The Collapse of Building 7 by Arthur Scheuerman December 8, 06
|
|
|
- Primrose Anderson
- 9 years ago
- Views:
Transcription
1 The Collapse of Building 7 by Arthur Scheuerman December 8, 06 WTC s Building 7 was a 47-story office building completed in 1987 by Silverstein Properties on land owned by the Port Authority. It was built according to PA-NY- NJ codes developed for tenant alterations in the tower buildings. Building 7 was not hit by any planes but had some damage from parts of Tower 1 impacting the south wall. Because of the damage to the building and the failure of the water supply, after talking to the owner, the Fire Department decided to evacuate the building and not to attempt to control the fires but to let them burn out. Since it was a fire resistive building, there would have been every expectation that the fires would burn out without any local or global collapse. However, given that the towers had collapsed and that there had been a serious interior collapse of Building 5, there was concern, and the collapse area around the building was cleared. The building suffered global collapse from fire after several hours of uncontrolled burning. There were no known injuries or fatalities in the collapse. Building 7 was built over an existing Consolidated Edison power station. Above the seventh floor, the construction was very similar to that of the towers: with long-span outer floors, large open areas, unknown fireproofing on the steel, little lateral bracing in the core, and most likely weak column splicing. Since the perimeter wall columns were shear walls that resisted wind loads, the long-span floors (53 feet) acted as a diaphragm, transferring loads between exterior walls and between the walls and the core; the center core structure, as in the towers, supported only gravity loads. One important difference was that instead of steel bar-joists, the primary floor structure was more typical in that it had two-foot-deep wide flange steel I-beams, nine feet on center, composite with a concrete slab.. Figure 20a. Floors 8 to 45 plan. (Courtesy of NIST)
2 Photo 21. Building 7 before September 11 (left) and hours before collapsing (right). (Courtesy of Fire Department of New York.) The long-span steel I-beams had ¾-inch diameter by five-inch-long steel shear studs, about two feet on center that projecting into the concrete. These studs provided bonding and composite action under load with the 5½-inch concrete floor. Shear studs were not provided in the core. Similar sorts of floor-failure mechanisms, as those responsible for the towers collapse, might have been responsible for Building 7 s interior column failure, which triggered the progressive collapse. NIST studies (2, Appendix L) show that failure of one or more of three key interior columns on the east side of the building would travel vertically to the roof, collapsing all the floors and producing the initial kink in the east penthouse roof, the first indication of collapse as videotaped. That the west penthouse roof sank into the building, as seen on the videotape, five seconds after the east penthouse sank indicates a horizontal collapse progression to the rectangular core, imploding the building.
3 I believe the collapse was unlikely to have started below the 5th floor, since the construction below the 5th floor was more conventional. These lower floors were reinforced with much lateral bracing and thick, reinforced membrane floors that would redistribute any lateral loads throughout the lower floors. The 5th floors to 7th floors were transition floors. There was speculation about the fire s being on these floors and fed from oil-fired generators supplied from tanks on the lower floors, but I have seen no hard evidence of fire from this source. The fire shown in photos 21 and 22 appears to be a very severe, but ordinary, office fire and was well above the area supplied with oil lines. There is a strong possibility that this building collapsed from this office fire alone. NIST was scheduled to complete its analysis of the cause of the collapse in June This report is my contribution toward the analysis. Photo 22. The north side of Building 7. Fires are on the 7th and 12th floors. (Courtesy of NIST.)
