PART 5 : WASTEWATER DRAINAGE
|
|
|
- Antonia Simon
- 10 years ago
- Views:
Transcription
1 Authorised by : City Waters Unit Manager Page 1 of 15 PART 5 : WASTEWATER DRAINAGE 5.1 INTRODUCTION This Manual sets out the basic design principles for drainage of wastewater. While some construction information is included for completeness, detailed information on construction standards can be found in the Council Standard Specifications (Volume 3). 5.2 GENERAL All lots shall be provided with a single connection to a wastewater drainage system. Council does not permit lots to be served by multiple connections. The wastewater drainage system shall be designed to serve the whole of the natural upstream catchment area. The flow from all portions of the upper catchment within the city boundary shall be calculated assuming complete urbanisation (excluding reserves). The system shall have a design life of not less than 100 years for in-ground pipeline components. Designers are to confirm with Council the specific requirements for each subdivision, including such information as areas of catchment to be either included or excluded in any design calculation. This will be particularly important where further subdivision, upstream of the one under consideration, is provided for in the district or regional planning scheme. In these cases the wastewater network is to be constructed to the upstream boundaries of the subdivision development. For general wastewater design requirements in participating districts refer to Volume 5, Part STANDARDS The list of Standards specified in Clause shall also be applicable to this Part of the Manual. 5.4 CALCULATION OF FLOWS A statement is to be submitted with each plan to show that the design of the wastewater network has been calculated to meet the projected flows of the area under consideration. The designer shall consider the appropriate allowances for growth and clearly define any assumptions or basis for design inputs. The pipe system shall be designed to ensure that the system is self cleaning and that the pipe gradients are such that the velocity at peak daily flow meets this requirement. Design should be in accordance with the information given in Figure 5.1.(see also Section 5.7 Pipeline Minimum Grade Guideline.)
2 Authorised by : City Waters Unit Manager Page 2 of 15 Calculation Of Flows Figure 5.1 Design Data 2.1 Domestic wastewater flows are a function of water consumption, ground water infiltration and surface water ingress and shall be calculated as follows: 2.2 The wastewater flow is calculated as the product of the water consumption, the peaking factor, and the population equivalent of the area being served. The water consumption for Hamilton is 200 litres per person per day. The variable peaking factor dependent on population density for residential areas is determined from Figure 5.2. The following equivalent population densities per hectare should be adopted in the absence of specific supportable design data: Urban = 45 persons per hectare Commercial = 30 persons per hectare (except central business area) Other establishments should be treated as follows:- Primary Schools = equivalent to 45 persons Secondary Schools = equivalent to 150 persons Hospitals = equivalent to 3.5 persons/bed Boarding houses/motels = equivalent to 0.6 persons/bed 2.3 The infiltration allowance is 2250 litres per hectare per day. 2.4 The surface water ingress allowance is litres per hectare per day. 2.5 The Average Daily Flow is calculated as the sum of the infiltration allowance and the daily wastewater flow (product of water consumption and the population equivalent). 2.6 The Peak Daily Flow is calculated as the sum of 2.2 and The Peak Wet Weather Flow is calculated as the sum of 2.2, 2.3 and 2.4. Industrial Domestic Flow and Trade Waste 2.8 Where the industrial domestic waste and trade waste flows from a particular industry are known, these shall be used as the basis for the wastewater design. When this information is not available, then flows shall be calculated as above, except that the industrial peaking factor shall be used as shown on Figure 5.2 and the equivalent population density shall be 45 persons per hectare. 2.9 Provision for liquid trade wastes and 'wet' industries shall be considered and provided for by the design Peak Daily and Peak Wet Weather flows shall be calculated as in 2.6 and 2.7. The Hydraulic Design of Pipelines 2.11 All wastewater pipelines shall be designed such that they have sufficient capacity to cater for the design wet weather flow from the area they serve without surcharge and that on at least one occasion every day a minimum velocity for solids re-suspension (self cleaning) is achieved. The minimum velocity for self cleaning at peak daily flow will be deemed to be 0.6 m/s The capacity and velocity of flow in wastewater pipelines shall be determined by using the Colebrook White formula with a roughness coefficient (k) of 1.5mm as shown in Figure 4.5. Figure 5.3 can be used as a check of the design so that if the operational point falls within the appropriate envelope, then the pipeline will have adequate capacity for peak wet weather flows and achieve a self cleaning velocity at least once every day.
