6. The estimated costs here do not include any applicable ITCC tax



Similar documents
Hyperlinks are Inactive

AORC Technical meeting 2014

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.

Teleprotection Schemes and Equipment. James W. Ebrecht Young Power Equipment Scottsdale, AZ

SCADA Controlled Multi-Step Automatic Controlled Capacitor Banks & Filter Banks

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

Morris S. Stover, P.E. Sponsor, Transmission Area

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China

Power Plant Electrical Distribution Systems

SECTION POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL

Emirates Aluminium starts up World s first fully integrated power distribution system from ABB

Switchgear Capabilities. NexGear is a Division of PowerSecure NASDAQ: POWR

CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE

Introduction to The Trans Bay Cable Project

PSEG-LONG ISLAND SMART GRID SMALL GENERATOR INTERCONNECTION SCREENING CRITERIA FOR OPERATING IN PARALLEL WITH LIPA S DISTRIBUTION SYSTEM

ISIO 200. Binary Input/Output (I/O) Terminal with IEC Interface

STATCOM Application at VELCO Essex Substation

Inverter / Charger Installation General Operations and AC and DC Connections

TRANSMISSION Field Services (January 30, 2014)

Evolution of Control for the Smart Transmission Grid

SOLARCARE SERIES PRODUCT AND APPLICATION GUIDE

Addendum #2 Contract UK-11-13

FACT SHEET. BSES, Delhi - Distribution Network. Power Systems Consultancy from ABB

Telephone Company Lease Line Elimination. Dewey Day Principal Operational Technology Architect Pacific Gas & Electric

INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V V V (at 50 Hz)

Fusible Disconnect Switch

Product overview brochure. ABB Medium Voltage Products Our one-stop approach for every medium voltage application

SWITCHGEAR SOLUTIONS FOR MISSION CRITICAL APPLICATIONS. Presented by SAI Advanced Power Solutions

FVSU REPAIR & UPGRADE FIBER OPTIC SECTION FIRE ALARM SYSTEM CONNECTIVITY

Colorado Springs Utilities Interconnection Guidelines For Transmission to Transmission Interconnections Version 1 12/04/2007

INTRODUCTION TO SYSTEM PROTECTION. Hands-On Relay School 2012

Rule Fast Track Analysis for National Life Insurance Co.

Q140 Cluster Addendum

Monitoring Underground Power Networks

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

Seattle City Light s Asset Management Program

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

(2) Words and expressions used and not defined in these regulations but defined in the Act shall have the meaning assigned to them in the Act.

Chapter 1. Network Structures

ABB PSPS Erich Steinmann; Generator control-2013

ENERGY NETWORKS ASSOCIATION. Electricity Industry EMF Measurement Protocol for High Field Areas

TRANSMISSION AND SUBSTATION PROJECTS

Asset Management Plans

Treasure Valley Electrical Plan

Estimation of electrical losses in Network Rail Electrification Systems

Commonwealth of Puerto Rico PUERTO RICO ELECTRIC POWER AUTHORITY. ANNUAL BUDGET OF CAPITAL EXPENDITURES FISCAL YEAR (Dollars in thousands)

16 West Coast Regional Plan

2012 San Francisco Colloquium

TERMS AND CONDITIONS

Simulation of Ungrounded Shipboard Power Systems in PSpice

Topics. HVDC Fundamentals

APPLICATION CASE OF THE END-TO-END RELAY TESTING USING GPS-SYNCHRONIZED SECONDARY INJECTION IN COMMUNICATION BASED PROTECTION SCHEMES

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION'^^ j E DIRECT TESTIMONY RAJESH GUPTA PROJECT MANAGER, ENTERGY SERVICES, INC.

Minimizing Impact of Electric Utility Outages with Backup Generation

EPCOR Distribution & Transmission Inc.

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003

Local Back-up Protection for an Electric Power System

The following components are common to most cubicles; this example is an ABB HK cubicle.

Houston Service Center Medium Voltage Service and Aftermarket Solutions

EMTP STUDIES PERFORMED TO INSERT LONG AC CABLES IN THE FRENCH GRID

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

The electrical energy produced at the gen

How To Choose A Transformer

Electric utilities may vary in their application of end-to-end testing

the amount of data will grow. It is projected by the industry that utilities will go from moving and managing 7 terabytes of data to 800 terabytes.

