CHARACTERISTICS OF SUCCESSFUL MEGAPROJECTS
|
|
|
- Moses Osborne
- 10 years ago
- Views:
Transcription
1 Chapter Six CHARACTERISTICS OF SUCCESSFUL MEGAPROJECTS Bibliographic Information: Committee to Assess the Policies and Practices of the Department of Energy to Design, Manage, and Procure Environmental Restoration, Waste Management, and Other Construction Projects, Board on Infrastructure and Constructed Environment, Commission on Engineering and Technical Systems, Characteristics of Successful Megaprojects, National Research Council, Washington, D.C.: National Academy Press, 2000 (available at Committee chair: Kenneth F. Reinschmidt. PURPOSE The National Research Council s Committee to Assess the Policies and Practices of the Department of Energy to Design, Manage, and Procure Environmental Restoration, Waste Management, and Other Construction Projects was established to develop recommendations to improve the Department of Energy s (DOE s) oversight and management of large scientific projects. BACKGROUND The U.S. Congress Conference Committee Report on Energy and Water Development entitled Making Appropriations for Energy and Water Development for the Fiscal Year Ending September 30, 1998, 39
2 40 A Review of Reports on Selected Large Federal Science Facilities and for Other Purposes, 1 directed the DOE to conduct a study to review the policies, procedures, and practices for identifying, planning, designing, and managing its portfolio of projects. To do this review, the DOE established the Committee to Assess the Policies and Practices of the Department of Energy to Design, Manage, and Procure Environmental Restoration, Waste Management, and Other Construction Projects (also known as the Reinschmidt Committee, after committee chairman Kenneth F. Reinschmidt of Stone and Webster, Inc. [retired]). During the committee s deliberations, it identified many factors that were common to large construction projects, or megaprojects, that were delivered successfully from the standpoint of cost, schedule, and scope. These characteristics were described in an appendix to the committee s final report entitled Characteristics of Successful Megaprojects and are summarized here. Thirteen experts with backgrounds in project management, contracting, budgeting, and cost estimation; environmental remediation and waste management; civil, environmental, and nuclear engineering; government management and administration; and systems and performance analysis served on the committee. 2 Committee members also had extensive experience with DOE policies, procedures, and practices for identifying project requirements, developing the scope of work, executing and managing design work, preparing cost estimates and schedules, selecting contract types, and executing and managing environmental restoration, waste management, and construction projects. 1 See U.S. Congress, Making Appropriations for Energy and Water Development for the Fiscal Year Ending September 30, 1998, and for Other Purposes, HR , pp. 96, for the appropriations bill language that relates to this report. 2 For a complete list of committee members and members of the Board on Infrastructure and Constructed Environment, see Committee to Assess the Policies and Practices of the Department of Energy to Design, Manage, and Procure Environmental Restoration, Waste Management, and Other Construction Projects (2000), pp. iv v.
3 Characteristics of Successful Megaprojects 41 METHODS/APPROACH Experience has shown that a greater amount of planning and greater skill are necessary to develop, sustain, and successfully deliver a megaproject than to do the same with a conventional construction project. The many characteristics of successful megaprojects are complex but are not well documented. Information on megaprojects is usually assembled solely to document what went wrong with a project rather than to document the circumstances surrounding success with a project. The information presented by the Committee to Assess the Policies and Practices of the Department of Energy can be used as a benchmark against which characteristics of megaprojects can be measured. These characteristics do not describe a process, but rather serve as checklists for comparing a specific project with other projects that have proven to be successful. These benchmarks are based on the collective experience and best practices of more than a dozen highly knowledgeable professionals with experience in large-scale projects. The following checklists can be used for assessing large projects at various stages e.g., during the development of baseline parameters, during a postmortem for identifying lessons to be shared with other project managers, or at any time during a project to identify likely sources of problems. FINDINGS AND RECOMMENDATIONS The findings of the Committee to Assess the Policies and Practices of the Department of Energy study were presented in the form of categorized checklists. The items in the checklists are divided into five groups of "conditions" (i.e., characteristics): general conditions, special conditions, and three types of technical conditions scope, costs, and schedule. Each of the five groups is further divided into three categories: conditions that are essential to success, conditions that are important to success, and conditions that are beneficial to success. These checklist items can apply to the settings, surroundings, and/or sponsors of megaprojects.
