COLUMN-FREE OFFICE SPACE RISES IN CHICAGO S LOOP



Similar documents
Residential Prototype III. Multi-Story. The Multi-Story. Your connection to ideas + answers. Prepared by: AISC Steel Solutions Center

Hunter College school of Social Work Thesis Proposal

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

How To Understand The World Trade Center'S Structural Design

4B The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.

SHARP. Focus. AESS serves as the focal point of a small eye-care office in Austin. BY BRIAN SAYRE, P.E., AND K. MARK MERRYMAN, P.E.

Analysis II Façade Redesign: Architectural Precast Panels

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM

EAST LYME HIGH SCHOOL

6 RETROFITTING POST & PIER HOUSES

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

POST AND FRAME STRUCTURES (Pole Barns)

US 51 Ohio River Bridge Engineering and Environmental Study

Residential Deck Safety, Construction, and Repair

STEEL. the healthcare structure PrototyPe ii. structural. Exploring Castellated Composite Framing. Your connection to i e n er

Technical Assignment 2 TABLE OF CONTENTS

The Collapse of Building 7 by Arthur Scheuerman December 8, 06

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

Designer s NOTEBOOK DESIGN ECONOMY, PART 3

Page & Turnbull imagining change in historic environments through design, research, and technology

STEEL. the parking structure prototype iii. structural. Exploring Conventional Composite and Castellated Composite Framing Options

Chapter 3 Pre-Installation, Foundations and Piers

A 38-story design-build steel structure features a staggered-truss frame

Occupancy: Assembly (A-3) and Business -Includes offices, seminar rooms, classrooms, and café facility. Duke University Medical School

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig some of the trusses that are used in steel bridges

INSTALLATION. General. Important Note. Design. Transport

[TECHNICAL REPORT I:]

PRODUCT AND ENGINEERING MANUAL

How To Design A Post Tensioned Deck For A Building

Analysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico

Code of Standard Practice for Timber Frame Structures

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA

Elevating Your House. Introduction CHAPTER 5

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

STEEL BUILDINGS IN EUROPE. Multi-Storey Steel Buildings Part 2: Concept Design

Residential Decks. Planning and Development Services Department

Conceptual design and design examples for multi-storey buildings

MULTI-RESIDENTIAL BUILDING SOLUTIONS

Estimated Cost of Repair

Steel joists and joist girders are

Leaky Homes Financial Assistance Package (FAP) Repair plan example

COMMON FOR ARCHITECTS AND ENGINEERS Excerpts from HB 2284, 82 nd R

The minimum reinforcement for the stem wall is the placement of:

Special Use Commercial Properties

Building Condition Assessment: North Howard Street Baltimore, Maryland

NUMBER EFFECTIVE DATE. July 23, 2003

FLAT ROOF CARPORT RECOMMENDED INSTRUCTION MANUAL

PART 1 GENERAL 1.1 SECTION INCLUDES

Safe & Sound Bridge Terminology

REQUIREMENTS FOR SUBMITTING PLANS FOR NEW CONSTRUCTION

Schematic Design: Quality Management Phase Checklist Project Phase Checklist Series

TD AMERITRADE Park Omaha

David C. Barrow Elementary School 100 Pinecrest Drive, Athens, GA 30605

HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES

Residential Foundations and Basements

COMMONLY USED RESIDENTIAL BUILDING CODES

Breakaway Walls

Envelope INSULATION BATT (2) Avoid Using Batt Insulation With Metal Framing. Pressure or Friction Fit

Saint Cloud Business Center

How To Build A Luxury Apartment Complex In London

Engineering for Stability in Bridge Construction: A New Manual and Training Course by FHWA/NHI

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

ENTRY FORM. DVASE 2013 Excellence in Structural Engineering Awards Program

March 14, Installation of Bay, Bow and Garden Windows

CE591 Lecture 8: Shear Walls

CH. 2 LOADS ON BUILDINGS

DESIGNING STRUCTURES IN EXPANSIVE CLAY

October 30, Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR. Report of Findings, Structural Investigation, Benton, Arkansas, Dear Mr.

