NB+ RCC-M Sect. I Subs. B Class 2 ASME + Sect. III NC ASME + Sect. III NC or RCC-M Subs. C + : supplemented when needed Class 3 ASME Sect. III ND+ Harmonized Standards PED 97/23 EC or ASME Sect. VIII div.1 or National Industrial Standards Plus specific requirements Nuclear codes optional NC Harmonized Standards: EN 13445, 13480, National Industrial Standards: ASME VIII, AD-M, BS, CODAP, 42 AREVA NP 42

43 Codes for mechanical components of EPR Nuclear Island For the main primary system components (Class 1): the first EPR TM units (OL3, FA3, TSN1&2) are RCCM and will be ASME III in US for UK it will have to be agreed with both clients and Regulator For the majority of all other equipment (Class 2, 3 and Non Classified): AREVA current practice is to open its specifications to the possible alternatives: ASME or RCCM or European Standards 43 AREVA NP 43

44 Table of contents The Nuclear Island Context A search to match Equipment and Supplier A set of specifications A reference to Codes & Standards The Qualification Process A need for project risk management A successful experience A running process 44 AREVA NP 44

45 Qualification: a need for project risk management Component technology and safety AREVA NSSS components Qualified suppliers key components Qualified suppliers standard design components growing project risk Qualified suppliers & new design New supplier & standard design New supplier & new design Supplier experience / New design 45 AREVA NP 45

46 AREVA NP Qualification Process Description Criteria for the qualification of Suppliers Technical capabilities in design and engineering to achieve successfully the requirements for a given scope of supply Quality management ability Project management capability Financial soundness and long term company stability Value charter 46 AREVA NP 46

47 AREVA NP Qualification Process Description Steps March Sourcing April 2009 No-Go Go Timescale No-Go 2. Preselection Go 3. Prequalification No-Go Go 4. Qualification 2011/2012 Approved Vendor List 47 AREVA NP 47

48 AREVA NP Qualification Process Description Qualification feedback experience Success factors: General Management commitment Employees safety culture & mobilization Quality Assurance + Quality Control internal surveillance & follow-up Management of Sub-contracts Management of non-conformance in trustworthy atmosphere: SAFETY CULTURE Responsibilities & authority of the Supplier Project manager Supplier proactive participation during the qualification process creates Customer Confidence 48 AREVA NP 48

49 Conclusion Supplier Qualification helps set up trustworthy and long term relationships between all the actors in the Supply Chain Such proven confidence is the best asset for the safety and success of the Nuclear Industry Thank you for your attention 49 AREVA NP 49

50 Conclusion Laurent-Olivier Coudeyre UK Supply Chain Coordinator 50 AREVA NP 50

51 UK nuclear new build is an opportunity for the UK supply chain To deliver multiple EPR new builds in UK, AREVA needs a strong UK supply chain We Need You! Start UK, then go global as an AREVA supplier 51 AREVA NP 51

52 Next Milestones: Project: By Spring, which Clients & Sites By Autumn, which Vendors By Christmas, which Consortia Supply Chain: RFI starting Q2/2009 Suppliers Selection Pre assessment visits On-going process 52 AREVA NP 52

53 UK contact with AREVA Purchasing Dedicated website Meet the AREVA purchasers 53 AREVA NP 53

54 54 AREVA NP 54

AREVA: supply chain network principles and company s vision

AREVA: supply chain network principles and company s vision AREVA: supply chain network principles and company s vision Virginie MOUCQUOT-LAIHO AREVA Finland Communications Director & Vice Country Manager Oulu, Finland 18.09.2012 1 AREVA & nuclear industry The

More information

Olkiluoto 3 Project. AREVA Suppliers Day Warsaw October 4, 2011

Olkiluoto 3 Project. AREVA Suppliers Day Warsaw October 4, 2011 Olkiluoto 3 Project AREVA Suppliers Day Warsaw October 4, 2011 Virginie MOUCQUOT-LAIHO AREVA OL3 Project Management Office & Communications Manager AREVA Reactor & Services - New Builds EPR Project Fleet

More information

Building New Generation Nuclear Plants Worldwide : AREVA's Experience

Building New Generation Nuclear Plants Worldwide : AREVA's Experience Building New Generation Nuclear Plants Worldwide : AREVA's Experience Philippe Guay Senior Vice President, New Builds Offers AREVA 37 th WNA Symposium 12-14 September 2012 LONDON Projects status The value

More information

The World Nuclear Supply

The World Nuclear Supply The World Nuclear Supply Chain An Overview Greg KASER Staff Director NEA International WPNE Workshop Paris 11 March 2014 Outline of Presentation 1. About WNA 2. Value of: New construction Early dismantlement

More information

AREVA, an unparalleled experience in building nuclear reactors

AREVA, an unparalleled experience in building nuclear reactors AREVA, an unparalleled experience in building nuclear reactors Frank APEL Senior Vice President Sales Central Europe and Nordic Countries AREVA, International Commercial Organisation 9 th Annual European

