Coast Trunk Sewer Rehabilitation Project for the Orange County Sanitation District

Size: px
Start display at page:

Download "Coast Trunk Sewer Rehabilitation Project for the Orange County Sanitation District"

Transcription

1 Coast Trunk Sewer Rehabilitation Project for the Orange County Sanitation District Paul F. Wilson 1 and Robert J. Warren Faraday Ave, Suite 290, Carlsbad, California, USA 92008; pwilson@pirnie.com Faraday Ave, Suite 290, Carlsbad, California, USA 92008; rwarren@pirnie.com. Abstract: The Coast Trunk Sewer is about 7,300 meters long consisting of 1,350, 1,800, and 2,100 mm RCP PVC lined pipe. The sewer was built in the early 1980 s in Huntington Beach, California to serve a large development that never was constructed and consequently, the flow in the sewer has always been much less than anticipated. Corrosion has occurred to the pipe below the PVC liner that covers only 240 to 270 degrees of the circumference. This paper presents the procedures and technical memoranda that were developed to inspect and assess the condition of the sewer as well as the approach that was followed to evaluate a number of rehabilitation options and ultimately select the alternative most suited for the rehabilitation. The alternatives included 1) replacing the corroded concrete with cementitious grout and maintaining the original shape of the sewer, 2) filling in the bottom of the pipe with concrete, 3) installing concrete weirs inside the pipe to raise the water level, 4) installing a fiber reinforced epoxy liner over the corroded areas, 5) installing a spiral wound pipe liner, 6) extending the PVC liner with PVC bonded to a cementitious grout resurface, 7) sliplining with HDPE and 8) sliplining with centrifugally cast, glass-fiber-reinforced, polymer mortar (CCFRPM) pipe. 1. Introduction The Coast Trunk Sewer is located within the City of Huntington Beach, California, USA. It carries flow from Huntington Beach to the Orange County Sanitation District s Wastewater Treatment Plant No. 2. It consists primarily of 2100 mm (84-inch) and 1350 mm (54-inch) diameter, single-elliptical cage reinforced concrete sanitary sewer pipe (RCP) with a PVC liner. For purposes of this report, the alignment is divided into three segments or zones as shown on Table 1. Table 1: Coast Trunk Sewer Zones Zone Pipe Diameter Manholes PVC Liner Coverage Length 1 1,350 mm ,462 meters 2 1,350 mm 1,800 mm 1,350 mm meters 88 meters 2,118 meters 3 2,100 mm ,587 meters Location Under city streets thru residential and downtown Huntington Beach Under First Street Crossing under Pacific Coast Hwy Under beach parking lot Under beach parking lot and wetlands into treatment plant Water Practice & Technology Vol 3 No 3 IWA Publishing 2008 doi: /WPT

2 The sewer was constructed in the early 1980s to service an area whose demographic projections were not realized. As a result, wastewater flow has been very low and below the termination of the PVC liner installed to protect the pipe from corrosion. Also, the pipe in Zone 3 operates under the influence of the treatment plant. The zone 3 pipe invert is well below the operating level of the plant influent pump station and consequently operates as a full pipe for most of its length. Previous studies had identified corrosion in the sewer but the extent of the damage had not been fully evaluated. The purpose of this project, No Coast Trunk Sewer Rehabilitation, was to quantify and qualify the condition of the Coast Trunk Sewer and provide recommendations for the repair. 2. Method The project was divided into 5 elements that defined the scope of work and set the goals of the project. The elements were: Project Element 1 Preliminary Physical Inspection and Videotaping of the Pipeline Assess the diurnal variation in flow from records and by performing limited depth measurements Conduct physical inspection of the facilities with manned entries into the pipeline to physically measure the amount of corrosion, take close-up digital photographs, and collect limited chemical data (ph of corroded concrete). Project Element 2 Assessment of the Quantity of Solids Deposited in the Pipeline Determine depth and width of sediments for the purpose of calculating estimated quantities of deposited material. Collect samples of the deposits and conduct chemical analyses to determine the characteristics of the deposits. Project Element No. 3 CCTV Inspection Perform a complete CCTV inspection of the entire length of the Coast Trunk Sewer. Project Element 4 Removal of Solids and Final Inspection Remove deposits from Coast Trunk Sewer. Evaluate condition and life expectancy of the RCP conduits and PVC lining material. Project Element No. 5 Preparation of a Pipeline Condition Assessment Report. Preparation of a report that documents the findings and provide recommendations for repair. Prior to any physical inspection that would require manned entry and ventilation, an odor assessment was conducted and an odor control plan was developed based on the findings The odor assessment was conducted by accessing a number of manholes along the alignment and taking measurements at three different times of the day to determine the diurnal variations in the level of sulfides and other odor producing chemicals in the liquid phase and vapor phase inside each manhole. The quantity and location of manholes were selected to develop a full analysis of the odor potential for the entire alignment. Samples were collected by taking grab samples and by setting continuous monitors in select manholes for 24 hour Page 2 of 12

