Project Environmental Plan for the CCURV PSDH

Size: px
Start display at page:

Download "Project Environmental Plan for the CCURV PSDH"

Transcription

1 CCURV PSDH Page 1 of 21 Project Environmental Plan for the CCURV PSDH Controlled Copy No LSE PEP - 38 Employer: Project Office Address: John Laing Partnership Highbury Grove HEADING PAGE N o Title, Contents & Authorisation 1-2 Part 1 General Issues 1.1 Purpose and Scope General Statement of Company Policy Project Profile and Scope of Work Management Structure and Responsibilities Environmental Objectives and Targets Communication and Liaison Training 7 Part 2 Environmental Management 2.1 Environmental Conditions of Site Environmental Requirements Key Construction Phases and Environmental Aspects for Consents and Notifications Sir Robert McAlpine Environmental Management System 9 Part 3 Site Specific Controls 3.1 Air Quality & Dust Water Nuisance (Noise & Vibration) Contaminated Ground Ecology Archaeology Material Use / Waste Minimisation Energy Traffic and Logistics Procurement and Supply Chain 16 Part 4 Monitoring and Reporting 4.1 Inspections and Audits Reporting 17 Part 5 Emergency Response 5.1 Definitions Control Measures Reporting 20

2 CCURV PSDH Page 2 of Training 20 Attachments Company Environmental Policy Appendix 1 Responsibilities Matrix Appendix 2 Environmental and Sustainability Objectives and Targets Appendix 3 Training Matrix Appendix 4 Environmental Constraints Plan Appendix 5 Environmental Compliance Schedule Appendix 6 Sustainability Tracking Register Appendix 7 Environmental Incident Log Appendix 8 Site Drainage Plans Appendix 9 AUTHORISATION Rev N o Prepared / Revised By Checked for Content by Regional Environmental Advisor Approved for Use by Project Director / Manager Date 0 Clare Masters Clare Masters Ken Edwards Nov 09

3 CCURV PSDH Page 3 of PART 1 GENERAL ISSUES 1.1 PURPOSE AND SCOPE The scope of the Project Environment Plan (PEP) is to set out the environmental requirements for the Croydon Council Urban Regeneration Vehicle; Public Sector Delivery Hub (CCURV PSDH) construction project as designed and built in line with Sir Robert McAlpine Ltd Environmental Management System and the requirements of the client CCURV PSDH (now referred to as the client and incorporating Croydon Council and John Laing Partnership). This plan covers the environmental compliance requirements as per the company s Environmental Management System and describes the operational plan to meet Sir Robert McAlpine s obligations under current legislation. In addition this plan provides a systematic framework for integrating the sustainability aspects of: Design; Procurement; Site management and logistics; Monitoring and measurement of specific sustainability indicators; The monitoring and review processes that are to be adopted. 1.2 GENERAL STATEMENT OF COMPANY POLICY Sir Robert McAlpine Ltd recognises the need to protect the environment and minimise the environmental impact of its activities. We believe in being a good neighbour on this and other construction projects and that by complying with an environmental management system and taking a positive proactive approach to environmental issues we can enhance the reputation of this project, the firm and the construction industry in general. The company environmental policy applies to this project and is included in Appendix PROJECT PROFILE AND SCOPE OF WORK This PEP covers the scope of works the demolition of the existing Croydon Council facilities at Fell Road in order for the site to be cleared for the delivery of the new PSDH scheme. The proposed scheme is bounded by Fell Road to the South and east, and Mint Walk to the North. The site conditions incorporate a significant level change around the perimeter of the site, for which the project will utilise to provide additional floor height in the Mint Walk wing and to ensure minimal carriageway works with the new ramp position. The proposal will require some re-modelling of aspects of Davis House. The new building will provide new office accommodation for Croydon Council with public access for council services at ground floor. The form of the new building is separated into two separate blocks which step from between five to thirteen storey height linked by internal bridges between the two and a separate link bridge back to the existing grade 2 listed Town Hall. The form of construction comprises of secant piled foundations, reinforced concrete super structure and glazed curtain walling to the external facade