4 Figure 21. The approximate fire location on the east side of floor 12. (Courtesy of NIST, modified by author) Fire is coming out of eight windows on the east side on the 12th floor. This fire must have dropped down to the 11th floor, since a later photo shows fire at four windows on the 11th floor. There was also fire showing at multiple 12th-floor windows on the north side. This is a serious high-rise building fire that would have necessitated multiple alarms to control. There were various other fires on different floors. These photos were taken at around 2 p.m.; the building collapsed about three hours later, after the 12th-floor fire had burned out. Collapse Initiation Hypothesis With a serious large area fire on the 12th floor, the two foot wide, long-span steel beams on the 13th floor, depending on the amount of fireproofing insulation installed, could have expanded and bowed, sagged or buckled downward and possibly twisted out or flopped over from the uncontrolled fire. The fire may have been burning long enough to weaken the steel causing a sag and catenary action. This same mechanism could have been happening on the 11th floor with the beams on the 12th floor being heated from both sides. Unlike the bar-joist failure producing early pull-in forces, short-span, steel I-beam composite floors usually maintain push-out forces caused by their expansion, during the fire, while the floors sag into tensile membrane action. It is unknown whether long-span floors act the same way. The large area of the concrete slab may have limited or increased tensile membrane action. As the steel beams first expanded from the heat, the studs might have pulled the slower expanding concrete into tension, possibly cracking it and removing some compression capabilities. This would have allowed the steel beams to bow or buckle sooner
5 from the loads and thermal forces and the floor to sag and put torque on the connections to the girder on the east side. The sag could have separated the wire mesh bond in the concrete over the girder. The girders themselves may have been sagging also. As the sagging steel beams and girders cooled after burnout, they began to contract. Since they would have been seriously deflected downward, the beams would have been unable to overcome the inertia and lift the floor loads as they contracted, and strong pull-in forces would have developed. The office furnishing and equipment loads on the 13th floor might have shifted down the slope toward the middle of the floor, increasing these pull-in forces. A question that needs to be studied is, what forces are developed by the shrinking of long span steel Ι-beams and girders in relation to the sag and temperature change, and over what distance does this force operate when the floor begins contracting after burnout? The increasing tension or torque in the 13th floor s connections from suspension forces as the floor bowed, buckled, or sagged or from contraction forces in the sagging floor as the floor cooled and contracted after burnout could have started an edge detachment, or rip failure, detaching the beams along the north-south girder along the line of columns 79, 80, and 81. The typical floor beam-to-girder and girder-to-core column connection was a single shear plate, (2, Appendix. L, 7) but certain floors had reinforced connections. This could have disconnected the west side of the east floor from this girder, allowing tension in the remaining portion of the floor to laterally displace one or more columns and break the column splices as the beams contracted. The sinking of the east roof penthouse before any other visible failure indicates that the three key columns (79, 80, and 81) were the first to fail. These were massive columns and most probably adequately fireproofed and would not have failed directly from heat. The girder along the line of columns 79, 80 and 81 could also have sagged and detached with the remaining girder creating pull-in forces on the column(s) as the girder buckled from the heat and/or contracted from cooling A less likely scenario is that the floor attachments to Columns 76, 77, and 78 initially failed. As the 13th floor sagged and contracted as it cooled, the floor could have initially detached at these east core columns. The loss of restraint could have allowed the remaining tension in sagging and contracting floors to laterally deflect one or more of the three key columns (79, 80, and 81). There was a layer of welded wire mesh reinforcement placed in the concrete over the girders along columns 79, 80, and 81; this additional reinforcement might have strengthened these connections and thus caused the core connections to fail first. There was also some fire on the 11th floor, and possibly the 14th floor. This could have assisted the failure of Columns 79, 80, and 81 by producing additional lateral forces.
6 Vertical Progression The failure of columns 79, 80, and 81 on the 13th floor put all the long-span floors above into suspension. Since the columns were widely spaced and floor spans were on the order of 50 feet, with a column failure, the floors would not have been able to effectively redistribute their loads to other columns, and the collapse would have progressed upward to the top of the building. A semi-plastic hinge would have formed along the north-south girder because of the singleplate, bolted beam-togirder connections. The tensile pull-in forces in all these upper buckled floors would have been great, since these floors were cool and there would have been no expansion-induced sag. (See Part 3, Theory.) Figure 22. East-West building section as viewed from the north showing column failure and resulting progression, putting all floors above in suspension; and the east roof shed is sinking. Darker floors are reinforced. (Diagram by author.) This initial column failure was evidenced by the kinking and sinking of the east penthouse into the building s roof and the simultaneous breaking of the windows on the east side of the north wall as it was pulled in by the suspended floors. NIST studies have shown that because of the large floor areas, the failure of just one [key] column on any one of the lower floors would cause a vertical progression of collapse so that the entire section would come down. (NIST, S. Shyam Sunder lecture) This single-column s failure initiating progressive
7 collapse is a design defect noncompliant with the NYC codes. The buckling of two or more of these three key columns (79, 80, and 81) would have removed support for all columns directly above, putting all upper floors in immediate longspan suspension with eventual collapse. The breaking of the widows on the east side of the north face simultaneously with the buckling of the roof shed was evidence of this tension as the north wall was pulled and leaned in. This high tension in all the floors above could have failed the floor connections or buckled more columns, depending on the stresses and strains developed. As can be seen in the illustration, the floors would have been equally deflected in the initial collapse because of the geometry of the rigid columns pulling or pushing on the floors. This combination of equal floor deflection along with the exterior walls leaning inward would have created increasing pull-in forces in the floors from the top floor downward. If the connections had held, the exterior walls and core columns would have been pulled inward with greater forces on the lower floors because of the lean. Because the 14th floor was still intact, even though sagging, if the floor to column connections held the exterior and interior columns more likely would have buckled at that floor. The question that needs analysis is what connections would fail first and what connections would hold with all 35 floors in suspension? NIST reported that the information available indicated that the floor to-column connections would fail under this scenario without seriously damaging the perimeter or interior columns. However, certain connections on Floors 19 and 20 were reinforced, and Floors 21 to 23 used heavier steel. (2,126) These floors could have developed a higher degree of column destabilizing tensile forces before connection failure cut off these lateral forces. Horizontal Progression West One of NIST s hypotheses involving the horizontal progression is that the impact of the debris from the falling floors hit a transverse truss between Floors 5 and 7 and rotated the truss, which would have pulled a line of core columns eastward, collapsing the core. This is certainly possible and may have happened, but probably not until after the core had already started collapsing from the tensile forces of the floors in suspension. Floors 21 to 23 had slightly heavier steel framing than the others (shown darker in diagram, Figure 22). Portions of Floors 10, 19, and 20 had reinforcing plates on the bottom flange, and certain connections were reinforced. If other floor connections failed, these strong connections might have held and pulled a line of core columns eastward, especially if impacted by falling debris from the collapsing floors above. The fact that Core Columns 76, 77, and 78 on all the floors would have been subjected to pull-in with increasing pull-in on the lower floors should be figured in.