3 fluctuations. Continuous monitors included gas data loggers for the vapor phase and composite samplers for the liquid phase. Significant findings of the assessment were that the level of odor producing compounds in the sewer were low to moderate and that in most cases, the manholes were under negative pressure which indicated a low potential for odor release. Also, there was no health risk from low oxygen levels within the sewer. Data to determine the flow characteristics in the sewer were obtained from a datalogger mounted inside the sewer. The datalogger consisted of a device set on the invert of the sewer at a manhole that measured depth of flow and flow velocity. Measurements were taken every 15 minutes and saved to a digital data storage unit hung inside the manhole. The data was uploaded for analysis on a regular basis. For the purpose of this study, data collected between the dates of November, 2002 thru July, 2003 were analyzed. This period was one of the more recent wet winters on record and provided data during both a wet weather and dry weather period. Analysis of the data was conducted using a popular spreadsheet software program. Initial physical inspection was conducted by manned entry through each manhole supported by a confined space entry crew. The inspector and the confined space entry crew all received special safety training on sewer rescue procedures. The sewer was ventilated using a forced air system to assure safe working conditions. Prior to entry, the air quality at the manhole was tested using a device that measured the oxygen deficiency, concentration of hydrogen sulfide, and level of explosive gases in the sewer. Measurements were taken every 5 minutes and recorded continuously during the manned entry. The individual entering the sewer wore a harness that was tethered to a power winch. He also carried a similar air quality monitor and a two-way radio so that he would know the environmental condition of the sewer and be in constant communication with individuals located above grade. Inspection was conducted at night during periods of low flow and covered a distance of 60 meters upstream and downstream from each manhole, accounting for well over 40% of the total sewer length. Areas of corrosion were photographed and physical measurements were taken. Also, depth and width measurements of sediment deposits were made and samples collected every 15 meters for further chemical analyses. Sediment and liquid samples were transported to a field laboratory unit where immediate chemical analyses could be conducted. Closed Circuit Television (CCTV) inspections were also conducted on the sewer. The inspection was done using a camera mounted on a robotic crawler. Due to the length between manholes, particularly in Zones 2 and 3, some CCTV inspection required the crawler to travel downstream from one manhole and upstream from the next manhole. Also, a procedure needed to be worked out with the treatment plant to permit inspection of the Zone 3 pipe. During low flow hours, the operating level of the plant influent pump station was lowered to dewater the Zone 3 pipe. Also, temporary bulkheads were installed upstream of Zone 3 to further dewater the pipe and assure a complete inspection and thorough inspection. The CCTV inspection included digital video recorded on DVD s and analog video recorded on VHS tapes. A log of the inspection was also made that documented defects and permitted classification and ratings of the pipe conditions according to standards developed by the National Association of Sewer Service Companies (NASSCO). The results of these investigations were used to permit evaluation of the solids found deposited in the sewer and to provide recommendations for repair and rehabilitation of the sewer line. Page 3 of 12

4 3. Results Based on the data collected from the first four project elements, a Pipeline Condition Assessment Report was prepared consisting of a series of technical memoranda that documented the condition of the pipeline and presented conceptual design recommendations of the proposed rehabilitation methods. The following is a list of the technical memoranda and a summary of their findings: 3.1 Odor Assessment and Odor Control Plan Because the odor potential was low and the physical inspection would be conducted during low flow condition between 11:P.M and 5:00A.M., the recommendation was made to locate fans at the siphon on the 2,100 mm portion of the sewer to exhaust the headspace air towards the ocean during the inspection. The beach parking lot closed at 10:00 p.m. so there was limited exposure to the public while the work was in progress. Also, the exhaust was located along a portion of the beach occupied by a power plant which further limited the public exposure. 3.2 Preliminary Physical Inspection The preliminary physical inspection consisted of entry into the sewer at a number of manholes and traversing approximately 60 meters upstream and downstream of each manhole. During the inspection, the condition of the sewer was assessed and digital photographs were taken. Sediment Deposits Results Isolated instances of sediment deposits were noted at manholes and at the downstream end of Zone 2 (where the Coast Trunk Sewer increases in size from a 1,350 mm diameter pipe to a 2,100 mm diameter pipe). The overall length of this portion of the sewer is approximately 4,694 meters. The majority of the deposits (688 cubic meters) were located within the 2,591 meters of sewer in Zone 3 where the pipe is 2,100 mm in diameter. The depth of the deposits ranged from 100 mm to 350 mm. Chemical analyses of the deposits determined that three individual samples out of 23 tested exceeded criteria for toxicity limits for selenium, copper, or barium. Flow monitoring Two flow meters were installed in the sewer during this portion of the study one in the 1,350 mm sewer close to a location currently monitored by the District, and one in the 2,100 mm section of the sewer. The data from the meter in the 1,350 mm sewer closely matched the District s data and demonstrated that the flow velocity averaged about.0.6 m/sec and peaked at about 0.76 m/sec. The depth of flow varied from 200 millimeters to 250 millimeters The average velocity in the 2,100 mm sewer was determined to be about 0.15 m/sc. Preliminary Condition Assessment Piping in Zone 1 was lined for 270 degrees of the pipe s circumference. Piping in Zone 2 had PVC lining for only 240 degrees. The 270 degree lining was adequate to submerge the termination line of the liner and thus protect the portion of the sewer that is bare concrete. Page 4 of 12