3 Authorised by : City Waters Unit Manager Page 3 of 15 Figure 5.2 Wastewater Peaking Factors Population Equivalent Wastewater Peaking Factor for Catchment or Sub-catchment Area Residential Commercial
4 Authorised by : City Waters Unit Manager Page 4 of 15
5 Authorised by : City Waters Unit Manager Page 5 of 15
6 Authorised by : City Waters Unit Manager Page 6 of LOCATION OF PIPELINES a) Wastewater pipelines within RESIDENTIAL ZONES shall normally be within the road reserve except where the properties served are below road level. (b) Wastewater pipelines in INDUSTRIAL ZONES shall either be in the road reserve or in the front yard area. (c) Wastewater networks (and connections) in COMMERCIAL ZONES shall be either in the rear service lane or at the rear of properties to be served where no service lane exists. The major reticulation and trunk lines, however, shall be in the road reserve (as for Residential Zones). Where the pipelines are in the road reserve they shall conform to the standard location of underground services and shall be sited within the carriageway, normally 2m from the kerb. Where the offset from the kerb varies due to curves in the street, the manholes shall be located 2m out from the kerb. Where a wastewater pipeline changes location within a street, it shall do so at an angle of 45 degrees or greater. Where a wastewater pipeline crosses other utility services, it shall do so at an angle of 45 degrees or greater. On the limited occasions where a wastewater pipeline is within a property, it is required to be parallel to and within m (preferably 0.75 m) from a boundary so as not to reduce the building area available. On sloping ground, the wastewater pipeline should be within the property of the higher land (to avoid conflict with excavation levelling of the lower property). Where Section 221 Resource Management Act 1991 applies... a consent notice shall be registered on the Certificate of Title of any allotment having a Council owned pipeline crossing the property. The consent notice shall advise that a public stormwater or wastewater (as appropriate) pipeline crosses under the property and conditions will be placed on any building consent for a structure over the pipeline. Manhole structures shall be clear of all boundary lines by at least 1.5 metres from the outer edge of the manhole chamber plus the height of any nearby retaining walls if they exist. Where the pipeline gradients are greater than 1 in 5, it is expected that anchor and/or antiscour blocks shall be constructed of a type comparable to that illustrated in Drawing TS405 (Volume 3). No new private drains shall pass between one lot and another. If crossing of private property is unavoidable, those parts of the pipeline serving more than one lot shall be Council mains with service connections to the property boundaries. Where Council pipes pass through private property, refer to Clause Pipe location for works under all consents should facilitate future fee-simple subdivision.
7 Authorised by : City Waters Unit Manager Page 7 of PIPES Acceptable pipeline products that may be used for wastewater pipe work are listed in Section A of the Drainage Standard Technical Specification. Where concrete-lined steel pipes are included in the design, these shall be as specified in the Water Technical Specification. Concrete pipes intended for wastewater applications shall be manufactured using a sulphate resistant concrete mix and, in addition to the standard thickness of concrete mix around steel reinforcing, the pipes shall have a 25 mm thick internal sacrificial lining of concrete mix. This reduced internal diameter shall be taken into account when determining the flow capacity of concrete pipes. upvc wastewater pipe may be used for pipe sizes ranging from 100mm to and including 375mm nominal diameter. The pipes and fittings shall comply with AS/NZS 1260:2002. Stiffness class SN16 pipes shall be specified in all cases. For a list of pipe materials suitable for use in participating districts and gradient requirements, refer to Volume 5, Part PIPELINE MINIMUM GRADE GUIDELINE Section 5.4 Calculation of Flows does not lend itself to determining the grade applicable to pipelines draining upper parts of a catchment. Council experience is that the minimum gradients shown in the following table provide satisfactory flow conditions for 150NB Pipe in both general soils and peat soils (those with greater than 300 mm of peat between 0.5 and 4.0m depth of the natural ground surface). Where the depth of soil exceeds 2.0 metres then specific design is required. Houses Population General Minimum Grade Peat soil Grades 3-4* : % 1: : % 1: : % 1:80 More than and above 1: % 1:80 *see also the guidelines for service connections Section JOINTS Specification of joints shall be as follows: All pipes shall normally have flexible joints of an approved type, such as RRJ. Steel pipes shall be flexibly jointed (gibault or approved rubber ring). Solvent cement joints shall only be used for PVC if specifically required by Council. Joints shall be provided adjacent to manholes to the requirements of AS/NZS 2566 with the exception of PVC where proprietary connections may be used. All joints are to be designed and constructed to remain fully watertight for the design life (100 years) of the pipe network.
8 Authorised by : City Waters Unit Manager Page 8 of STRUCTURAL STRENGTH OF PIPES AND BEDDING Pipe bedding will be designed to meet the requirements of the class of pipe used under the design loading conditions set out in the manufacturer s specifications PIPELINE CONSTRUCTION The construction of the pipelines shall be carried out in accordance with the requirements of Standard Technical Specification (Volume 3 of this Manual) GENERAL Pipes acceptable for use in wastewater drainage work are listed in the Standard Technical Specifications for Stormwater and Wastewater Sewers (Volume 3, Part 4) Requirements for Building Near or over Drainage Pipelines No structural loads are to be placed on public drainage pipelines. The first row of piles must be at least 1m clear of the outside of the pipe and down to a depth of at least 1m below the invert of the pipe. Subsequent rows of piles must be constructed to a depth of at least 1m below the 45 degree influence line form the pipe invert. All structural loads on piles shall be absorbed outside the 45 degree envelope and below the pipe invert level of the first row of pipes No pile ramming is permitted within 5m from the sewer centre line, or within the 45 degree envelope (piles within 5m must be drilled) The building or other work must be designed and constructed so that the sewer and trench line is not adversely affected by any future excavation necessary for maintenance of the sewer The structure must allow for settlement of the sewer trench line and backfill Drawings of the proposed works must accurately identify the location of the drainage pipeline affected and the distances with cross section details for all structures, footings or piles within the 45 degree line Buildings are not permitted to be located over connections to pipes or manholes Pipes Buildings to be built near or over pipes, then the HCC pipes shall be over shall be jetted and CCTV d before and after construction work. These requirements are shown in Figure TS 410.