8 Figure 23. The buckling of Columns 79, 80, and 81 would have allowed the east side floors directly above these columns to go into suspension and would have produced these strains in the remaining structure on all the floors above the 13th. (Diagram by author.) Tension in the floors above the buckled key columns could have put floor connections to the core columns under immediate severe lateral stress on all the floors above 13. These lateral stresses would be greater on the lower floors because of the exterior wall s leaning inward more at the top. If the floor connections to Column 77 s connection held on any of the levels above the 13th floor, the middle line of Core Columns 77 to 62, and possibly 59, could have been pulled eastward under the lateral forces. This line of middle core columns would more easily have been pulled eastward, since there were elevator shafts along this line and there were fewer floors that could have restrained these columns and floor beams from deflection. The connections to columns 76 and 78 on any floor above the thirteenth would probably fail first allowing the connection to column 77 to hold and pull the line the line of core columns 77 to 62 and possibly 59 eastward. The reinforced connections on Floors 19 to 23 could have made it more likely that these connections would have held and buckled the middle line of core columns and destabilized the remaining core columns. As this middle line of columns deflected, they would have pulled the remaining core columns inward toward the middle line, possibly buckling all the core columns on a floor. Debris hitting the girders and beams might have assisted in deflecting the middle line of columns. Columns 78 to 63 and/or 76 to 61 could have been pulled inward since the attached beams would not have shear studs connecting them to the floors. The elevator shafts without floors would offer little resistance to this inward buckling. These core columns which probably had weak splices would have had
9 to buckle on only one floor to collapse the core structure and implode the whole building. Photo 23. Façade kink. (Courtesy of NIST) The massive façade kink, which increased as the perimeter wall came down as a unit, was aligned with Columns 76, 77, and 78. This supports the idea that these particular columns were the first core columns to fail on one or more floors and were followed by the remaining core columns, pulling in the entire exterior facade. The pull-in tension on a particular floor or floors could have buckled, say columns 76 to 61, This pull-in tension on the remaining core columns was possibly assisted by a floor or floors disconnecting from the girder along the east-west axis of the core, since shear studs were not indicated in the design drawings for the core girders (NIST). A line or lines of core columns buckling would have collapsed the core and put all the west side floors into suspension putting extreme lateral forces on remaining perimeter column connections on all the upper floors, buckling the entire perimeter wall. Five seconds after the east penthouse failed, the west shed disappeared into the roof indicating that the core failed before the building began descending. The breaking of the vertical line of windows near Column 54 on the east side of the north wall simultaneously with the sinking of the east penthouse indicates that the wall was being pulled inward by the floors in suspension. The evidence of dust expulsions from floor to floor upward from the southwest corner near the roof, said to be from detonations, would have been caused by the floors disconnecting sequentially in the corner as the tensions in the suspended collapsing floors increased from core failure. That these failures were upward shows that there were sequentially increasing tensions in lower floors due to exterior wall s leaning inward.
