Basis of Cost Estimates



Similar documents
Cost Estimating Procedures for Raw Sewage Overflow Control Program

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

After the Flush. Safe disposal of our wastewater is a valued and complex, not-for-profit municipal service.

Appendix S Pump Station Evaluation

Dry Weather Flow from Footing Drains and Service Connections

Sanitary Sewer Master Plan

COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY

COMBINED SEWER OVERFLOW LONG-TERM CONTROL PLAN Executive Summary

PERMITTEE/FACILITY NAME: City of Detroit Water and Sewerage Department / Detroit Wastewater Treatment Plant

Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows to Prevent Contamination of Drinking Water

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

Technical Feasibility of a Wet Weather Flow Treatment Facility

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Key cost factors include: Year: Engineering News Record Construction Cost Index: AACE Cost Estimate Classification: 4.

Executive Director, Engineering & Construction Services Director, Purchasing & Materials Management Division

Wastewater Collection Practice Test #3 Page 1 of 15

ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT

SEWER CLEANING, INSPECTION AND ASSESSMENT

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

FY08 SEWER POINT REPAIRS BID TABULATION

LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD

Coast Trunk Sewer Rehabilitation Project for the Orange County Sanitation District

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

FY15 Gravity Sewer and Manhole Rehabilitation

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Rehabilitation or Replacement? That Is The Question

DRAFT Public Outreach Document for What s an SSMP?

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD DIRECT TESTIMONY OF STEPHEN J. FURTEK

Review of Footing Drain Disconnection Projects

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

MIAMI-DADE LATERAL PILOT PROGRAM. James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E.

Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses

Oakland Macomb Interceptor Drain Rehabilitation State Revolving Fund Project Plan Overview. Public Meeting June 10, 2009

SECTION CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE

High-Rate Retention Treatment Facility for CSO Control in Windsor Riverfront East

Critical Facilities and Flow Management

Chapter 8: Common Treatment Facilities, Programs, Operational Improvements and Policies for the Recommended Plan

SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING

Purpose and Approach. Introduction

BASEMENT FLOODING. Prevention Guide for. Homeowners

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

DEPARTMENT OF ENVIRONMENTAL QUALITY

5.1 SIZING OF FACILITIES 5.2 PHASING CONSIDERATIONS

See Appendix A for additional information, or contact ASTM directly.

812-3 LIMITATIONS: b. No fire hydrant shall be obstructed or used when there is a fire in the area.

Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1

SECTION 807 PUMP STATION REHABILITATION

City of Shelbyville Site Inspection Checklist

CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R

City of East Lansing CSO Control Facility Evaluation Demonstrative Approach to Meet WQS

Sanitary Sewer Overflow (SSO) Incident Report Form

Emergency Response Plan

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION STORM DRAIN SYSTEMS PART 1 - GENERAL

Wastewater Collection and Treatment Systems For Small Cities

Type of Sewer Systems. Solomon Seyoum

Emerging Technologies in Wastewater Collection Systems

Clean Water State Revolving Fund (CWSRF) Requirements and Guidance for a Fiscal Sustainability Plan (FSP)

GIS Applications for Regulatory Compliance

City of Bakersfield Public Works Department Sewer System Management Plan December 2014

Sanitary Sewers LINK TO THE COMPREHENSIVE PLAN

Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology

REQUEST FOR PROPOSALS SANITARY SEWER MAINTENANCE SERVICES FOR THE TOWN CENTER SEWER ASSESSMENT DISTRICT WITHIN THE TOWN OF WOODSIDE

2.1 Development of Risk-Based Asset Management Framework

5. Environmental Analysis

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

ecmar SECTION INSTRUCTIONS: Sanitary Sewer Collection Systems

A Systematic Approach to Reduce Infiltration and Inflow (I&I) and Sanitary Sewer Overflows (SSO) PETE GORHAM, P.E. MIKE LYNN FEBRUARY 19, 2015

DID YOU KNOW... THE IMPACT OF ON-SITE SEWAGE SYSTEMS AND ILLICIT DISCHARGES ON THE ROUGE RIVER

City and County of San Francisco 2030 Sewer System Master Plan TASK 400 TECHNICAL MEMORANDUM NO. 405

SANITARY SEWER SPECIFICATIONS

Work Practice: Wastewater Collection System Maintenance Plan Potential Safety Hazards

CHALLENGES IN LINING A 100 YR OLD BRICK SEWER

Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES

Maricopa Association of Governments. Technical Memorandum No. 1 INFRASTRUCTURE DEVELOPMENT COSTS. August 2001

Rouge River Watershed, MI Region 5. Community Case Study ROU-1. Number of CSO Outfalls. Combined Sewer Service Area. Wastewater Treatment Capacity

THE BIG FIX: Public works administration would be easy if infrastructure. San Diego s Sewer Renewal Program. By Steve Gibbs

City of Los Altos Sewer System Management Plan

City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014

Soapstone Sewer Rehabilitation Alternative Concepts Design and Associated Impacts

Terry Biederman, PE- Director of Public Works Greg Gucwa, PE- Principal Johnson and Anderson Engineering

SECTION 810 SEWER LINE CLEANING

FISCAL YEAR CAPITAL IMPROVEMENT PLAN WASTEWATER TREATMENT FACILITIES

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

REVIEW OF TRENCHLESS TECHNIQUES FOR THE REHABILITATION OF SEWERS. Gerhard (Gerry) P. Muenchmeyer, P.E. Muenchmeyer Associates, LLC

Preliminary Design Report Clay County, Florida Carpet n Drapes Culvert Repair and Rehabilitation July 21, 2006

Special Specification 7021 Water Main and Sewer Line Replacements

Technical Memorandum Cost Criteria for 2010 System Capacity Plan

Monterey Regional Water Pollution Control Agency. Sewer System Management Plan

Office of Environment, Health and Safety (EH&S) - Sanitary Sewer Overflow Incident Form (rev. 12/2014)

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

SANITARY SEWER SYSTEM ASSESSMENT

SECTION STORM DRAIN SYSTEM

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects

Transcription:

Wastewater Master Plan DWSD Project No. CS-1314 Technical Memorandum Original Date: May 8, 2003 Revision Date: September 2003 Author: Tucker, Young, Jackson, Tull Inc.