Measurement Standards for Structures

Detailing of Reinforcment in Concrete Structures

Project Report. Structural Investigations Hotel del Sol Yuma, Arizona

The Impact of Building Shape on Space Planning Efficiency By Randall Walker, AIA, Executive Vice President, Kirksey

5200, 5250, 5300 AUTO CLUB DRIVE A PREMIER OFFICE/RESEARCH & DEVELOPMENT CAMPUS

MEZZANINE SPECIFICATIONS PART 1 GENERAL 1.1 SCOPE 1.2 APPROVED MANUFACTURER 1.3 REGULATORY ORGANIZATIONS AND GROUPS 1.4 QUALITY ASSURANCE

CITY OF BERKELEY BUILDING PERMIT DETAILED CHECKLIST

Building Code Clarifications - 7. Fire Resistance

STRUCTURAL STEEL DESIGN AND CONSTRUCTION. Gary S. Berman, PE GREYHAWK North America, LLC. GREYHAWK North America, LLC

Overhang Bracket Loading. Deck Issues: Design Perspective

TAX APPRAISAL DISTRICT OF BELL COUNTY STORES & COMMERCIAL IMPROVEMENT CLASSIFICATION GUIDE

SECTION 5 ANALYSIS OF CONTINUOUS SPANS DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE LEAD AUTHOR: BRYAN ALLRED

OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

REHABILITATION PACKAGE 1-a

Engineered Material Handling. Overhead Bridge Cranes and Gantry Cranes

Chapter 6 ROOF-CEILING SYSTEMS

Foundation Evaluation Report for PROPERTY ADDRESS Houston, Texas August 30, Prepared for:

IH-635 MANAGED LANES PROJECT, SEG. 3.2

SLAB DESIGN. Introduction ACI318 Code provides two design procedures for slab systems:

QUALITY ASSURANCE FOR STRUCTURAL ENGINEERING FIRMS

CHAPTER 6 CONSTRUCTION TYPES

U.S. Department of Labor Occupational Safety and Health Administration Directorate of Construction. April 2015

DUDERSTADT FOUNDATION & CONSTRUCTION, LLC.

Quality Control and Quality Assurance Guide

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

88 Wood Street. Project Basics. Background and Context

Joist. Reinforcement. Draft 12/7/02

Expected Performance Rating System

Design Development Quality Management Phase Checklist Project Phase Checklist Series

Transcription:

COLUMN-FREE OFFICE SPACE RISES IN CHICAGO S LOOP 30 x45 bay provides maximum tenant flexibility and increases leasing marketability By David E. Eckmann AIA, S.E. P.E. SURGING DEMANDS FOR RENTABLE OFFICE SPACE IN CHICAGO has created a need for more tall buildings in Chicago s downtown Loop area. Though many tall buildings have been proposed, the first speculative office building to get out of the ground since the late 1980s is Union Tower. Union Tower, an 18-story state-of-the-art office tower located in the desirable West Loop area, is a 330,000 square foot speculative office building. The office space is comprised of 21,000 square foot floor plates designed to accommodate cabling, mechanical, and open floor plan needs of the 21st century. Located a block from the historic Union Station train station, the 250 tall Union Tower benefits from access to two train stations, the el and ample adjacent parking. The design of Union Tower is intended to maximize the tenant s flexibility - maximizing usable floor space, while minimizing circulation space. The developer, Development Resources, LLC, also had an aggressive construction schedule, requiring occupancy in 1999. OWP&P Architects, an architectural engineering firm located in Chicago, Illinois was retained to design Union Tower on a fast-track schedule. OWP&P worked with Brininstool & Lynch, the lobby