Federal Wage System Job Grading Standards for Electric Power Controlling, Table of Contents

Design and Implementation of SCADA System Based Power Distribution for Primary Substation ( Monitoring System)

IEC 61850: Communication Networks and Systems in Substations

Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process

QUESTIONS and ANSWERS RFB , Metal Clad Switchgear and Power Control Room

January 23, Minimum Design Standards Task Force

INTERNATIONAL POWER DISTRIBUTION CONGRESS CIDEL ARGENTINA 2002

Type SA-1 Generator Differential Relay

LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems

Introduction To SCADA and Telemetry

Trip circuit supervision relay. Type RXTCS

Preliminary Information Memorandum. Thanet Offshore Transmission Assets. July 2009

The design and performance of Static Var Compensators for particle accelerators

DC Power Solutions Overview. DC Power Solutions for EVERY Network Application.

FFI. Advances in Medium and Low Voltage Power Distribution ESS Metron Expo and Technical Seminars. Presented By: Greg Pelster & Robert Schmid

GPS Interfacing of Banediya Feeder (M.P) Using MI Power Software

Emergency Response Solution- Keyspan

About us. Eugensa is an ISO 9001:2008 certified company. CERT

LAB1 INTRODUCTION TO PSS/E EE 461 Power Systems Colorado State University

SGTech Europe 2015 September 22 th Amsterdam. Pedro Gama, Head of SCADA & Telecom Department at EDP Distribuição, SA

The Impact of Transmission Cable System Construction and Design on Commissioning Test Options & Results

SECTION PROGRAMMABLE LOGIC CONTROLLERS AND COMPUTER CONTROL SYSTEM PART 1 GENERAL Summary. A. Section Includes:

SPECIFICATION COG-2007

Modular Systems wind portfolio overview Power Collection and Grid Connection products

Submit shop drawings for equipment provided under this section Shop drawings shall indicate:

Mladen Kezunovic Texas A&M University

LOGAN TERMINAL B SUBSTATION UPGRADE

Voltage Stability Improvement using Static Var Compensator in Power Systems

CHAPTER 4 UTILITY SYSTEMS ELECTRICAL. Utility Systems Electrical. Main Panel

1. Who is CenterPoint Energy Houston Electric, LLC?

ANCILLARY EQUIPMENT AND ELECTRICAL EQUIPMENT Power Supply Systems and Electrical Equipment for Desalination Plants - Y.M. Hamud and A.H.

ATTACHMENT F. Electric Utility Contact Information Utility Name. For Office Use Only

Transcription:

General Notes and Clarifications: 1. The following estimated costs are based on past experiences and are intended to provide an order of magnitude of the total project cost given the major system components. Under the same category final detailed scope components do vary depending on site conditions. 2. For substation estimated costs below, the accuracy is expected to be in the +/- 25% range. Contigency is not included in the unit costs but are included in detailed estimates which typically vary from 10% to 25%. 3. Some categories have no costs entered because either they are rarely installed or for lack of good cost data. For these categories, costs estimates will be provided after some detail engineering has been completed. 4. The equipment or installation categories below are what have been more commonly experienced in PG&E's service territory. 5. Installations at 500kV are rare for generation interconnection projects in PG&E's service area and good cost data are not available. Costs will have to be estimated on a case-by-case basis after some engineering work. 6. The estimated costs here do not include any applicable ITCC tax 7. April 1, 2009 update: added item numbers for easier reference and revised Items 6, 15, 16, and 21. 8. Feb. 12, 2010 update: some substation costs revised for Year 2010. ACRONYMS and TERMS for Substation Work MPAC - Modular Protection, Automation and Control. An MPAC building is similar to a control building containing all the equipment and devices for substation protection, automation and control. This building is built in the factory by a PG&E-approved supplier and shipped to the job site for final interface with outdoor installation and for commissioning testing. BAAH - Breaker-And-A-Half bus scheme or bus configuration DBSB - Double Bus Single Breaker bus configuration ITCC Tax - ITCC is Income Tax Component of Contribution. A tax (currently 34%) that has not been added to the estimates here. PG&E RTU - Generation Developer is required to install EMS telemetry /SCADA at their facility to provide information to PG&E per PG&E Interconnection Handbook for visibility. Often part of this is done by PG&E by installing a "PG&E RTU" at the Gen. Site to satisfy the SPS - Special Protection Scheme DTT - Direct Transfer Trip Scheme (usually using the RFL Gard 8000 teleprotection unit for Year 2010) DA - Direct Assignment. This term may be obsolete now but is here for illustration only since some of us are familiar with this term for what it meant. PGE ES_4Caiso022210_Rev A.xls Sht: General Notes 1 of 7 Updated 2-12-2010

