LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD
|
|
|
- Virginia Bell
- 10 years ago
- Views:
Transcription
1 LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD Bob Fisher and Lance Stracner Ameron Protective Lining J.R. Pipeline Co Inc. Abstract: The City of Los Angeles sewer tunnel infrastructure is in need of major repairs. The NOS was constructed in the early 1900 s. At that time, the newest materials to combat sewer gases and corrosion was a ceramic tile lining. However, the sewer gases were still able to penetrate and degrade the grout in between the tiles causing them to fail. The tile and sections of the concrete of the tunnel are now failing and collapsing to the tunnel floor. The method that was selected for the project had to structurally rehabilitate the tunnel and protect the new concrete from future corrosion. The City of Los Angeles awarded two contracts to complete the sewer tunnel rehabilitation. Phase I rehabilitated 30,512 LF of the Lower North Outfall Sewer (LNOS) and Phase II rehabilitated 16,876 LF of the North Outfall Sewer (NOS). Colich/J.R. Pipeline Joint Venture (JV) was the low bidder on each project and selected Amerons T Hab method for rehabilitating the sewer tunnel. The concrete used in the process was a 4000psi self consolidating concrete designed by J.R. Pipeline, Cemex, and Grace Materials. Introduction: The City of Los Angeles North Outfall Sewer (NOS) and the Lower North Outfall Sewer (LNOS) were constructed in the 1900 s. The NOS begins as a 48 concrete pipe and increases in size up to a 10 6 tunnel as it passes through the downtown area. The NOS was the first large diameter sewer tunnel completed in the City of Los Angeles. It collects the wastewater from all the downtown sewer systems, transporting it to the Hyperion Sewer Treatment Plant. Rehabilitating the LNOS Phase I was the first phase of the City s master plan to rehabilitate the large sections of the NOS wastewater system. The sewer was originally constructed with ceramic tiles to protect the concrete from sewer gases. However, the mortar used to install the tiles corroded and failed causing the tiles to fall off of the tunnel exposing the concrete beneath. This concrete over the next 70 years eroded to a point of failure. In 1992 the City of Los Angeles constructed the North Outfall Relief Sewer (NORS) to divert the wastewater from the NOS. This allowed Figure 1 Original NOS Construction in 1920's 1
2 time for the City of Los Angeles Engineers to design an appropriate rehabilitation method with the lasted in rehabilitation technologies. Design Requirement: In designing the rehabilitation for the LNOS Phase I the City of Los Angeles designers disregarded the integrity of the existing concrete due to its level of unknown corrosion. The rehabilitation involved casting a new PVC liner inside the existing sewer tunnel. The City had approved three PVC liners for the rehabilitation, Ameron T Lock, Agru CIP Liner, and Anjac Doran Conplast. The Concrete specified was 4000psi, self consolidating, and shrinkage reduced. The new cast in place concrete section had a minimum thickness of 9 at the invert and 12 at the soffit. The NOS Phase II rehabilitation design accepted the structural integrity of the existing sewer tunnel. This allowed the City to reduce the new cast in place concrete section. The City required hydro demolition to remove all the corrosion and expose sound grey concrete to prepare the existing surface of the tunnel. Local sewer flows had to be bypassed and a new 72 sewer diversion constructed. Two brick siphon structures were rehabilitated, three 78 concrete siphon barrels were rehabilitated, 13 maintenance holes were rehabilitated, and 5 new maintenance hole were constructed. Figure 2 Cross Section of New CIP Liner 2
3 Project Construction Phase The first phase was the LNOS Phase I Rehabilitation which began in July of 2004 and finished in April of The LNOS was 30,512 lineal feet of 10 6 clay tile lined tunnel. The rehabilitation consisted of 12 inches of new self consolidating concrete and Amerons T Hab PVC liner. The rehabilitation required cleaning of the exiting sewer tunnel, surface preparation, and sewer bypassing. The second phase was the NOS Phase II Rehabilitation. This phase began in March of 2007 and will finish in February The NOS Phase II was 10,929 Lineal feet of 10 6 semi elliptical clay tile lined tunnel and 5,945 lineal feet of 7 9 semi elliptical clay tile lined tunnel. The rehabilitation consisted of 6 to 9 inches of new