10 Figure 24. As-built elevations. Building 7. (Courtesy of NIST.)
11 The belt truss around the building at the 22nd to the 24th floors stiffened the perimeter wall and probably supported the outer frame so that it came down as a unit above the buckling columns. There were numerous diagonal braces in the core below the 7th floor. There were also thick reinforced concrete floors on the 5th and 7th floors. The 5th floor diaphragm was 14 inches thick and reinforced with imbedded steel T sections. The 7th floor was eight-inch reinforced concrete. This would have made it unlikely that the initial failure started or progressed on these lower floors. As the core failed, the perimeter walls were pulled inward, with the greatest deflection at the top floors. This lean in of the perimeter walls sequentially decreased the pull-in forces on each floor moving upward, and produced increasing forces on each consecutive floor moving lower. Various exterior columns and connections would have failed on the lower floors with the increasing tension. This perimeter wall s buckling was not seen in the videos because it was below the line of sight because of the buildings in the foreground; it looked as though the building had just descended straight into the ground. The possibility that some weaknesses exist in high-rise buildings constructed with long-span floors and cores without lateral bracing and weak column splices necessitates that all possible failure mechanisms be studied to determine the cause of failure and means to prevent such failure. NIST can do a computer analysis of the forces involved and connection strength to confirm or disprove the analysis and clarify the theory. With the increasing spans and size of floor areas of high-rise office buildings allowed by the use of steel, there is a critical need for new methods to test long-span floors to determine if they are, or can be, adequately protected from fire. New methods should be developed for testing and determining the forces that affect these floors and their connections under collapse conditions. Long span I beams may be affected by differential heating and expansion of different parts of the web or flanges causing early bowing, buckling or twisting out of alignment, affecting structural integrity. Contraction of sagging steel beams of girders may put extra pull-in forces on columns pulling them out of alignment and buckling them. If these long-span floors cannot be adequately tested and protected against progressive or global collapse, the spans should be reduced and the steel size and strength increased. Surely, lateral bracing of core columns on each floor should be required, the column splice strength increased and alternate load paths should be built in to handle floor loads in case columns fail. In situations where the failure of floor assemblies could affect the stability of the columns, these floors should be considered part of the frame and should have the same degree of fireproofing protection as the columns.
Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig. 7.21 some of the trusses that are used in steel bridges
7.7 Truss bridges Fig. 7.21 some of the trusses that are used in steel bridges Truss Girders, lattice girders or open web girders are efficient and economical structural systems, since the members experience
How To Understand The World Trade Center'S Structural Design
Emerging Technologies in Structural Engineering Proc. of the 9 th Arab Structural Engineering Conf., Nov. 29 Dec. 1, 2003, Abu Dhabi, UAE WORLD TRADE CENTER COLLAPSE, FIELD INVESTIGATIONS AND ANALYSES
Page & Turnbull imagining change in historic environments through design, research, and technology
DCI+SDE STRUCTURAL EVALUATIONS OFFICE BUILDING, TOOL SHED & WATER TANK, AND BLACKSMITH & MACHINE SHOP BUILDINGS SAN FRANCISCO, CALIFORNIA [14290] PRIMARY PROJECT CONTACT: H. Ruth Todd, FAIA, AICP, LEED
4B-2. 2. The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.
Shear Walls Buildings that use shear walls as the lateral force-resisting system can be designed to provide a safe, serviceable, and economical solution for wind and earthquake resistance. Shear walls
Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing
1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize
What is Seismic Retrofitting?
What is Seismic Retrofitting? SEISMIC RETROFITTING A Seismic Retrofit provides existing structures with more resistance to seismic activity due to earthquakes. In buildings, this process typically includes
INTRODUCTION TO BEAMS
CHAPTER Structural Steel Design LRFD Method INTRODUCTION TO BEAMS Third Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering Part II Structural Steel Design and Analysis
Structural Failures Cost Lives and Time
Structural Failures Cost Lives and Time Recent failures of storage bins, silos and other structures highlight the need to increase awareness of hazards associated with these structures. Since 2010, one
Chapter 6 ROOF-CEILING SYSTEMS
Chapter 6 ROOF-CEILING SYSTEMS Woodframe roof-ceiling systems are the focus of this chapter. Cold-formed steel framing for a roof-ceiling system also is permitted by the IRC but will not be discussed;
COLUMN-FREE OFFICE SPACE RISES IN CHICAGO S LOOP
COLUMN-FREE OFFICE SPACE RISES IN CHICAGO S LOOP 30 x45 bay provides maximum tenant flexibility and increases leasing marketability By David E. Eckmann AIA, S.E. P.E. SURGING DEMANDS FOR RENTABLE OFFICE
Structural Fire Response and Probable Collapse Sequence of the World Trade Center Towers
NIST NCSTAR 1-6 Federal Building and Fire Safety Investigation of the World Trade Center Disaster Structural Fire Response and Probable Collapse Sequence of the World Trade Center Towers John L. Gross
EAST LYME HIGH SCHOOL
Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed
Elevating Your House. Introduction CHAPTER 5
CHAPTER 5 Elevating Your House Introduction One of the most common retrofitting methods is elevating a house to a required or desired Flood Protection Elevation (FPE). When a house is properly elevated,
Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections
Materials Standard shapes W sections, C channels, Structural T, Angles, Pipes, Tubes, Rods and Plates Fabricated members, Built-up sections Adding plates to beam flanges, Stiffeners to beam webs Built
Chapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
STRUCTURAL ASSESSMENT REPORT BOLINAS MARINE STATION - BOLINAS, CALIFORNIA