4 42 A Review of Reports on Selected Large Federal Science Facilities Not every listed characteristic must be present for a project to succeed. However, a good correlation with a successful project, particularly if the characteristics listed as essential to success are met, indicates a higher likelihood of project success. 3 General Conditions Conditions Essential to Success The project has a purpose, and the benefits are clearly defined and understood by all participants. The sponsor/owner/user is clearly focused on the successful completion of the project throughout the life of the project. All stakeholders attend regularly scheduled management review meetings with prepublished agendas. The responsibilities of owners and contractors are clearly understood by all parties. Incentives, as applicable, may be provided so that each contracting party shares in the benefits of improvements in project performance. Risks are borne by the parties most able to manage, control, or reduce those risks. Responsibility and accountability for project success or failure should be clearly assigned to key individuals. There is no change in the political will during the execution of the project. 4 3 For a complete list of items in the report s checklist, see Committee to Assess the Policies and Practices of the Department of Energy to Design, Manage, and Procure Environmental Restoration, Waste Management, and Other Construction Projects (2000). 4 It should be noted that some large projects have been canceled for good political reasons (e.g., the end of the Cold War and a lessening of the need for nuclear weapons facilities) that specifically addressed changing national needs. These project cancellations should be viewed as national successes, not project failures.
5 Characteristics of Successful Megaprojects 43 Conditions Important to Success Contracts are awarded on the basis of value, not just cost. The roles and responsibilities for each key person are published, and the chain of command is clearly defined. The depth, stability, and time commitments by key personnel are appropriate for the project to ensure low turnover in management and key technical positions. The public and stakeholders understand and accept the purpose of the project, the types of technologies to be employed, the processes used to award contracts, and the past relationships of the contractors with the local labor force, suppliers, and vendors. All stakeholders have a voice in decisionmaking. Agreed-upon project protocols have been published and are observed by all. Conditions Beneficial to Success The project is relatively immune to external factors that could affect its scope, mission, quality, cost, or duration. Project leaders are open to outside information, advice, improvements, technology, and independent assessments. Special Conditions Conditions Essential to Success Scope, cost, schedule, and quality are closely interrelated. The benefit-to-cost ratio for the project is high enough that increases in costs within preset limits will not threaten the viability of the project. Budgets include allowances for explicit contingencies. Actual cost and schedule performance are periodically compared with planned performance.
6 44 A Review of Reports on Selected Large Federal Science Facilities All proposed scope or design changes are justified with regard to configuration and project objectives and are priced out and documented to include their nonlinear effects. Milestones that are significant to each interested party have been identified and explained. Contractors are brought into the project early in the process so that they can participate in the project design. Conditions Important to Success Wherever possible, budgets are multiyear, updated, and extended annually. The uncertainties in costs and schedules are estimated and include a range of impacts from public or political opposition to the project. Systems are in place to track and report progress against the cost and schedule baselines at regular, planned intervals. Conditions Beneficial to Success Actual and budgeted costs of performed work are tracked in the field. Suppliers and vendors are involved during the planning and design stages to ensure that supplies of required materials and the latest technology are available. An active quality-improvement program addresses every level of staff and all processes, as well as work products. Technical Conditions: Scope Conditions Essential to Success The scope of work is clearly defined in terms that are relevant to the project team. The quality-assurance/quality-control program is tailored to meet project-specific requirements, and the scope of the project
7 Characteristics of Successful Megaprojects 45 reflects both project requirements and expectations as set forth in the contract. Site conditions are well known and have been thoroughly investigated. Conditions Important to Success A project s published quality-control plan establishes quality requirements for all staff and parties at all levels. When an environmental impact statement (EIS) and record of decision precede project initiation, every environmental action noted in the EIS is translated into specific mitigation plans that are attached to each work package to ensure compliance with the EIS and applicable law. Condition Beneficial to Success The project does not take so long to execute that the science or technology upon which it is based becomes obsolete before the project is completed. Technical Conditions: Costs Condition Essential to Success Cost estimates, at all stages, reflect the level of detail and explicit contingencies required at each stage of design development, so as to limit the likelihood of significant cost increases during design development, following project authorization. Conditions Important to Success Biases in the cost estimates are addressed through independent reviews. Cost estimates objectively account for all risks, changes, and hazards.