self consolidating concrete and Amerons T Hab PVC liner. Debris Removal Access pits were constructed at City designated locations. These were spaced approximately 10,000 lineal feet apart. The initial cleaning removed all the debris that had built up within the sewer tunnel. The debris ranged in depth from 6 to 24 in some areas. The LNOS Phase I had 4 steel ribs installed on a previous contract to shore up the collapsing sewer tunnel. The ribs were very corroded and degraded. The debris consisted of clay tile, degraded concrete, steel ribs, and sewer sludge. The debris was collected within the tunnel with a skidsteer loader and transported to the access point where it was removed and placed into covered 20yd roll off containers. The containers were staged and allowed to dewater prior to disposal. All of the debris was recycled at a local material recycle facility. Figure 3 Existing steel ribs in LNOS 3
4 Sewer Bypass and Diversions The City of Los Angeles had constructed the North Outfall Relief Sewer (NORS) in 1992 to remove the LNOS Phase I and the NOS Phase II from service. To facilitate the installation of the Ameron T Hab system the local sewer flows had to be contained into a bypass line or diverted to adjacent sewer systems. The LNOS Phase I bypass required two 8 submersible pumps and a 12 internal bypass pipeline to control the main sewer flows. The main flows were diverted up to one mile internally along the tunnel invert to a diversion structure and discharged into an adjacent wastewater system. The local 8 flows were collected and bypass internally along a gravity 6 and 8 bypass pipeline. One 18 force main was re piped to an alternate wastewater system at the upstream project limits. The NOS Phase II project required a large sewer diversion to allow rehabilitation of the uppermost reaches of the sewer tunnel. The sewer diversion consisted of micro tunneling 204 lineal feet of 72 Hobas Pipe USA and the construction of one sewer junction structure over the 11 diameter East Coastal Interceptor Sewer (ECIS) and one sewer diversion structure over the La Cienega San Fernando Valley Relief Sewer (LCSFVRS). The diversion removed approximately 17 MGD from the NOS system. The structures were both 50 deep excavations solid shored with steel beam and plates. The new structures were cast in place concrete with Ameron s T Lock Lining for protection. Nada Pacific performed the 72 micro tunnel. The local sewer flows were collected and bypass internally along gravity 8 bypass line. Surface Preparation Figure 4 Before and After Surface Preparation Once the sewer diversions were operational and the tunnel was cleaned of all debris, the surface of the tunnel had to be prepared to receive the new concrete liner. The LNOS Phase I specified pressure washing with 3000psi water. The JV modified standard diesel powered pressure washing equipment to be used inside the tunnel. Pressure washing removed all the loose and deleterious materials from the surface of the tunnel walls. However, it does not remove the corrosion on the immediate surface of the concrete. This was verified by a low PH test reading on the interior tunnel surface. The NOS Phase II contract required hydro demolition to the existing concrete surface. (Figure4) Because of the thinner concrete section, the design engineer wanted clean sound concrete exposed with a PH of 7 or greater for accurate bonding with the new concrete. This was achieved by hydro blasting the surface with 18,000psi water. The work was subcontracted to National Infrastructure Hydro Demolition from Vancouver Canada. 4
5 Installation of Ameron T Lock PVC Liner The JV in conjunction with Everest Equipment designed and built steel tunnel forms for both projects. The forms included a starter wall section, arch section, and a form carrier. The carrier strips, relocates, and sets up the arch form sections. The starter wall was stripped and relocated by hand. The process begins with the installation of a 14 starter wall section lined with Ameron PVC. (Figure 5) The starter wall allows for vertical room to setup and strip the Figure 5 Starter Wall Forms arch section of formwork. The starter wall was cast 100 lineal feet ahead of the arch section to allow curing time. The connection between the starter wall and the invert of the tunnel was accomplished with #5 316LN stainless steel rebar at 18 O.C. doweled in 5 and affixed with Sika Dur Hi Mod Epoxy. The thickness of the starter wall section varied between 6 to 9 dependent upon the level of corrosion and the accuracy of the original construction in maintaining the designed internal measurements. The arch section of formwork is set up after the starter wall section has 24 hours of cure time. The form carrier mobilizes the arch sections into place. (Figure 6) The Ameron T Lock PVC is applied and secured onto the formwork. The crews then adjust the formwork to finalize the set up and meet the contract dimensions. (Figure 2) Once the forms are in place the carrier is moved out of the way to allow the concrete slick line and grout port connections to be assembled.