More information

ABSTRACT. The Guidelines Section F is related to the Purchasing requirements of NSQ100 (Chapter 7.4). Summary

ABSTRACT. The Guidelines Section F is related to the Purchasing requirements of NSQ100 (Chapter 7.4). Summary Page 1 / 9 ABSTRACT This document is the Section F to NSQ-100 Guidelines. Its objective is to help to the understanding of NSQ-100 requirements through some examples or recommendations and descriptions

More information

Fire Protection Program Of Chashma Nuclear Power Generating Station Pakistan Atomic Energy Commission 5/28/2015 1

Fire Protection Program Of Chashma Nuclear Power Generating Station Pakistan Atomic Energy Commission 5/28/2015 1 Fire Protection Program Of Chashma Nuclear Power Generating Station Pakistan Atomic Energy Commission 5/28/2015 1 Nuclear Power in Pakistan Nuclear Power Plants Capacity (MWe) Year of Commissioning In

More information

Olkiluoto 3 Project June 2010

Olkiluoto 3 Project June 2010 Olkiluoto 3 Project June 2010 Author: R&S Communications Department, La Défense, France. The reproduction, transmission or use of this document or its contents is not permitted without express written

More information

New nuclear project financing Warsaw, June 26, 2013 p. 1

New nuclear project financing Warsaw, June 26, 2013 p. 1 New nuclear project financing Warsaw, June 26, 2013 p. 1 The EPR design: a reference technology Loïc ELOY Director of New Builds Offers Poland Platts Conference Warsaw, 26 June 2013 EPR reactor design

More information

Best Practices and Approaches to Supply Chain Management

Best Practices and Approaches to Supply Chain Management Best Practices and Approaches to Supply Chain Management ATOMEX Forum 2012 Moscow 12.12. 14.12.2012 AF-Consult Switzerland Ltd Jan Kocourek 1 Objectives Provide information available regarding both the

More information

AREVA is Clean Energy and American Jobs Ohio Manufacturers Association April 28, 2010 Columbus, OH

AREVA is Clean Energy and American Jobs Ohio Manufacturers Association April 28, 2010 Columbus, OH AREVA is Clean Energy and American Jobs Ohio Manufacturers Association April 28, 2010 Columbus, OH Thomas M. Williamson, P.E. VP, New Plant Market Strategy AREVA Inc. Introduction AREVA Overview Nuclear

More information

The EPR design: the European reference

The EPR design: the European reference The EPR design: the European reference Jean-Bernard Ville Executive Vice-President, New Builds June 25 th, London 1 EPR Design safety 2 EPR project delivery 3 A partnership-based approach Platts 7 th European

More information

Olkiluoto 3 Experience

Olkiluoto 3 Experience Olkiluoto 3 Experience CNRA International Workshop on New Reactor Siting, Licensing and Construction Experience Hosted by the State Office for Nuclear Safety Prague, Czech Republic 15-17 September 2010

More information

Course available 24/7 for up to six months from the date of purchase or until completion

Course available 24/7 for up to six months from the date of purchase or until completion SPED ONLINE COURSE TRAINING Piper BootCamp and Process Plant Layout BOTH Piper BootCamp and Process Plant Layout online courses contain: Approximately 25 hours of online videos Printable notes Links to

More information

Published in the Official State Gazette (BOE) number 166 of July 10th 2009 [1]

Published in the Official State Gazette (BOE) number 166 of July 10th 2009 [1] Nuclear Safety Council Instruction number IS-22, of July 1st 2009, on safety requirements for the management of ageing and long-term operation of nuclear power plants Published in the Official State Gazette

More information

ENEC Management System and Quality Assurance Program

ENEC Management System and Quality Assurance Program ENEC Management System and Quality Assurance Program Shami S. Dua Quality Assurance Director IAEA TM on Management System Grading 23-27 January 2012, Vienna, Austria Safety moment ENEC Management System

More information

Engineered Solutions

Engineered Solutions Engineered Solutions Long established partnerships bring together the world s leading instrumentation companies within BKW. Our manufacturing facility enables us to quickly adapt standard instruments to

More information

Plant Design for Oil & Gas Industry Client

Plant Design for Oil & Gas Industry Client Plant Design for Oil & Gas Industry Client An Enventure Case Study Enventure with its team of engineers having multi-disciplinary skills provided complete plant design, detailing and procurement services

More information

ABSTRACT. The Guidelines Section A is related to the general requirements of NSQ100 (Chapters 0, 1, 4, 5 and 6). Summary

ABSTRACT. The Guidelines Section A is related to the general requirements of NSQ100 (Chapters 0, 1, 4, 5 and 6). Summary Page 1 / 12 ABSTRACT This document is the Section A to NSQ-100 Guidelines. Its objective is to help to the understanding of NSQ-100 requirements through some examples or recommendations and descriptions