8 46 A Review of Reports on Selected Large Federal Science Facilities Conditions Beneficial to Success A cost estimate should be stochastically stated to reflect the risks inherent in the project. Confidence factors, or the likelihood that a given cost will not be exceeded, are associated with cost estimates at all stages to give project sponsors a clear idea of the risk of cost variances and overruns. Technical Conditions: Schedule Conditions Essential to Success Schedules and cost estimates are prepared simultaneously and are based on key factors. To minimize exposure to internal and external changes, the schedule is aggressive and is pursued vigorously. Condition Important to Success Risk analysis and probability techniques are applied to the duration of tasks. Condition Beneficial to Success Critical equipment and materials are available to support the schedule.
How to successfully manage your mega-project. Part III Continuously improve your chances for project success. kpmg.com
How to successfully manage your mega-project Part III Continuously improve your chances for project success kpmg.com 2 Building, Construction & Real Estate Mega-project keys to success Early planning and
INFORMATION TECHNOLOGY: Reservation System Infrastructure Updated, but Future System Sustainability Remains an Issue
INFORMATION TECHNOLOGY: Reservation System Infrastructure Updated, but Future System Audit Report OIG-A-2015-010 May 19, 2015 This page intentionally left blank. NATIONAL RAILROAD PASSENGER CORPORATION
GAO MAJOR AUTOMATED INFORMATION SYSTEMS. Selected Defense Programs Need to Implement Key Acquisition Practices
GAO United States Government Accountability Office Report to Congressional Addressees March 2013 MAJOR AUTOMATED INFORMATION SYSTEMS Selected Defense Programs Need to Implement Key Acquisition Practices
How to successfully manage your mega-project
BUILDING, CONSTRUCTION & REAL ESTATE How to successfully manage your mega-project Part II Stakeholder communication and project controls integration kpmg.com 2 Building, Construction & Real Estate How
How to successfully manage your mega-project
How to successfully manage your mega-project Part I Early planning and organizing for success kpmg.com 2 Building, Construction & Real Estate How to successfully manage your mega-project A three-part series
Introduction to the ITS Project Management Methodology
Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I 050 07010 002
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN April 2009 SLAC I 050 07010 002 Risk Management Plan Contents 1.0 INTRODUCTION... 1 1.1 Scope... 1 2.0 MANAGEMENT
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
Appendix V Risk Management Plan Template
Appendix V Risk Management Plan Template Version 2 March 7, 2005 This page is intentionally left blank. Version 2 March 7, 2005 Title Page Document Control Panel Table of Contents List of Acronyms Definitions
Module 1 Diploma of Project Management
Module 1 Diploma of Project Management Project Management Fundamentals in association with This two day course takes participants through all aspects of Project Management and provides in depth examination
Project Risk Analysis toolkit
Risk Analysis toolkit MMU has a corporate Risk Management framework that describes the standard for risk management within the university. However projects are different from business as usual activities,
Step by Step Project Planning
Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2
U.S. Nuclear Regulatory Commission. Plan of Action Strategic Workforce Planning
U.S. Nuclear Regulatory Commission Plan of Action Strategic Workforce Planning January 19, 2001 Strategic Workforce Planning Plan of Action January 19, 2001 Content Overview This plan of action outlines
Army Regulation 702 11. Product Assurance. Army Quality Program. Headquarters Department of the Army Washington, DC 25 February 2014 UNCLASSIFIED
Army Regulation 702 11 Product Assurance Army Quality Program Headquarters Department of the Army Washington, DC 25 February 2014 UNCLASSIFIED SUMMARY of CHANGE AR 702 11 Army Quality Program This major
Project Management Guidelines
Project Management Guidelines Overview Section 86-1506 (5) directs the NITC to adopt guidelines regarding project planning and management. The goal of project management is to achieve the objectives of
Project Management Topics
S E C T I O N II T W O Project Management Topics SECTION II: PROJECT MANAGEMENT TOPICS TABLE OF CONTENTS Introduction 3 1. PROJECT TRIAGE 5 1.1 Gather the Data 7 1.2 Review and Analyze the Data 10 1.3
Project Management Guidebook
METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple
Auditing Capital Projects and Project Controls. March 2013
Auditing Capital Projects and Project Controls March 2013 Internal Audit Perspective Oversight Insight Foresight Is the process operating as planned? Are controls, resources, and performance measures adequate
Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3
/01 PROJECT ADVISORY Stakeholder management and communication Leadership Series 3 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital programmes,
PROJECT MANAGEMENT PLAN <PROJECT NAME>
PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
Audit of Veterans Health Administration Blood Bank Modernization Project
Department of Veterans Affairs Office of Inspector General Audit of Veterans Health Administration Blood Bank Modernization Project Report No. 06-03424-70 February 8, 2008 VA Office of Inspector General
DEPARTMENT OF DEFENSE. MARKET RESEARCH REPORT GUIDE FOR IMPROVING THE TRADECRAFT IN SERVICES ACQUISITION Version 2.0
DEPARTMENT OF DEFENSE MARKET RESEARCH REPORT GUIDE FOR IMPROVING THE TRADECRAFT IN SERVICES ACQUISITION Version 2.0 OCTOBER 2014 1 MARKET RESEARCH INTRODUCTION The imbedded market research template, when
R000. Revision Summary Revision Number Date Description of Revisions R000 Feb. 18, 2011 Initial issue of the document.