1 2 Build a new switching station complete with two BAAH (breaker-and-a-half) bays and an MPAC or control building (Engineer, Design and Build) New switching station complete with with three BAAH bays and an MPAC or control building New installations @ PG&E Substation Facilities per unit x $12,000,000 $14,000,000 Total installed cost including control building but excluding land, land rights, permitting, incoming T- lines, and relay modifcation or upgrade work at remote stations. Also Note: new stations are typically required to be designed to be expandable). This new station and cost do not include the Generation Developer's switchyard should it be interconnected to PG&E's main buses, nor do they include AC station service power that needs be obtained from PG&E Distribution through a separate application process per unit x $15,000,000 $18,000,000 See 1 comments. 3 Install a complete new switching station with four BAAH bays, complete with MPAC or control building per unit x $18,000,000 $22,000,000 See 1 comments. 4 5 New switching station with 4-breaker ring bus, complete with MPAC or control building New switching station with 5 breaker ring bus, complete with MPAC or control building per unit $8,500,000 $10,500,000 $13,000,000 See 1 comments. per unit $9,500,000 $12,000,000 $15,000,000 See 1 comments. PGE ES_4Caiso022210_Rev A.xls 2 of 7 Updated 2-12-2010

6 PG&E support for a new PG&E-owned switching station that will be designed and built by the generation developer and deeded back to PG&E. PG&E support includes: Preparation of PG&E specification and requirements. Engineering review and approval of design. PG&E Civil, Electrical and Mechnical site inpectors during construction, Project Management, and other support activities per unit $900,000 $900,000 $900,000 This cost does not include work that needs be done at PG&E's remote stations 7 Add one line breaker position to existing substation with DBSB (Doube- Bus-Single-Breaker) bus configuration per unit $1,500,000 $2,000,000 $2,500,000 includes foundations, breaker, switches, structures, CVT's or PT's and line relays and protection inside existing control building. Assumes a spare bay is available. Cost does not include bus extension if needed 8 9 10 Add one bus sectionalizing breaker to existing substation Add one pair of bus sectionalizing breakers to existing substation on the main buses Add one bus parallel or substitute breaker to existing DBSB substation per unit $1,500,000 $2,000,000 $2,500,000 See 7 comments.. Includes also removal cost for bus disconnect sw, etc. Assumes space is available. Cost does not include relocating an existing line position if needed per unit x $4,000,000 $5,000,000 See 7 comments.. Includes also removal cost for bus disconnect sw, etc. Assumes space is available. Cost does not include relocating an existing line position if needed per unit x $2,000,000 $2,500,000 See 7 comments.. Includes also removal costs. Also Note: these are typical incremental costs, not total project cost by itself. Also cost does not include relocating an existing line position if needed PGE ES_4Caiso022210_Rev A.xls 3 of 7 Updated 2-12-2010

11 Add one line position to a BAAH scheme with one breaker (one busside breaker) per unit x $1,700,000 $2,000,000 Assumes that existing bus configuration already set-up for expansion this way with two existing breakers in the BAAH bay, and space is available. Also these are typical incremental costs only. 12 13 14 15 Add one line position to a ring bus with one breaker Add one 3-phase transformer, 420 MVA, includes one breaker on high side and one on low side. Typical 230kV/115kV, 230kV/60 or 70kV Add one 3-phase transformer, 200 MVA, includes one breaker on high side and one on low side. Typical 230kV/115kV, 230kV/60 or 70kV, 115kV/60 or 70kV Add shunt capacitor banks, 4 steps 75 MVAR each step per unit $1,500,000 $2,000,000 $2,500,000 Assumes that existing bus configuration already set-up for expansion this way and space is available. Also these are typical incremental costs only. per unit x x $10,000,000 includes transformer, foundations, breakers, switches, structures, CVT's and line relays and protection inside existing control building per unit x $7,000,000 $8,000,000 includes transformer, foundations, breaker, switches, structures, CVT's and line relays and protection inside existing control building per unit x x $10,000,000 Assumes space is readily available. Includes 5 breakers plus four cap banks each 75 MVAR 16 Add SVC (Static Var Compensator) per unit x $20,000,000 $30,000,000 Assumes space is readily available 17 18 Add Current Limiting Reactors on Main Double-Bus, 8 ohms Add DTT (Direct Transfer Trip scheme) without upgrading relays. Each terminal only per unit x x $10,000,000 Assumes space is readily available. Does not include relocating line positions to make space if needed per unit $220,000 $220,000 $220,000 Cost is for one terminal only. Does not include costs for matching equipment at other terminal or terminals. Does not include cost of leased line PGE ES_4Caiso022210_Rev A.xls 4 of 7 Updated 2-12-2010