STRUCTURAL ASSESSMENT REPORT BOLINAS MARINE STATION - BOLINAS, CALIFORNIA College of Marin c/o Swinerton Management & Consulting P.O. Box 144003 835 College Avenue, Building MS-3 Kentfield, California
STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM
Chapter 9 STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM 9.1 BACKGROUND Steel is widely used in the construction of multi-storey buildings. However, steel construction is seldom used and is traditionally
4.3.5 - Breakaway Walls
4.3.5 - Breakaway Walls Elevation of a structure on a properly designed foundation reduces the potential for water damage from flooding. When the space below the lowest elevated floor is maintained free
SECTION 5 ANALYSIS OF CONTINUOUS SPANS DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE LEAD AUTHOR: BRYAN ALLRED
SECTION 5 ANALYSIS OF CONTINUOUS SPANS DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE LEAD AUTHOR: BRYAN ALLRED NOTE: MOMENT DIAGRAM CONVENTION In PT design, it is preferable to draw moment diagrams
TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE
TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General
Envelope INSULATION BATT (2) Avoid Using Batt Insulation With Metal Framing. Pressure or Friction Fit
R-H-DI1 INSULATION BATT NR-E-IB1 Avoid Using Batt Insulation With Metal Framing Batt insulation should not be used with metal framing systems. Although it is common to see fiberglass batt insulation installed
INSTALLATION. General. Important Note. Design. Transport
General The roof trusses you are about to install have been manufactured to precise engineering standards. To ensure that the trusses perform as designed, it is essential that they be handled, erected
STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA
STRUCTURAL ASSESSMENT FOR Full Metal Jacket Building 0 Prince Street, Prepared by: ALPHA CORPORATION (Alpha) 1850 S. Loudoun Street, Suite 200 Winchester, VA 22601 540-723-0704 September 22, 2010 J. Michael
Analysis II Façade Redesign: Architectural Precast Panels
Analysis II Façade Redesign: Architectural Precast Panels Analysis II Façade Redesign: Architectural Precast Panels Overview: This analysis covers the comparison of the current EIFS façade and my proposed
2.0 External and Internal Forces act on structures
2.0 External and Internal Forces act on structures 2.1 Measuring Forces A force is a push or pull that tends to cause an object to change its movement or shape. Magnitude, Direction, and Location The actual
Joist. Reinforcement. Draft 12/7/02
Joist Reinforcement Draft 12/7/02 1 JOIST REINFORCING The purpose of this CSD Design Aid is to provide procedures and suggested details for the reinforcement of open web steel joists. There are three basic
SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM
Shepherd University Board of Governors June 9, 2005 Agenda Item No. 9 SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM In 1994 construction began on the Byrd Science and
The minimum reinforcement for the stem wall is the placement of:
PolySteel creates an ideal insulated stem wall for concrete slabs that can make this part of your project easier and faster, in addition to making your finished project more energy-efficient. Figures 3.20
Technical Assignment 2 TABLE OF CONTENTS
2 TABLE OF CONTENTS Executive Summary...3 Introduction..5 Gravity Loads......6 Design Codes......7 Materials..8 Existing Structural System.. 10 Existing Floor System 15 Alternate Floor Framing Systems...17
Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations
Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet
POST AND FRAME STRUCTURES (Pole Barns)
POST AND FRAME STRUCTURES (Pole Barns) Post and frame structures. The following requirements serve as minimum standards for post and frame structures within all of the following structural limitations:
Project Report. Structural Investigations Hotel del Sol Yuma, Arizona
Project Report Structural Investigations Yuma, Arizona Prepared by: 2619 Spruce Street Boulder, CO 80302 303-444-3620 Prepared for: Principle Engineering Group, Inc. 833 East Plaza Circle, Suite 100 Yuma,
Design of reinforced concrete columns. Type of columns. Failure of reinforced concrete columns. Short column. Long column
Design of reinforced concrete columns Type of columns Failure of reinforced concrete columns Short column Column fails in concrete crushed and bursting. Outward pressure break horizontal ties and bend
Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI 318-14
Draft Table of Contents Building Code Requirements for Structural Concrete and Commentary ACI 318-14 BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE (ACI 318 14) Chapter 1 General 1.1 Scope of ACI 318
Fire Preventive and Fireproof Performance Test and Evaluation Procedure Manual
BR BO-01-02 Effective from June 1, 2000 Revision: March 26, 2002 Fire Preventive and Fireproof Performance Test and Evaluation Procedure Manual (Unofficial Manual) Technical Appraisal Department, Building
SEISMIC DESIGN. Various building codes consider the following categories for the analysis and design for earthquake loading:
SEISMIC DESIGN Various building codes consider the following categories for the analysis and design for earthquake loading: 1. Seismic Performance Category (SPC), varies from A to E, depending on how the
Hunter College school of Social Work Thesis Proposal
Fall 2009 Hunter College school of Social Work Thesis Proposal To analyze how energy efficiency can be implemented using facade and green roof redesign. It ties structural engineering concepts with existing
Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training
Foundations 65 5 FOUNDATIONS by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. 66 Foundations Foundations 67 FOUNDATIONS Let's assume that the retrofit has been done correctly from the roofline
6 RETROFITTING POST & PIER HOUSES
Retrofitting Post & Pier Houses 71 6 RETROFITTING POST & PIER HOUSES by James E. Russell, P.E. 72 Retrofitting Post & Pier Houses Retrofitting Post & Pier Houses 73 RETROFITTING POST AND PIER HOUSES This
How To Repair A House
Assessing Structural Damages Please note-this presentation is only intended to be used as a basic educational tool and is by no means all encompassing. Each property should be treated on a case by case
Appendix A EXAMPLES OF PERIMETER PANEL FLOOR TRUSS CONNECTORS
Appendix A EXAMPLES OF PERIMETER PANEL FLOOR TRUSS CONNECTORS The floor trusses were attached to the perimeter panels at the interior intersection of the columns and spandrels by different types of connectors.