9 Authorised by : City Waters Unit Manager Page 9 of MINIMUM COVER OVER PIPES General All pipelines other than those in private property shall be specifically designed to support the likely loading in relation to the minimum cover to be provided in accordance with the terms of NZS The minimum cover for all types of pipes (other than those in private property) under all conditions, shall be 600mm Private Property The minimum cover over unreinforced Council pipes in private property shall be 500mm. Where, due to the topography, this cover cannot be provided, the pipeline shall be protected. Specific design information will be required. Where the reticulation lines are located in the front yard of lots, the invert level shall be deep enough so as not to interfere with any future development such as driveway construction Under Carriageways Where pipes are designed below carriageway, they shall be specifically designed to support the pavement design loading appropriate to the minimum cover to be provided at both subgrade and finished level Private Pipes The depth of cover of private pipes is dealt with under the Building Act, 2004 and overseen by the Council Building Unit MANHOLES General Manholes shall be located away from areas likely to pond water and away from potential building sites. They are to be designed and constructed to exclude groundwater for the life of the network. Manholes up to 2400mm deep shall be constructed using a single riser with a pre-cast external flange base. Manholes in excess of 2400mm deep shall be constructed using a 2400mm long pre-cast riser with external flange base and then completed to final ground level using no more than a single riser for manholes up to 5.0m deep. Three risers are allowable for manholes in excess of 5.0m depth. In no case shall a series of short risers be permitted. Manholes shall be a minimum of 1050mm diameter for depths of 1.0m or more. Manholes of 750 mm diameter may be used for depths less than 1.0m (typically infill situation). Manholes on pipelines less than 300mm diameter shall be provided at each change of direction or gradient, and at each branching pipe, and at a spacing of not more than 100m.
10 Authorised by : City Waters Unit Manager Page 10 of 15 Manholes in pipelines 300mm diameter and over may have the spacing increased with the specific approval of Council. For infill developments, manholes shall not be required for a 150mm connection on a 150mm pipeline where a manhole is provided immediately inside the property being served and another manhole exists within 100 metres on the existing pipe and these provide adequate accessibility without needing another manhole. Manholes structures shall be clear of all boundary lines by at least 1.5 metres from the outer edge of the manhole chamber plus the height of any nearby retaining walls if they exist. New structures in private property are to be located 2.0 m clear of manholes as shown in Drawing TS 410. For specific requirements relating to manholes in participating districts, refer to Volume 5, Part Standard Manholes These are to be circular manholes with a minimum internal diameter of 1050mm (refer Drawing No s TS ) and are to be used on pipelines up to and including 600 mm diameter. Manhole steps shall be provided in accordance with Standard Technical Specification (Volume 3 of this Manual) Specific Design Manholes Where manholes are more than 5.0m deep they shall be specifically designed (wall strength, foundation support and adequate ballast to resist buoyancy). Where a manhole is to be constructed in soft ground, the area under the manhole shall be undercut down to solid and backfilled with suitable hard fill to provide an adequate foundation for the manhole base. Where undercutting exceeds 1.5m, a special design will be required Hydraulic flow in Manholes In addition to the normal pipeline gradient, all manholes for pipelines less than 1 metre in diameter shall have a minimum drop of 20mm plus 5mm per 10 degrees of the angle of change of flow within the manhole. In addition to the normal pipeline gradient, all manholes on pipelines greater than 1metre in diameter shall have the drop through the manhole designed to a minimum of 20mm plus compensation for the energy lost due to the flow through the manhole at the deviation angle (see Volume 2 Part 4 Figure 4.1, Clause 2.3). The construction tolerance for drop through the manhole shall be; Constructed Manhole Drop = Manhole Drop (as calculated above) + 5 mm 0 mm.
11 Authorised by : City Waters Unit Manager Page 11 of CONNECTIONS General A single connection provided at the boundary of each lot shall be of a type capable of taking an approved pipe of 100mm nominal diameter, unless a larger size is required by design. Council does not permit lots to be served by multiple connections. Each connection shall be capable of serving the whole of the lot by gravity. This requirement shall allow adequately graded drains within the lot, together with the depth required for gully traps. The standard depth of a new connection at the boundary is 1.2m (range metres). Note: Private wastewater pumps will not be approved where gravity discharge is feasible. In laying greenfield service connections which are capped pending connection of house drainage (refer drawing TS404) the maximum depth at the end of the service connection pipe shall be 1.5 metres. Sections which slope away from the drainage direction may require a service connection which is deeper that 1.5m at the boundary in order to comply with the requirement to drain the whole of the lot. In such cases the service pipe shall be extended into the property on grade and to the extent that its end cap is no deeper than 1.5metres. Note the service pipe needs to be located near the boundary or within a right of way in order to avoid conflict with possible building locations. This detail shall be shown on construction plans. Where the wastewater pipe is outside the lot to be served by it, the connection shall be extended to the boundary of the lot. If the above conditions cannot be met, then contact Council for further advice. Drop connections at manholes shall be designed as external connections in a manner similar to the illustrations in Drawing TS 400. Internal drops shall only be used where manhole diameters are 1200mm or greater. All connections, which are to be made directly to the line, shall be designed using a factory manufactured "wye" or "London Junction" and shall be watertight. Service connections shall generally enter each lot from the road frontage. Where a property has no road frontage, pipes are located within that property s legal access (right of way). Where feasible: Private pipes will not cross property boundaries; and Existing private connections crossing boundaries shall be replaced by a public connections. Note: Generally existing private pipe work shall not be acceptable for vesting to Council due to the lower standard of construction. The standard size and material for single lot domestic connections is 100mm RRJ SN16 upvc.