5 However, the 240 degree liner was insufficient to submerge the liner s termination edge. Due to the low flowrate in the 1,350 mm and 1,800 mm diameter segments of the Coast Trunk Sewer in Zone 2, flow depths were typically below the edge termination of the PVC liner. Approximately 2,680 meters (38% of total length) of 1,350 mm and 1,800 mm pipe had delaminated PVC liner. Concrete below the PVC liner and underneath the delaminated portions of the PVC liner has been exposed to hydrogen sulfide gas, resulting in concrete degradation and exposed aggregate. Most of the sewer was located in the beach parking lot. The condition of the 2,100 mm (Zone 3) sewer could not be ascertained due to excessive flow depths caused by the operation of treatment plant influent pump station. However, it was possible to measure the depth and width of sediment deposits and collect samples for chemical analyses. Under normal operating conditions, the depth of the sewer is such that it is about 75% full when the influent wetwell is operating at its normal level. While this mode of operation encourages sedimentation inside the sewer, it also protects the pipe because it raises the depth of flow above the termination edge of the liner. 3.3 CCTV Inspection Prior to CCTV inspection, a study was conducted regarding the fate of the solids deposited in the 2,100 mm pipe reach. The estimated cost to remove the solids ranged from $730,000 to $1,580,000 and the benefits were questionable. Due to the influence of the treatment plant, flushing velocities in the sewer cannot be attained and solids will naturally settle in the sewer. Removal of the deposits is a costly procedure with limited disposal options. The deposits do no harm to the sewer and provide a benefit by protecting the bare concrete from exposure to potentially corrosive conditions. Based on the analysis of flow, it was determined that the 2,100 mm sewer could be inspected without bypassing or cleaning if the wetwell at the treatment plant was lowered and upstream flow was held back with plugs during the inspection period. The CCTV inspection of the 1,350 and 1,800 mm sewers confirmed the findings of the preliminary inspection. The inspection of the 2,100 mm reach found one area where corrosion was present. This occurred in a reach where design grade was not maintained during construction. To re-establish invert elevation, the slope of the pipe had been increased to lower the pipe invert by 0.6 meters over a distance of 78 meters which caused the depth of flow to decrease and expose the concrete pipe invert. The pipe walls below the PVC termination edge in a 274 meter reach was found to be as badly corroded as the pipe in the 1,350 mm reach of the sewer. 3.4 Physical Inspection and Condition Assessment As a result of the preliminary physical inspection and the CCTV inspection, a more focused, comprehensive inspection was conducted along the corroded reach of the 1,350 mm and 2100 mm sewer reaches. The inspection involved manned entry with a high pressure sprayer to wash the corroded concrete to remove any soft concrete that might be present to determine the extent of exposure of reinforcing steel. Due to the location of the corroded section of the 2,100 mm pipe, access with a high pressure sprayer was not possible, but a close visual inspection was conducted that defined the scope of the corrosion. The results of the inspections are summarized in Table 2 as follows: Page 5 of 12

6 Table 2: Summary of Inspections of the Coast Trunk Sewer PARAMETER ZONE 1 ZONE 2 ZONE 3 Condition Satisfactory Damaged Isolated Damage PVC Liner Delamination Maximum Depth of Corroded Concrete Minimum ph of Concrete Sediment Level None 1 st T-Lock rib detached from pipe wall for over 2,100 meters No corrosion found 50 mm 90 mm Not measured Heavy in curved section of sewer None found 1 st T-Lock rib detached from pipe wall on a 274 meter section Heavy Exposed Steel Joint Yes, at several None Spigot locations None ExposedJoint Yes, at several None None Gasket locations NASSCO Rating Structural O&M Structural O&M Structural O&M Severity Overall Rating NASSCO Quick Grade NASSCO Grade Score Preliminary Recommendations Re-inspect in 10 years QQQ 524J Repair delaminated PVC liner and concrete in 0 to 2 years Repair delaminated PVC liner and concrete in 0 to 2 years The integrity of the PVC liner was determined to be excellent except where the corrosion extended about 100 mm up under the termination edge. The maximum depth of corrosion in the 1,350 mm sewer was measured at 75 mm, which is half of the 150 mm pipe wall. The maximum circumferential length was 275 mm. The maximum depth of corrosion in the 2,100 mm sewer was 87 mm and the maximum circumferential length was measured at 400 mm. Due to the elliptical configuration of the reinforcing steel, the depth of coverage at the point of maximum corrosion exceeded 75 mm and none of the reinforcing steel was exposed. In a number of locations, the depth of corrosion was severe enough to expose and corrode the metal bell and spigot connections at the end of each fabricated length of pipe. 3.5 Rehabilitation Options and Recommendations Eight alternatives for rehabilitation were evaluated against a series of criteria to determine the best alternative for the Coast Trunk Sewer. The alternatives included 1) replacing the corroded concrete with cementitious grout and maintaining the original shape of the sewer, 2) filling in the bottom of the pipe with concrete, 3) installing concrete weirs inside the pipe to raise the water level, 4) installing a fiber reinforced epoxy liner over the corroded areas, 5) installing a spiral wound pipe liner, 6) extending the PVC liner with PVC bonded to a cementitious grout resurface, 7) sliplining with HDPE and 8) sliplining with centrifugally cast, glass-fiber-reinforced, polymer mortar (CCFRPM) pipe. Page 6 of 12

7 The criteria for evaluation of the alternatives included estimated construction costs, structural value, flow carrying capacity, odor and corrosion control, constructability and maintenance requirements. There also was an issue regarding the location of the sewer. The portion of the sewer that required repair was located under a parking lot utilized by the community for access to the Pacific Ocean. The community was very sensitive to any limitations that the rehabilitation activities may have had on their ability to use the parking lot as well concerns about the potential release of sewage and odors during construction, particularly from exposed bypass pumping equipment. A summary of the results for the feasible alternatives are listed in Table 3 below. The cementitious grout rehabilitation, by itself, was not considered a feasible alternative because it did not resolve the root cause of the corrosion. However, it is a necessary step for preparation of the existing surface for the epoxy liner as well as extending the PVC liner. Using concrete to fill in the pipe invert would raise the water surface above the bottom of the liner, but reduced the pipe carrying capacity to unacceptable levels. The same applied to using concrete weirs to raise the water level. This alternative also would encourage sedimentation and increased odor production. The epoxy liner was unacceptable because there is no apparent method available to transition from the epoxy to the existing PVC liner without exposing the underlying concrete to corrosion..utilizing PVC repair strips to cover the corroded areas was also unacceptable due to complicated preparation procedures, safety concerns while working in confined spaces, requiring ventilation, and public exposure to increased odors during construction and bypassing operations in the parking lot. The three remaining alternatives; spiral wound pipe liner, sliplined HDPE, and CCFRPM liner addressed the corroded area by lining the entire circumference of the pipe. Sliplined HDPE was eliminated because of cost and impacts to the community due to the large amount of lay down area required. The construction footprint for the CCFRPM liner was the smallest of all alternatives because the liner could be installed from one location for the entire 2,680 meter reach of the 1,350 mm pipe. However, it would also require replacement of all the manholes and the total cost was prohibitive. Page 7 of 12