Table of Contents 1 Purpose...1 2 Methodology...1 2.1 Wastewater Conveyance Facilities...1 2.2 Wastewater Treatment Facilities...2 3 Limitations...3 4 Allowances and Contingencies...3 5 Cost Index...5 6. Program 1: Sewer Infrastructure Program...7 6.1 Subprogram No. 1A: Lateral and Connector Sewers Cleaning, Sediment Disposal & Condition Assessment...7 6.2 Subprogram No. 1B: Interceptor and Trunk Sewer Cleaning, Disposal and Condition Assessment...8 6.3 Subprogram No. 1C: Lateral & Connector Sewer Improvements...9 6.4 Subprogram No. 1D: Interceptor and Trunk Sewer Improvements...10 6.5 Subprogram No. 1E: Manholes and Catch Basin Improvements...13 6.6 Subprogram No. 1F: Regulators, Outfalls, Backwater Gates, Diversion Dams and In- System Storage...14 6.7 Subprogram No. 1G: Pump Stations...19 6.8 Subprogram No. 1H: Meters...20 7. Program 2: CSO and SSO Control Program...21 7.1 Ongoing CIP Projects...21 7.2 New Projects...21 7.3 CSO Rehabilitation...22 8 Program 3: System Control and Wastewater Treatment Program...22 8.1 Wastewater Treatment Plant Ongoing and Major Rehabilitation...22 Appendix A: Data Tables Used for CIP Appendix A Data Tables Used for CIP...26 Appendix B Data Tables Not Used for CIP...38 B.1 Alternate Data Category Tables...38 B.1.5 Historical References...47 B.1.6 Means and Manufacturers Estimates...48 B.1.7 Mean s Unit Cost Estimates...53 Appendix C: Unit Costs for Treatment Facilities...56 Appendix D: Wastewater Treatment Plant Ongoing Repair and Replacement Cost Estimates...64 Link to Complete Spreadsheets...65 September 2003 i

1 Purpose In the development of a Master Plan for wastewater conveyance and treatment that extends 50 years into the future, it is necessary to utilize a set of common assumptions as to the capital cost of facility construction. The cost assumptions provide the basis for establishing the estimated annual expenditure in the capital improvement plan (CIP) that was developed as a component of the Detroit Wastewater Master Plan (WWMP). The guidelines are intended to provide unit costs for construction and rehabilitation of conveyance and treatment facilities. These unit costs can then be used to establish total costs of planning alternatives for comparative purposes. Unit costs can also be applied to recommended system upgrades, improvements, and rehabilitation projects to develop total project costs for CIP development. While conveyance facilities are common elements of the DWSD system, the treatment facilities being investigated are each somewhat unique in nature and thus not as readily subjected to the application of generalized unit cost factors. For this reason, a different approach to cost development has been employed for treatment facilities. 2 Methodology Development of component costs for a Master Plan covering the range of potential project types anticipated within the DWSD planning area over a 50-year time frame required evaluation of historic costs as well as ground up estimates. These costs can be applied to proposed projects with varying site conditions and complexities throughout the planning area. 2.1 Wastewater Conveyance Facilities To better account for a range of conditions, if possible, the unit costs were derived from a convergence of two sources. The cost estimates for wastewater conveyance facilities are based on an assembly and comparison of historical construction costs from multiple cost estimates and reports compiled from 1971 to present, and construction estimates using the R.S. Means Sitework and Landscaping Data and methodology. Since, in many cases, the two methods produced differing results final, unit costs were established within the range of estimated costs through review by experienced design construction professionals. Section B.1.5 in Appendix B presents the historical cost development. Section B.1.6 in Appendix B presents the Means method cost development. In some cases, one of the two estimating methods was applicable for conveyance facilities. September 2003 1

It was necessary to establish a time reference for historical data reviewed as part of the cost evaluation. The year 2003 was selected as this reference point for the CIP development. The CIP developed for the Wastewater Master Plan (WWMP) used 2003 as the base year. Section 2 contains the base data for the CIP estimates. Cost data tables that were used for the CIP estimates are contained in Appendix A. The 2000 costs from these tables were escalated to 2003 costs using the ENR Construction Cost Index (CCI) shown in Table 1. Both Means estimates and historical costs were calculated to use the year 2003 as a base. Historical sources, which are taken from the year in which they were reported, were adjusted to 2003 unit costs using the ENR Construction Cost Index (CCI). Costs for specific items were then averaged to determine the historical unit cost in year 2003 dollars. It should be noted that some projects with costs that were extremely high or low compared to the others for the same type of facility were excluded from the average. Some assumptions were made for the historical data due to a lack of detail in the original estimates. For example, many of the pipe depths were assumed based on size. For sections where variable depths are shown, the original estimate, which is based upon a shallower depth, is multiplied by a factor to obtain a number for the deeper depths. These factors were obtained from the RS Means estimates and then applied to the historical data. Where historical costs were not available, manufacturers estimates were used. Section B.1.6 in Appendix B shows the estimates based on RS Means costs for the same material and the same assumed conditions as in the cost guidelines section. The RS Means numbers were taken from the 2002 Means data then converted to the year 2000 using the suggested Means factors for year and location (Detroit) adjustment. For example, an item costing $23 in 2002 would be multiplied by the index in 2000 (95.9) then divided by the index for 2002 (100) to obtain $22.06 then adjusted for the location by multiplying by.962, the Means city cost index, to give an adjusted 2000 price of $21.22. These 2000 values were then escalated to 2003 values for the unit costs used in the CIP development. 2.2 Wastewater Treatment Facilities To address the treatment needs within the planning area over the 50-year planning period a series of treatment alternatives were developed by Tetra Tech MPS. These ranged from expansion of treatment capacity at the existing Detroit WWTP; to utilization of existing outlying (satellite) facilities with upgrade and expansion in Pontiac, Warren and/or Mt. Clemens; to construction of dedicated facilities to treat wet weather flow and the dewatered flows from CSO and SSO storage facilities. Each of these alternatives has been documented in technical memoranda specific to the alternative type. September 2003 2