12 Authorised by : City Waters Unit Manager Page 12 of Infill Developments Connection proposals for infill developments shall be fully documented with regard to depth to invert, pipe size and distances to boundaries. (Where Council records are not available, applicants must determine the details of existing connections). Any private pipe work needs a Drainage Consent from Council s Building Unit. All connections and disconnections of Council services to the property boundary are undertaken by a Council approved Contractor REQUIREMENTS FOR SERVICE PIPE SIZE AND ALIGNMENT For 1 to 4 dwellings a 100mm nominal bore service pipeline is adequate. For 5 or 6 dwellings the capacity of a 100mm nominal bore service is only adequate if installed at a grade 1:60 or steeper. The service pipeline shall be laid to a public drain as a straight pipeline between boundary inspection fitting and manhole, or between boundary inspection fitting and a wye connection on the wastewater main, or between a boundary inspection fitting and a wye connection on a service pipeline conforming to either of the previously listed variations. The minimum acceptable grade is 1:80 (preferred grade 1:60) except on peat soils where 1:60 is required. It shall be no longer than 50 metres. It must comply generally with the in-roadway alignment guideline, ie where a wastewater pipeline changes location within a street, it shall do so at an angle of 45 degrees or greater. Where a wastewater pipeline crosses other utility services, it shall do so at an angle of 45 degrees or greater. More than 6 dwellings (also suitable for 3 or more dwellings) requires the capacity of a 150mm nominal bore pipeline. (Refer Volume 2, Part 5, Clause 5.7) RAMPED RISERS Unless required otherwise by the Engineer, a ramped riser shall be constructed to bring the connection to within metres of ground level, or to such depth that will permit a gravity connection to service the whole lot. Ramped risers shall be constructed as shown in Drawing TS CONNECTION TO TRUNK AND INTERCEPTOR PIPELINES Connections to wastewater interceptor pipelines shall only occur at manholes. Connections to wastewater trunk pipelines shall be preferably at manholes, or alternatively, and only with specific approval of Council, utilizing factory fabricated wye junctions in pipelines of PVC or vitrified clay materials. For specific requirements relating to wastewater connections in participating districts, refer to Volume 5, Part 5.
13 Authorised by : City Waters Unit Manager Page 13 of CONNECTIONS TO DEEP LINES Where an existing or proposed sewer is more than 5 m deep to the top of the pipe, or where required by the ground conditions, the connection shall be designed as a manhole constructed on the deep line and a shallower branch sewer shall be laid from the manhole TESTING All wastewater mains and branch pipelines, including extended connections, shall be pretested during construction. On completion of all other engineering work within the subdivision, there shall be a final test conducted. Test requirements are set out in Volume 3, Part 4, Section 16Section B, Clause For specific testing requirements in participating districts refer to Volume 5, Part PUMPING STATIONS For specific pump station requirements in participating districts refer to Volume 5, Part General All equipment and/or components used for similar functions and purposes must be of the same design, make or model for ease of operation and maintenance. This includes new pumping stations. The requirements for the design of new pumping stations are detailed on Drawing TS501, and must be in accordance with the Standard Technical Specifications. Calculations shall be submitted in a similar format as that shown in Checklist 5.1 of Volume 2, Part Structural Stability The pump station wet well shall be designed to have negative or zero buoyancy. Ground water level shall be assumed to be at ground level unless an actual level is established by geotechnical investigation. The mass of the wet-well structure included in the stability analysis shall not include the associated mechanical and electrical components of the pump station. Nor can the soil friction forces of backfill around the wet well chamber be taken into account. Any additional weight needed shall be added in the form of mass concrete in the bottom of the chamber as indicated in Drawing TS 502. The pump station drawings shall provide dimensions of the extent of mass concrete needed to counter buoyancy of the chamber Pumps, Rising Main, Delivery Point and Overflow Pumps shall be Flygt MT pumps (medium head performance range) models CP or NP versions 3085, 3102, 3127 or 3153 or Homa equivalent for the 3153 models. The pumping range shall be selected to give between 1 and 15 starts per hour at peak daily flow.
14 Authorised by : City Waters Unit Manager Page 14 of 15 The pump system shall be an N + 1 system where N pumps are required for duty and a standby pump identical to the duty pumps shall be installed. Exceptions to the duty plus one standby pump requirement can be made in small installations serving no more than 12 residential dwellings. In such installations the wet well shall be designed to have a minimum storage capacity sufficient to contain 12 hours of the catchment's Average Daily Flow. The rising main will be a minimum size of 80mm and designed such that the minimum velocity, with one pump operating, is one metre per second and the maximum velocity, with all duty pumps operating, is three metres per second. The point at which the pumping station is connected to the City system will be governed by the capacity of the network downstream from that point. The emergency overflow pipeline shall be of sufficient capacity to carry peak wet weather flow from the station without surcharge. The inlet to the overflow pipe shall be baffled to restrict the entry of solid floatable material. This can normally be done using a 90 degree downturn bend. The overflow pipe shall be from the pump station chamber to the nearest stormwater system. A backflow device shall be fitted where there is potential for stormwater to backflow into the pump well. The upstream impacts of a pump station overflow shall be checked to ensure no overflow occurs elsewhere Pump Chamber, Valve Chamber and Manifolding The layout of the pumping chamber, valve chamber and pipe work shall be similar to that shown on Drawing TS 503. The valve chamber shall be attached to the pumping chamber. Where the delivery point is within close proximity to the pumping station the valve chamber may be dispensed with and a separate rising main from each pump laid to the delivery point. The floor of the pumping station shall be set at such a level below the inlet pipe so that the inlet pipe will not surcharge during the normal pump operation cycle. The floor shall be designed to be of sufficient thickness to ensure that the pump station cannot become buoyant with groundwater at ground level and in any case not less than 600mm thick. Other specific requirements for standard pump stations are covered by the Standard Technical Specifications Pump Station Storage Pump stations shall provide for wastewater storage in the event of pump failure, control malfunction, electricity outage etc. A minimum of six hours storage at Average Daily Flow, shall be provided before emergency overflow occurs. For pump stations having just one pump, 12 hours storage at Average