8 Table 3 : Rehabilitation Alternative Matrix Rehabilitation Alternative Construction Cost Structural Integrity Feasible Alternatives for Repair and Rehabilitation Cementitious Grout Repair Concrete Weir Concrete Fill Fiber Reinforced Epoxy PVC Liner Repair Spiral Wound Pipe Liner HDPE Slipline CCFRPM Slipline $490/m 2 $2.0 million $577/ m 2 $2.8 million $1,120/ m 2 $3.8 million $1,155/ m 2 $5.3 million $1,400/ m 2 $6.9 million $1,290/ m 2 $5.4 million $1,930/ m 2 $8.5 million $2140/ m 2 $9.4 million No Impact No impact No impact Improved No impact Hydraulic Capacity No reduction 67% reduction 41% reduction No reduction No impact Odor Potential/ Corrosion Control No change Control decreased Potential Increased Potential Increased No Change No change No Change Improved 12% reduction Improved Improved 20% reduction 18% reduction No Change No Change Constructability Continuous bypass, extensive prep work, manned entry, traffic control Continuous bypass, minor prep work, manned entry, traffic control Continuous bypass, minor prep work, manned entry, traffic control Continuous bypass, minor prep work, manned entry, traffic control Continuous bypass, extensive prep work, manned entry, traffic control No bypass, minor prep work, reduced manned entry, minor traffic control No bypass, minor prep work, minimal manned entry, traffic control No bypass, minor prep work, minimal manned entry, traffic control Maintenance Requirements Increase Increase Increase Increase No change Decrease Decrease Decrease Page 8 of 12

9 4. Summary The spiral wound pipe liner ultimately was selected for the repair because it provided a viable solution with a small construction footprint and minimal impact to the surrounding community. The project had the distinct advantage of extremely low flow which permits this technology to be used without the need for bypassing. Also, since the liner is grouted in place, the need to prepare the corroded surface prior to applying cementitious grout or any of the partial liners was negated. Finally, the exposure of the installation crew to confined space issues and the need to ventilate was minimized by utilizing spiral wound liner technology. For most installation methods, the equipment used to install the liner is fixed in one location from where approximately 450 meters can be installed. Table 4 is a summary of the recommendations and future action for operation of the Coast Trunk Sewer. Table 4: Summary of Recommendations Issue Recommendation Action Rehabilitation Construction Maintenance Monitoring Zone 1 No rehab work required Zone 2 Spiral Wound Pipe Liner Zone 3 Spiral Wound Pipe Liner in 274 meters of pipe Construct rehab following design plans for sequence of work Limit bidding to experienced contractors Establish Maintenance and Monitoring Plan for entire Coast Trunk Sewer Leave sediments in 2,100 mm sewer Zone 1 Re-inspect in 10 years Zone 2 Inspect manholes and clean annually Zone 3 Inspect manholes annually Design Phase shall establish final scope of rehab and maintenance impacts Work with the City of Huntington Beach to establish and coordinate bypassing options Include experience clause in construction bid package Design Phase shall establish final impacts to maintenance activities Maintenance and Monitoring Plan developed during design or construction phase Create and implement sustainable Maintenance and Monitoring Program based on post-rehab construction conditions Odor Control Maintain current odor control practices No further action required. 5. Conclusion A thorough inspection of sewers in municipal settings demands attention to impacts on the public that can occur during the inspection. The inspection of the Coast Trunk Sewer has demonstrated that lines made of RCP must be protected for 360 degrees of their circumference to assure that corrosion will not occur. When corrosion does occur there are many alternatives that are available for rehabilitation which should be evaluated based not only on cost, but also on their impact to the surrounding community and on the requirements of the owner. Page 9 of 12

10 REFERENCES 1. California Code of Regulations Title 22 Division 4.5 ( ) governs treatment or disposal of hazardous wastes and sets limits used to provide criteria for identification and classification of hazardous wastes. 2. The National Association of Sewer Service Companies (NASSCO). Page 10 of 12

San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by

More information

March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS

March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS March 2006 CW 2140 - SEWER AND MANHOLE CLEANING TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Constructions... 1 3. CONSTRUCTION METHODS... 1 3.1 High

More information

Rehabilitation or Replacement? That Is The Question

Rehabilitation or Replacement? That Is The Question Rehabilitation or Replacement? That Is The Question Chris L. Windley PE Greg Anderson, PE 94th Annual Conference November 18, 2014 Overview Project Background Existing Sewer Condition Flow Projections

More information

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer

More information

Section 402. STORM SEWERS

Section 402. STORM SEWERS 402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide

More information

SEWER CLEANING, INSPECTION AND ASSESSMENT

SEWER CLEANING, INSPECTION AND ASSESSMENT 3.1 OVERVIEW Chapter 3 SEWER CLEANING, INSPECTION AND ASSESSMENT Preventive maintenance protects the investment of the sanitary sewer collection system infrastructure. Higher frequency cleaning of gravity

More information

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

Storm Sewer Trenchless Upgrade Alternatives and Recommendations Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for

More information

SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE

SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE PART 1 - GENERAL 1.01 WORK INCLUDED A. This section covers the initial and final cleaning, and the initial and final

More information

Letty Arvide-Gomar, PE

Letty Arvide-Gomar, PE Letty Arvide-Gomar, PE Outline DIP History and Applications Corrosion Issues Internal Cleaning Technologies Rehabilitation Options DIP History and Applications Corrosion Issues Internal Cleaning Technologies