The three technical memoranda describing alternatives Expanded Facilities within the City of Detroit, Technical Feasibility of Satellite Treatment, and Technical Feasibility of a Wet Weather Flow Treatment Facility- contain detailed descriptions of the proposed facilities and include, as appendices, the complete cost estimates for each facility. As part of the alternatives development, conceptual (planning level) cost estimates were developed for the facilities being proposed. These estimates would be based on specific facility locations, preliminary facility layouts and defined treatment process capacities. Because this additional detail is available, more detailed estimates could be prepared than could be expected for conveyance facilities. These estimates used standard construction cost estimating procedures and formats. Designers broke down facilities by each component process and prepared cost estimates at the process level for the specific size and configuration appropriate for each facility. Appendix C contains the treatment facility unit cost tables derived from the alternatives. Any unit costs for conveyance items used in these alternative estimates, such as pipes, were used with other data in calculating the CIP costs. 3 Limitations Every construction project presents unique conditions with respect to location, site constraints, and soil or geotechnical considerations. Also, construction industry market conditions can greatly affect project costing. By considering both historical costs as well as current cost estimating methods, an attempt was made to account for the range of potential costs. However, no estimates can be considered final until complete construction plans and specifications have been prepared. At the Master Planning stage, these unit costs, as well project costs derived from them, need to be evaluated appropriately. Thus, these generalized costs are appropriate for comparison of alternative approaches to providing service, but additional detail should be provided for site-specific construction estimates. 4 Allowances and Contingencies At every stage of construction cost estimating, certain unknown factors need to be accounted for in the development of estimated costs. This is even true at the time final plans and specifications are completed for a specific project. It is especially critical at the planning stage. The unit costs presented throughout this technical memorandum are base construction costs, for the most part. This means that, in most cases, no allowances or contingencies of any type have been applied. Contingencies need to be added to cost estimates prior to inclusion in the CIP. The following cost categories need to be considered in the development of complete cost estimates: Contractor Overhead and Profit; Contingency; and Engineering, Legal, Administrative, and Management. September 2003 3

Contractor Overhead and Profit accounts for the markup that contractors employ to cover costs, such as mobilization, and the profit they would expect to garner from the project. The Contingency markup has two main parts, Planning Level Contingency and Contractor Contingency. The Planning Level Contingency accounts for the uncertainty of the cost estimate due to the basic level of design development appropriate at the planning level. This contingency should decrease significantly as each project proceeds from the Master Plan stage through the Project Plan stage, the Preliminary Design Stage and the Final Design Stage. For a Master Plan looking 50 years into the future, the contingency will be a considerable portion of the total costs. The contractor contingency allows for uncertainty in the final contract cost due to market conditions at the time the project is bid, and for potential changes to the project during the construction stage (change orders). Engineering, Legal, Administrative, and Management markups account for several aspects of the projects. These include providing funds for performing the engineering design calculations, preparing plans and specifications, bidding the construction contract and awarding the work, contractor oversight, shop drawing review and approval, on site inspection services, change order development, development of record drawings, and contract close out. They also account for the costs associated with legal review of construction contracts and, when necessary, the involvement of financial professionals in preparation of bond statements and the sale of bonds. A review of contingencies used in other recent DWSD projects led to the use of the following multipliers. For new construction (replacement) or major rehabilitation, the multipliers applied are: Contractor Overhead and Profit: Contingency: Engineering, Legal, Administrative, and Management: 25% of base construction costs 30% of total construction cost, including contractor overhead and profit 20% of total construction cost, including contractor overhead and profit For all other categories (inspection, cleaning, rehabilitation, etc.), the multipliers applied are: Contractor Overhead and Profit: Contingency: Engineering, Legal, Administrative, and Management: 25% of base construction costs 15% of total construction cost, including contractor overhead and profit 10% of total construction cost, including contractor overhead and profit September 2003 4

Most unit costs presented in this technical memorandum are basic construction costs without contingencies. The above contingencies needed to be added to the base costs as project specific estimates are developed. The estimates that are based on actual costs from past projects already include these contingencies. 5 Cost Index Historical costs have been adjusted using data from the Engineering News Record (ENR) Construction Cost Index History, which provides annual cost indices from 1913 to present. Table 1 shows the annual cost indices from 1969 to 2002. Extrapolation of this data gives the annual indices for the year 2003. The cost estimates developed for the CIP used a 2003 cost. The 2003 costs were obtained by escalating any base data used from their base year to 2003 using the CCI. Using the example for a 1990 estimated cost for 12" sanitary line of $212 per linear foot, convert it to 2003 cost by dividing the unit price by the year s index (212/4732). Then multiply by the year 2003 index (6698) to get the escalated 2003 unit cost of $300. September 2003 5

Table 1 ENR Construction Cost Index (CCI) Year Index Year Index 1969 1269 1986 4295 1970 1381 1987 4406 1971 1581 1988 4519 1972 1753 1989 4615 1973 1895 1990 4732 1974 2020 1991 4835 1975 2212 1992 4985 1976 2401 1993 5210 1977 2576 1994 5408 1978 2776 1995 5471 1979 3003 1996 5620 1980 3237 1997 5825 1981 3535 1998 5920 1982 3825 1999 6060 1983 4066 2000 6221 1984 4146 2001 6342 1985 4195 2002 6538 Detroit Water and Sewerage Department 2003 6698** Index for 2002 was averaged in 12/02 using 11 months of data. ** This number was forecasted September 2003 6

Cost Guideline Summaries The following pages contain cost guidelines for those items included in the CIP and rate model, including pipe installation, special structures and manholes; pump stations, pipe rehabilitation, miscellaneous repair, and pipeline inspection and cleaning. The categories and layout correspond to the CIP cost estimating spreadsheets. For each category, the material and assumed construction conditions are identified. These include type and depth of excavation, utility and pavement restoration anticipated, and number of manholes or other structures included in the estimate. Additionally, a useful life expectancy for the specific type of facility is provided for use in CIP development. 6. Program 1: Sewer Infrastructure Program This section of the CIP development includes the inspection, cleaning, rehabilitation, and replacement of DWSD sewers. 6.1 Subprogram No. 1A: Lateral and Connector Sewers Cleaning, Sediment Disposal & Condition Assessment Lateral and Connector sewers were defined previously in consultation with DWSD. A lateral sewer collects flows from homes and businesses for discharge into trunk sewers. These sewers range in size from 6 to 24 in diameter, with an average size of 18. A connector sewer is a pipe that carries the wastewater flow from a lateral sewer to a trunk sewer. Connector sewers range from 24 in diameter to a 4 by 6 egg shape, with an average size of 30 in diameter. An assessment of DWSD sewers from the technical memorandum Lateral Sewers and Connection Sewers indicates that there are 2,258 miles of laterals and 559 miles of connector sewers in the DWSD sewer system. 6.1.1 Inspection The CIP costs for inspection of lateral and connector sewers were developed with the assumption that this inspection would be accomplished through sewer televising. Sewer televising consists of remote televising of sewers using robotically controlled cameras. The estimate includes mobilization, set up for camera entry, and furnishing of all incidentals. The actual CIP cost estimation was derived from the technical memorandum entitled Physical Inspection of Lateral and Connector Sewers, revised May 2003, which describes a recent pilot project performed by Inland Waters Pollution Control, Inc. for DWSD. Inspections occurred in June, July, and October of 2002. This project inspected several DWSD sewers in the lateral and connector categories using TV inspection methods. The selected sewers for these inspections included varying pipe diameters as well as material types. The average inspection costs from the pilot project are used for the CIP. Table A-1 in Appendix A shows an alternate cost estimation for sewer inspections based on historical data. These unit costs in Table A September 2003 7