More information

POWER & RENEWABLE ENERGY SERVICES

POWER & RENEWABLE ENERGY SERVICES POWER & RENEWABLE ENERGY SERVICES Nuclea Siting - Assistance to permitting Environmental Impact Assessment Safety and environmental audits Construction code compliance and design review Supplier Technical

More information

Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+)

Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+) Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+) 1. In addition to the information scheduled below, the pre-tender designer is responsible for: (i)

More information

Ensuring Quality Going Down the Supply Chain

Ensuring Quality Going Down the Supply Chain Ensuring Quality Going Down the Supply Chain (Including Vendor Qualification) What is the Role of Operators, Vendors and Regulators? April 21, 2015 DAE-HEE LEE Contents Nuclear Quality Issues The Role

More information

POWER & RENEWABLE ENERGY SERVICES

POWER & RENEWABLE ENERGY SERVICES POWER & RENEWABLE ENERGY SERVICES Siting - Assistance to permitting Environmental Impact Assessment Safety and environmental audits Construction code compliance and design review Supplier Technical Assessment

More information

NOT PROTECTIVELY MARKED

NOT PROTECTIVELY MARKED Title of document ONR GUIDE Supply Chain Management Arrangements for the Procurement of Nuclear Safety Related Items or Services Document Type: Unique Document ID and Revision No: Nuclear Safety Technical

More information

INDUSTRIAL SERVICES PRESSURE EQUIPMENT CERTIFICATION (PED) Pressure equipment certification. Your key to market access in Europe. www.tuv.

INDUSTRIAL SERVICES PRESSURE EQUIPMENT CERTIFICATION (PED) Pressure equipment certification. Your key to market access in Europe. www.tuv. INDUSTRIAL SERVICES PRESSURE EQUIPMENT CERTIFICATION (PED) Pressure equipment certification. Your key to market access in Europe. www.tuv.com Comply with legal regulations and requirements. We help you

More information

APPENDIX B SUPPLEMENTAL INSPECTION PROGRAM A. OBJECTIVES AND PHILOSOPHY OF THE SUPPLEMENTAL INSPECTION PROGRAM

APPENDIX B SUPPLEMENTAL INSPECTION PROGRAM A. OBJECTIVES AND PHILOSOPHY OF THE SUPPLEMENTAL INSPECTION PROGRAM APPENDIX B SUPPLEMENTAL INSPECTION PROGRAM A. OBJECTIVES AND PHILOSOPHY OF THE SUPPLEMENTAL INSPECTION PROGRAM The supplemental inspection program is designed to support the NRC s goals of maintaining

More information

Flamanville 3 Nuclear Power Plant

Flamanville 3 Nuclear Power Plant Flamanville 3 Nuclear Power Plant Prepared by: Giorgio Locatelli (University of Lincoln) and Mauro Mancini (Politecnico di Milano) Contacts: Giorgio Locatelli University of Lincoln Lincoln School of Engineering

More information

Pressure Equipment Certification. Ensure the Conformity and Quality of Your Pressure Equipment. Worldwide. www.tuv.com/asme

Pressure Equipment Certification. Ensure the Conformity and Quality of Your Pressure Equipment. Worldwide. www.tuv.com/asme INDUSTRIAL SERVICES PRESSURE EQUIPMENT CERTIFICATION Pressure Equipment Certification. Ensure the Conformity and Quality of Your Pressure Equipment. Worldwide. www.tuv.com/asme Worldwide Compliance of

More information

HEALTH & SAFETY EXECUTIVE NUCLEAR DIRECTORATE ASSESSMENT REPORT. New Reactor Build. EDF/AREVA EPR Step 2 PSA Assessment

HEALTH & SAFETY EXECUTIVE NUCLEAR DIRECTORATE ASSESSMENT REPORT. New Reactor Build. EDF/AREVA EPR Step 2 PSA Assessment HEALTH & SAFETY EXECUTIVE NUCLEAR DIRECTORATE ASSESSMENT REPORT New Reactor Build EDF/AREVA EPR Step 2 PSA Assessment HM Nuclear Installations Inspectorate Redgrave Court Merton Road Bootle Merseyside

More information

Building our industrial future. Hinkley Point C Supply Chain be part of it

Building our industrial future. Hinkley Point C Supply Chain be part of it Building our industrial future Hinkley Point C Supply Chain be part of it Building an industrial future - be part of it Contents Introduction 02 Working together to deliver Hinkley Point C 04 Supporting

More information

Introductions: Dr. Stephen P. Schultz

Introductions: Dr. Stephen P. Schultz Introductions: Dr. Stephen P. Schultz Vienna, Austria 1 3 September 2015 Work Experience Current Member Advisory Committee on Reactor Safeguards, U.S. Nuclear Regulatory Commission, 12/2011 Chair, Fukushima

More information

Solutions for nuclear technology

Solutions for nuclear technology Solutions for nuclear technology Corrosion resistant pipes Clad pipes Special pipes and components ready for installation Prefabricated piping / spools Vessels, tanks and columns Assemblies 2 NUCLEAR TECHNOLOGY

