Memorandum. PROJECT: Postmark Emergency Storm Repair Alternative Analysis



Similar documents
Storm Sewer Trenchless Upgrade Alternatives and Recommendations

Repair or Replacement - Band-Aids vs. Surgery

ITD Pipe Materials Selection & Specification Procedures. July 2011

INSPECTION FINDINGS. for. Paragon Condominiums 2102 W 31 st Avenue Denver, Colorado. Inspection Date: August 8, Perfonned By: Drew Schneider

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

Section 2100-Trenching and Tunneling

SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER

X Planning X Quality X Maintenance & Operations

SECTION GRAVITY SANITARY SEWERS

CULVERT AND STORM SEWER PIPE MATERIAL POLICY ON FEDERALLY FUNDED LOCAL AGENCY PROJECTS UPDATED March 2013

SECTION 5: SANITARY SEWER SYSTEM DESIGN

MEMORANDUM: RECOMMENDATIONS FOR PIPE MATERIAL SELECTION

SECTION STORM DRAINAGE TABLE OF CONTENTS

Preliminary Design Report Clay County, Florida Carpet n Drapes Culvert Repair and Rehabilitation July 21, 2006

Nebraska Department of Roads Drainage and Erosion Control Manual December 2011 Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY

Small Dam Repair The Stone Lake Dam Story. Joe Barron, P.E. SynTerra formerly the Fletcher Group, Inc. 148 River St. Suite 220 Greenville, S.C.

Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses

Beacon Hill Sewer District Standard Specifications

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

APPENDIX M-2 SANITARY SEWER TECHNICAL MEMORANDUM. Stadium Reconstruction EIR

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

DIVISION 4300 STORM DRAINAGE

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET

Section 402. STORM SEWERS

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS

SECTION FACILITY STORM DRAINAGE PIPING

Sewer Rehabilitation Design Requirements

SECTION SANITARY SEWER AND STORM DRAIN SYSTEMS

Premature Storm Drainage System Repairs and Replacement

Summary 7/11/2012. Michigan Water Environment Association 2012 Annual Conference Boyne Mountain Resort

CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R

Informational Workshop Public Meeting Kanawha Falls Bridge Project

DESCRIPTION OF WORK:

Wastewater Capital Projects Management Standard Construction Specification

Ultraviolet (UV) Light Cured Fiberglass Reinforced Cured-In-Place Pipe (CIPP) It is not just for sanitary sewer rehabilitation

CHAPTER 17: STORM SEWER STANDARDS Introduction Administration Standards 17.1

12/8/2014. Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA.

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects

Emerging Technologies in Wastewater Collection Systems

First in Service First in Safety

Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe

DEPARTMENT OF ENVIRONMENTAL QUALITY

See Appendix A for additional information, or contact ASTM directly.

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

Guidelines for Fiber Optic Cable Permits

MOBILE HOME LAW. Revised November 2001

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

2011 HYDRAULICS MANUAL

ENGINEERING DESIGN GUIDELINES. for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS

Chapter 9 Sanitary Sewers

CHAPTER 3 STORM DRAINAGE SYSTEMS

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

550 PIPE CULVERTS, SEWERS AND DRAINS

SECTION 3 SANITARY SEWER DESIGN

CITY UTILITIES DESIGN STANDARDS MANUAL

COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY

3. Amend the following: Item 410 Traffic Compacted Surface, Type C to Item 446 Cold Patch.

CITY OF ANN ARBOR PUBLIC SERVICES PLAN REVIEW CHECKLIST

FIBER-OPTIC CABLE PLAN CHECK

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION STORM DRAIN SYSTEMS PART 1 - GENERAL

STORM DRAINS CHAPTER 7

SECTION 7 UNDERDRAIN SERVICE

SPR PE Steel Reinforced Liner

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY. a guide to PREVENTING SEWER BACKUPS AND FLOODING

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

A perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. or structures.

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

Managing North Carolina's MSE Wall Assets through Design, Construction and Performance

MAIN STREET IMPROVEMENTS Water, Sewer, Stormwater and Streetscape Improvements

STANDARD SPECIFICATIONS FOR STORM SEWER CONSTRUCTION CITY OF PLYMOUTH, MINNESOTA

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS

Specifications for Residential Property Owners Connection to New Public Sewer

SECTION 5 - STORM DRAINS

SECTION 6A STORM DRAIN DESIGN Mar S E C T I O N 6A STORM DRAIN - DESIGN

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

McGOEY, HAUSER and EDSALL CONSULTING ENGINEERS D.P.C.