More information

San Antonio, TX July 28, 2011

San Antonio, TX July 28, 2011 Rehabilitation of a Deteriorated 60 RCP Wastewater Interceptor Using Competing Trenchless Technologies Bruce Cole, PE Corey Anderson, EIT TAWWA/WEAT Summer Seminar San Antonio, TX July 28, 2011 Wendy Martinez,

More information

SCOPE OF WORK SEWER LINE CLEANING FOR CITY OF THE OF HUNTINGTON BEACH PROPERTY

SCOPE OF WORK SEWER LINE CLEANING FOR CITY OF THE OF HUNTINGTON BEACH PROPERTY SCOPE OF WORK SEWER LINE CLEANING FOR CITY OF THE OF HUNTINGTON BEACH PROPERTY A. General The City of Huntington Beach is an urban city with a population of 197,000 residents. It contains approximately

More information

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION ITEM 866 SEWER MAIN TELEVISION INSPECTION 866.1 DESCRIPTION: The Contractor shall furnish all labor, materials, equipment, and incidentals to provide the televising and a NASSCO-(PACP) standard video,

More information

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE 6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction

More information

FY15 Gravity Sewer and Manhole Rehabilitation

FY15 Gravity Sewer and Manhole Rehabilitation Contract Drawings For FY15 Gravity Sewer and Manhole Rehabilitation TRAVELERS REST TAYLORS Frazier Project No. -030 BASIN 850 Greenville, South Carolina April 2015 BASIN 700A GREENVILLE BASIN 700B FIVE

More information

SPR PE Steel Reinforced Liner

SPR PE Steel Reinforced Liner ENGINEERED SOLUTIONS SPR PE Steel Reinforced Liner Reline Done Right Contech is your single source for rehabilitation of sanitary & storm sewers, culverts and bridges. Contech Engineered Solutions has

More information

CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R

CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R CCTV PIPE INSPECTION AND EVALUATION For RUNWAY 17L-35R At ST. PETERSBURG CLEARWATER INTERNATIONAL AIRPORT February 2011 CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R ST. PETERSBURG CLEARWATER INTERNATIONAL

More information

CONSTRUCTION OF NON-CIRCULAR SEWER REHABILITATION PROJECTS IN LOS ANGELES

CONSTRUCTION OF NON-CIRCULAR SEWER REHABILITATION PROJECTS IN LOS ANGELES North American Society for Trenchless Technology (NASTT) No-Dig Show 2010 Chicago, Illinois May 2-7, 2010 Paper C-4-04 CONSTRUCTION OF NON-CIRCULAR SEWER REHABILITATION PROJECTS IN LOS ANGELES Brad Jenson

More information

LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD

LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD www.norcalpug.com LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD Bob Fisher and Lance Stracner Ameron Protective Lining J.R. Pipeline Co Inc. Abstract: The

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located

More information

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental

More information

SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING

SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING 812-1 SCOPE OF WORK: SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING a. The Contractor shall provide all labor, materials, equipment, and incidentals necessary to perform the cleaning of sewer lines,

More information

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, Storm Drain Installation, of these Standard Provisions. SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and

More information

Section 4 Pipe and Maintenance Hole Inspection and Condition Assessment Plan

Section 4 Pipe and Maintenance Hole Inspection and Condition Assessment Plan and Condition Assessment Plan 4.1 Introduction 4.1.1 Purpose This addresses the requirements of Section IV.A. of the EPA Order. The plan documents the progress that each agency has made to date regarding

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,

More information

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel

More information

MODEL WEB CONTENT FOR CITY SANITARY SEWER DEPARTMENTS

MODEL WEB CONTENT FOR CITY SANITARY SEWER DEPARTMENTS MODEL WEB CONTENT FOR CITY SANITARY SEWER DEPARTMENTS The following information is designed to be used in conjunction with the Sewer Toolkit, located in the Wastewater section of the Florida Rural Water

More information

REVIEW OF TRENCHLESS TECHNIQUES FOR THE REHABILITATION OF SEWERS. Gerhard (Gerry) P. Muenchmeyer, P.E. Muenchmeyer Associates, LLC

REVIEW OF TRENCHLESS TECHNIQUES FOR THE REHABILITATION OF SEWERS. Gerhard (Gerry) P. Muenchmeyer, P.E. Muenchmeyer Associates, LLC REVIEW OF TRENCHLESS TECHNIQUES FOR THE REHABILITATION OF SEWERS Gerhard (Gerry) P. Muenchmeyer, P.E. Muenchmeyer Associates, LLC What is really out there? DO YOU DIG IT? INDUSTRY CONCERNS UNEXPECTED DEVELOPMENTS

More information

Sewer Rehabilitation Design Requirements

Sewer Rehabilitation Design Requirements Sanitary Sewer Overflow (SSO) Control and Wastewater Facilities Program Sewer Rehabilitation Design Requirements City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared

More information

SECTION XXXXXX TECHNICAL SPECIFICATIONS FOR INSTALLATION OF PROTECTIVE COATINGS FOR MANHOLES, WETWELLS, AND OTHER SANITARY SEWER STRUCTURES

SECTION XXXXXX TECHNICAL SPECIFICATIONS FOR INSTALLATION OF PROTECTIVE COATINGS FOR MANHOLES, WETWELLS, AND OTHER SANITARY SEWER STRUCTURES 1.00 PART 1 GENERAL 1.01 SCOPE A. It is the intent of this contract to install a 100% solids epoxy monolithic coating to the walls, benches and inverts of all manholes and the specified surfaces of other

More information

812-3 LIMITATIONS: b. No fire hydrant shall be obstructed or used when there is a fire in the area.

