Public Outreach Meeting



Similar documents
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

McGOEY, HAUSER and EDSALL CONSULTING ENGINEERS D.P.C.

SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS

Sewer Rehabilitation Design Requirements

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

Structural Pipe Lining Technology

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

SEWER CLEANING, INSPECTION AND ASSESSMENT

WATER SERVICE 2

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

Work Practice: Wastewater Collection System Maintenance Plan Potential Safety Hazards

Contracting Opportunities Vendor Day May 17, 2011

Sanitary Sewer Master Plan

Summary 7/11/2012. Michigan Water Environment Association 2012 Annual Conference Boyne Mountain Resort

Section 4 Pipe and Maintenance Hole Inspection and Condition Assessment Plan

Construction Specification for Sewer Bypass Flow Pumping

SAWS SSO Reduction Program

High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines

Soapstone Sewer Rehabilitation Alternative Concepts Design and Associated Impacts

City of Balch Springs, Texas. Request for Proposal (RFP ) Pipe Bursting Sewer Line Replacement

REVIEW OF TRENCHLESS TECHNIQUES FOR THE REHABILITATION OF SEWERS. Gerhard (Gerry) P. Muenchmeyer, P.E. Muenchmeyer Associates, LLC

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

DRAFT Public Outreach Document for What s an SSMP?

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

BERNALILLO COUNTY CAPITAL IMPROVEMENT PLAN (CIP) & GENERAL OBLIGATION BOND

A Systematic Approach to Reduce Infiltration and Inflow (I&I) and Sanitary Sewer Overflows (SSO) PETE GORHAM, P.E. MIKE LYNN FEBRUARY 19, 2015

Beechmont Park Project

Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives

CHELTENHAM TOWNSHIP. SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall

ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT

Technical Memorandum Cost Criteria for 2010 System Capacity Plan

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

REPAIRS TO DAMAGED SEWERS

2014 Sewer Replacement Project

PUBLIC NOTICE. Federal Aid Project MO F-54-D-20 May 1, 2016 December 31, Project Description

See Appendix A for additional information, or contact ASTM directly.

SEWER LINE CLEANING, DEBRIS AND GREASE REMOVAL, DEBRIS AND GREASE DISPOSAL

Water Mains Rehabilitation Framework (NI) Northern Ireland Water

Sewerage Agency of Southern Marin Cash For Sewers Program

GENERAL SPECIFICATIONS AND GUIDELINES FOR INSTALLATION MASTERLINER CURED-IN-PLACE PIPE SYSTEMS

Pipe bursting provides viable alternative for rehab work By Greg Key, U.S. Pipe

Ultraviolet (UV) Light Cured Fiberglass Reinforced Cured-In-Place Pipe (CIPP) It is not just for sanitary sewer rehabilitation

Oakland Macomb Interceptor Drain Rehabilitation State Revolving Fund Project Plan Overview. Public Meeting June 10, 2009

SECTION STORM DRAINAGE TABLE OF CONTENTS

SECTION STORM DRAIN SYSTEM

SECTION CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE

Phased Assessment Strategy for Sewers

SANITARY SEWER BACKUP. Causes & Prevention

PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY

APPENDIX M-2 SANITARY SEWER TECHNICAL MEMORANDUM. Stadium Reconstruction EIR

Final Report. Sacramento County Sanitation District No. 1. Engineering Sustainability of Piping Materials

PLANNING CAREFUL NORTH VANCOUVER PIPE BURST REQUIRES

City of Largo Environmental Services Department Environmental Control Program th Avenue North Clearwater, FL Phone: (727)

Sewer systems: Failures and rehabilitation

SECTION NONREINFORCED CONCRETE SEWER PIPE

The AQUAFIN Approach to Concrete Repair

by Leonard Friesenhahn, P.E.

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING


CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

San Antonio, TX July 28, 2011

Sewer System Management Plan (SSMP) Eastern Municipal Water District

MIAMI-DADE LATERAL PILOT PROGRAM. James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E.

Columbus State Community College MASTER PLANNING

PORTLAND BES ADVANCES IN SEWER MAINTENANCE AND REPAIRS BY OPERATING MULTIPLE CIPP CREWS.

SANITARY SEWER SYSTEM ASSESSMENT

THE MYTH OF DEEP PIPES: CRITICALITY AND PIPE REHABILITATION STRATEGIES

STANDARD SPECIFICATIONS SECTION INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223

12/8/2014. Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA.