More information

MATCH FUNDING TO GET YOUR BUSINESS FIT FOR NUCLEAR (F4N)

MATCH FUNDING TO GET YOUR BUSINESS FIT FOR NUCLEAR (F4N) MATCH FUNDING TO GET YOUR BUSINESS FIT FOR NUCLEAR (F4N) F4N FUNDING CALL Grants averaging 10k per project (for Business Excellence and R&D projects) to help manufacturers in England measure and improve

More information

The Essential Guide to the new build nuclear supply chain

The Essential Guide to the new build nuclear supply chain The Essential Guide to the new build nuclear supply chain Opportunities, routes to market, codes and quality arrangements for nuclear new build in the UK Stage One February 2011 Created by: Endorsed by:

More information

Office for Nuclear Regulation

Office for Nuclear Regulation ONR GUIDE LC17 Management Systems Document Type: ONR Nuclear Safety Technical Inspection Guide Unique Document ID and Revision No: NS-INSP-GD-017 Revision 2 Date Issued: November 2012 Review Date: November

More information

SINGLE SOURCE CAPABILITY, RESPONSIBILITY, ACCOUNTABILITY.

SINGLE SOURCE CAPABILITY, RESPONSIBILITY, ACCOUNTABILITY. NUCLEAR Services Black & McDonald Limited was founded in 1921 as a partnership between William J. McDonald and William R. Black; they established the company s long-standing commitment to fairness, quality,

More information

Engineering Procurement Construction Quality Plan

Engineering Procurement Construction Quality Plan Engineering Procurement Construction Quality Plan Index 1 Introduction... 4 1.1 Project Background... 4 1.2 Document Purpose... 4 1.3 Change Control... 4 1.4 Contract... 4 1.5 Quality system... 4 1.6 Distribution...

More information

Pressure Vessel acc. to PED for Chemical Industry fabricated in China

Pressure Vessel acc. to PED for Chemical Industry fabricated in China Pressure Vessel acc. to PED for Chemical Industry fabricated in China Kurt Schumacher ACHEMASIA 2013 Beijing May 14, 2013 Folie 1 Introduction Investment projects in the chemical/petrochemical industry

More information

VENDOR PREQUALIFICATION QUESTIONNAIRE

VENDOR PREQUALIFICATION QUESTIONNAIRE FM/PR/PM11/03 VENDOR PREQUALIFICATION Project. Doc. : LOCATION: Page. : 1 of 9 Company Name: Company Address: 1. Invitation to Pre qualify Pyramid E&C hereby invites your company to participate in a pre

More information

Westinghouse and the AP1000 Offering Great Opportunity for the Czech Republic

Westinghouse and the AP1000 Offering Great Opportunity for the Czech Republic Westinghouse Non-Proprietary Class 3 2010 Westinghouse Electric Company LLC. All Rights Reserved. Westinghouse and the AP1000 Offering Great Opportunity for the Czech Republic Aziz Dag Vice-President,

More information

Building Services Engineering Technician

Building Services Engineering Technician Building Services Engineering Technician A competent Building Services Engineering Technician is expected to be able to demonstrate the following skills and competences: Systems design in the building

More information

Nuclear power plant systems, structures and components and their safety classification. 1 General 3. 2 Safety classes 3. 3 Classification criteria 3

Nuclear power plant systems, structures and components and their safety classification. 1 General 3. 2 Safety classes 3. 3 Classification criteria 3 GUIDE 26 June 2000 YVL 2.1 Nuclear power plant systems, structures and components and their safety classification 1 General 3 2 Safety classes 3 3 Classification criteria 3 4 Assigning systems to safety

More information

Structural Integrity and NDE Reliability II

Structural Integrity and NDE Reliability II Structural Integrity and NDE Reliability II Preparing for EPR TM Reactor Vessel Inspection J. Laube, AREVA NDE Solutions / intelligendt, Germany Y. Bouveret, AREVA NDE Solutions / Intercontrole, France

More information

Questionnaire Pure Media Systems

Questionnaire Pure Media Systems 1. PROJECT INFORMATION: Project Name: Client: Contact Person: Telephone / Fax N : Email: 2. BASIC INFORMATION Type of Pure Media System PW / HPW - Generation PW / HPW - Storage & Distribution System Cold

More information

Nuclear Consultancy & Engineering Services

Nuclear Consultancy & Engineering Services Insert a caption to go with the photograph in here ITER, France Wednesday, 14 December 2011 Nuclear Consultancy & Engineering Services T H E N U C L E A R A T K I N S A S S Y S T E M A L L I A N C E CONSTRUCTION

More information

Mechanical Engineering Technician- Plant Technician

Mechanical Engineering Technician- Plant Technician Mechanical Engineering Technician- Plant Technician A competent Mechanical Engineering Technician- Plant Maintenance is expected to: 1. Ability to plan and execute work in a safe and responsible manner