do not include contingencies. Note that the pilot project costs are within the ranges set in Table A. 2003 Lateral and Connector Sewer Inspection Costs = $2.11 per linear foot ($11,141 per mile) 6.1.2 Cleaning Sewer Cleaning consists of preparatory cleaning (also called light cleaning) or heavy cleaning utilizing a hydraulic sewer jet/vacuum unit. The estimate includes mobilization, set up for jet/vacuum truck, and furnishing of all incidentals. The CIP costs for the cleaning of lateral and connector sewers were taken from the technical memorandum entitled Physical Inspection of Lateral and Connector Sewers, revised May 2003, which describes a recent pilot project performed by Inland Waters Pollution Control, Inc. for DWSD. Table A-2 in Appendix A shows an alternate cost estimation for sewer cleaning based on historical data. The unit costs do not include contingencies. 2003 Lateral and Connector Sewer Light Cleaning Costs = $3.25 per linear foot ($17,160 per mile) 2003 Lateral and Connector Sewer Heavy Cleaning Costs = $9.00 per linear foot ($47,520 per mile) 6.1.3 Sediment Testing A concern regarding the pipes in the DWSD system is that the buildup of sludge contains toxic materials, such as PCBs or mercury. This sludge should be removed and disposed of in a different manner than the current sewer jet / vacuum unit practices (washing sludgedown the sewers to the WWTP). Sludge removal should therefore include a sampling station to test the sludge components. If sludge tests indicate hazardous materials, the sludge will need to be disposed of in an apporpiate landfill. The cost per truckload comes from CDM and assumes two tests, one for PCB s and one for mercury, would be performed on each load. 2003 Lateral and Connector Sewer Sediment Testing Costs = $200 per truck load (10 truck loads per mile.) 6.2 Subprogram No. 1B: Interceptor and Trunk Sewer Cleaning, Disposal and Condition Assessment Interceptor and trunk sewers are defined previously in the Interceptor and Trunk Sewers technical memorandum. A trunk sewer collects flows from lateral and connector sewers for discharge into interceptor sewers. These sewers are generally larger than laterals, ranging in size from 18 to 10 in diameter. An interceptor sewer is a large sewer that carries the wastewater flow from a number of trunk sewers to the wastewater treatment plant. These sewers do not connect to any homes, buildings, or September 2003 8

catch basins. Interceptor sewers are generally larger than trunk sewers (10 or larger). An assessment of DWSD sewers indicated that there are 483 miles of trunk sewers and 83 miles of interceptors (39 miles serving Macomb County only) in the DWSD sewer system. 6.2.1 Inspection The CIP costs for inspection of interceptor and trunk sewers were developed with the assumption that inspection would be accomplished through sewer televising. Other methods such as diving may be more effective because of the larger sizes of pipes. Sewer televising consists of remote televising of sewers using robotically controlled cameras. The estimate includes mobilization, set up for camera entry, and furnishing of all incidentals. The estimate is unit cost per mile of pipe. The CIP costs for the inspection of interceptor and trunk sewers were taken from Table A-1, which is based on historical data. This unit cost does not include contingencies. 2003 Interceptor and Trunk Sewer Inspection Costs = $4.31 per linear foot ($22,747 per mile) 6.3 Subprogram No. 1C: Lateral & Connector Sewer Improvements Costs for improvements to the lateral and connector sewers in the DWSD system were derived. These improvements can include the rehabilitation of the existing sewers or the construction of new sewers to replace existing sewers to enhance the sewer system where there are deficiencies. This memorandum only considers the rehabilitation of lateral and connector sewers. 6.3.1 Rehabilitation - Lateral and Connector Relining There are a few different methods of rehabilitating sewers that were considered for lateral and connector sewers. These include chemical grouting of joints, sliplining and cured-in-place-pipe (CIPP). CIPP was the preferred method used for the CIP estimates. CIPP Lining CIPP lining is considered to be major rehabilitation. CIPP installation includes the installation of Cured-In-Place Pipe, mobilization, sewer preparation, and furnishing of all incidentals. The service life of CIPP Lining is 50 years. The CIP cost estimation for lateral and connector sewer rehabilitation was derived from the recent pilot project performed by Inland Waters for DWSD. This information is found in the technical memorandum entitled Physical Inspection of Lateral and Connector Sewers. For this project, CIPP was installed for several lengths of laterals and connectors within the DWSD system. These unit costs do not include contingencies. 2003 Lateral Sewer CIPP Rehabilitation Costs = $122.35 per linear foot ($646,000 per mile) 2003 Connector Sewer CIPP Rehabilitation Costs = $220.30 per linear foot ($1,163,184 per mile) September 2003 9

Table A-3 in Appendix A shows an alternate cost estimation for CIPP Lining based on historical data. 6.4 Subprogram No. 1D: Interceptor and Trunk Sewer Improvements Costs for improvements to the interceptor and trunk sewers in the DWSD system were derived. These improvements include the rehabilitation of the existing sewers and the construction of new sewers to replace existing sewers, or to enhance the sewer system where there are deficiencies. 6.4.1 Rehabilitation Structural Repairs The rehabilitation of the larger interceptor and trunk sewers requires methods different than for lateral and connector sewers. In addition to a CIPP relining, specific structural repairs can be accomplished because the sewers are large enough to be entered. As a result of recent inspections of some of the interceptors and trunk sewers in the DWSD system, some structural repairs were identified. These can be found in the CS-1158 report called Long Term CSO Plan for the Detroit and Rouge Rivers, 1996. These inspections covered approximately 886,400 linear feet, or about 30% of the system, with structural repair costs (mostly CIPP lining) estimated at $18,000,000. Table A-3 shows the CIPP lining cost estimation based on historical data. This table, however, only goes up to 48 pipe, while the pipes used in this structural repair calculation range from 24 to 177. The unit cost below is an extrapolation of Table A- 3 and does not include contingencies. 2003 Interceptor and Trunk Sewer Structural Repair Costs = $1,000 per linear foot 6.4.2 Cleaning Sewer Cleaning of the interceptor and trunk sewers consists of heavy cleaning utilizing a hydraulic sewer jet/vacuum unit. The estimate includes mobilization, set up for jet/vacuum truck, and furnishing of all incidentals. The CIP costs for the cleaning of interceptor and trunk sewers were taken from Table A-2, which is based on historical data. This unit cost does not include contingencies. 2003 Interceptor and Trunk Sewer Heavy Cleaning Costs = $16.41 per linear foot 6.4.3 Sludge Removal An analysis of inspection reports on interceptor and trunk sewers by TYJT calculated that sludge removal and disposal for 30% of the system would cost approximately $1,867,043. These can be found in the CS-1158 report called Long Term CSO Plan for the Detroit and Rouge Rivers, 1996. This sludge removal is considered to be heavy cleaning and uses the costs from the historical data in Table A-2. 2003 Interceptor and Trunk Sewer Sludge Removal Costs = $16.41 per linear foot September 2003 10