(figure 7) The form is then filled with 4000psi self consolidating concrete. The concrete mix was designed with the help from Cemex and Grace Materials. The concrete mix includes four additives to meet the specification requirements and allow for the pumping of long distances as well as maintaining its consolidation within the form sections. The quality control for the concrete was measured by weight and a J Ring spread of 21 to 23. (Figure 8) Due to the limited access points the City granted the request to allow the existing and new manhole to be used for concrete pumping operations. The manholes were spaced approximately 1,000 to 2,000 lineal feet apart. Therefore our typical pumping distance was between 500 and 1,000 lineal feet to the formwork. In one case due to the terrain the manholes were 4,000 lineal feet apart. This required a pumping distance of 2,000 lineal feet to the formwork. The concrete then had to flow 100 lineal feet within the formwork. The self consolidating concrete performed as expected with good consolidation and Figure 6 Form Carrier with Arch Forms 5
6 strength. After an eighteen hour cure the forms are stripped and relocated to the next section. The Ameron T Lock installation is completed by welding all the seams with 1 PVC weld strip. (Figure 9) The Ameron T lock PVC is test by the City for any defects using a 10,000 volt holiday detector. The final result is a newly restored sewer ready for service. (Figure 10) The LNOS Phase I was complete on time and NOS Phase II was completed 10 months ahead of schedule. Figure 7 Formwork with Grout Lines Figure 8 J Ring Test 4,000psi SCC with 22" Spread Figure 9 PVC Welding of all Seams 6
7 Figure 5 Complete Rehabilitation with Ameron T Hab The City of Los Angeles considered these projects a great success due to the limited impact on the local residents and neighboring cities. The restoration of the LNOS Phase I and NOS Phase II expanded the City s wastewater capacity to a level that they have never seen. The service life of the newly rehabilitated sewers is estimated to be over 100 years. Description LNOS Phase I NOS Phase II Total Tunnel Lineal Footage 30,512 LF 16,876 LF 47,388 LF Debris Remove 7,000 Tons 5000 Tons 12,000 Tons Concrete Placed 35,000 yds 13,500 yds 48,500 yds Ameron T Lock Installed 854,336 sqft 421,768 sqft 1,276,104 sqft Table 1 The totals of critical points within the projects. 7
CONSTRUCTION OF NON-CIRCULAR SEWER REHABILITATION PROJECTS IN LOS ANGELES
North American Society for Trenchless Technology (NASTT) No-Dig Show 2010 Chicago, Illinois May 2-7, 2010 Paper C-4-04 CONSTRUCTION OF NON-CIRCULAR SEWER REHABILITATION PROJECTS IN LOS ANGELES Brad Jenson
SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS
SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and
NON-CIRCULAR SEWER LINER INSTALLATION AND FUTURE PROJECTS IN LOS ANGELES
North American Society for Trenchless Technology 2008 No-Dig Conference & Exhibition Dallas, Texas April 27 May 2, 2008 NON-CIRCULAR SEWER LINER INSTALLATION AND FUTURE PROJECTS IN LOS ANGELES Brad Jenson
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer
Storm Sewer Trenchless Upgrade Alternatives and Recommendations
Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for
San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS
ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by
Rehabilitation or Replacement? That Is The Question
Rehabilitation or Replacement? That Is The Question Chris L. Windley PE Greg Anderson, PE 94th Annual Conference November 18, 2014 Overview Project Background Existing Sewer Condition Flow Projections
Sewer Rehabilitation Design Requirements
Sanitary Sewer Overflow (SSO) Control and Wastewater Facilities Program Sewer Rehabilitation Design Requirements City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared
CHALLENGES IN LINING A 100 YR OLD BRICK SEWER