Chapter 9 Storm Sewers

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

a guide to PREVENTING HOME FLOODING DURING STORMS

DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

SANITARY SEWER BACKUP. Causes & Prevention

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

ENGINEERED SOLUTIONS. A2 Liner Pipe for Trenchless Technology

Township of Enniskillen. Asset Management Plan

STORM WATER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix F

Transcription:

Memorandum CRW Engineering Group, LLC 3940 Arctic Blvd. Suite 300 Anchorage, AK 99503 (907) 562-3252 FAX 561-2273 TO: Mike Lee, P.E., Chief Engineer, ADOT/ANC FROM: Shane Blanchard, P.E. THRU: Mike Rabe, P.E. DATE: August 28, 2009 PROJECT: Postmark Emergency Storm Repair Alternative Analysis PROJECT DESCRIPTION ANC requested CRW to prepare storm drain alternatives to repair the failing storm pipe from the Taxiway V headwall at Gate N10 to approximately 1100 feet north of DeHavilland Avenue. The Postmark storm drain system is a vital conduit for storm flows for ANC as it receives runoff from the North Terminal area, Postmark and DeHavilland roadways. This memo presents a description of the pipe failure, the alternatives and construction cost estimates along with recommendations. EXISTING PIPE CONDITIONS In the summer of 2008 ANC Field Maintenance performed an emergency repair on a collapsed portion of the Postmark storm drain system. After the repair Field Maintenance requested the remaining sections be inspected. In October 2008 ANC contracted CRW to perform an assessment of three storm drain systems. The three systems were inspected and the report Ron 12 to 14, Runway 7R, & Postmark Drive Storm Pipe and Manhole Assessment was published in December 2008. The Postmark Drive system showed signs of pipe deformation and joint separation in the plastic pipe installed in 1998. In June 2009 the report North Tug Road and Taxiway Victor Storm Sewer Pipe and Manhole Condition Assessment Report investigated the storm drain system exiting the Taxiway V headwall for a distance of 240 feet towards Lake Hood. This system, normally closed by a sluice gate at the headwall, is showing structural failure and pipe deformation.

Postmark Emergency Repair Page 2 of 4 The geotechnical report Storm Drain Emergency Repairs - ANC East Airpark Phase 2 was prepared to asses possible causes of the failure and give recommendations. Possible causes of the pipe failure are: improper bedding materials not implementing the design requirements for different native soil conditions improper pipe joint sealing unsatisfactory bedding compaction overloading with unanticipated fill (snow or vehicle traffic) REPAIR RECOMMENDATIONS The geotechnical report investigated three pipe materials for use in the repair corrugated metal pipe (CMP), steel pipe, and reinforced concrete pipe (RCP). The materials were evaluated against a variety of factors, including ease of installation, impact to existing ANC facilities, and hydrological efficiency. Of these three, RCP best met the needs of the project and are presented as the new pipe material in all alternatives. Figure 1 illustrates a typical RCP installation. ROUTE ALTERNATIVES Alternatives 1 and 2 were previously presented to ANC. During a review meeting in February 2008 ANC requested 2 more alternatives be investigated to remove conflicts with the controlled access point to the AOA at Gate N10. After the previous May 2009 Technical Memorandum the storm drain system exiting the headwall eastward towards Lake Hood was inspected, and afterwards created a 5 th alternative. A description of each alternative is presented below. See Figure 2 for plan view layout of the individual alternative routes. Alternative 1 This alternative is simply a replace in kind - the existing plastic pipe is replaced by an equivalently sized RCP pipe. No change in grade is made; the RCP pipes are installed at the same depth and slope as the existing pipe. No change to the existing dual 36 inch CMP section under DeHavilland. This option has the advantage keeping the Lake Hood discharge line and not needing to reconstruct 850 feet of sanitary sewer. Disadvantages would be no increase in pipe slope, impacts to the C Parking area and the Gate N10 operations. Alternative 2 This alternative uses the same alignment as Alternative 1, but increases the overall pipe slope. The pipe sizes are also increased to 48-inches from the Taxiway V manhole to DeHavilland for the purpose of potentially being the tie-in point for the future East Airpark force main.