Nueva Edición del libro clásico para estudiantes de grado.
Nueva Edición del libro clásico para estudiantes de grado. Ha aparecido la quinta edición del que ya se ha convertido en uno de los libros más vendidos de Diseño de estructuras de Acero para su uso en
SLAB DESIGN. Introduction ACI318 Code provides two design procedures for slab systems:
Reading Assignment SLAB DESIGN Chapter 9 of Text and, Chapter 13 of ACI318-02 Introduction ACI318 Code provides two design procedures for slab systems: 13.6.1 Direct Design Method (DDM) For slab systems
Design of Bridges. Introduction. 3 rd to 4 th July 2012. Lecture for SPIN Training at the University of Dar es Salaam
Design of Bridges Introduction 3 rd to 4 th July 2012 1 FUNCTION OF A BRIDGE To connect two communities which are separated by streams, river, valley, or gorge, etc. 2 EVOLUTION OF BRIDGES 1. Log Bridge
NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)
NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:
Handling, Erection and Bracing of Wood Trusses
Handling, Erection and Bracing of Wood Trusses Follow these guidelines for safe installation of Wood Trusses. These guidelines should not be considered to be the only method for erecting and bracing of
SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS
July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional
STEEL BUILDINGS IN EUROPE. Single-Storey Steel Buildings Part 5: Detailed Design of Trusses
STEEL BUILDIGS I EUROPE Single-Storey Steel Buildings Part 5: Detailed Design of Trusses Single-Storey Steel Buildings Part 5: Detailed Design of Trusses 5 - ii Part 5: Detailed Design of Trusses FOREWORD
Overhang Bracket Loading. Deck Issues: Design Perspective
Deck Issues: Design Perspective Overhang Bracket Loading Deck overhangs and screed rails are generally supported on cantilever brackets during the deck pour These brackets produce an overturning couple
ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT
ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load
SEISMIC RETROFITTING TECHNIQUE USING CARBON FIBERS FOR REINFORCED CONCRETE BUILDINGS
Fracture Mechanics of Concrete Structures Proceedings FRAMCOS-3 AEDIFICA TIO Publishers, D-79104 Freiburg, Germany SEISMIC RETROFITTING TECHNIQUE USING CARBON FIBERS FOR REINFORCED CONCRETE BUILDINGS H.
ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R00060057. Lecturer: Jim Cahill
ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R00060057 Lecturer: Jim Cahill 29 th November 2011 TABLE OF CONTENTS SUMMARY 1 MAIN BODY SECTION
Chapter 10 - Scaffolding Systems
Chapter 10 - Scaffolding Systems Contents Chapter 10 - Scaffolding Systems... 10-1 Check and Oil the Pump Jacks... 10-4 Set Pump Jack Brackets... Error! Bookmark not defined. Set Pump Jack Poles... 10-5
Bracing Webs in Trusses that have Dissimilar Configurations
Bracing Webs in Trusses that have Dissimilar Configurations Released April 25, 2006 Issue: Truss Design Drawings (TDD) that are prepared in accordance with ANSI/TPI 1, National Design Standard for Metal
1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona
for Earthen Material and Straw Bale Structures SECTION 70 - GENERAL "APPENDIX CHAPTER 7 - EARTHEN MATERIAL STRUCTURES 70. Purpose. The purpose of this chapter is to establish minimum standards of safety
Firewalls. By Gary Sturgeon, B.Eng., MSc., P.Eng. Technical Services Engineer, CCMPA. w w w. c c m p a. c a 5A-0
By Gary Sturgeon, B.Eng., MSc., P.Eng. Technical Services Engineer, CCMPA 5A-0 This Chapter of the CCMPA Metric Technical Manual has been largely reproduced from Firewalls, A Design Guide, published by
METHOD OF STATEMENT FOR STATIC LOADING TEST
Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents
Mark Cramer Inspection Services, Inc.