More information

MANAGEMENT SYSTEM FOR A NUCLEAR FACILITY

MANAGEMENT SYSTEM FOR A NUCLEAR FACILITY GUIDE YVL A.3 / 2 June 2014 MANAGEMENT SYSTEM FOR A NUCLEAR FACILITY 1 Introduction 5 2 Scope of application 6 3 Management system 6 3.1 Planning, implementation, maintenance, and improvement of the management

More information

How To Make A Pressure Relief Valve

How To Make A Pressure Relief Valve 0510 First Line of Safety: Farris Engineering Our Company Farris Engineering, a business unit of Curtiss-Wright Flow Control Company, has been at the forefront of the design and manufacture of spring-loaded

More information

Piping Systems for Nuclear Power Industry. Prague, October 2011

Piping Systems for Nuclear Power Industry. Prague, October 2011 Piping Systems for Nuclear Power Industry Prague, October 2011 Introduction of the company Leading Czech supplier of piping systems for power engineering 60 years of experience in the field of power industry

More information

This occurrence is considered to be of no significance with respect to the health and safety of the public.

This occurrence is considered to be of no significance with respect to the health and safety of the public. Serial No. MNS-15-072 September 10, 2015,. DUKESteven Vice D. President Capps, ENERGYMcGuire Nuclear Station Duke Energy MGOIVP 1 12700 Hagers Ferry Road Huntersville, NC 28078 0: 980.875.4805 f: 980.875.4809

More information

Electrical Systems. Emergency Diesel Generator Solutions

Electrical Systems. Emergency Diesel Generator Solutions Electrical Systems Emergency Diesel Generator Solutions AREVA Competence in Emergency Power Supply Emergency Diesel Generators (EDGs) Business Areas e Modernization of existing EDGs p Customer support

More information

Advanced Construction Methods for New Nuclear Power Plants

Advanced Construction Methods for New Nuclear Power Plants Advanced Construction Methods for New Nuclear Power Plants A. Introduction Relative to coal fired and natural gas fired power plants, nuclear power plants are more expensive to build but less expensive

More information

FIRE RISK ASSESSMENT IN GERMANY - PROCEDURE, DATA, RESULTS -

FIRE RISK ASSESSMENT IN GERMANY - PROCEDURE, DATA, RESULTS - International Conference Nuclear Energy in Central Europe 2000 Golf Hotel, Bled, Slovenia, September 11-14, 2000 FIRE RISK ASSESSMENT IN GERMANY - PROCEDURE, DATA, RESULTS - H.P. Berg Bundesamt für Strahlenschutz

More information

February 19, 2014. Senior Fellow, Nuclear Energy Systems & Services Division Power Systems Company

February 19, 2014. Senior Fellow, Nuclear Energy Systems & Services Division Power Systems Company JAPAN-U.S. DECOMISSIONING AND REMEDIATION FUKUSHIMA RECOVERY FORUM February 19, 2014 Senior Fellow, Nuclear Energy Systems & Services Division Power Systems Company Toshiba global formation Information

More information

Wilfred C. LaRochelle Principal Nuclear Consultant HSB Global Standards, USA

Wilfred C. LaRochelle Principal Nuclear Consultant HSB Global Standards, USA Wilfred C. LaRochelle Principal Nuclear Consultant HSB Global Standards, USA ASME Vice President, Conformity Assessment and Vice Chairman of Committee on Nuclear Certification 2nd NRC Workshop on Vendor

More information

26 3213.13 Diesel Engine Driven Generators Page 1 of 6

26 3213.13 Diesel Engine Driven Generators Page 1 of 6 Last Update: December 8, 2014 A. Description of System Consultant s Handbook Page 1 of 6 1. Provide a diesel engine driven electric generating unit, factory assembled, tested and certified to operate at

More information

UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION WASHINGTON, DC 20555-0001. June 16, 2011

UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION WASHINGTON, DC 20555-0001. June 16, 2011 UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION WASHINGTON, DC 20555-0001 June 16, 2011 NRC INFORMATION NOTICE 2011-12: REACTOR TRIPS RESULTING FROM WATER INTRUSION INTO

More information

Annex of the Certificate (Page 1/4) Scope of Accreditation

Annex of the Certificate (Page 1/4) Scope of Accreditation Annex of the Certificate (Page 1/4) As a "Type A" Inspection Body Accreditation Nr: Address :Centrum İş Merkezi Aydınevler Sanayi Cad. No:3 Küçükyalı - Maltepe 34854 ISTANBUL / TURKEY Phone : +90 216 518

More information

www.klmtechgroup.com TABLE OF CONTENT

www.klmtechgroup.com TABLE OF CONTENT Page : 1 of 10 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia PIPING FLEXIBILITY ANALYSIS TABLE

More information

Process Plant Construction: A Handbook for Quality Management

Process Plant Construction: A Handbook for Quality Management Process Plant Construction: A Handbook for Quality Management Process Plant Construction: A Handbook for Quality Management Patrick Noble ISBN: 978-1-4051-8725-1 Hardcover 232 pages January 2009, Wiley-Blackwell