North American Society for Trenchless Technology 2007 No-Dig Conference & Exhibition San Diego, California April 15-20, 2007 CHALLENGES IN LINING A 100 YR OLD BRICK SEWER Brad Jenson 1, Keith Hanks 2,
Wastewater Capital Projects Management Standard Construction Specification
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,
FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
SECTION XXXXXX TECHNICAL SPECIFICATIONS FOR INSTALLATION OF PROTECTIVE COATINGS FOR MANHOLES, WETWELLS, AND OTHER SANITARY SEWER STRUCTURES
1.00 PART 1 GENERAL 1.01 SCOPE A. It is the intent of this contract to install a 100% solids epoxy monolithic coating to the walls, benches and inverts of all manholes and the specified surfaces of other
Coast Trunk Sewer Rehabilitation Project for the Orange County Sanitation District
Coast Trunk Sewer Rehabilitation Project for the Orange County Sanitation District Paul F. Wilson 1 and Robert J. Warren 2 1 1525 Faraday Ave, Suite 290, Carlsbad, California, USA 92008; e-mail: [email protected].
FY08 SEWER POINT REPAIRS BID TABULATION
6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "
Panel Lok Pipe Renovation System Danby LLC (formerly Danby of North America, Inc.) Waterfront Mall - 90 Diameter Rehabilitation
Waterfront Mall - 90 Diameter Rehabilitation 1. Project Location: 4 th & M Streets, SW, Washington, DC. This 100 year old line conveys storm drainage to the Potomac River. Since a building is to be constructed
Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority
Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Abstract The United States Virgin Islands Waste Management Authority
Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development
7 SPECIFICATIONS There is currently no Irish specification for construction of drainage works, or water supply works. There are several publications that give guidance on drainage works, such as the Building
San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS
ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located
53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:
Division 53: Slip-Lining of Existing Sewer Line 53.01 GENERAL: This section includes all labor, materials, transportation, equipment necessary to rehabilitate by means of Instituform deteriorated sections
SECTION 807 PUMP STATION REHABILITATION
SECTION 807 PUMP STATION REHABILITATION 807-1 DESCRIPTION: Rehabilitation of pump stations shall be defined as the cleaning, removal, repair and/or replacement of any and/or all components including but
SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.
SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price
PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY
PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY Cured-In-Place Pipe Pressure & Gravity Lines Pipe Splitting Trenchless Pipe Replacement EcoCast Advanced
Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects
Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental
Utilizing Remaining Useful Life for Asset Management of Critical Wastewater Assets
*Jessica Brown, P.E., Freese and Nichols, Inc., (817) 312-6980; [email protected] Mazen Kawasmi, Freese and Nichols, Inc. ABSTRACT The City of Fort Worth s wastewater collection system includes
San Antonio, TX July 28, 2011
Rehabilitation of a Deteriorated 60 RCP Wastewater Interceptor Using Competing Trenchless Technologies Bruce Cole, PE Corey Anderson, EIT TAWWA/WEAT Summer Seminar San Antonio, TX July 28, 2011 Wendy Martinez,
CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General
General All sanitary sewers, manholes and force mains shall be acceptance tested, as hereinafter specified in the presence of a City representative. Acceptance testing shall be performed after backfilling
Rehabilitation of an Aging Concrete Reservoir Adit Tower
Rehabilitation of an Aging Concrete Reservoir Adit Tower Raymond S. Tombaugh, Senior Coatings Consultant KTA-Tator, Inc. and Mongkol Mahavongtrakul, P.E. Corrosion Control Contract Manager San Francisco
March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS
March 2006 CW 2140 - SEWER AND MANHOLE CLEANING TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Constructions... 1 3. CONSTRUCTION METHODS... 1 3.1 High
Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe
Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe September 11, 2012 NEWEA Collection Systems Conference Presented by: Laurie L. Perkins, PE Dennis A. Dievert, PE C. Frederick
Section 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
See Appendix A for additional information, or contact ASTM directly.