and common tenant space designer, to optimize the building s marketability while abiding by budgetary constraints and zoning requirements. Upon review of the client s request for maximum tenant flexibility, OWP&P suggested using large bay sizes, offering potential tenants the ultimate in tenant flexibility a column-free space. The type of building, the requirement for flexible use, and the required speed of construction made steel the obvious structural material of choice.. Using a 30 x45 bay, the developer could obtain a column-free floor plan with steel girders that span from columns at the exterior wall to a vertical circulation core in the center of the building. Other benefits resulted from the column free space more rentable square footage, uninterrupted executive parking at the first floor, as well as more flexible use for the first floor lobby and retail space. The building, currently under construction, is evolving into a new glass and precast landmark in Chicago s West Loop. FOUNDATIONS & TOWER CRANE The foundation for the building is a series of belled drilled piers that extend 75 below grade to a hard sandy strata above the hardpan. Grade beams span between the drilled piers to support the weight of precast concrete walls and steel columns that must be located within inches of the property lines. The foundation system also needed to support a tower crane near the center of the building. The tower crane was necessary to erect the steel structure, the precast cladding, and other heavy materials. The crane had to be located within the building extents, because there was no available space on the small city lot. The tower crane cantilevered from a foundation platform and extended above the top of the structure. The crane was raised in two lifts, first to the ninth floor, and then when the struc- Union Tower features a 30 x45 bay, resulting in column-free space, more rentable square footage, uninterrupted executive parking at the first floor and more flexible use for the first floor lobby and retail space. ture was erected to that level, the crane was raised to the top of the building. SUPERSTRUCTURE BAY SIZE STUDY The developer was interested in marketing a 9-0 ceiling height for each floor of the building. The 30 x45 bay sizes required deeper framing members than a system with smaller bays. At the same time, the premium for increasing the building height was approximately $20,000 per lineal foot. Multiple methods of framing the bays were investigated. Since Power Contracting and Engineering Corp., the general contractor, was involved with the project team from the beginning of the project, they were able to study the cost/benefits of many framing schemes. The contractor was able to analyze, and provide timely answers to the ever elusive questions: Is 2 metal deck with more beams less expensive than 3 metal deck with fewer beams? Is it better to use a heavier

gage deck and fewer beams, or a lighter gage deck with more beams? The team decided that maximizing the span capabilities of the metal deck, and erecting as few beams as possible was the most economical solution. Using a 3 galvanized metal deck (18 gage) with 3 1 /4 lightweight concrete topping, it was possible to support the design loads and achieve the required two-hour floor fire rating. To keep the floor-to-floor heights as low as possible, the steel framing was oriented so that secondary composite beams span the short direction into the longer composite girders. The girders were limited to W27 s and cambered for the dead load. Penetrations were installed in the girder webs to accommodate the mechanical ductwork. The results are large bays with 9 ceiling heights and only 12-10 floor-to-floor heights. This floor system reduced steel tonnage, increased repetition of members, and minimized the number of beams and girders that needed to be picked at each level of framing - allowing for quicker erection of the building structure. An increase to the vertical circulation core size prior to issuing the fast-tracked structural drawings created another savings opportunity for the project. The increase in core size reduced the girder spans to 43. The 2 difference was enough to eliminate a beam per bay and have the metal deck supported at one-third points as opposed to one-quarter points. The elimination of a beam, multiplied by the number of bays, and again by the 18 floors, generated a $70,000 savings to the client. LATERAL SYSTEM Several lateral systems for the building were discussed at the beginning of the project. However, there seemed to be only one obvious choice a braced steel frame. The layout of the core was designed to allow for diagonal members to be located in each direction on all four sides of the core. In fact, the core layout allowed symmetrical bracing on each side of the core. These factors, along with the contractor s insistence that a braced frame could be constructed much more quickly than any type of concrete core, led to the braced frame decision. The profile of the bracing was a series of single diagonal braces. The diagonal braces were located to allow for door openings through the braced bays. The braces also did not clutter the upper corners of each bay with gusset plates and connections that would prevent distribution of large mechanical ductwork supplied from the core. The overall building drift, as well as the inter-story drift at each level, was limited to h/500. To best utilize column groupings and column splice locations, moment connections were incorporated at the top twelve levels of the building to meet the drift criteria. Initially, the diagonal members were designed as rectangular HSS sections, taking advantage of their greater weak-axis moment of inertia. However, the contractor advised that for this particular application, HSS sections were approximately 3 times the cost of wide flange sections. Therefore, details were revised, and wide flanges were incorporated as the diagonal bracing members. SPECIAL DESIGN CONSIDERATIONS Several unique design considerations were addressed on this building that are not typically considered for shorter building types. The first consideration