6.4.4 Sediment Testing Detroit Water and Sewerage Department A concern regarding the pipes in the DWSD system is that the buildup of sludge contains toxic materials, such as PCBs or mercury. This sludge should be removed and disposed of in a different manner than the current sewer jet / vacuum unit practices (washing sludge down the sewers to the WWTP). Sludge removal should therefore include a sampling station to test the sludge components and disposal of hazardous material in a landfill. Sludge amounts were obtained from inspection reports found in the CS-1158 report called Long Term CSO Plan for the Detroit and Rouge Rivers, 1996. The cost per truckload comes from CDM and assumes two tests, one each for PCBs and mercury, would be performed on each load. 2003 Interceptor and Trunk Sewer Sediment Testing Costs $200 per truck load (10 cu. yds.) 6.4.5 New Relief Sewers DWSD previously identified areas of the system where relief sewers were needed. These areas were defined in Status Report on Storm Relief Sewer Program, by DWSD, issued July 1975, reissued July 1978. The Wastewater Master Plan (WWMP) team has reviewed these relief sewers (Local Alternatives for SSO Control technical memorandum) and concluded that the following may be needed; pending further system inspections and cleaning: 7 Mile Road Relief o 7,920 ft. of 120 at depth of 30 o 13,200 ft. of 120 at depth of 25 Fenkell Relief o 7,920 ft. of 156 at depth of 25 o 13,200 ft. of 192 at depth of 10 Schoolcraft Relief o 10,560 ft. of 192 at depth of 15 Hubbell Relief o 10,660 ft. of 144 at depth of 10 o 7,920 ft. of 144 at depth of 20 Joy / Clark Relief o 6,833 ft. of 192 at depth of 25 o 27,216 ft. of 192 at depth of 15 o 169 ft. of 120 at depth of 10 The cost of construction of relief sewers was estimated in 1978 and again in 1996 for the CS-1158 Long Term CSO Control Plan for the Detroit and Rouge Rivers, Volume 3, 10.04 C1 Alternative Evaluations (Table C.4 in Alternative 6). Table A-4 shows the 1996 estimates as well as the 2003 costs, derived by escalation using the CCI. The costs from this table used for the new relief sewer cost are shown here. 120 at depth of 10 Costs = $1,289 per linear foot 120 at depth of 25 Costs = $1,557 per linear foot September 2003 11

120 at depth of 30 Costs = $1,712 per linear foot 144 at depth of 10 Costs = $1,389 per linear foot 144 at depth of 20 Costs = $1,579 per linear foot 156 at depth of 25 Costs = $1,938 per linear foot 192 at depth of 10 to 15 Costs = $2,399 per linear foot 192 at depth of 25 Costs = $2,771 per linear foot 6.4.6 Future Modeling The CIP cost estimation has included future modeling of the DWSD sewer system. This modeling of data from the Segmented Facilities plan is scheduled to take place from 2008 to 2010. The estimate, from CDM, includes contingencies. 2003 Future Modeling Costs = $100,000 6.4.7 Oakwood Interceptor A cost estimate was prepared for the installation of a new redundant sewer system parallel to the Oakwood Interceptor section of the NW Interceptor. This estimate was performed by Tetra Tech MPS and can be found in the CS-1314 technical memorandum entitled Conceptual Plan for Oakwood Northwest Interceptor, revised May 2003. The estimate does not include contingencies. 2003 Oakwood Redundant Interceptor Costs = $8,700,000 6.4.8 Macomb Meter Stop Gates A project is proposed to install stop gates at meters CV-3 and MB-25 in Macomb County. The estimate, from SDA and found in the technical memorandum entitled Capital Improvement Programs for Macomb County, does not include contingencies. 2003 Stop Gate Installation Costs = $1,700,000 each 6.4.9 North Gratiot Interceptor This project will install the new North Gratiot Interceptor Sewer (NGIS) in Macomb County. The estimate, from SDA and found in the technical memorandum entitled Capital Improvement Program for Macomb County, includes contingencies. 2003 NGIS Installation Costs = $40,000,000 6.4.10 Northwest Interceptor Improvements This project includes improvements to the Northwest Interceptor Sewer (NWIS) from 8 Mile Road to the WWTP. This estimate was performed by Tetra Tech MPS and can September 2003 12

be found in the technical memorandum entitled Conceptual Plan for Oakwood Northwest Interceptor. The estimate does not include contingencies. 2003 10 Diameter Lining Costs = $1,000 per linear foot 2003 10 Diameter Replacement Sewer Costs = $2,500 per linear foot 6.5 Subprogram No. 1E: Manholes and Catch Basin Improvements Inspection and repair of sewer structures in the DWSD system are required to ensure the system operates efficiently. Therefore, the CIP estimated costs for the inspection and repair of manholes and catch basins. 6.5.1 Manhole Inspections Manhole inspection consists of either topside inspection or full inspection. Table A-5 in Appendix A shows the estimate in unit cost per manhole inspection based on historical data. The CIP estimate for manhole inspections assumes 5% of the manholes in the system will undergo topside inspection every year. This unit cost does not include contingencies. 2003 Manhole Inspection Costs = $52 per structure 6.5.2 Manhole Repairs Manhole repairs can consist of: Manhole wrapping External chemical grout Manhole shelf repair Manhole channel repair Pipe connection repair Raising / replacing manhole frames Each repair is separate. The CIP estimate assumes that the quantity of manholes needing the above categories of repairs varies, with the amounts per inspection cycle as follows: 5% need manhole wrapping 8% need external chemical grout 10% need manhole shelf repair 10% need manhole channel repair 10% need pipe connection repair 15% need raising / replacing manhole frames 2003 Manhole Wrapping Costs = $215 per structure 2003 External Chemical Grouting Costs = $1,938 per structure September 2003 13