812-3 LIMITATIONS: b. No fire hydrant shall be obstructed or used when there is a fire in the area. 812-1 SCOPE OF WORK: SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING a. The Contractor shall provide all labor, materials, equipment, and incidentals necessary to perform the cleaning of sewer lines,

More information

Section 2100-Trenching and Tunneling

Section 2100-Trenching and Tunneling SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial

More information

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542 1.0 INTENT REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES 1.01 It is the intent of this specification to provide for the reconstruction of pipelines and conduits by the installation of a resin-impregnated

More information

City of Bakersfield Public Works Department Sewer System Management Plan December 2014

City of Bakersfield Public Works Department Sewer System Management Plan December 2014 City of Bakersfield Public Works Department Sewer System Management Plan December 2014 C:\Users\hmayberry\Desktop\SEWER SYSTEM MANAGEMENT PLAN 2014.doc 1 Sewer System Management Plan Index: Section 1 Goals

More information

LS 2540 SEWER LATERALS AND INSPECTION TEES

LS 2540 SEWER LATERALS AND INSPECTION TEES LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal

More information

Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses

Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses Repairs Made With Under Pressure Installations Can Offer Reduced Risks And Expenses They also give the community a built-in re-entry system for future monitoring and repair. BY BRETT HANES According to

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Abstract The United States Virgin Islands Waste Management Authority

More information

Repair or Replacement - Band-Aids vs. Surgery

Repair or Replacement - Band-Aids vs. Surgery Repair or Replacement - Band-Aids vs. Surgery Using RCP for the Replacement of Failed or Undersized Culverts www.concrete-pipe.org Introduction and Background Our Nation s infrastructure owners are facing

More information

Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe

Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe September 11, 2012 NEWEA Collection Systems Conference Presented by: Laurie L. Perkins, PE Dennis A. Dievert, PE C. Frederick

More information

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING 1.0 General 1.1 The work covered by this section consists of providing all labor, equipment, material and supplies, insurance, accessories, tools, transportation,

More information

Emerging Technologies in Wastewater Collection Systems

Emerging Technologies in Wastewater Collection Systems Keville Enterprises Emerging Technologies in Wastewater Collection Systems Douglas McCutchen, CCM Brian Karmasin, P.E., BCEE CMAA Annual Conference Oct 2008 San Francisco, California Today s s Presentation

More information

NON-CIRCULAR SEWER LINER INSTALLATION AND FUTURE PROJECTS IN LOS ANGELES

NON-CIRCULAR SEWER LINER INSTALLATION AND FUTURE PROJECTS IN LOS ANGELES North American Society for Trenchless Technology 2008 No-Dig Conference & Exhibition Dallas, Texas April 27 May 2, 2008 NON-CIRCULAR SEWER LINER INSTALLATION AND FUTURE PROJECTS IN LOS ANGELES Brad Jenson

More information

Waste Management. Infrastructure Rehabilitation in the U.S. Virgin Islands

Waste Management. Infrastructure Rehabilitation in the U.S. Virgin Islands Waste Management Infrastructure Rehabilitation in the U.S. Virgin Islands The United States Virgin Islands is a group of islands in the Caribbean that are an insular area of the United States. The islands

More information

CLEANING, INSPECTION, AND TESTING OF SEWERS

CLEANING, INSPECTION, AND TESTING OF SEWERS CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and

More information

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and

More information

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation 644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING

More information

Condition Assessment of Underground Pipes April 2015 With excerpts from: Condition Assessment of Wastewater Collection Systems, EPA/600/R-09/049

Condition Assessment of Underground Pipes April 2015 With excerpts from: Condition Assessment of Wastewater Collection Systems, EPA/600/R-09/049 Condition Assessment of Underground Pipes April 2015 With excerpts from: Condition Assessment of Wastewater Collection Systems, EPA/600/R-09/049 EPA New England Water Infrastructure Outreach provides tools,

More information

INSTALLATION OF INSITUFORM LINER

INSTALLATION OF INSITUFORM LINER PART 1 GENERAL 1.1 SCOPE: A. This item shall include all work and materials to install, insert a flexible polyester felt liner saturated with a thermo-setting resin into the existing sewer line for rehabilitation

More information

STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS

STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements to execute internal closed

More information

Sanitary Sewer Overflow (SSO) Incident Report Form

Sanitary Sewer Overflow (SSO) Incident Report Form Submit completed form to EHS. Date of SSO spill: Sanitary Sewer Overflow (SSO) Incident Report Form Identify the SSO category (check one): Category 1 SSO Spills of any volume that reach surface water Category

More information

INTRODUCTION. WASTEWATER MANAGEMENT PLAN MAY 2009 Metropolitan North Georgia Water Planning District 7-1

INTRODUCTION. WASTEWATER MANAGEMENT PLAN MAY 2009 Metropolitan North Georgia Water Planning District 7-1 INTRODUCTION There are approximately 16,000 miles of sewers and more than 450,000 manholes within the Metro Water District. Sewers and manholes within the Metro Water District range in age from new to

More information

STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS

STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements to execute internal closed

More information

SECTION 724 PIPE CULVERTS

SECTION 724 PIPE CULVERTS SECTION 724 PIPE CULVERTS 724.1 Description. This work shall consist of providing pipe or pipe arch of the diameter or shape designated, laid upon a firm bed and backfilled as specified. Where appropriate

More information

12/8/2014. Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA.