More information

Engineering g Procurement. 02-Feb-2015

Engineering g Procurement. 02-Feb-2015 Engineering g Procurement Construction & Operation Capability Presentation About Pyramid E&C Est. 1995, professionally managed Company Over 500 projects executed till date Employs over 600 Engineers and

More information

Business Management System Manual. Context, Scope and Responsibilities

Business Management System Manual. Context, Scope and Responsibilities Business Management System BMS Manual Page 1 of 11 Business Management System Manual Context, Scope and Responsibilities ISO 9001:2015 BMS.0100 R1 MAS Solutions LLC 29810 FM 1093 Suite C Fulshear, TX 77441

More information

Nuclear Safety Council Instruction number IS- 23 on in-service inspection at nuclear power plants

Nuclear Safety Council Instruction number IS- 23 on in-service inspection at nuclear power plants Nuclear Safety Council Instruction number IS- 23 on in-service inspection at nuclear power plants Published in the Official State Gazette (BOE) No 283 of November 24 th 2009 Nuclear Safety Council Instruction

More information

Safety culture in the construction phase lessons learned from Olkiluoto 3 Pia Oedewald, Senior scientist VTT Technical Research Centre of Finland

Safety culture in the construction phase lessons learned from Olkiluoto 3 Pia Oedewald, Senior scientist VTT Technical Research Centre of Finland Safety culture in the construction phase lessons learned from Olkiluoto 3 Pia Oedewald, Senior scientist VTT Technical Research Centre of Finland IAEA Technical meeting on Safety culture in pre-operational

More information

AREVA Advanced nuclear power plants

AREVA Advanced nuclear power plants AREVA Advanced nuclear power plants Bernard Bastide AREVA Brazil and South America VP University of Rio de Janeiro III Semana da Engenharia Nuclear UFRJ August 2013 AREVA presentation AREVA EPR projects

More information

Essentials Welding QA/QC Plan Sample

Essentials Welding QA/QC Plan Sample Essentials Welding QA/QC Plan Sample Good for smaller projects and bid qualifications Has All the Essential Elements of a well-founded Quality Control Plan Contact: Ed Caldeira 410-451-8006 Pat [Pick the

More information

SECTION III, DIVISIONS 1 AND 2

SECTION III, DIVISIONS 1 AND 2 SECTION III, DIVISIONS 1 AND 2 Subject Interpretation File No. Division 1, Appendix I, Fig. I-9.1, Design Fatigue Curve for Martensitic Stainless Steel... III-1-13-48 12-1021 Division 1, NB-2223.3, Coupons

More information

BUSINESS PLAN CEN/TC 54 UNFIRED PRESSURE VESSELS EXECUTIVE SUMMARY

BUSINESS PLAN CEN/TC 54 UNFIRED PRESSURE VESSELS EXECUTIVE SUMMARY Page: 1 BUSINESS PLAN CEN/TC 54 UNFIRED PRESSURE VESSELS EXECUTIVE SUMMARY Business Environment CEN/TC 54 deals with a wide range of vessels for the energy and process industries that fall within the scope

More information

C-41 (May 13) Procurement Engineering and Supply Chain Guidelines in Support of Operation and Maintenance of Nuclear Facilities

C-41 (May 13) Procurement Engineering and Supply Chain Guidelines in Support of Operation and Maintenance of Nuclear Facilities C-41 (May 13) Procurement Engineering and Supply Chain Guidelines in Support of Operation and Maintenance of Nuclear Facilities FOREWORD One of the IAEA s statutory objectives is to seek to accelerate

More information

JUBILEE TECHNICAL TRAINING CENTRE TAKORADI POLYTECHNIC 2015 TRAINING PROGRAMMES

JUBILEE TECHNICAL TRAINING CENTRE TAKORADI POLYTECHNIC 2015 TRAINING PROGRAMMES JUBILEE TECHNICAL TRAINING CENTRE TAKORADI POLYTECHNIC 2015 TRAINING PROGRAMMES Main Courses Duration: 26 weeks 1. NVQ Level 2 Performing Process Operation in Replicating Environment 2. NVQ Level 2 Performing

More information

CONSTRUCTION EXPERIENCE FROM MODULAR NUCLEAR POWER PLANTS

CONSTRUCTION EXPERIENCE FROM MODULAR NUCLEAR POWER PLANTS CONSTRUCTION EXPERIENCE FROM MODULAR NUCLEAR POWER PLANTS Presented by W.J. (Chris) Zhang University of Saskatchewan Saskatoon, Canada Email: chris.zhang@usask.ca Outline 1. Modularization in NPP 2. Comparison

More information

www.klmtechgroup.com TABLE OF CONTENT

www.klmtechgroup.com TABLE OF CONTENT Page : 1 of 23 Rev: 01 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia TABLE OF CONTENT SCOPE 2 DEFINITIONS

More information

Practical Guidelines for Electrical Area Classification in Combustion Turbine-Generator Power Plants