Mark Cramer Inspection Services, Inc. 492 Twentieth Avenue, Indian Rocks Beach, FL 34635-2970 (727) 595-4211 Fax (727) 596-7583 Certified Member #12085 American Society of Home Inspectors Construction
Weight Measurement Technology
Kistler-Morse (KM) introduced bolt-on weight measuring systems three decades ago. These devices featured Walter Kistler s invention, the Microcell. Over the years, many improvements were made to the Microcell
SECTION 26 05 49 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS
SECTION 26 05 49 VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes seismic restraints and other earthquake-damage-reduction measures for electrical
WEBSTER ELEMENTARY SCHOOL New Rochelle, New York Evaluation of Collapsed Ceiling Room 204
WEBSTER ELEMENTARY SCHOOL New Rochelle, New York Evaluation of Collapsed Ceiling Room 204 Structural Inspection Report Client: CSArch Architecture Engineering Construction Management 19 Front Street, Newburgh,
Detailing of Reinforcment in Concrete Structures
Chapter 8 Detailing of Reinforcment in Concrete Structures 8.1 Scope Provisions of Sec. 8.1 and 8.2 of Chapter 8 shall apply for detailing of reinforcement in reinforced concrete members, in general. For
National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination
Structural Effective Beginning with the April 2011 The structural engineering exam is a breadth and exam examination offered in two components on successive days. The 8-hour Vertical Forces (Gravity/Other)
Designed and Engineered to Perform
History EARTH CONTACT PRODUCTS, L.L.C., is a family owned company, based in Olathe, Kansas. This company was built upon Don May s U.S. Patented fourth-generation Steel Piering System that has led to the
16. Beam-and-Slab Design
ENDP311 Structural Concrete Design 16. Beam-and-Slab Design Beam-and-Slab System How does the slab work? L- beams and T- beams Holding beam and slab together University of Western Australia School of Civil
Optimum proportions for the design of suspension bridge
Journal of Civil Engineering (IEB), 34 (1) (26) 1-14 Optimum proportions for the design of suspension bridge Tanvir Manzur and Alamgir Habib Department of Civil Engineering Bangladesh University of Engineering
Prepared For San Francisco Community College District 33 Gough Street San Francisco, California 94103. Prepared By
Project Structural Conditions Survey and Seismic Vulnerability Assessment For SFCC Civic Center Campus 750 Eddy Street San Francisco, California 94109 Prepared For San Francisco Community College District
Analysis and Repair of an Earthquake-Damaged High-rise Building in Santiago, Chile
Analysis and Repair of an Earthquake-Damaged High-rise Building in Santiago, Chile J. Sherstobitoff Ausenco Sandwell, Vancouver, Canada P. Cajiao AMEC, Vancouver, Canada P. Adebar University of British
CHAPTER 6 CONSTRUCTION TYPES
CHAPTER 6 CONSTRUCTION TYPES SECTION 601 GENERAL 601.1 Scope. Provisions of this chapter shall govern the classification of construction type by materials and fire resistance of its elements and the use
Steel joists and joist girders are
THE STEEL CONFERENCE Hints on Using Joists Efficiently By Tim Holtermann, S.E., P.E.; Drew Potts, P.E.; Bob Sellers, P.E.; and Walt Worthley, P.E. Proper coordination between structural engineers and joist
Safe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES
HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES 101 Retrofits Required. Pursuant to Section 553.844 553.884, Florida Statutes, strengthening of existing site-built,
Truss. are both simple and A Matsuo Example continuous trusses. The
Girder Bridge A girder bridge is perhaps the most common and most basic bridge. A log across a creek is an example of a girder bridge in its simplest form. In modern steel girder bridges, the two most
FORM DESIGN. easy to work with, and generally available.
Forms play a major role in concrete construction. They give the plastic concrete its shape and hold it until it hardens. Forms protect the concrete, assist in curing it, and support any reinforcing rods
Rigid and Braced Frames
Rigid Frames Rigid and raced Frames Rigid frames are identified b the lack of pinned joints within the frame. The joints are rigid and resist rotation. The ma be supported b pins or fied supports. The
Excerpts from the Canadian National Building Code (NBC)
Excerpts from the Canadian National Building Code (NBC) Reproduced here with Permission of the Copyright Owner, the National Research Council of Canada, Institute for Research in Construction. For more
SECTION 7 Engineered Buildings Field Investigation
SECTION 7 Engineered Buildings Field Investigation Types of Data to Be Collected and Recorded A field investigator looking at engineered buildings is expected to assess the type of damage to buildings.