2003 Manhole Shelf Repair Costs = $646 per structure 2003 Manhole Channel Repair Costs = $646 per structure 2003 Pipe Connection Repair Costs = $538 per structure 2003 Manhole Frame Replacement / Repair Costs = $646 per structure 6.5.3 Manhole Replacement Manhole installation (replacement) includes: Pre-cast reinforced concrete manholes risers and cones, cast-in-place bases, frames, castings, steps Excavation and backfill of common earth Sheeting, shoring, bracing and dewatering Up to 6 of bituminous pavement removal and replacement And furnishing of all incidentals. Table A-6 in Appendix A shows the estimate in unit cost per vertical linear foot of installation based on historical information. This estimate for manhole replacement assumes that manholes are 4' in diameter and 15' deep and that 2% would need to be replaced for each inspection cycle (20 years). This unit cost does not include contingencies. 2003 Manhole Replacement Costs = $6,053 per manhole 6.5.4 Catch Basin Cleaning The CIP cost estimations assume that all 200,000 catch basins will be cleaned every cycle. Table A-7 in Appendix A shows the cost per catch basin. Catch basin cleaning includes labor, trucks, and disposal. This unit cost does not include contingencies. 2003 Catch Basin Cleaning Costs = $59 per catch basin 6.5.5 Catch Basin Repair The CIP cost estimation for catch basin repair assumes that the repairs will be pipe connection repair and frame replacement as shown in Section 6.5.2 for manholes. These unit costs do not include contingencies. 2003 Catch Basin Pipe Connection Repair Costs = $538 per catch basin 2003 Catch Basin Frame Replacement Costs = $646 per catch basin 6.6 Subprogram No. 1F: Regulators, Outfalls, Backwater Gates, Diversion Dams and In-System Storage 6.6.1 Outfall Flow Regulators Inspection Outfall regulator inspection includes inspection and report writing. September 2003 14

The cost estimate assumes that a five-person crew can dive and inspect two outfall regulators each day. The cost per day for a five-person crew is $6,000/day, as shown in an invoice for the installation of backwater gate sensors for the Baby Creek outfall. It should be noted that some outfall regulators might cost more to inspect than others, depending on regulator accessibility and condition. This unit cost does not include contingencies. 2003 Outfall Regulator Inspection Costs = $3,000 per average outfall regulator 6.6.2 Outfall Flow Regulators Rehabilitation Outfall regulator rehabilitation includes cleaning and inspection of the regulator, float, and sump chamber; removal of existing regulator gates and associated components; removal of flap gates and sluice gates, rehabilitation of regulator, float; replacement of access manhole frames and covers; installation of new slide gates and flexible flap gates and temporary diversion of sewage flow. Regulator rehabilitation was performed under Contract PC-695 Regulator / Remote Flow Control Structures and Dam Rehabilitation. This project rehabilitated 40 gates for a total cost of $7,708,000. The average cost of $192,700 per gate is rounded to $200,000 per gate. This contract ended in 2000, so the cost is escalated to $218,000 using a CCI escalation factor of 1.077. It should be noted that some outfall regulators might cost more to rehabilitate than others, depending on regulator accessibility and condition. This cost estimate includes any contingencies. 2003 Outfall Regulator Rehabilitation Costs = $218,000 per average outfall regulator 6.6.3 Outfall Flow Regulators Replacement Outfall regulator replacement includes the mechanical work described in the outfall regulator rehabilitation work described above and, additionally, replacement of the concrete regulator chamber. As noted above, the cost for the mechanical equipment replacement is $218,000 per outfall regulator. It is assumed that the regulator junction chamber replacement costs would be similar to the influent junction chamber construction costs for the St. Aubin Screening and Disinfection Facility, Contract PC-731. The contractor has provided a detailed cost estimate, which indicates that the construction cost for this junction chamber would be $105,000. An additional $10,000 is added for destruction and removal of the existing regulator chamber. In summary, the regulator replacement costs are: Installation of mechanical components = $218,000 Construction of new regulator chamber = $105,000 Destruction/removal of existing regulator chamber = $10,000 Total = $333,000 September 2003 15

Although the mechanical components portion includes some contingencies, the unit cost here does not include contingencies. 2003 Outfall Regulator Replacement Costs = $333,000 per average outfall regulator 6.6.4 Outfall, Backwater Gate, and Diversion Dam Inspection Outfall inspection includes inspection and report writing. Backwater gates and diversion dams are inspected at the same time as outfalls and do not require any additional costs. The cost estimate assumes that a five-person crew can dive and inspect two outfalls each day. The cost per day for a five-person crew is $6,000/day as shown in an invoice for the installation of backwater gate sensors for the Baby Creek outfall. It should be noted that some outfalls might cost more to inspect than others, depending on outfall size, depth, number of conduits, and condition. This unit cost does not include contingencies. 2003 Outfall Inspection Costs = $3,000 per average outfall 6.6.5 Outfall Rehabilitation Outfall rehabilitation includes repair work at each outfall, as needed. The cost estimate is based on outfall rehabilitation costs budgeted for the DWSD contract DWS 849/850, Inspection and In-place Rehabilitation of Outfalls. The cost for this project is $15,540,000 for rehabilitation of twelve outfalls. This results in an average cost of $1,295,000 per outfall. The cost shown is an average amount for all outfalls. Outfall rehabilitation costs can vary widely, because the work involved could range from nothing to significant structural repairs. This unit cost does include contingencies. 2003 Outfall Rehabilitation Costs = $1,295,000 per average outfall 6.6.6 Outfall Replacement Outfall replacement includes removal of the existing outfall and installation of a new outfall from the junction chamber to the river. Outfall replacement costs are estimated based on the equivalent installation of a sewer line for the average size, length, and depth outfall. The average outfall calculations assume that outfalls with multiple barrels can be represented by a longer length of single barrel outfall. For example, a double barrel outfall with a length of 15 ft. can be considered a single barrel outfall with length 30 ft. Similarly, outfalls with box, egg, or arch shapes are converted to cylinders with equivalent diameters. For example, a 10 ft. x 10 ft. box sewer is considered equivalent to an 11.3 ft. diameter cylinder. These considerations are used to calculate the average length and diameter for all outfalls. The average outfall is 8.5 ft. in diameter and 1,280 ft. in length. Outfall depth is not readily available and is assumed to be 10 ft. September 2003 16