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

ASBESTOS CEMENT PIPE: WHAT IF IT NEEDS TO BE REPLACED?

SECTION 1 UTILITY OVERVIEW, INTRODUCTION, and PROJECT BACKGROUND

Repair or Replacement - Band-Aids vs. Surgery

SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD

Interactive Decision Tree Automates Sewer Rehabilitation Planning

Alphington sewer replacement

PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET

Chapter 6 INFRASTRUCTURE ELEMENT 6.1 INTRODUCTION 6.2 AUTHORITY FOR THE ELEMENT 6.3 KEY THEMES AND VISION FOR GENERAL PLAN

CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R

Township of Enniskillen. Asset Management Plan

MODEL WEB CONTENT FOR CITY SANITARY SEWER DEPARTMENTS

White Paper I C G. How to Reduce I&I and Prevent Structural Damage with Intelligent Use of Chemical Grout. A Infiltration Control Grouting Association

Transcription:

Ross Valley Sanitary District Magnolia Trunk Sewer Rehabilitation Project April 16 2014 Public Outreach Meeting

Ross Valley Sanitary District Magnolia Trunk Sewer Rehabilitation Project April 16 2014

Purpose of the Magnolia Trunk Sewer Rehabilitation Project Renovate a critical District pipeline Provide long term reliability and capacity Reduce long term maintenance needs Brown and Caldwell 3

Existing Magnolia Trunk Sewer Constructed in 1960 s and 1970 s Critical facility in District collection system Pipe Materials Techite Asbestos Cement Vitrified Clay Pipe in poor condition Brown and Caldwell 4

Condition assessment of sewers - many problems Holes in sewers Cracked sewers Leaking sewers Exposed gaskets Heavy grease build up Leaking manholes Brown and Caldwell 5

Condition assessment of sewers - many problems Holes in sewers Cracked sewers Leaking sewers Exposed gaskets Heavy grease build up Leaking manholes Brown and Caldwell 6

Condition assessment of sewers - many problems Holes in sewers Cracked sewers Leaking sewers Exposed gaskets Heavy grease build up Leaking manholes Brown and Caldwell 7

Condition assessment of sewers - many problems Holes in sewers Cracked sewers Leaking sewers Exposed gaskets Heavy grease build up Leaking manholes Brown and Caldwell 8

Condition assessment of sewers - many problems Holes in sewers Cracked sewers Leaking sewers Exposed gaskets Heavy grease build up Leaking manholes Brown and Caldwell 9

Condition assessment of sewers - many problems Holes in sewers Cracked sewers Leaking sewers Exposed gaskets Heavy grease build up Leaking manholes Brown and Caldwell 10

Your building lateral Property Line Clean Out Manhole Main Line The District maintains sewer main The property owner maintains the lateral Brown and Caldwell 11

Rehabilitation methods meet project needs Provide a structural pipe Provide required capacity Minimize disruption Reduce construction costs Three rehabilitation methods selected Cured in place pipe CIPP Pipe bursting Open cut pipe replacement Brown and Caldwell 12

Cured in place pipe Brown and Caldwell 13

Pipe bursting Brown and Caldwell 14

Open cut replacement/realignment Improve hydraulic flows Deeper sewer Safer alignment for maintenance New alignment to reduce disruption Coordinate with Larkspur paving and bridge projects Brown and Caldwell McAllister and Lilac South Eliseo-temporary traffic stop 15

Safe access around construction Provide clearly signed alternate routes: Pedestrians Cyclists Automobiles, etc. Safe Routes to Schools Brown and Caldwell 16

Notification during construction Notifications will be issued 3 times prior to construction in your area. 30-Day Prior 7-Day Prior 24/48 hours Prior District Website will track project status District Construction Management on site during all construction activities Contact person and on call response will be available 24/7 Brown and Caldwell 17

Next steps for project Complete the engineering design Coordinate project details: Hall Middle School Mt. Tam Racquet Club Corbet s Hardware Golden Gate Transit and Marin Transit Buses City of Larkspur Bon Air Bridge project Magnolia repaving project ADA compliance efforts Advertise, bid, and construct the project Brown and Caldwell 18

Project construction timing Coordination needed: Construction with Bon Air Bridge project starting late summer 2014 No construction at Hall Middle School while school is in session Coordinate construction with scheduled tournaments at Mt. Tam Racquet Club Some night work required for construction Some weekend/holiday work will be needed mainly for Hall Middle School area Brown and Caldwell 19