was elastic column shortening. Due to the height of the building, and particularly due to the weight of the precast concrete cladding panels that span 43 between exterior columns, the loads on the W14x500 columns were substantial. It was significant enough that the steel fabricator increased the column lengths by 1 /16 per floor. One-sixteenth of an inch may not sound like much, but when it is multiplied by the number of floor, it adds up to almost 1 1 /2 of anticipated column shortening enough to make the difference between the building s cladding fitting and not fitting. As expected, while the steel frame was erected, the floor slabs placed, and the precast panels erected, the building shortened to the correct design elevations. Two faces of the building are pulled inward 20 at the first floor to create a colonnade at the street level. Therefore, some of the two-story columns below the second floor are not enclosed within the heated building structure. As a result, those columns will be subjected to significant temperature differentials. The thermal stresses in those columns were analyzed, and the columns were designed so that the internal stresses caused by seasonal changes in column length (elongating/shortening), combined with the compressive stresses of the gravity loads above, did not exceed the column capacity. It was also important to seriously consider floor vibration for this building. Since it is a speculative office building without an identified tenant, it is not clear how this building will be used. Depending on the tenant, the floors may be filled with workstations, or they may be completely open, with virtually no floor damping. The more critical case, the open floor plan, was designed and determined to be within acceptable vibration limits. The layout of the core was designed to allow for diagonal members to be located in each direction on all four sides of the core. LEARNING FROM THE FABRICATOR/ERECTOR A post-construction discussion was held with the contractor and erector to determine what things went well on the project, and what can be done to improve the erection of the next project. In general, this project went up extremely quickly, and with few problems. However, a few things were learned: When column sizes were grouped and column splice locations were determined, it was obvious that the columns could be grouped into either two-story or three-story height segments. To comply with OSHA fall-protection height limits, steel is generally erected in two-story segments. However, fewer column splices and longer column lengths could lead to substantial cost savings. We asked the contractor and steel fabricator about their preference. They said that that the longer columns (and fewer column splices) would be the most economical solution. However, when the longer columns were erected, the erector discovered that it was difficult to erect the building in two story segments, and still keep the building plumb. After the first two floors were in place with the three-story columns, the erector needed to erect another three-story column to complete the second two-story segment of building height. This meant that columns were extending to the sixth floor when the erector was trying to make (connect) the steel on the third and fourth floors. To keep columns plumb, the erector didn t feel they could detail (tighten bolts) the steel at the lower levels until the steel was erected to the sixth floor. Obviously, this slowed down the building erection, and complicated the temporary bracing of the steel. The lesson learned on this project is that it may sound more economical to fabricate longer columns, but it would have been far less difficult for the erector to erect the structure with two-story column segments. The erector appreciated the fabricator s extensive use of bolted details. Virtually all field connections were bolted, even the column splices and diagonal braces. The erector felt this saved them a great amount of time. The erector also enjoyed working with the 3 metal deck. Their opinion was that the deck was stiffer, and therefore, easier

to handle and work on. What the erector did not appreciate however, was the slab edge detail at the perimeter of the building. Since the structure was fast-tracked, and the steel was to be fabricated prior to decisions on slab edge locations or precast wall panel supports, a bent plate pour-stop was shop attached to the perimeter members at each floor. The local iron workers union, however, have a safety requirement that no vertical projection from a steel member can be within five-feet of where the iron worker needs to make a connection to that member. What this meant was that the vertical leg of the bent plate needed to be field cut from each beam, and then replaced after the supported member was erected and attached. This was a time consuming process. In retrospect, the erection of the entire structure went smoothly. Even with a twomonth fast-track design period, everyone agreed that the project team worked well together, and that the use of structural steel created a structure that was simple and efficient. The result is a structure that meets the clients needs and was easy to fabricate and erect. Project Team Structural Engineer: OWP&P Architects Architect: OWP&P Architects Lobby and Common Tenant Space Designer: Brininstool & Lynch Developer: Development Resources, LLC General Contractor: Power Contracting and Engineering Corp. David E. Eckmann is a Senior Structural Engineer at OWP&P Architects, Chicago, IL