2 of 34 Revision Summary Revision Number Date Description of Revisions Initial issue of the document. Table of Contents Item Description Page 1. Introduction and Purpose... 5 2. Project Management Approach...
Guidance Note: Corporate Governance - Board of Directors. March 2015. Ce document est aussi disponible en français.
Guidance Note: Corporate Governance - Board of Directors March 2015 Ce document est aussi disponible en français. Applicability The Guidance Note: Corporate Governance - Board of Directors (the Guidance
Risk Management Plan template <TEMPLATE> RISK MANAGEMENT PLAN FOR THE <PROJECT-NAME> PROJECT
RISK MANAGEMENT PLAN FOR THE PROJECT Prepared by: Approved by: Reference: Version: Date: INTRODUCTION This document is the Risk Management
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE
PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1
Acompany that consistently selects the right projects and
PM.01 How to Create a World Class Project Management Organization Dr. Nick J. Lavingia, PE Acompany that consistently selects the right projects and executes them with excellence can improve return on
PHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
LEVEL 5. Advanced Diploma in Purchasing and Supply. Senior Assessor s Report. July 2012. Risk Management and Supply Chain Vulnerability L5-02
LEVEL 5 Advanced Diploma in Purchasing and Supply Risk Management and Supply Chain Vulnerability L5-02 Senior Assessor s Report July 2012 L5-02 Senior Assessor Report July 2012 FV 1/8 SECTION A Candidates
Information Technology Project Management (ITPM)
FUNCTIONAL AREA 10 Project Management (ITPM) Incumbents in this functional area direct information technology system solution and/or improvement projects for cost, time, scope, risk, and quality. They
Guidance Note: Stress Testing Class 2 Credit Unions. November, 2013. Ce document est également disponible en français
Guidance Note: Stress Testing Class 2 Credit Unions November, 2013 Ce document est également disponible en français This Guidance Note is for use by all Class 2 credit unions with assets in excess of $1
Release Management: Effective practices for IT delivery
Release Management: Effective practices for IT delivery Introduction Today s health plans face a unique combination of technology challenges due to their complex IT environments. These environments serve
1. What is PRINCE2? Projects In a Controlled Environment. Structured project management method. Generic based on proven principles
1. What is PRINCE2? Projects In a Controlled Environment Structured project management method Generic based on proven principles Isolates the management from the specialist 2 1.1. What is a Project? Change
Project success depends on
Project success depends on many factors both within and outside the control of the project team. One of the aspects that is within the control of the project team is the planning. Almost everything we
Project Management Methodology
Project Management Methodology 1/6/2015 PAGE 1 OF 28 Version 2.0 Contents INTRODUCTION... 4 1. Overview... 4 PHASE 1 PROJECT INITIATION... 5 1. Governance Model... 6 2. Project Prioritization Process...
MNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
How PRINCE2 Can Complement PMBOK and Your PMP Jay M. Siegelaub Impact Strategies LLC. Abstract. About PRINCE2
How PRINCE2 Can Complement PMBOK and Your PMP Jay M. Siegelaub Impact Strategies LLC Abstract PMBOK is the recognized (de facto) standard of project management knowledge. In the UK and Europe, PRINCE2
U.S. Dept. of Defense Systems Engineering & Implications for SE Implementation in Other Domains
U.S. Dept. of Defense Systems Engineering & Implications for SE Implementation in Other Domains Mary J. Simpson System Concepts 6400 32 nd Northwest, #9 Seattle, WA 98107 USA Joseph J. Simpson System Concepts
CORPORATE GOVERNANCE GUIDELINES
CORPORATE GOVERNANCE GUIDELINES The following guidelines have been approved by the Board of Directors and, along with the charters of the Board committees, provide the framework for the governance of Darden
School Construction Projects
The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect
MARKET RESEARCH REPORT GUIDE FOR IMPROVING THE TRADECRAFT IN SERVICES ACQUISITION Version 1.0
DEPARTMENT OF DEFENSE MARKET RESEARCH REPORT GUIDE FOR IMPROVING THE TRADECRAFT IN SERVICES ACQUISITION Version 1.0 APRIL 2012 PREPARED BY THE: JOINT MARKET RESEARCH WORKING GROUP FOR THE: OFFICE OF THE
Understanding Enterprise Risk Management. Presented by Dorothy Gjerdrum Arthur J Gallagher
Understanding Enterprise Risk Management Presented by Dorothy Gjerdrum Arthur J Gallagher Learning Objectives Understand the components of a wellrun ERM program Review scope and process Explore the role
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION HUMAN CAPITAL PLAN FOR MISSION EXECUTION, TRANSITION, AND RETIREMENT OF THE SPACE SHUTTLE PROGRAM
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION HUMAN CAPITAL PLAN FOR MISSION EXECUTION, TRANSITION, AND RETIREMENT OF THE SPACE SHUTTLE PROGRAM April 14, 2006 1 4/14//2006 EXECUTIVE SUMMARY NASA has prepared
Offshore Megaprojects - Why we fail and how to fix it
------ ---- Track Two: Deepwater Developments: Increasing Demand While Maintaining Quality & Reliability Offshore Megaprojects - Why we fail and how to fix it Roy Robinson Global Contracts Manager for
Measurement Information Model
mcgarry02.qxd 9/7/01 1:27 PM Page 13 2 Information Model This chapter describes one of the fundamental measurement concepts of Practical Software, the Information Model. The Information Model provides
[project.headway] Integrating Project HEADWAY And CMMI
[project.headway] I N T E G R A T I O N S E R I E S Integrating Project HEADWAY And CMMI P R O J E C T H E A D W A Y W H I T E P A P E R Integrating Project HEADWAY And CMMI Introduction This white paper
CONTINUITY OF OPERATIONS AUDIT PROGRAM EVALUATION AND AUDIT
CONTINUITY OF OPERATIONS AUDIT PROGRAM EVALUATION AND AUDIT April 16, 2014 INTRODUCTION Purpose The purpose of the audit is to give assurance that the development of the Metropolitan Council s Continuity
1.0 Purpose. 2.0 Roles and Responsibilities. Management System Description: Project Management. Management System Owner: Lorie Howard
Management System Description: Project Management Management System Owner: Lorie Howard Point of Contact: Lorie Howard EMCBC Home Page Issue Date: Revision: 1 1.0 Purpose The purpose of the Office of Environmental
Oversight of Information Technology Projects. Information Technology Audit
O L A OFFICE OF THE LEGISLATIVE AUDITOR STATE OF MINNESOTA FINANCIAL AUDIT DIVISION REPORT Oversight of Information Technology Projects Information Technology Audit May 29, 2009 Report 09-19 FINANCIAL
IT SYSTEM LIFE-CYCLE AND PROJECT MANAGEMENT
United States Department of Agriculture Agricultural Marketing Service Directive 3130.8 IT SYSTEM LIFE-CYCLE AND PROJECT MANAGEMENT I. PURPOSE... 1 II. POLICY... 1 III. DEFINITIONS... 1 IV. DOCUMENTATION
Business Logistics Specialist Position Description
Specialist Position Description March 23, 2015 MIT Specialist Position Description March 23, 2015 Page i Table of Contents General Characteristics... 1 Career Path... 2 Explanation of Proficiency Level
Service Transition. ITIL is a registered trade mark of AXELOS Limited.. The Swirl logo is a trade mark of AXELOS Limited.. 1
Service Transition ITIL is a registered trade mark of AXELOS Limited.. The Swirl logo is a trade mark of AXELOS Limited.. 1 Lesson Objectives Service Transition - Introduction - Purpose and Objectives
ENTERPRISE RISK MANAGEMENT FRAMEWORK
ROCKHAMPTON REGIONAL COUNCIL ENTERPRISE RISK MANAGEMENT FRAMEWORK 2013 Adopted 25 June 2013 Reviewed: October 2015 TABLE OF CONTENTS 1. Introduction... 3 1.1 Council s Mission... 3 1.2 Council s Values...