15 Authorised by : City Waters Unit Manager Page 15 of 15 daily Flow shall be provided before emergency flow occurs. The required storage volume shall be provided in the volume of the wet well, plus any additional ancillary storage chambers, plus the volume of pipelines (below overflow level) draining to the facility. The wet well volume below pump switch off level shall be excluded from the calculation of available storage volume. If necessary the required storage capacity can be obtained through use of an associated storage chamber constructed as an adjacent manhole haunched and connected to the wet well so as to completely drain into the wet well before the pump shuts off on the pump out cycle. Preferably the storage volume shall be provided in the pumping wet well structure and upstream pipelines. Where this is impractical, additional storage can be provided in an additional manhole type structure adjoining the wet well. Or if this configuration is impractical, the storage shall be provided in a horizontal chamber made from large pipes. Standard configuration and details are in preparation (in the interim refer to Council for assistance) Water Supply A standard 630D MDPE pipeline as used for water supply ridermains (Volume 3, Part 6, Section D) shall be provided to the pump station. Wastewater pump stations are a High Hazard risk requiring reduced pressure zone type backflow prevention devices installed above ground level (refer BIA Acceptable Solution G12/AS1 and AS.NZS2845.1). The backflow prevention device is to be positioned adjacent to the electrical control cabinet as shown on Drawing TS Access A permanent concrete all-weather vehicle access shall be provided to the pump station to allow maintenance vehicles to access wet wells RISING MAINS Rising mains shall meet the requirements for water supply pressure mains. Rising mains in private property shall be located clear of building sites and the alignment protected by 'Easement in Gross'. The test pressure shall be at least twice the maximum working pressure and the final test must be witnessed by Council. Only polyethylene pipe may be used for wastewater rising mains. (Refer Volume 3, Part 5 Section A). Air relief valves shall be fitted as necessary and/or as required by Council COMMISSIONING TEST PUMP STATIONS All pumping stations shall undergo a commissioning test witnessed by Council. A minimum of 24 hours notice shall be given prior to the test taking place. See Volume 3, Part 5, Section C for as-built requirements.
ENGINEERING STANDARDS MANUAL SECTION 5 WASTEWATER DRAINAGE
CODE OF PRACTICE FOR CITY INFRASTRUCTURE & LAND DEVELOPMENT ENGINEERING STANDARDS MANUAL SECTION 5 WASTEWATER DRAINAGE Issue 4.6 Sept 2008 Section 5 Page 1 SECTION 5.0 WASTEWATER DRAINAGE Note: The adoption
SECTION 5: SANITARY SEWER SYSTEM DESIGN
SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities
Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development
7 SPECIFICATIONS There is currently no Irish specification for construction of drainage works, or water supply works. There are several publications that give guidance on drainage works, such as the Building
SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION
SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown
Prepare a drainage system layout and specification notes for a low- rise building.
STUDENT MATERIALS Prepare a drainage system layout and specification notes for a low- Outcome 1 - rise building. In this outcome you will study the technology of below and above ground drainage systems.
SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS
SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING
Engineering Specifications February, 2004 Schedule H to Bylaw 7452, Subdivision Bylaw Page 18
Schedule H to Bylaw 7452, Subdivision Bylaw Page 18 3.4 Sanitary Sewers 3.4.1 Materials 3.4.1.1 The class and type of pipe and fittings, together with required class of bedding and trench widths, shall
CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT
Page 1 CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT CIVIC CENTRE 2141 MAJOR MACKENZIE DRIVE MAPLE ONTARIO L6A 1T1 905-832-2281 Page 2 SECTION 1 - GENERAL OBJECTIVES To provide
Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects
Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental
CHAPTER 5. Storm Sewer
CHAPTER 5 Storm Sewer A. Introduction All proposed developments shall have a properly designed and constructed storm water conveyance system. This chapter deals only with the conveyance system. Storm water
Standard Specification for the Laying of Sewer Lines and Appurtenances in the Hurunui District
Standard Specification for the Laying of Sewer Lines and Appurtenances in the Hurunui District 1. SCOPE OF WORK This Specification applies to the laying of sewer pipes and all associated appurtenances
SANITARY SEWER SPECIFICATIONS
SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,
EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS
NMP 1.4 EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS Index Purpose... 2 Application... 2 Referral Agency... 2 Associated Requirements... 2 Referenced Standards...2 Definitions...
SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or
Emerging Technologies in Wastewater Collection Systems
Keville Enterprises Emerging Technologies in Wastewater Collection Systems Douglas McCutchen, CCM Brian Karmasin, P.E., BCEE CMAA Annual Conference Oct 2008 San Francisco, California Today s s Presentation
SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.
SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
DESIGN STANDARDS PINE RIVERS SHIRE COUNCIL. Design Standards for Sewerage Works DESIGN MANUAL CIVIL INFRASTRUCTURE DESIGN
PINE RIVERS SHIRE COUNCIL DESIGN MANUAL CIVIL INFRASTRUCTURE DESIGN DESIGN STANDARDS Part 1 Part 2 Part 3 Part 4 Design Standards for Roadworks Design Standards for Stormwater Drainage Works Design Standards
Policy 11: Land Development Guidelines
Policy 11: Land Development Guidelines Section 5 5.0 Sewerage Reticulation Design Requirements Table of Contents 5.0 Sewerage Reticulation Design Requirements...1 5.1 Introduction...2 5.2 Design Requirements
BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY
MURRAY SHIRE COUNCIL BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY ADOPTED: 1 May 2012 1 BUILDING OVER OR NEAR WATER AND SEWER MAINS POLICY CONTENTS 1. Objective... 2 2. Requirements for Building Near
Building over or close to a public sewer
Building over or close to a public sewer thameswater.co.uk/developerservices thameswater.co.uk/developerservices 1 Questions and answers Did you know Thames Water is legally responsible for more than 100,000
PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE
REGION OF PEEL PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE Storm Sewer Design Criteria REVISED July 2009 PUBLIC WORKS STORM SEWER DESIGN CRITERIA TABLE OF CONTENTS 1.0
CHAPTER 3 STORM DRAINAGE SYSTEMS
CHAPTER 3 STORM DRAINAGE SYSTEMS 3.7 Storm Drains 3.7.1 Introduction After the tentative locations of inlets, drain pipes, and outfalls with tail-waters have been determined and the inlets sized, the next
Town House 11265 Center Highway North Huntingdon, PA 15642
APPENDIX C SPECIFICATIONS FOR THE CONSTRUCTION OF BUILDING LATERAL SANITARY SEWERS DECEMBER 2004, INCLUDING AMENDMENTS ADOPTED ON FEBRUARY 6, 2008 AND APRIL 2, 2008; EFFECTIVE ON MAY 1, 2008 Town House
Reticulation sewers in basements Technical guidelines
Reticulation sewers in basements Technical guidelines Overview What These guidelines explain our technical requirements for laying sewers in building basements. The scope of the guide is restricted to
OAR52 A-1 (September, 1981)
APPENDIX A SEWER PIPELINES (1) MINIMUM REQUIREMENTS FOR SEWER - PIPELINES (a) Capacity: Sewers shall be of such diameter as to pass without overflow, bypass, or back flow onto damageable property of a
SECTION 7- STORM SEWER
SECTION 7- STORM SEWER 7.1. STORM SEWERS.... 7-1 7.2. SUMP DRAINS... 7-3 7.3. CATCH BASINS... 7-3 7.4. MANHOLES... 7-4 7.5. STORM SEWER CALCULATIONS... 7-4 7.6. CULVERTS AND BRIDGES... 7-5 7.7. OPEN CHANNELS...
SECTION 6A STORM DRAIN DESIGN Mar. 2002 S E C T I O N 6A STORM DRAIN - DESIGN
S E C T I O N 6A STORM DRAIN - DESIGN 6A.l Scope 6A.2 Storm Water Quantity 6A.3 Storm Drain Hydraulics 6A.4 Depths 6A.5 Locations 6A.6 Curved Storm Drains 6A.7 Manholes 6A.8 Catch basins 6A.9 Storm Drain
Introduction. Contents. General. Materials and workmanship. Diagrams. Other regulations. References
Introduction General This Technical Booklet has been prepared by the Department of the Environment for Northern Ireland and provides for certain methods and standards of building which, if followed, will
Beacon Hill Sewer District Standard Specifications
Beacon Hill Sewer District Standard Specifications Residential Gravity Side Sewer Including Design Criteria and Standard Construction Drawings Residential Gravity Side Sewer Design Criteria 1. Provisions
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,
32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.
SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and
CHAPTER 17: STORM SEWER STANDARDS. 17.00 Introduction. 17.01 Administration. 17.02 Standards 17.1
CHAPTER 17: STORM SEWER STANDARDS 17.00 Introduction 17.01 Administration 17.02 Standards 17.1 17.00 INTRODUCTION The purpose of this chapter is to provide guidance for the design and construction of storm
LS 2540 SEWER LATERALS AND INSPECTION TEES
LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal
Appendix A: Acceptable pipe and fitting materials
Watercare Services Limited Water and Code of Practice Content from the NZS 4404:2010 Land development and subdivision infrastructure has been reproduced for use in the Infrastructure Design s Manual for
PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE
REGION OF PEEL PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE Sanitary Sewer Design Criteria REVISED July 2009 PUBLIC WORKS SANITARY SEWER DESIGN CRITERIA TABLE OF CONTENTS
Type of Sewer Systems. Solomon Seyoum
Type of Sewer Systems Solomon Seyoum 0 Learning objectives Upon completion of this lecture, the participants will be able to differentiate between types of sewer systems and discuss different aspects of
Guide to working on Public Sewers
Guide to working on Public Sewers affected by Building Works Introduction Severn Trent Water Ltd requires the work to be done in order to protect the public sewer and minimise the risk of us having to
ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application.
ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application. Article II provides rules governing the allowable connection to the City POTW and the construction and inspection of
Mandatory Part 1.4 BUILD OVER OR NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS
Mandatory Part 1.4 BUILD OVER OR NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS Table of Contents Purpose... 2 Commencement... 2 Application... 2 Referral Agency... 2 Compliance with the QDC... 2 Associated
SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE
6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction
The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:
Page 1 of 6 Section 1. PURPOSE This policy is an Engineering checklist of the Local Review Program for sanitary sewer improvement projects by the Bedford Regional Water Authority ( Authority ). Section
DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES
SECTION INCLUDES Domestic Water Fire Water Service Water Well Sanitary Sewer Storm Drains Foundation Drainage RELATED SECTIONS 03 30 00 Concrete 21 00 00 Fire Suppression - Sprinklers 22 00 00 Plumbing
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection
Top 10+ Mistakes of DWV plumbing design
Top 10+ Mistakes of DWV plumbing design Listed below are the some of the most frequently missed items, noticed by our inspectors, at plumbing rough-in when non-plumbers attempt plumbing design. Most of
The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11
Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;
City of Edmonton Page 1 of 5 Foundation Drain Discharge Collection System Guideline November, 2005
City of Edmonton Page 1 of 5 This guideline will apply to all new developments involving singledetached, semi-detached or duplex houses in the City of Edmonton effective January 1, 2006. Preamble: This
CITY OF SALEM DEPARTMENT OF PUBLIC WORKS ADMINISTRATIVE RULES CHAPTER 109 DIVISION 003 SANITARY SEWER COLLECTION SYSTEM
CITY OF SALEM DEPARTMENT OF PUBLIC WORKS ADMINISTRATIVE RULES CHAPTER 109 DIVISION 003 SANITARY SEWER COLLECTION SYSTEM SECTION 3.1 INTRODUCTION... 1 (a) Objectives...1 (b) Applicability...1 (c) Drafting
DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST
DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST CERTIFICATION 1. Did the engineer submit a certificate of completion utilizing the appropriate page of the issued
Stormwater/Wetland Pond Construction Inspection Checklist
: Construction Inspection ChecklistsTools Stormwater/Wetland Pond Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: SATISFACTORY/ UNSATISFACTORY COMMENTS Pre-Construction/Materials
SECTION 3 SANITARY SEWER DESIGN
SECTION 3 SANITARY SEWER DESIGN 3.1 GENERAL DESIGN CRITERIA 3.1.1 Requirement for Sanitary Sewer 3.1.2 Design Approval 3.1.3 IEPA Permit Required 3.1.4 Differentiation Between Public and Private Sanitary
3. QUALITY ASSURANCE REQUIREMENTS
3. QUALITY ASSURANCE REQUIREMENTS 3.1 General This section covers the Kaipara District Council requirements for monitoring and testing of physical asset construction to ensure that the final asset delivered
SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING
SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent
Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department
Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant
CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is
~: ~,,' " CITY OF ST. CA THARINE S BY-LAW NO. cn- Olc.4 A By-law to regulate sanitary and storm drainage. WHEREAS the Council of the Corporation of the City of St. Catharines, is authorized by the provisions
www.defra.gov.uk Annex B
www.defra.gov.uk Annex B National Build Standards Design and Construction of new gravity foul sewers and lateral drains Water Industry Act 1991 Section 106B Flood and Water Management Act 2010 Section
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0
Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains
1 P age Module 7: Hydraulic Design of Sewers and Storm Water Drains Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains 2 P age 7.1 General Consideration Generally, sewers are laid at steeper
FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
Chapter 9 Storm Sewers
Contents 1.0 Introduction... 1 2.0 Design Storms... 1 2.1 Minor Event... 1 2.2 Major Event... 1 3.0 Pipe Material and Size... 2 3.1 Pipe Material... 2 3.2 Minimum Pipe Size... 2 3.3 Service Life... 2 3.4
Design and Construction of Cantilevered Reinforced Concrete Structures
Buildings Department Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-68 Design and Construction of Cantilevered Reinforced Concrete Structures
CHAPTER 11 STORM DRAINAGE
CHAPTER 11 STORM DRAINAGE SECTION 11 GENERAL 11.1 Scope. The provisions of this chapter shall govern the materials, design, construction and installation of storm drainage. 11.2 Where required. All roofs,
SEPTIC TANKS FOR THE COLLECTION & SETTLEMENT OF DOMESTIC SEWAGE
SEPTIC TANKS FOR THE COLLECTION & SETTLEMENT OF DOMESTIC SEWAGE Let us help! Free professional site visit with friendly support and advice. [email protected] to make the right decision or call
Standard terms and conditions
Standard terms and conditions INTRODUCTION For the provision of a water service (Water Supply, Wastewater and Drainage) Under Section 73(2)(a) of the Water Services Act 2012, landowners may be entitled
SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS
1001 SOUTH LEECHBURG HILL LEECHBURG, PA 15656 Phone: 724-845-9355 Fax: 724-845-1186 SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS 1. General
Section 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
CHAPTER 11 STORM DRAINAGE
CHAPTER STORM DRAINAGE SECTION PC 0 GENERAL 0. Scope. The provisions of this chapter shall govern the materials, design, construction and installation of storm drainage. Storm water discharge shall be
Does Part of My Basement Floor Have to Be Removed to Install. Where Does the Water from the Sump Pump Go?...Page 5
PROTECTIVE PLUMBING - WHAT IS IT? TABLE OF CONTENTS Protective Plumbing What is it?...page 1 What is Foundation Drainage?...Page 2 What is a Sump Pumping System?...Page 4 Does Part of My Basement Floor
APPENDIX 9 INFRASTRUCTURE SERVICING REPORT
APPENDIX 9 INFRASTRUCTURE SERVICING REPORT Lot 50 Cockram Street, Mundijong Infrastructure Servicing Report Peet Ltd August 2012 LOT 50 COCKRAM STREET, MUNDIJONG-INFRASTRUCTURE SERVICING REPORT Project
Sewer Rehabilitation Design Requirements
Sanitary Sewer Overflow (SSO) Control and Wastewater Facilities Program Sewer Rehabilitation Design Requirements City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared
Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems
Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems The septic tank-absorption field sewage treatment system is composed of two major elements; the
9.00 THE USE OF HUNTER LAND DRAINAGE PERFORATED PIPES. Hunter Underground Systems
9.00 THE USE OF HUNTER LAND DRAINAGE PERFORATED PIPES Hunter Underground Systems 9.01 General 9.02 Surface water Drainage 9.03 Groundwater Drainage 9.04 Dispersal of Septic Tank Effluent 9.01 The use of
Northeast Tri County Health District
Northeast Tri County Health District Standards and Guidance for Performance, Application, Design, and Operation & Maintenance Holding Tank Sewage System Based on the Washington State DOH of Health Recommended
A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.
PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,
31. ECO-INFO -- SEPTIC SAFE PROTECT YOUR HEALTH AND ENVIRONMENT YOUR SEPTIC PUMP-OUT SYSTEM with SELF ASSESSMENT TROUBLE SHOOTING GUIDE
31. ECO-INFO -- SEPTIC SAFE PROTECT YOUR HEALTH AND ENVIRONMENT YOUR SEPTIC PUMP-OUT SYSTEM with SELF ASSESSMENT TROUBLE SHOOTING GUIDE Edited 21/12/01 Wyong Shire Council has many non sewered areas that
Design Templates Stormwater Calculation Summary
Infrastructure Technical Specifications Stormwater Calculation Summary F4.1 Site Address: Consent Number: Application by: Total Site Area Prior to Subdivision Lot 1 Area Lot 1 C Design Storm Details ARI
CHAPTER 2 HYDRAULICS OF SEWERS
CHAPTER 2 HYDRAULICS OF SEWERS SANITARY SEWERS The hydraulic design procedure for sewers requires: 1. Determination of Sewer System Type 2. Determination of Design Flow 3. Selection of Pipe Size 4. Determination
Specifications for Residential Property Owners Connection to New Public Sewer
Specifications for Residential Property Owners Connection to New Public Sewer Spalding Tract property owners are required to connect to the community sewer system when construction is complete and the
Septic System Design Manual
Septic System Design Manual Prince George s County Health Department Largo Government Center 9201 Basil Court, Suite 318 Largo, Maryland 20774 (Office) 301-883-7681 (Fax) 301-883-7266 (January 2007) Table
Architectural Processing and Inspections for Home Mortgage Insurance
Page 1 of 5 [Text Only] Architectural Processing and Inspections for Home Mortgage Insurance Directive Number: 4145.1 SITE GRADING AND DRAINAGE GUIDELINES Construction complaints and structural defect
SUSTAINABLE URBAN DRAINAGE SYSTEMS
overflow can lead into a permeable conveyance system to increase further the benefit and reduce the need for pipe systems. Pollutant removal rates have been shown to be high, with some pollutants being
THE CORPORATION OF THE CITY OF GUELPH. THEREFORE the council of the Corporation of the City of Guelph enacts as follows:
THE CORPORATION OF THE CITY OF GUELPH By-law (1993)-14515 A by-law respecting storm water disposal from private property in the City of Guelph, to amend By-law (1987)-12602 and to adopt Municipal Code
EFFECTIVE FEBRUARY 2014. note: drainage permit required to call for a dampproof inspection
EFFECTIVE FEBRUARY 2014 note: drainage permit required to call for a dampproof inspection 1. ROOF DRAINS/DECK DRAINS (INTERIOR ) All roof and deck drains within the perimeter of the building shall be APPROVED
SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.
SUBDRAINS AND FOOTING DRAIN COLLECTORS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subdrains B. Subdrain Cleanouts and Outlets C. Footing Drain Collectors D. Storm Sewer Service and Connections 1.02 DESCRIPTION
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit
CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS
CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection
Cast iron swing grate in cast iron frame. 300x300 ID concrete chamber. Available chamber depths 400mm or 600mm deep. K&C Roadway SITE PLAN
Cast iron swing grate in cast iron frame Nominal 90 mm inlet SECTION x ID concrete chamber. vailable chamber depths 400mm or 600mm deep CHMBER PLN Stormwater pipe House Chamber location in vehicle cutdown
SANITARY SEWER BACKUP. Causes & Prevention
SANITARY SEWER BACKUP Causes & Prevention A. PURPOSE The purpose of this publication is twofold: 1. It provides homeowners with basic information on the causes of sanitary sewer backups. 2. It provides
SECTION 5 DRAFTING STANDARDS
SECTION 5 DRAFTING STANDARDS 1 SECTION FIVE TABLE OF CONTENTS Description Page TABLE OF CONTENTS... 5-2 GENERAL... 5-3 DRAFTING STANDARDS... 5-5 DRAFTING MINIMUM REQUIREMENTS HANDOUT... 5-8 2 GENERAL 1.
PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET
PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET Name of Municipality or Sewer District Name of Project Original Township and Lot Number Name of Engineer of Firm Preparing Plans
STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.
STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill
SUMP PUMP. City of Ann Arbor & C O L L E C T I O N S Y S T E M G L O S S A R Y
Foundation A foundation is the bottom part of a building. It s the element that anchors the building to the ground and transmits the building s gravity load directly to the earth. Water damage weakens
Gas Meter Clearances and Service Installation Requirements
March 2015 Gas Meter Clearances and Service Installation Requirements Builder/Owner/Developer Requirements Call PSE s Customer Construction Services 1-888-321-7779 or visit PSE.com/CustomerConstruction
San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS
ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located
SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST
SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST For permanent structures per Delaware SCS Pond Code 378 and Delaware Sediment and Stormwater Regulations KEY PROJECT INFORMATION Item meets standard