Practical Guidelines for Electrical Area Classification in Combustion Turbine-Generator Power Plants Practical Guidelines for Electrical Area Classification in Combustion Turbine-Generator Power Plants Ram K. Saini, P.E. Principal Engineer, Chuck Emma, P.E. Principal Engineer, Burns and Roe Enterprises,

More information

U.S. EPR Design Overview

U.S. EPR Design Overview U.S. EPR Design Overview Brian A. McIntyre U.S. EPR Design Certification Project Manager WM2009 Conference March 4, 2009 The EPR Story 1989: Agreement between Framatome and Siemens on development of common

More information

Whitepaper Modular Integration of Process Equipment Packages for Oil and Gas Facilities

Whitepaper Modular Integration of Process Equipment Packages for Oil and Gas Facilities Whitepaper Modular Integration of Process Equipment Packages for Oil and Gas Facilities Author: Allan Bozek P.Eng, MBA, EngWorks Inc, Calgary, Canada Abstract An integrated design approach to a modular

More information

21.1 Functions, Basic Configuration, and Interfaces

21.1 Functions, Basic Configuration, and Interfaces 21 (6.2.M) Site Services Building 21.1 Functions, Basic Configuration, and Interfaces 21.1.1 Functions The primary functions performed by the site services building are to house, support, provide a suitable

More information

THE DELTON GROUP MANPOWER TRAINING CONSULTANCY SHORT COURSE PROGRAMME TOPICS LISTING

THE DELTON GROUP MANPOWER TRAINING CONSULTANCY SHORT COURSE PROGRAMME TOPICS LISTING THE DELTON GROUP MANPOWER TRAINING CONSULTANCY SHORT COURSE PROGRAMME TOPICS LISTING Delton Short Course Programmes English Language Technical English Language English Language for the Oil Industry Oil

More information

IAEA Safety Standards for Regulatory Activities

IAEA Safety Standards for Regulatory Activities Safety Standards for Regulatory Activities April 2010 Gustavo Caruso Regulatory Activities Section Division of Nuclear Installation Safety International Atomic Energy Agency Content Safety Standards and

More information

IAEA Research Reactor Operations & Maintenance Support 2014 TRTR Meeting August 3rd-7th, 2014 Benson Hotel Portland Oregon

IAEA Research Reactor Operations & Maintenance Support 2014 TRTR Meeting August 3rd-7th, 2014 Benson Hotel Portland Oregon IAEA Research Reactor Operations & Maintenance Support 2014 TRTR Meeting August 3rd-7th, 2014 Benson Hotel Portland Oregon By Charles R Morris Personal Nuclear History Contents 1. Introduction 2. Digital

More information

Energy Design Resources Commissioning Plan Outline Template

Energy Design Resources Commissioning Plan Outline Template IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC is not rendering advice concerning any commission project or practices. This document is neither approved nor intended

More information

MANAGEMENT AND USE OF WORK EQUIPMENT: PRESSURE SYSTEMS

MANAGEMENT AND USE OF WORK EQUIPMENT: PRESSURE SYSTEMS Health & Safety Services Unit name goes here Safety Code of Practice 46, Part 2 1st Edition, November 2009 MANAGEMENT AND USE OF WORK EQUIPMENT: PRESSURE SYSTEMS University of Reading 2015 Page 1 Contents

More information

KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM

KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM AIR HANDLING UNITS... 1 CHILLERS... 2 COOLING TOWERS... 2 CLOSED LOOP COOLERS... 2 MISCELLANEOUS SUPPLY FANS...

More information

Supporting New Build and Nuclear Manufacturing in South Africa

Supporting New Build and Nuclear Manufacturing in South Africa ASME Nuclear Codes and Standards Supporting New Build and Nuclear Manufacturing in South Africa Sandton, South Africa, October 7-8, 2008 Session 3 Section III - Component Design and Construction Ralph

More information

ROK s Assistance Programs for New comers

ROK s Assistance Programs for New comers ROK s Assistance Programs for New comers TM on Topical Issues in the Development of Nuclear Power Infrastructure, 3-6 February 2015 Kyo Hwang Technology Policy & Strategy Department Korea Hydro & Nuclear

More information

Statement of Work. 3.0 Details of Service Pre Start-up. - 1 - Cooling Start-up Service. Installation Service. Table of Contents. 1.0 Executive Summary

Statement of Work. 3.0 Details of Service Pre Start-up. - 1 - Cooling Start-up Service. Installation Service. Table of Contents. 1.0 Executive Summary Installation Service Statement of Work - 1 - Cooling Start-up Service Cooling Start-up Service Service 1.0 Executive Summary Table of Contents 1.0 Executive Summary 2.0 Features & Benefits 3.0 Details

More information

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES A. The Owner will contract separately and directly for the majority of the commissioning work

More information

APEC CAPABILITIES PROJECT MANAGEMENT / SUPPORT

APEC CAPABILITIES PROJECT MANAGEMENT / SUPPORT PROJECT MANAGEMENT / SUPPORT Capital Cost Savings Construction Monitoring and Assistance In-Plant Production Assistance In-Plant Maintenance Assistance Procurement Assistance Project Cost Estimating o

More information

NORSOK STANDARD H-001 Rev. 4, Nov. 2001. Heating, ventilation and air-conditioning

NORSOK STANDARD H-001 Rev. 4, Nov. 2001. Heating, ventilation and air-conditioning NORSOK STANDARD H-001 Rev. 4, Nov. 2001 Heating, ventilation and air-conditioning This NORSOK standard is developed by NTS with broad industry participation. Please note that whilst every effort has been

More information

Peach Bottom Atomic Power Station, Units 2 and 3 Renewed Facility Operating License Nos. DPR-44 and DPR-56 NRC Docket Nos.

Peach Bottom Atomic Power Station, Units 2 and 3 Renewed Facility Operating License Nos. DPR-44 and DPR-56 NRC Docket Nos. Exelon Generation 200 Exelo11 Way Kennett Square. PA 19348 www.pxeloncoroi.c cm 10 CFR 50.55a August 13, 2015 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Peach

More information

PITTSBURG TANK AND TOWER CO., INC.

PITTSBURG TANK AND TOWER CO., INC. PITTSBURG TANK AND TOWER CO., INC. HEALTH, SAFETY & ENVIROMENTAL PROGRAM INDEX 1.SAFETY POLICY & MANAGEMENT RESPONSIBILITIES - Safety Policy - Administrative Duties * Top Management * Safety Director *

More information

An introduction to BSI

An introduction to BSI An introduction to BSI 8/18/2015 Who is BSI? Leading Global Standards Creation Body: British, European, ISO, Public, Private The UK National Standards Body: The source of British Standards Specialist Focus

More information

HOISTING AND TRANSFER EQUIPMENT OF A NUCLEAR FACILITY

HOISTING AND TRANSFER EQUIPMENT OF A NUCLEAR FACILITY HOISTING AND TRANSFER EQUIPMENT OF A NUCLEAR FACILITY 1 Introduction 5 2 Scope of application 6 3 Equipment requirement specifications for hoisting device units 7 4 Manufacturer 7 4.1 General 7 4.2 Obligations

More information

Fuel Treatment and Conditioning Systems

Fuel Treatment and Conditioning Systems RULES FOR CLASSIFICATION OF Ships PART 6 CHAPTER 14 NEWBUILDINGS SPECIAL EQUIPMENT AND SYSTEMS ADDITIONAL CLASS Fuel Treatment and Conditioning Systems JULY 2006 This chapter has been amended since the

More information

9.4 Air Conditioning, Heating, Cooling and Ventilating Systems

9.4 Air Conditioning, Heating, Cooling and Ventilating Systems 9.4 Air Conditioning, Heating, Cooling and Ventilating Systems 9.4.1 Control Building HVAC The Control Building (C/B) Heating, Ventilating and Air-Conditioning (HVAC) System is divided into two separate

More information

Management of Contractors and Suppliers Procedure

Management of Contractors and Suppliers Procedure Management of Contractors and HSE P1101 Table of Content 1 DOCUMENT CONTROL... 2 2 PURPOSE... 3 3 SCOPE... 3 4 DEFINITIONS... 3 5 ROLES AND RESPONSIBILITIES... 5 6 PROCESS DETAILS... 9 6.1 Confirm Need

More information

CORDEL Cooperation in Reactor Design Evaluation and Licensing

CORDEL Cooperation in Reactor Design Evaluation and Licensing CORDEL Cooperation in Reactor Design Evaluation and Licensing Greg KASER Senior Project Manager African Utility Week Nuclear Focus Day Cape Town 12 May 2014 World Nuclear Association (WNA) Cooperation

More information

May 23, 2011 Tokyo Electric Power Company

May 23, 2011 Tokyo Electric Power Company Analysis and evaluation of the operation record and accident record of Fukushima Daiichi Nuclear Power Station at the time of Tohoku-Chihou-Taiheiyou-Oki-Earthquake (summary) May 23, 2011 Tokyo Electric

More information

Hydraulic control unit series 0086-372-01

Hydraulic control unit series 0086-372-01 Technical Product Information No. 1290 EN Hydraulic control unit series 0086-372-01 Contents Page About this Technical Product Information (TPI) 2 The ORTLINGHAUS numbering system 2 About the product 3

More information

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project. DIVISION 23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) SECTION 23 08 02 PART 1 GENERAL 1.01 AUTHORITY (CxA) A. The Commissioning Authority (CxA) has been contracted or will be contracted directly

More information

This document is the property of and contains Proprietary Information owned by Westinghouse Electric Company LLC and/or its subcontractors and

This document is the property of and contains Proprietary Information owned by Westinghouse Electric Company LLC and/or its subcontractors and This document is the property of and contains Proprietary Information owned by Westinghouse Electric Company LLC and/or its subcontractors and suppliers. It is transmitted to you in confidence and trust,

More information