Chapter 3 DESIGN AND CONSTRUCTION FEATURES IMPORTANT TO SEISMIC PERFORMANCE
Chapter 3 DESIGN AND CONSTRUCTION FEATURES IMPORTANT TO SEISMIC PERFORMANCE To satisfy the performance goals of the NEHRP Recommended Seismic Provisions, a number of characteristics are important to the
Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26
2014 HDR Architecture, 2014 2014 HDR, HDR, Inc., all all rights reserved. Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26 Brandon Chavel, PhD, P.E.,
CASE HISTORY #2. APPLICATION: Piping Movement Survey using Permalign Laser Measurement System
CASE HISTORY #2 APPLICATION: Piping Movement Survey using Permalign Laser Measurement System EQUIPMENT: Dresser-Clark Hot Gas Expander (Turbine), 60-inch Inlet Flange HISTORY: Piping support modifications
[TECHNICAL REPORT I:]
[Helios Plaza] Houston, Texas Structural Option Adviser: Dr. Linda Hanagan [TECHNICAL REPORT I:] Structural Concepts & Existing Conditions Table of Contents Executive Summary... 2 Introduction... 3 Structural
The Base Shear Formula
The Base Shear Formula You will have to do a bit of arithmetic and use a very simple formula known as the base shear formula to determine exactly how many bolts, how much plywood, and how many shear transfer
Engineers, Civil Structural Survey
Engineers, Civil Structural Survey 317 STREET 0 6 3 6 0 886-1966 886-9165 FAX. September 1 1 Mr. Alan Bergren City Manager City of Norwich Broadway, Floor Norwich, 06360 Re: Limited Structural Condition
The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma
The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma Bart B. Barrett, B.S., P.E.1 Kerry S. Lee, M.B.A., P.E., M. ASCE2 Erik L. Nelson, Ph.D., P.E., M. ASCE3
MAE 1033 Structural Assessment & Repair Faculty of Civil Engineering, Universiti Teknologi Malaysia (UTM).
MAE 1033 Structural Assessment & Repair Faculty of Civil Engineering, Universiti Teknologi Malaysia (UTM). The Collapse of Buildings & Duties of a Forensic Engineer (Compiled from various internet-based
Building Condition Assessment: 109-111 North Howard Street Baltimore, Maryland
KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore,
INSTALLATION OF A BAY WINDOW
INSTALLATION OF A BAY WINDOW Installation of a Bay Window These instructions relate to the replacement of an existing bay window or replacement of a straight window with a new bay window, in an opening
ARCH 331 Structural Glossary S2014abn. Structural Glossary
Structural Glossary Allowable strength: Nominal strength divided by the safety factor. Allowable stress: Allowable strength divided by the appropriate section property, such as section modulus or cross
Numerical Analysis of the Moving Formwork Bracket Stress during Construction of a Curved Continuous Box Girder Bridge with Variable Width
Modern Applied Science; Vol. 9, No. 6; 2015 ISSN 1913-1844 E-ISSN 1913-1852 Published by Canadian Center of Science and Education Numerical Analysis of the Moving Formwork Bracket Stress during Construction
Chapter 5 Bridge Deck Slabs. Bridge Engineering 1
Chapter 5 Bridge Deck Slabs Bridge Engineering 1 Basic types of bridge decks In-situ reinforced concrete deck- (most common type) Pre-cast concrete deck (minimize the use of local labor) Open steel grid
STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM
STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM Installed in Pre-engineered Steel Buildings Provides Lowest Cost Construction Method for CORROSIVE AND WET Environments PREFERRED SOLUTIONS, INC.
Architectural Condition Survey
Architectural Condition Survey Santa Fe Railroad / AMTRAK Depot, Lawrence. Kansas for the City of Lawrence, 2002 Survey: (student) PI: William Carswell, Associate Dean, School of Architecture, University
FIRE AND SMOKE PROTECTION FEATURES
CHAPTER 7 FIRE AND SMOKE PROTECTION FEATURES SECTION 70 GENERAL 70. Scope. The provisions of this chapter shall govern the materials, systems and assemblies used for structural fire resistance and fire-resistance-rated
ETABS. Integrated Building Design Software. Concrete Shear Wall Design Manual. Computers and Structures, Inc. Berkeley, California, USA
ETABS Integrated Building Design Software Concrete Shear Wall Design Manual Computers and Structures, Inc. Berkeley, California, USA Version 8 January 2002 Copyright The computer program ETABS and all
RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS
RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS Johnson County Building Officials Association January 2008 Residential Foundation Guideline Foundation designs for one-and two-family dwellings may use
Building Condition Assessment: 215-219 West Lexington Street Baltimore, Maryland
KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore,