12/8/2014. Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA. Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA. 1 Pipe Bursting A Mature and Diverse Trenchless Technology December 10, 2014 1:00 3:00 pm Eastern How to Participate Today

More information

Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology

Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology 2007 Pumper & Cleaner Environmental Expo International Wednesday February 7, 2007 Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology What is Cured-In-Place Pipe (CIPP)

More information

SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS

SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS Introduction City of Tacoma property owners are responsible for the construction, maintenance and repair of private side sewers, which connect

More information

Section 02702 SEWER PIPE INSTALLATION AND TESTING

Section 02702 SEWER PIPE INSTALLATION AND TESTING PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete

More information

Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries

Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries Introduction Wastewater of petrochemical industries and refineries contains high amounts of emulsified aliphatic or

More information

SECTION 02400 - STORM DRAIN SYSTEM

SECTION 02400 - STORM DRAIN SYSTEM SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And

More information

DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST

DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST CERTIFICATION 1. Did the engineer submit a certificate of completion utilizing the appropriate page of the issued

More information

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development 7 SPECIFICATIONS There is currently no Irish specification for construction of drainage works, or water supply works. There are several publications that give guidance on drainage works, such as the Building

More information

Section 2651 Television Inspection

Section 2651 Television Inspection Section 2651 Television Inspection PART 1: General 1.1 Description Provide all labor, materials, tools, equipment and incidentals as shown, specified, and required to perform television (TV) inspection

More information

BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION

BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION GENERAL Rehabilitation of culverts with pipe liners is one of several methods available for extending the life of an existing culvert. It is often cost

More information

Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam

Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam Education Master of Business Administration University of Houston, 1985 Bachelor of Science, Civil Engineering University

More information

SANITARY SEWER SPECIFICATIONS

SANITARY SEWER SPECIFICATIONS SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,

More information

PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY

PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY Cured-In-Place Pipe Pressure & Gravity Lines Pipe Splitting Trenchless Pipe Replacement EcoCast Advanced

More information

Dhaka Water Supply and Sewerage Authority. Financial and Capacity Building Consultancy of Dhaka Water Supply Sector Development Project.

Dhaka Water Supply and Sewerage Authority. Financial and Capacity Building Consultancy of Dhaka Water Supply Sector Development Project. Draft Dhaka Water Supply and Sewerage Authority of Volume 4 Sewer Cleaning May 2010 Schedule of maintenance activities are to assist the maintenance personnel of Dhaka WASA to conduct maintenance programs

More information

DRAFT Public Outreach Document for What s an SSMP?

DRAFT Public Outreach Document for What s an SSMP? DRAFT Public Outreach Document for What s an SSMP? This easy to read document is developed and provided to interested parties to assist in educating cities, agencies, their management, elected officials

More information

PRE INSTALLATION MANUAL

PRE INSTALLATION MANUAL REINFORCED CONCRETE PIPE PRE INSTALLATION INSPECTION & REPAIR MANUAL Kentucky Transportation Cabinet Kentucky Department of Highways Division of Materials 1227 Wilkinson Boulevard Frankfort, KY 40601 (502)

More information

2.1 Development of Risk-Based Asset Management Framework

2.1 Development of Risk-Based Asset Management Framework SECTION 2 Development of Asset Management Framework 2.1 Development of Risk-Based Asset Management Framework As part of the master planning effort, WES developed a risk-based asset management framework

More information

SEWER SIPHONS AND ODOR CONTROL: A PRACTICAL APPROACH

SEWER SIPHONS AND ODOR CONTROL: A PRACTICAL APPROACH ABSTRACT SEWER SIPHONS AND ODOR CONTROL: A PRACTICAL APPROACH *David Bennett, P.E., Lizanne Douglas, P.E., Rebecca Musk, EIT Freese and Nichols, Inc. 1017 Main Campus Drive, Suite 3100, Raleigh, NC 27606-4929

More information

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe. SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price

More information

Working together to improve beach water quality. Fixing our. public and private. sewers

Working together to improve beach water quality. Fixing our. public and private. sewers Working together to improve beach water quality Fixing our public and private sewers May 2004 FIND FIX DECIDE Narrow Neck Beach on a summer day As part of Project CARE, our long-term project to improve

More information

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant

More information

ecmar SECTION INSTRUCTIONS: Sanitary Sewer Collection Systems

ecmar SECTION INSTRUCTIONS: Sanitary Sewer Collection Systems ecmar SECTION INSTRUCTIONS: Sanitary Sewer Collection Systems Please see the DEFINITIONS of terms at the end of this section. If you have any questions about these definitions, do not understand a question,

More information

UVDB empowered by Achilles

UVDB empowered by Achilles UVDB empowered by Achilles DISAB Centurion: High Performance Wet/Dry Materials Handling Unit DISAB Centurion: High performance vacuum tanker that will vacuum dry or wet material The DISAB can vacuum material

More information

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains 1 P age Module 7: Hydraulic Design of Sewers and Storm Water Drains Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains 2 P age 7.1 General Consideration Generally, sewers are laid at steeper

More information

Texas Commission on Environmental Quality Page 1 Chapter 217 - Design Criteria for Domestic Wastewater Systems

Texas Commission on Environmental Quality Page 1 Chapter 217 - Design Criteria for Domestic Wastewater Systems Texas Commission on Environmental Quality Page 1 217.31. Applicability. SUBCHAPTER B: TREATMENT FACILITY DESIGN REQUIREMENTS 217.31-217.39 Effective August 28, 2008 This subchapter details the design values

More information

City of Regina Standard Construction Specification SECTION 1320 SEWERMAIN TESTING

City of Regina Standard Construction Specification SECTION 1320 SEWERMAIN TESTING 1.0 GENERAL 1.1 Scope 2.0 PRODUCTS 1.1.1 The work shall consist of testing wastewater and/or storm mains to ensure construction conforms to the proper line, grade, cross section and performance. 2.1 The

More information

Platte River Interceptor Slipline Rehabilitation

Platte River Interceptor Slipline Rehabilitation Platte River Interceptor Slipline Rehabilitation Owner: Metro Wastewater Reclamation District Contractor: American West, Denver CO Slipline Pipe Manufacturer : Hobas Pipe USA Presented by: Tom Furie, Area

More information

Collection Systems Technology Fact Sheet Sewers, Conventional Gravity

Collection Systems Technology Fact Sheet Sewers, Conventional Gravity United States Environmental Protection Agency Collection Systems Technology Fact Sheet Sewers, Conventional Gravity DESCRIPTION Sewers are hydraulic conveyance structures that carry wastewater to a treatment