19 Add SPS (Special Protection Scheme) at one terminal only per unit x x x Costs of SPS's have a wide range depending on scope. It could be from $250K to well over a million 20 21 22 Replace one overstressed breaker with new relays Replace one overstressed breaker without relay upgrade Replace or upgrade relays on one line position per unit $1,000,000 $1,200,000 $1,500,000 Includes adding or pulling new CT wires, modifying breaker foundation, replacing CVT's or PT's, etc. May include replacing existing breaker disconnect switches. per unit $750,000 $900,000 $1,200,000 Includes adding or pulling new CT wires, modifying breaker foundation, replacing CVT's or PT's, etc. May include replacing existing breaker disconnect switches. per unit $500,000 $550,000 $550,000 Assumes panel space is available on existing switchboard and existing line relays do not share the same panel with another line position. Cost does not include cost of new communication circuits between two or three stations when fiber is required for line current differential protection schemes. This communication cost has to be determined on a case-by-case basis 23 Converting an existing bus per unit x x x Conversion costs vary and depend on size of configuration to a ring bus or a breakerand-a-half existing station and site condition. Costs will scheme have to be determined on a case-by-case basis PGE ES_4Caiso022210_Rev A.xls 5 of 7 Updated 2-12-2010

24 25 26 27 28 29 Provide engineering and protection review for gen site for conformance to Interconnection Handbook requirements Provide Pre-parallel inspection and witness testing at gen site Provide PG&E revenue meter at gen site and pull secondary wires Maintenance and Operation (switching, etc) Pro-rated PG&E project management for gen site Install "PG&E RTU" for EMS telemetry at generation site and provide Telecom Support "DA" or Direct Assignment Costs at Generation Site $40,000 $40,000 $40,000 This cost assumes a medium size generation project or medium complexity $15,000 $15,000 $15,000 This task is typically performed by PG&E Station Test Group $25,000 $25,000 $25,000 This task is typically performed by PG&E Metering Department $15,000 $15,000 $15,000 $25,000 $25,000 $25,000 $100,000 $100,000 $100,000 Mounting space, DC and AC power, wires and and raceway, etc., to be provided by gen developer. This part is performed mainly by PG&E ISTS Department. PGE ES_4Caiso022210_Rev A.xls 6 of 7 Updated 2-12-2010

Transmission Line Work New Transmission Line 30 31 32 33 34 Double Circuit, Strung on both sides, Lattice Tower Double Circuit, Strung on one side, sides, Lattice Tower Double Circuit, Strung on both sides, Tubular Steel Pole Double Circuit, Strung on one side, sides, Tubular Steel Pole Single Circuit, Tubular Steel Pole $1,350,000 $1,350,000 $1,600,000 $1,050,000 $1,050,000 $1,250,000 $1,460,000 $1,460,000 $1,800,000 $1,250,000 $1,250,000 $1,450,000 $940,000 $940,000 $1,100,000 Unit cost shown is based on flat land/rural setting, engineering and construction costs only. Environmental, Permitting, and Right of way Acquisition costs are not included. Additional factors applied for hilly (1.2X), mountainous (1.3X), and forested (1.5X) terrain. Factors also apply for suburban (1.2X) or urban (1.5X) population density. Line length <10 miles (2X), line length 10 to 20 miles (1.5X). Costs for 60/70kV are same as for 115kV due to same 115kV standards used for new installation or design 35 36 Removal of Transmission Line (Complete Tear Down) Double Circuit Single Circuit $250,000 $250,000 $400,000 $150,000 $150,000 $275,000 Cost of removal only, assume any rebuild would use "new transmission line" from section above. Will include similar factors as new transmission line PGE ES_4Caiso022210_Rev A.xls 7 of 7 Updated 2-12-2010