The replacement cost for the average size and length outfall can then be calculated based on the cost of installation of a new sewer with these dimensions. The costs for sewer installation as a function of size and depth are displayed in Table A-4. This table indicates that the replacement cost for an 8.5 ft. diameter, 1,280 ft. long, and 10 ft. deep outfall would be about $12,600,000. It should be noted that outfall replacement costs would vary significantly because of differences in size, number of conduits, and depth below the surface. This unit cost does not include contingencies. 2003 Outfall Replacement Costs = $12,619,680 per average outfall 6.6.7 Backwater Gate Rehabilitation Backwater gate rehabilitation includes cleaning, leak repair, repair/replacement of rotted or deteriorated timber, and repair/replacement of hardware. The estimated total cost for repair of twelve backwater gates under Contract CS-1158 Long Term CSO Control Plan for the Detroit and Rouge Rivers (1996) is $182,000. This results in an average cost of $15,200 per gate. This cost is then multiplied by a CCI escalation factor, resulting in an average 2003 cost of $18,100 per gate. This cost is then rounded to $20,000 for the estimate. Actual backwater gate rehabilitation costs will vary considerably depending on the condition and accessibility of the gate. This unit cost does include contingencies. 2003 Backwater Gate Rehabilitation Costs = $20,000 per average backwater gate 6.6.8 Backwater Gate Replacement Backwater gate replacement includes replacement of the backwater gates and associated stop logs. The cost for installation of two backwater gates and associated stop logs at the St. Aubin Screening and Disinfection Facility is $336,000, according to the detailed cost breakdown for Contract PC-731 St. Aubin Screening and Disinfection Facility. It is assumed that removal of the existing gates and other site work would cost approximately $14,000. This results in a total cost of $350,000 for the installation of two gates at one location. There are 154 gates at 54 locations, or an average of 2.81 gates per location. It is assumed that the cost of gate replacement is proportional to the total number of gates. Hence, the cost for replacing all of the gates would be: $350,000/ 2 gates * 154 gates/ all locations = $26,460,000 $26,460,000/ 54 locations = $490,000 per location This cost was then multiplied by a CCI escalation factor to obtain a 2003 average cost of $517,000 per location. It should be noted that the cost at each location would vary based on the number and size of backwater gates and stop logs. This unit cost does not include contingencies. 2003 Backwater Gate Replacement Costs = $517,000 per average backwater gate September 2003 17

6.6.9 Diversion Dam Rehabilitation Detroit Water and Sewerage Department Diversion dam rehabilitation includes cleaning and repair of deteriorated dam surfaces, restoration of connection between dam surface and bottom of flashboards, and repair/replacement of associated stop logs. The needed repairs are identified in the CS-1314 Review of Collection System Regulators and Outfalls technical memorandum, revised May 2003. The cost for diversion dam rehabilitation is based on simple cost estimates for a three man crew working two days. The average cost for diversion dam rehabilitation based on three locations is $1,000 per dam. It should be noted that diversion dam rehabilitation costs will vary based on the size, type, and condition of the diversion dam. This unit cost does not include contingencies. 2003 Diversion Dam Rehabilitation Costs = $1,000 per average diversion dam 6.6.10 Diversion Dam Replacement Diversion dam replacement includes the installation of a new inflatable dam at the existing location. This cost also includes the cost of removing the existing diversion dam. The cost for diversion dam replacement is based on the detailed cost breakdown for Contract PC-731 St. Aubin Screening and Disinfection Facility. The installation cost for an inflatable diversion dam, according to this contract, is $70,000. This cost is multiplied by a CCI escalation factor to get a 2003 installation cost of $74,000. It is assumed that there is an additional cost of $10,000 for destruction and removal of the existing diversion dam and other site work. The total cost for diversion dam replacement is $84,000 per dam. The cost of each diversion dam will vary based on dam size and accessibility. This unit cost does not include contingencies. 2003 Diversion Dam Replacement Costs = $84,000 per average diversion dam 6.6.11 In-System Storage Devices & System Gate Inspection In-system storage device (ISSD) inspection includes inspection and report writing. The cost estimate assumes that a three-person crew can inspect one ISSD each day. The cost for one three-person crew should be about $3,000. This unit cost does not include contingencies. 2003 ISSD Inspection Costs = $3,000 per ISSD 6.6.12 In-System Storage Devices & System Gate Rehabilitation ISSD rehabilitation includes removal of existing regulator gates and associated components; removal of existing operating systems for the regulator gates; installation of new slide gates with self-enclosed hydraulic operating systems; installation of instrumentation and control systems for remote operation of the slide gates from the SCC. September 2003 18

This type of work was performed under Contract PC-695 Regulator / Remote Flow Control Structures and Dam Rehabilitation. This project rehabilitated 40 gates for a total cost of $7,708,000. The average cost of $192,700 per gate was rounded to $200,000 per gate. This contract ended in 2000, so the cost was then escalated to $218,000 using a construction cost escalation factor. It should be noted that some ISSDs cost more to rehabilitate than others, depending on ISSD type, accessibility, and condition. This unit cost does include contingencies. 2003 ISSD Rehabilitation Costs = $218,000 per ISSD 6.6.13 In-System Storage Devices & System Gate Replacement ISSD replacement includes removal of all existing ISSD mechanical, electrical, and instrumentation components and replacement with new components. ISSD replacement costs are based on Contract PC-747 In-System Storage. Under this contract, thirteen new ISSDs were installed for a total cost of $26,400,000. This would result in an average cost of $2,030,000 per ISSD. It is assumed that this installation cost is comparable to the average ISSD replacement cost. It should be noted that ISSD replacement costs would vary depending on the size, type, and accessibility of the device. This unit cost does include contingencies. 2003 ISSD Replacement Costs = $2,030,000 per ISSD 6.7 Subprogram No. 1G: Pump Stations 6.7.1 Inspections Pump station inspection includes inspection of the structural condition of the station and wet well (if equipped), pump testing, and inspection of the instrumentation and control devices. The pump station inspection costs are estimated to run about $1,000 per pump for testing, based on a cost breakdown from Contract PC-744 Wastewater Treatment Plant Rehabilitation and Program Management. It was assumed that it would take an engineer about 2.5 weeks to inspect the pump station and write a report. At $100 per hour, this would cost $10,000 per pump station. This unit cost does not include contingencies. In summary, pump station inspection costs include: Pump testing = $1,000 per pump Pump station inspection and report writing = $10,000 per pump station 2003 Pump Station Inspection Costs = $10,000 per pump station + $1,000 per pump 6.7.2 Rehabilitation Pump station rehabilitation includes pump and motor testing; station cleaning, painting, and repair; repair/replacement of damaged pump, motor, control panel parts; and minor pump station structural repairs. September 2003 19