DEFINITIONS Wherever used in these specification guidelines, the following words and terms have the meanings indicated. AREAWAY: A paved surface, serving as an entry area to a basement or subsurface portion
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing
BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY
MURRAY SHIRE COUNCIL BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY ADOPTED: 1 May 2012 1 BUILDING OVER OR NEAR WATER AND SEWER MAINS POLICY CONTENTS 1. Objective... 2 2. Requirements for Building Near
REHABILITATION OR REPLACEMENT? THAT IS THE QUESTION
REHABILITATION OR REPLACEMENT? THAT IS THE QUESTION ABSTRACT Chris L. Windley PE, McKim & Creed, Inc. Ben R. Latino, Jr., PE, McKim & Creed, Inc. Greg Anderson, PE, McKim & Creed, Inc. When designing to
WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598
Lessons Learned from Large Diameter Sanitary Sewer Pipe Bursting Project: Conversion of Abandoned Gravity Sewer Main Into Upsized Sanitary Force Main South San Francisco, CA Kent Von Aspern,* Collins Orton**
SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE
6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction
SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section 01 33 00 - Submittals.
SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS PART 1: GENERAL 1.01 SCOPE A. Abandonment in place, by cutting and capping, of existing water mains, hydrants, service lines, and valves. B. Abandonment in
Meeting the Challenge of Pipeline Emergency Repair
Meeting the Challenge of Pipeline Emergency Repair Michael R. McReynolds, PE, SE 1 Tao Peng, PE, SE 2 ABSTRACTS The Metropolitan Water District of Southern California (MWD) is the nation s largest provider
SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE
SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel
SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER
Village of Shorewood, Wisconsin SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER Prepared By: Thomas A. Zoulek, P.E., LEED A.P. Vice President Mid City Plumbing & Heating
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit
ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING
ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING 1.0 General 1.1 The work covered by this section consists of providing all labor, equipment, material and supplies, insurance, accessories, tools, transportation,
Rehabilitation Alternatives. MWEA Collection System Seminar October 1, 2009
Rehabilitation Alternatives MWEA Collection System Seminar October 1, 2009 Overview Types of Rehabilitation Trenchless Categories On-Line Replacement In-Situ Options Selecting the Best Solution Types of
CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS
CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection
Special Specification 7021 Water Main and Sewer Line Replacements
Special Specification 7021 Water Main and Sewer Line Replacements 1. DESCRIPTION Furnish, install, or replace water pipe, water valves, water meters and boxes, water service connections, fire hydrant assemblies,
Waste Management. Infrastructure Rehabilitation in the U.S. Virgin Islands
Waste Management Infrastructure Rehabilitation in the U.S. Virgin Islands The United States Virgin Islands is a group of islands in the Caribbean that are an insular area of the United States. The islands
Force Main Condition Assessment: New Technologies & Case Studies
Force Main Condition Assessment: New Technologies & Case Studies Andy Dettmer, Ph.D., P.E. CMOM Workshop August 19, 2014 2 1 Three takeaways 1. Most of your force mains are good 2. We can pinpoint the
SECTION 02400 - STORM DRAIN SYSTEM
SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And
SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING
812-1 SCOPE OF WORK: SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING a. The Contractor shall provide all labor, materials, equipment, and incidentals necessary to perform the cleaning of sewer lines,
SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS
SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING
CLEANING, INSPECTION, AND TESTING OF SEWERS
CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and
Section 402. STORM SEWERS
402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide
Module 3 : Sewer Material. Lecture 3 : Sewer Material
1 P age Module 3 : Sewer Material Lecture 3 : Sewer Material 2 P age 3.1 Important Factors Considered for Selecting Material for Sewer Following factors should be considered before selecting material for
Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair
Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair Eric M. Klein, P. E., Rummel, Klepper & Kahl, LLP, Baltimore, Maryland Kenneth B. Andromalos, P. E., Brayman Environmental,
SECTION 02612 NONREINFORCED CONCRETE SEWER PIPE
SECTION 02612 PART 1 GENERAL 1.1 SUMMARY A. Section Includes: Furnishing and installing nonreinforced concrete sewer pipe. Provide concrete sewer pipe less than 12 inches in diameter, and in other sizes
Platte River Interceptor Slipline Rehabilitation
Platte River Interceptor Slipline Rehabilitation Owner: Metro Wastewater Reclamation District Contractor: American West, Denver CO Slipline Pipe Manufacturer : Hobas Pipe USA Presented by: Tom Furie, Area
SEWER CLEANING, INSPECTION AND ASSESSMENT
3.1 OVERVIEW Chapter 3 SEWER CLEANING, INSPECTION AND ASSESSMENT Preventive maintenance protects the investment of the sanitary sewer collection system infrastructure. Higher frequency cleaning of gravity
A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.
PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,
Collection Systems Technology Fact Sheet Sewers, Conventional Gravity
United States Environmental Protection Agency Collection Systems Technology Fact Sheet Sewers, Conventional Gravity DESCRIPTION Sewers are hydraulic conveyance structures that carry wastewater to a treatment
External Wrapping of Steel Riser Pipe. Case Study HJ3 CS200902
External Wrapping of Steel Riser Pipe Case Study HJ3 CS200902 Introduction Refineries process a wide variety of petroleum products. As part of the process, they rely on cooling towers, which recycle water
INSTALLATION OF INSITUFORM LINER
PART 1 GENERAL 1.1 SCOPE: A. This item shall include all work and materials to install, insert a flexible polyester felt liner saturated with a thermo-setting resin into the existing sewer line for rehabilitation
812-3 LIMITATIONS: b. No fire hydrant shall be obstructed or used when there is a fire in the area.
812-1 SCOPE OF WORK: SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING a. The Contractor shall provide all labor, materials, equipment, and incidentals necessary to perform the cleaning of sewer lines,
SECTION 3 SANITARY SEWER DESIGN
SECTION 3 SANITARY SEWER DESIGN 3.1 GENERAL DESIGN CRITERIA 3.1.1 Requirement for Sanitary Sewer 3.1.2 Design Approval 3.1.3 IEPA Permit Required 3.1.4 Differentiation Between Public and Private Sanitary
Beacon Hill Sewer District Standard Specifications
Beacon Hill Sewer District Standard Specifications Residential Gravity Side Sewer Including Design Criteria and Standard Construction Drawings Residential Gravity Side Sewer Design Criteria 1. Provisions
Module 3: Sewer Material Lecture 3: Sewer Material
Module 3: Sewer Material Lecture 3: Sewer Material [NPTEL, IIT Kharagpur, Prof. M.M.Ghangrekar, Department of Civil Engineering Page 1 3.0 SEWER MATERIAL 3.1 Important Factors Considered for Selecting
SPR PE Steel Reinforced Liner
ENGINEERED SOLUTIONS SPR PE Steel Reinforced Liner Reline Done Right Contech is your single source for rehabilitation of sanitary & storm sewers, culverts and bridges. Contech Engineered Solutions has
SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines
High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines Jeff Schell General Manager United Pipeline Middle East, Inc. Introduction HDPE Liners A cost effective and environmentally beneficial
32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.
SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and
COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY
COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY Revised: April 2014 Village of Wilmette, Illinois NPDES CSO Permit No. ILM580012 Chapter 1 Introduction This Operational and Maintenance
TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe
TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines
SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD
SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD 21.01 SCOPE: It is the intent of the Specification to define the approved methods and materials
1.3.2 Method of construction and restoration of existing water service connections. This shall include:
1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting
San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS
San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS 854.1 DESCRIPTION: This item shall govern sanitary sewer laterals installed in accordance with these
Section 02702 SEWER PIPE INSTALLATION AND TESTING
PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete
San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION
ITEM 866 SEWER MAIN TELEVISION INSPECTION 866.1 DESCRIPTION: The Contractor shall furnish all labor, materials, equipment, and incidentals to provide the televising and a NASSCO-(PACP) standard video,
Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam
Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam Education Master of Business Administration University of Houston, 1985 Bachelor of Science, Civil Engineering University
Monterey Regional Water Pollution Control Agency. Sewer System Management Plan
Monterey Regional Water Pollution Control Agency Sewer System Management Plan March 31, 2013 Sewer System Management Plan Introduction I. Goals II. Organization III. Legal Authority IV. Operation and Maintenance
Sewer Line Rehabilitation
1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing sanitary sewers using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting
SECTION 810 SEWER LINE CLEANING
SECTION 810 SEWER LINE CLEANING I. GENERAL 1.1 DESCRIPTION OF WORK The work covered by this section consists of providing all labor, equipment, material and supplies and performing all operations required
TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth
TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 [email protected]
SECTION 02732 BUILDING SEWERS. B. Connection of building sanitary drainage system to municipal sewers.
SECTION 02732 BUILDING SEWERS PART 1 GENERAL 1.01 SECTION INCLUDES A. Lateral piping, fittings, and accessories. B. Connection of building sanitary drainage system to municipal sewers. 1.02 REGULATORY
CW 2130 - GRAVITY SEWERS TABLE OF CONTENTS
August 2010 CW 2130 - GRAVITY SEWERS TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Construction Specifications... 1 1.4 Referenced Standard Details...
SECTION 1 GENERAL REQUIREMENTS
Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,
Annular Space Grouting of Slipline Products
Annular Space Grouting of Slipline Products by David Gellings(, M.APWA & John Jurgens(, M.WWCPA Traditional methods of using neat cement slurries, (Portland cement and water, cement with fly ash or cement
VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10
VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 SECTION B1: PREPARATION GUIDE B1.1 INTRODUCTION... B1-1
SECTION 1 UTILITY OVERVIEW, INTRODUCTION, and PROJECT BACKGROUND
SECTION 1 UTILITY OVERVIEW, INTRODUCTION, and PROJECT BACKGROUND Wastewater Utility Overview In the late 1950 s, the Village of Old Forge began to realize the impacts of dumping sewage in the Moose River.
SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.
SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings
SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES
SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with
SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS
SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS Introduction City of Tacoma property owners are responsible for the construction, maintenance and repair of private side sewers, which connect
STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223
STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES PART 1 - GENERAL A. Description This section describes the installation of gravity sewer pipelines fabricated of vitrified
Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe
Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe 1. GENERAL The following supplemental sewer main specifications are intended to address the installation of high-density polyethylene
LOWELL REGIONAL WASTEWATER UTILITY SPECIFICATIONS FOR THE LOWELL MA CONCRETE FLOODWALL REPAIRS
Concrete Repairs LOWELL REGIONAL WASTEWATER UTILITY SPECIFICATIONS FOR THE LOWELL MA CONCRETE FLOODWALL REPAIRS PART 1 - GENERAL 1.01 DESCRIPTION OF WORK A. The work will occur within the City of Lowell
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS Section Page 36-1 GENERAL... 36.1 36-2 PIPEMAKING EQUIPMENT... 36.1 36-3 TRENCH EXCAVATION... 36.1 36-4 SPECIAL FOUNDATION TREATMENT...
CHAPTER 6 - SANITARY SEWER
CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings
