SECTION IX SLIP LINING PIPELINES



Similar documents
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

Sewer Line Rehabilitation

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

SECTION ABANDONMENT OF SEWER MAINS

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

SPR PE Steel Reinforced Liner

Section 2100-Trenching and Tunneling

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

Policy Guidance Notes and Requirements

INSTALLATION OF INSITUFORM LINER

WILDCAT CANYON ROAD SPECIFICATION NO SLIDE REPAIR BIDDER'S PROPOSAL (continued)

725-R-599 PIPE LINING. (Revised ) SECTION 725, BEGIN LINE 1, INSERT AS FOLLOWS: SECTION 725 SLIP LINING OF EXISTING PIPE

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

SECTION HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

SECTION ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section Submittals.

Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam

Section 402. STORM SEWERS

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES

PART 5 : WASTEWATER DRAINAGE

Pipeline Replacement using Relining

SECTION CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

SECTION STORM DRAINAGE SYSTEM

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542

Platte River Interceptor Slipline Rehabilitation

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

Trenching and Excavation Safety

City of Regina Standard Construction Specification SECTION 1320 SEWERMAIN TESTING

FY08 SEWER POINT REPAIRS BID TABULATION

Sewer Rehabilitation Design Requirements

Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology

LEE S SUMMIT USES PIPE BURSTING TO BROADEN ITS ASSET MANAGEMENT TOOLBOX AND REHABILITATE POTABLE WATER DISTRIBUTION SYSTEM

SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD

Earthquake damage in wastewater systems and postearthquake repair methods; limitation and practice

CCTV INSPECTION OF SEWER LINES. A. Section Sanitary Gravity Sewer Lines. B. Section Sanitary Gravity Sewer Line Testing

Let Us Give Utilities the Respect that they Deserve.

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS

DIVISION 4300 STORM DRAINAGE

SECTION 807 PUMP STATION REHABILITATION

SECTION SELECTIVE DEMOLITION

The Manitoba Water Services Board SECTION Standard Construction Specifications September 2013 Page 1 of 21

Rehabilitation or Replacement? That Is The Question

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION

REHABILITATION OF THE LONG WHARF SEWER FORCE MAIN USING SLIPLINING METHODOLOGY IN NEWPORT, RHODE ISLAND

TG 105 ALLOWABLE PIPE SIZE, CLASS AND MATERIALS FOR WATER MAINS TECHNICAL GUIDELINE. Manager Asset Management SOUTH AUSTRALIAN WATER CORPORATION

Federation of Piling Specialists

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

LS 2540 SEWER LATERALS AND INSPECTION TEES

San Antonio, TX July 28, 2011

3. QUALITY ASSURANCE REQUIREMENTS

LIFELINE PIPELINE RESTORATION AND SEISMIC MITIGATION

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

To prevent increased stormwater runoff entering Council s drainage system and causing overloading of the system that in turn might cause flooding.

ENGINEERING STANDARDS MANUAL SECTION 5 WASTEWATER DRAINAGE

STANDARD SPECIFICATIONS SECTION CLEANING AND LINING WATER MAINS

Building over or close to a public sewer

Guideline Specification for the Replacement of Mainline Sewer Pipes By Pipe Bursting

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

SECTION GRAVITY SANITARY SEWERS

C. Section TESTING LABORATORY SERVICE.

12/8/2014. Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA.

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

Standard Specification for the Laying of Sewer Lines and Appurtenances in the Hurunui District

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

What is water main cleaning & lining

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

Table 4.9 Storm Drain Inlet Protetion Applicable for

Engineering Policy 146. Severe Weather Management Plans

Standard terms and conditions

Public Works Operations Manual Standard Operating Procedures for Water and Sewer WS-A412 Water Connection Repair

Rainwater is directed away from walls at surface. Any water infiltrating is captured in drains below foundation

SA Pipe Relining is dedicated to finding simple, non intrusive

ALL YOUR DRAINAGE NEEDS. Tel:

SECTION STORM DRAIN SYSTEM

Transcription:

AN SECTION IX SLIP LINING PIPELINES February, 2008

TABLE OF CONTENTS SECTION IX - SLIP LINING PIPELINES 9.01.00 GENERAL...2 9.01.01 SCOPE... 2 9.02.00 MATERIAL...2 9.03.00 CONSTRUCTION...2 9.03.01 REQUIREMENTS... 2 9.03.02 EXISTING SERVICES... 2 9.03.03 ENTRY AND EXIT PITS... 2 9.03.04 PIPE JOINTING... 3 PVC PIPES... 3 POLYETHYLENE PIPES... 3 9.03.05 BYPASS PUMPING... 3 9.03.06 PIPE LINING... 3 9.04.00 CONNECTIONS...4 9.04.01 SERVICE CONNECTIONS... 4 9.04.02 CONNECTIONS TO EXISTING NETWORK... 4 9.05.00 GROUTING...4 9.06.00 TESTING...4 9.07.00 MEASUREMENT FOR PAYMENT...4 Section IX - Sliplining Pipelines.doc February, 2008 1

SECTION 9 - SLIP LINING PIPELINES 9.01.00 GENERAL Slip lining is a technique used to renovate an existing pipeline by inserting a new pipe usually of a smaller diameter, by pushing or pulling it into the existing pipe and grouting the annulus between them. 9.01.01 SCOPE Specified in this section are requirements of slip lining of existing pipelines generally, including but is not limited to the following: flow diversion and temporary works traffic management excavating entry and exit pits pipe lining fabrication, storage and placement service connections, connecting to access chambers and make water tight Grouting other specific structural works testing reinstatement 9.02.00 MATERIAL Suitable pipe lining materials are HDPE, MDPE and UPVC. Contractor may specify other material for consideration by the Superintendent. Use clause 2.04 joints, of general specifications pipe works. Grout to comply with AS3600. Use cement and water at a water cement ratio of 0.5. If blockage with pumps is a problem Contractor may use additives such as Methocell. Obtain prior approval before using any additives. 9.03.0 CONSTRUCTION 9.03.01 REQUIREMENTS Provide all necessary plant, equipment, material and labour for carrying out the slip lining activities. 9.03.02 EXISTING SERVICES Locate existing service connections using closed circuit television (CCTV) method or using sonde and mark them on site. Carry out the necessary excavation to verify their locations. 9.03.03 ENTRY AND EXIT PITS The approximate locations of the entry and exit pits are shown on the drawing. Review the pit locations and submit details of the pit dimensions and any change of locations to the Superintendent for approval. Avoid locating these pits closer to buildings if possible. Carry out excavation as specified in Section I, Earthworks. Section IX - Sliplining Pipelines.doc February, 2008 2

9.03.04 PIPE JOINTING PVC PIPES Solvent welded pipe joints are permitted. Ensure pipe pushing or pulling apparatus does not cause shattering or compression of the new pipeline. POLYETHYLENE PIPES Butt fusion weld all pipe joints to Australian Standard AS 1159. Remove both the internal and the external beading around the pipe joint caused by the welding. 9.03.05 BYPASS PUMPING Maintain the flow in the system during lining by bypass pumping or flow diversion. Submit details of bypass pumping or flow diversion to the Superintendent for approval. Stopping of the live flow and storing in the pipeline may be permitted only if there is sufficient storage in the upstream pipeline that will prevent overflows, flooding or blockage of the system. In such cases, provide detail of the length of time proposed for stopping flows. In any case stopping of live flow is permitted for a maximum of 8 continuous hours and thereafter the drainage system must be put back into operation. Give one week notice to the Superintendent, so that the affected public can be notified. 9.03.06 PIPE LINING Submit details of the pipelining plan to the Superintendent for approval. Include in the details at least the following: Type of mechanical head to be use, Application pressure, Length of pipe to be install per day, Impact of any vibration on adjacent buildings, Storage requirements Environmental issues such as noise, vibration and how they will be minimised, Calibration details of measuring devices, Safety aspects, and Any temporary works proposed Carry out the pipelining operations as approved by the Superintendent and in accordance with the drawings. Stop pipe-cracking operations immediately and take direction from the Superintendent if any of the following occurs: surrounding structures show signs of cracking or vibration pipe lining tool goes off-line incomplete insertion of new pipe flooding of the system due to blockage Arrange for storage of materials and plant with the property owners, if the work is located within the property boundary. Provide adequate traffic management in accordance with Special Conditions of Contract Clause S9.0, if the work is located on roadways. Minimise the impact of disturbances to buildings and property owners. Reinstate the site to its existing conditions and obtain satisfactory written clearance from property owners and the Superintendent ( Use form 596). Section IX - Sliplining Pipelines.doc February, 2008 3

On completion of the pipelining and the installation of the new pipe, inspect all access chambers. Make the connections of the new pipe and the access chambers watertight by using approved sealant. If mortar is used, it should comply with AS3600, Clause 19.1.11. Maximum shrinkage allowable is 1% by volume. 9.04.00 CONNECTIONS 9.04.01 SERVICE CONNECTIONS Reconnect all service lines to the new pipeline as identified by the CCTV survey and in accordance with Standard Drawing 7600 series. Property connections or adjoining mains are not to be out of service for more than 8 hours. If this is not possible, temporary connections are to be made at convenient locations, as approved by the Superintendent. 9.04.02 CONNECTIONS TO EXISTING NETWORK Reconnect all new works to the existing network in accordance with Section 4.03.00 - Drainage. 9.05.00 GROUTING Carry out grouting of the annulus between the old and the new pipes using grout specified in Clause 9.02.00. Submit to Superintendent details of grouting technique and verification methods to be used for approval prior to commencement of grouting. 9.06.00 TESTING Provide CCTV equipment and inspect pipeline after all connections have been reconnected. Submit the CCTV surveys to the Superintendent for approval. Field test the pipelines as directed by the Superintendent and in accordance with Section 4.02.00 General Specifications, Drainage. 9.07.00 MEASUREMENT FOR PAYMENT Payment shall be based on the Schedule of Rates as tendered for the contract. The following units of measurement shall be used in the preparation of the Schedule of Rates if lump sum prices are not required. a) Pipe material is measured in linear metres. Include all items in accordance with Section 2.07.00 - Pipe Works. b) Slip lining is measured in linear metres. Include in the rate the supply of all plant, equipment and labour including all CCTV, temporary works, bypass pumping, jointing and positioning the pipeline in its final alignment and testing. c) Entry pits and exit pits are measured by cubic metres. Include in the rate the cost of excavation, backfilling and support if required. Excavation in rock if encountered shall be measured for payment in cubic metres separately. d) Service and access chambers connections are measured by numbers. Include in the rate locating them above ground, CCTV, any temporary works, all fittings, connecting to pipeline and making water tight using mortar. e) Relaying of service connections is measured in linear metre. Include in the rate the supply of materials, equipment, labour, excavation, backfilling and reinstatement. Section IX - Sliplining Pipelines.doc February, 2008 4