The pump station rehabilitation costs can be estimated based on the total pump station rehabilitation costs, estimated for Contract PC-744 Wastewater Treatment Plant Rehabilitation and Program Management. In the PC-744 report, the total cost for immediate, short-term, and long term rehabilitation; routine and long lead time spare parts: CMMS system; and motor repair/replacement was $7,737,500. It is assumed that this cost is representative of pump rehabilitation needs for each fiveyear interval. This cost does not include contingencies. 2003 Pump Station Rehabilitation Costs = $7,737,500 for rehabilitation of all pump stations 6.7.3 Major Rehabilitation Major rehabilitation of pump stations includes the capital cost of renovating a wastewater pump station, including all pumps and related equipment. The cost for pump station major rehabilitation was estimated by CDM and for the Tetra Tech MPS alternatives development (technical memoranda Expanded Facilities within the City of Detroit, Technical Feasibility of Satellite Treatment, and Technical Feasibility of a Wet Weather Flow Treatment Facility) and is found in Table A-9a. Pump station major rehabilitation will vary considerably depending on pump station and wet well condition, number and capacity of pumps, and instrumentation and control requirements. Table A-9b shows the breakdown of these costs into low or high flow categories. The average flow of DWSD pump stations is more than 500 MGD, so the high flow cost is used for the CIP. This unit cost does not include contingencies. 2003 Pump Station Major Rehabilitation Costs (500 + MGD)= $20,000,000 for the average pump station 6.7.4 Energy Management The CIP estimates reflect the need for better energy management in terms of pumps at the pump stations. This is expected to be accomplished through the installation of variable-frequency drives (VFD) on these pumps. The CIP includes VFD installation at the Clintondale and Woodmere Pump Stations. The estimate, based on the technical memorandum entitled Energy Management, was made by TYJT and did not include contingencies. The following estimate has had contingencies added. 2003 Energy Management Costs (VFD installation at Clintondale and Woodmere) = $682,500 6.8 Subprogram No. 1H: Meters 6.8.1 Inspection and Maintenance Flow meter maintenance includes maintenance, repair and some replacement (mostly mechanical, but some structural) of current meters; billing and database management; and dye testing/flow accuracy. The costs shown are based on the maintenance budget for CS-1249 Greater Detroit Regional Sewer System Model Billing Meter September 2003 20

Program. This project maintains 50 meters with an annual budget of $2,000,000. This unit cost does include contingencies. 2003 Meter Maintenance Costs = $40,000/average meter 6.8.2 Replacement Flow meter replacement includes meter equipment and installation costs, as well as meter vault replacement. The CIP cost is based on a CDM estimate from the CS-1249 Greater Detroit Regional Sewer System Model Billing Meter Program and is representative of the average meter. Meter replacement costs may vary considerably depending on the type and location of the meter. This unit cost does not include contingencies. 2003 Meter Replacement Costs = $500,000/average meter 6.8.3 Macomb Odor Control Some additional specific projects were included in the CIP estimation. These involve odor control measures at 12 Macomb County meter chambers through the installation of carbon adsorption units. The estimates are based on the CS-1292 Task Order Nos. 33 and 34 Final Draft Report that did not include contingencies. The following estimate has had contingencies added. 2003 Macomb County Odor Control Costs = $772,500 7. Program 2: CSO and SSO Control Program 7.1 Ongoing CIP Projects The WWMP CIP estimation has identified several projects included in the current CIP that have carry-over costs. These rollover CIP costs are as shown in Table A-8 and include any contingencies. 2003 Ongoing CIPRollover Costs = $617,759,000 7.2 New Projects The WWMP CIP estimation has identified some new CSO projects. These CIP costs are as shown below and include any contingencies. The Detroit River CSO is based on an estimate of $25,000,000 per outfall, assuming the construction of a screening and disinfection facility. Table 2: New CSO Project Costs Project CIP Cost Lower Rouge River Outfalls $25,000,000 Detroit River CSO's Upper Range $750,000,000 Detroit River CSO's Lower Range* $375,000,000 * Based on half as many outfalls constrd September 2003 21

7.3 CSO Rehabilitation Detroit Water and Sewerage Department The WWMP also considered the rehabilitation of the CSO s in the DWSD system. The upper range estimate assumes that the rehabilitation costs would be approximately 1% of the CSO construction costs. The table below shows the construction and CIP rehabilitation costs, without contingencies. It is assumed that each facility will be rehabilitated annually from 2008 to 2050. The lower range estimate assumes a yearly rehabilitation cost. Table 3: Upper Range CSO Rehabilitation Costs Facility Construction Cost Rehabilitation Cost (each) Conner Creek CSO $199,049,172 $1,990,492 Fox Creek CSO $11,582,891 $ 115,829 Leib CSO $31,327,898 $ 313,279 St. Aubin CSO $21,540,250 $ 215,403 Upper Rouge CSO $418,000,000 $4,180,000 Baby Creek CSO $50,389,000 $ 503,890 7 Mile CSO $17,638,861 $ 176,389 Fenkell CSO $22,281,777 $ 222,818 Hubbell Southfield CSO $67,975,783 $ 679,758 Belle Isle CSO $14,960,000 $ 149,600 2003 Lower Range CSO Rehab Costs = $6,000,000 per year 8 Program 3: System Control and Wastewater Treatment Program 8.1 Wastewater Treatment Plant Ongoing and Major Rehabilitation The DWSD Wastewater Treatment Plant (WWTP) is the largest facility in the DWSD sewer system. An overall assessment of funding needed for the Wastewater Treatment Plant Program was first estimated for planning purposes by summarizing the current yearly funding for wastewater treatment plant programs. This data is summarized in Table 6.1, and additional information is presented in Table A.11 in Appendix A. Table 4 shows that current proposed expenditures have increased from about $99 million from the 1997-2002 CIP to $175 million in the 2002-07 CIP. However, this amount includes many projects that are not directly related to the Wastewater Treatment Plant, such as work at system pump stations. Deleting these projects, the total is closer to $134 million per year. September 2003 22