More information

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20

More information

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection

More information

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials. PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,

More information

REVISED SHORT TERM AND LONG TERM SEWER PIPE INSPECTION AND CONDITION ASSESSMENT PROGRAM SOUTH COAST WATER DISTRICT. June 2005

REVISED SHORT TERM AND LONG TERM SEWER PIPE INSPECTION AND CONDITION ASSESSMENT PROGRAM SOUTH COAST WATER DISTRICT. June 2005 REVISED SHORT TERM AND LONG TERM SEWER PIPE INSPECTION AND CONDITION ASSESSMENT PROGRAM SOUTH COAST WATER DISTRICT FOR SOUTH COAST WATER DISTRICT Prepared with the requirements identified in the United

More information

SANITARY SEWER SYSTEM ASSESSMENT

SANITARY SEWER SYSTEM ASSESSMENT SANITARY SEWER SYSTEM ASSESSMENT What is this tool? The Sanitary Sewer System Assessment is a form that helps your utility identify and document all of the components in your utility s sanitary sewer system.

More information

DIVISION 4300 STORM DRAINAGE

DIVISION 4300 STORM DRAINAGE DIVISION 4300 STORM DRAINAGE SECTION 4305 STORM SEWER PART 1 - GENERAL 1.01 SCOPE This section covers the construction of storm sewers for the collection and transport of stormwater runoff. 1.02 REFERENCES

More information

Town House 11265 Center Highway North Huntingdon, PA 15642

Town House 11265 Center Highway North Huntingdon, PA 15642 APPENDIX C SPECIFICATIONS FOR THE CONSTRUCTION OF BUILDING LATERAL SANITARY SEWERS DECEMBER 2004, INCLUDING AMENDMENTS ADOPTED ON FEBRUARY 6, 2008 AND APRIL 2, 2008; EFFECTIVE ON MAY 1, 2008 Town House

More information

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines: Division 53: Slip-Lining of Existing Sewer Line 53.01 GENERAL: This section includes all labor, materials, transportation, equipment necessary to rehabilitate by means of Instituform deteriorated sections

More information

Monterey Regional Water Pollution Control Agency. Sewer System Management Plan

Monterey Regional Water Pollution Control Agency. Sewer System Management Plan Monterey Regional Water Pollution Control Agency Sewer System Management Plan March 31, 2013 Sewer System Management Plan Introduction I. Goals II. Organization III. Legal Authority IV. Operation and Maintenance

More information

Waste Collection Systems

Waste Collection Systems Waste Collection Systems System Maintenance and Repair Maintenance and Repair Training Objectives To gain an understanding of: System Maintenance and Repair vocabulary System Maintenance and Repair techniques

More information

COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY

COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY Revised: April 2014 Village of Wilmette, Illinois NPDES CSO Permit No. ILM580012 Chapter 1 Introduction This Operational and Maintenance

More information

Special Specification 7021 Water Main and Sewer Line Replacements

Special Specification 7021 Water Main and Sewer Line Replacements Special Specification 7021 Water Main and Sewer Line Replacements 1. DESCRIPTION Furnish, install, or replace water pipe, water valves, water meters and boxes, water service connections, fire hydrant assemblies,

More information

CCTV INSPECTION OF SEWER LINES. A. Section 02730 Sanitary Gravity Sewer Lines. B. Section 02731 Sanitary Gravity Sewer Line Testing

CCTV INSPECTION OF SEWER LINES. A. Section 02730 Sanitary Gravity Sewer Lines. B. Section 02731 Sanitary Gravity Sewer Line Testing CCTV INSPECTION OF SEWER LINES PART 1 GENERAL 1.1 SECTION INCLUDES A. CCTV Inspections 1.2 RELATED SECTIONS A. Section 02730 Sanitary Gravity Sewer Lines B. Section 02731 Sanitary Gravity Sewer Line Testing

More information

SECTION 807 PUMP STATION REHABILITATION

SECTION 807 PUMP STATION REHABILITATION SECTION 807 PUMP STATION REHABILITATION 807-1 DESCRIPTION: Rehabilitation of pump stations shall be defined as the cleaning, removal, repair and/or replacement of any and/or all components including but

More information

2016 - SECTION 25 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER LINES

2016 - SECTION 25 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER LINES 2016 - SECTION 25 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER LINES 25.1 GENERAL This section of the specifications shall form a part of the contract documents and should be read in conjunction with

More information

SECTION 02630 STORM DRAINAGE SYSTEM

SECTION 02630 STORM DRAINAGE SYSTEM SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE

More information

Affordable Asset Management Making Use of the Data You Have: An Owner s Perspective

Affordable Asset Management Making Use of the Data You Have: An Owner s Perspective Affordable Asset Management Making Use of the Data You Have: An Owner s Perspective An Owner Operator s Approach for Asset Management on a Budget Lane Longley, City of St. Petersburg Presented by the April

More information

CITY OF SALEM DEPARTMENT OF PUBLIC WORKS ADMINISTRATIVE RULES CHAPTER 109 DIVISION 003 SANITARY SEWER COLLECTION SYSTEM

CITY OF SALEM DEPARTMENT OF PUBLIC WORKS ADMINISTRATIVE RULES CHAPTER 109 DIVISION 003 SANITARY SEWER COLLECTION SYSTEM CITY OF SALEM DEPARTMENT OF PUBLIC WORKS ADMINISTRATIVE RULES CHAPTER 109 DIVISION 003 SANITARY SEWER COLLECTION SYSTEM SECTION 3.1 INTRODUCTION... 1 (a) Objectives...1 (b) Applicability...1 (c) Drafting

More information

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains

More information