How To Write A Contract For Software Quality Assurance
U.S. Department of Energy Washington, D.C. NOTICE DOE N 203.1 Approved: Expires: 06-02-01 SUBJECT: SOFTWARE QUALITY ASSURANCE 1. OBJECTIVES. To define requirements and responsibilities for software quality
How To Save Money On A Data Center
Federal Data Center Consolidation Initiative Data Center Consolidation Plan for the U.S. Small Business Administration Maintained by: The Office of the Chief Information Officer Paul Christy, CIO Revised:
PM Services. Transition Program Management
PM Services Transition Program Management Transition Program Management The PM Services team brings strong PM knowledge, years of program management experience, and a proven PM tool set to assure successful
The New International Standard on the Practice of Risk Management A Comparison of ISO 31000:2009 and the COSO ERM Framework
The New International Standard on the Practice of Risk Management A Comparison of ISO 31000:2009 and the COSO ERM Framework Dorothy Gjerdrum, ARM-P, Chair of the ISO 31000 US TAG and Executive Director,
March 2007 Report No. 07-009. FDIC s Contract Planning and Management for Business Continuity AUDIT REPORT
March 2007 Report No. 07-009 FDIC s Contract Planning and Management for Business Continuity AUDIT REPORT Report No. 07-009 March 2007 FDIC s Contract Planning and Management for Business Continuity Results
Governance Guideline SEPTEMBER 2013 BC CREDIT UNIONS. www.fic.gov.bc.ca
Governance Guideline SEPTEMBER 2013 BC CREDIT UNIONS www.fic.gov.bc.ca INTRODUCTION The Financial Institutions Commission 1 (FICOM) holds the Board of Directors 2 (board) accountable for the stewardship
Project Management Office (PMO)
Contents I. Overview of Project Management...4 1. Project Management Guide (PMG)...4 1.1 Introduction...4 1.2 Scope...6 1.3 Project Types...6 2. Document Overview, Tailoring, and Guidance...7 3. The Project
Using PRINCE2 to Manage US Federal Government IT Projects
For Portfolio, Programme, Project, Risk and Service Management Using PRINCE2 to Manage US Federal Government IT Projects Applying the PRINCE2 project management method to support Capital Planning and Investment
Linking Risk Management to Business Strategy, Processes, Operations and Reporting
Linking Risk Management to Business Strategy, Processes, Operations and Reporting Financial Management Institute of Canada February 17 th, 2010 KPMG LLP Agenda 1. Leading Practice Risk Management Principles
Personal Financial Planning As a Project
Personal Financial Planning As a Project By Greg Caramanica, PMP, General Securities Representative Financial Planner with Arlington Wealth Planning (www.arlingtonwealthplanning.com) Introduction Having
Independent Evaluation of NRC s Implementation of the Federal Information Security Modernization Act of 2014 for Fiscal Year 2015
Independent Evaluation of NRC s Implementation of the Federal Information Security Modernization Act of 2014 for Fiscal Year 2015 OIG-16-A-03 November 12, 2015 All publicly available OIG reports (including
Project Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
Table of Contents PERFORMANCE REVIEWS STRATEGIC REVIEWS
SECTION 270 PERFORMANCE AND STRATEGIC REVIEWS Table of Contents 270.1 To which agencies does this section apply? 270.2 What is the purpose of this section? PERFORMANCE REVIEWS 270.3 What is the purpose
Capital Project Services Middle East. Establishing a basis for effective project control
Capital Project Services Middle East Establishing a basis for effective project control The ca 2 The challenges of the Board in delivering Capital Projects Maturing economies and population growth across
Head, Office of Project Management Oversight
SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Management Oversight REVISION: 43 APPROVED BY: TITLE Head, Office of Project Management
BUSINESS CONTINUITY PLAN OVERVIEW
BUSINESS CONTINUITY PLAN OVERVIEW INTRODUCTION The purpose of this document is to provide Loomis customers with an overview of the company s Business Continuity Plan (BCP). Because of the specific and
PROJECT MANGEMENT PLAN EXAMPLES Prepare Project Support Plans and Documentation - Project Risk Assessment Examples
PROJECT MANGEMENT PLAN EXAMPLES Prepare Project Support Plans and Documentation - Project Risk Assessment Examples Example 54 10.0 PROJECT RISK This section outlines a methodology which will be used to
DEFENSE ACQUISITION WORKFORCE
United States Government Accountability Office Report to Congressional Committees December 2015 DEFENSE ACQUISITION WORKFORCE Actions Needed to Guide Planning Efforts and Improve Workforce Capability GAO-16-80
The Four Planes of Capital Projects
The Four Planes of Capital Projects An Integrated Approach to Capital Project Due Diligence August 2009 Westney Consulting Group, Inc. www.westney.com Management by objectives work - if you know the objectives.
Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria
Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost
B.2.2. Project Management Principles
B.2.2. Project Management Principles Project management is the application of knowledge, skills, tools, and techniques to project activities in order to meet or exceed stakeholder needs and expectations
PROCUREMENT MANAGEMENT PLAN <PROJECT NAME>
PROCUREMENT MANAGEMENT PLAN TEMPLATE This Project Procurement Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template
Corporate Risk Management Policy
Corporate Risk Management Policy Managing the Risk and Realising the Opportunity www.reading.gov.uk Risk Management is Good Management Page 1 of 19 Contents 1. Our Risk Management Vision 3 2. Introduction
Project Integration Management
Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform
HHS OCIO Policy for Information Technology (IT) Enterprise Performance Life Cycle (EPLC)
Office of the Chief Information Officer Office of the Assistant Secretary for Resources and Technology Department of Health and Human Services HHS OCIO Policy for Information Technology (IT) Enterprise
UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL
UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL AUDIT SERVICES August 24, 2015 Control Number ED-OIG/A04N0004 James W. Runcie Chief Operating Officer U.S. Department of Education Federal
How To Manage A Contract
Contract Management Checklist Preparation This section deals with laying good foundations before a contract is let. The contract should be actively managed. You should have a plan for doing this, which
7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers
Contents Page 1 Introduction 2 2 Objectives of the Strategy 2 3 Data Quality Standards 3 4 The National Indicator Set 3 5 Structure of this Strategy 3 5.1 Awareness 4 5.2 Definitions 4 5.3 Recording 4
User s Guide for Microsoft Excel Workbook Template for Conducting Simplified Risk Management Planning for Rapid Renewal Projects
SHRP 2 Renewal Project R09 User s Guide for Microsoft Excel Workbook Template for Conducting Simplified Risk Management Planning for Rapid Renewal Projects SHRP 2 Renewal Project R09 User s Guide for Microsoft
RISK MANAGEMENT POLICY AND STRATEGY. Document Status: Draft. Approved by. Appendix 1. Originator: A Struthers. Updated: A Struthers
Appendix 1 RISK MANAGEMENT POLICY AND STRATEGY Document Status: Draft Originator: A Struthers Updated: A Struthers Owner: Executive Director Corporate Services Version: 01.01.03 Date: 30/3/14 Approved
COMPARATIVE EFFECTIVENESS RESEARCH (CER) AND SOCIAL WORK: STRENGTHENING THE CONNECTION
COMPARATIVE EFFECTIVENESS RESEARCH (CER) AND SOCIAL WORK: STRENGTHENING THE CONNECTION EXECUTIVE SUMMARY FROM THE NOVEMBER 16, 2009 SWPI INAUGURAL SYMPOSIUM For a copy of the full report Comparative Effectiveness
Resource Management. Determining and managing the people resources on projects can be complex as:
Baseline Resource Management RESOURCE MANAGEMENT Purpose To provide a procedure and associated guidelines to facilitate the management of project people resources. Overview This Phase is used to establish
Ensuring Quality Going Down the Supply Chain
Ensuring Quality Going Down the Supply Chain (Including Vendor Qualification) What is the Role of Operators, Vendors and Regulators? April 21, 2015 DAE-HEE LEE Contents Nuclear Quality Issues The Role
Capital Projects. Providing assurance over effective delivery of projects
Capital Projects Providing assurance over effective delivery of projects Governance and oversight Project Scope and change Reporting and communication Project risk and success factors Delivery Major projects