Postmark Emergency Repair Page 3 of 4 Advantages would be an increase in the hydrologic efficiency of the system and capable of handling the future East Airpark flows, along with keeping the Lake Hood discharge line. Disadvantages are the need to reconstruct 850 feet of sanitary sewer main, impacts to the C Parking area and the guard post operation. Additionally, the existing fuel line crossing the Tug Road and paralleling Taxiway V would be impacted and require adjustment/relocation. Alternative 3 This alternative consists of using a portion the existing 48 inch CMP line exiting the Taxiway V headwall that discharges to Lake Hood. This line is normally closed at the headwall. A manhole would be installed near Postmark Drive and new 48 inch RCP would run northwest along Postmark Drive to DeHavilland, where it would follow the alignment of the previous alternatives. Due to the increased alignment length and slope within the existing 48 inch CMP, the new RCP pipe would have an unsatisfactory pipe slope and was not investigated any further. Additionally, after the June 2009 inspection is was discovered that this line is failing within the lengths investigated. Finally, discharge to Lake Hood would be eliminated. Alternative 4 This alternative uses a portion of the existing 48 inch CMP exiting the headwall to both clear the existing fuel line and not impact the operations of Gate N10. A manhole is installed approximately 150 feet east of the headwall and connected to the existing CMP. New 48 inch RCP crosses Taxiway V and follows the same alignment as alternatives 1 and 2. Advantages of this alternative are increased pipe slopes, no impacts to the existing fuel line and no impacts to the operation of Gate N10. This alternative would require the reconstruction of 850 feet sanitary sewer main and have impacts to the C Parking area and the connection to Lake Hood would be eliminated. Additionally, the June 2009 inspection showed the existing 48 inch CMP to be structurally failing. Alternative 5 Similar to Alternative 4 with the addition of replacing a portion of the existing 48 CMP with RCP and slip-lining the failing 48 CPEP pipe under the Gate N10 roadway. A manhole is installed approximately 70 feet east of the headwall. New 48 inch RCP crosses Taxiway V and follows the same alignment as alternatives 1 and 2. Advantages of this alternative are increased pipe slopes and limited impacts to the operation of Gate N10. This alternative would require the reconstruction of 850 feet sanitary sewer main, have impacts to the C Parking area and the existing fuel lines, and the connection to Lake Hood would be eliminated. Plan and profile drawings for alternatives 1,2, & 5 are included.

Postmark Emergency Repair Page 4 of 4 COST ESTIMATES The follow table gives the estimated construction costs of the four individual alternatives. ESTIMATED ALTERNATIVE CONSTRUCTION COSTS Segment Construction Cost* Description Alternative 1 $2,100,000 Replace pipe only Alternative 2 $2,660,000 Replace pipe, increase slope Alternative 3 Not Evaluated Reroute around Postmark Alternative 4 $2,640,000 Alternative 5 $2,740,000 Use existing CMP, replace pipe, increase slope Slip-line under Gate N10 roadway, replace pipes, increase slope *Does not include cost to relocate/adjust existing fuel line. RECOMMENDATIONS In the previous May 2009 Technical Memorandum, Alternative 4 was the recommended alternative. Two issues arose that have changes this recommendation: The existing 48 CMP is failing ANC would like to maintain a connection to Lake Hood for emergency storm flows For these reasons, Alternative 2 is the preferred alternative. By increasing the pipe slope the efficiency of the system is improved and removes the constriction caused by the dual 36 CMP pipes at DeHavilland. Clearance from the fuel lines is minimal (< 1 ), which will require coordination with ASIG (see Figure 3). Detour routes will need to be provided for traffic using the Tug Road and Taxiway V while construction activities occur with the Taxiway. As for the failing 48 CMP discharging to Lake Hood, on August 10, 2009 during a review meeting on this project ANC personnel indicated that keeping system in its current state is an acceptable risk and would be corrected at a later date. Even so, the segment under the Gate N10 roadway from the headwall to the first manhole should be corrected by slip-lining or other trenchless repair to ensure that the Gate N10 roadway is not compromised.

30102.00 Location.dwg CRW ENGINEERING GROUP STATE OF ALASKA DEPARTMENT OF TRANSPORTATION AND PUBLIC FACILITIES Ted Stevens Anchorage International Airport ANC EMERGENCY STORM DRAIN REPAIR TECHNICAL MEMORANDUM EXISTING FUEL LINE IMPACTS SHEET FIG 2 3of 4

TED STEVENS ANCHORAGE INTERNATIONAL AIRPORT

TED STEVENS ANCHORAGE INTERNATIONAL AIRPORT

TED STEVENS ANCHORAGE INTERNATIONAL AIRPORT

TED STEVENS ANCHORAGE INTERNATIONAL AIRPORT