4 CCURV PSDH Page 4 of MANAGEMENT STRUCTURE & RESPONSIBILITIES Project Control Plan LSE-PCP-XXX includes details on key Sir Robert McAlpine project personnel with their individual responsibilities in Section 7.0. It also includes the Management Team Organisation Chart in Appendix 1 and Project Staff Responsibilities Matrix in Appendix 2. As a summary the following applies to personnel with environmental responsibilities: Project Manager Ken Edwards Construction Manager - TBA Environmental Advisor Clare Masters (part time) Design Manager Martin Collis Commercial Manager Mark Andrews Waste Co-ordinator TBA Health and Safety Advisor - Lawrence Parker (part time) Community Relations Manager Bill Bourne (TBC) COSHH Controller TBA Quality Manager- Ian Cumming (part time) Specific Environmental Roles The following responsibilities are assigned. Project Manager The Project Manager (Ken Edwards) is responsible to the Director & Regional Manager. Detailed duties include but are not limited to: Responsible for implementation of the Sir Robert M c Alpine Environmental Policy and Environmental Objectives through the PEP and compliance with Contractual requirements regarding Environmental matters; Approval of the PEP and control measures, and participation in regular reviews of the EMS to ensure its continued suitability and effectiveness; Designate responsibility for environmental control during the Works; Regular meetings with project team members to review environmental matters; Regular reporting to the Employer on environmental matters. Ensure adequate resources are made available. Construction Managers The Construction Manager (TBA) is responsible for implementation of this plan on site with respect to all construction activities and in raising and supporting environmental issues with relevant subcontractors and works staff. Environmental Advisor (full or part time)

5 CCURV PSDH Page 5 of 21 The Environmental Advisor (full time role TBA, part time for pre-construction, Clare Masters) is directly responsible to the Project Manager for the day to day administration of environmental issues. This shall include, but not be limited to: Managing and advising on environmental matters affecting the Project; Implementing the EMS on the project; Carrying out regular internal audits and procedure review on environmental matters; Review and updating of environmental system procedures and method statements; Review and mitigate all environmental impacts of method statements; Record and maintain all environmental matters in accordance with reporting procedures; Promote environmental awareness and training throughout the Contract; Ensure all team members work in accordance with the PEP; Liaise with subcontractors through procurement process and during their activities on site. Liaison with clients, government departments, local authorities, other statutory authorities on environmental matters, as required; Liaison with Community Relations Officer Liaison with the other members of the Sir Robert McAlpine Environmental Team on environmental matters; Reporting to the Regional Environmental Advisor and Project Director on environmental objectives and targets and development of project specific environmental procedures. Maintaining the Sustainability Tracking Schedule. Maintaining and raising awareness of BREEAM credit availability Monitoring against project and BREEAM targets Collection of data and process of information for monthly environmental reporting (including waste stats, fuel use, electricity use, water consumption, noise records, CO 2 figures). Maintaining the timber register. Coordinator of waste documentation and paperwork. Design Manager The Design Manager (Martin Collis) is responsible for the implementation of this plan with respect to all design and engineering activities associated with the development. Duties include: Considering Best Available Techniques (BAT) of environmental engineering in the design. Designing towards achieving environmental objectives and targets. Commercial Manager The Commercial Manager (Mark Andrews) is responsible for ensuring that project environmental requirements are adequately described to subcontractors (with input from the Environmental Team). All Other Project Team Members Liaison with the Environmental Advisor as necessary; To be familiar with the PEP and co-operate in its implementation at all times. To observe all environmental requirements and show a responsibility to the environment. To raise any environmental matters with their immediate supervisor which they consider could lead to improvement. To report all potential or actual environmental risks to their supervisor as soon as possible. To liaise with subcontractors in implementation of the PEP and sustainability objectives. A guidance document identifying site specific roles and responsibilities for environmental management is outlined in the Responsibilities Matrix in Appendix Consultants / Contractors / Design Team The team is comprised of the following organisations: Main Contractor Sir Robert McAlpine Ltd (SRM) Architect EPR Structural Engineer Aecom Services Engineer Aecom Landscape Architects Capita Lovejoy Cost Consultants Arcadis AYH BREEAM Advisor John Laing Partnership

6 CCURV PSDH Page 6 of ENVIRONMENTAL OBJECTIVES AND TARGETS The project team will report against the following targets: BREEAM credit requirements applicable to the construction Construction objectives and targets. Sir Robert McAlpine Ltd Company Environmental Objectives and Targets The Environmental and Sustainability Objectives and Targets for the project are summarised in Appendix 3. The status of Objectives and Targets will be reviewed on a regular basis (and in any event not less than three monthly intervals). 1.6 COMMUNICATION AND LIAISON Sir Robert McAlpine recognises that sustainability is not just about compliance with environmental controls, but also requires positive action to foster co-operation, innovation and continuous improvement. Our approach therefore is one of open communication and recognition of individual effort as we recognise that the training programme, management systems, information and posters and the way in which we deal with people must present a consistent message Internal and Onsite Communications: Sustainability issues and environmental management are to be communicated to staff and subcontractors as soon as starting on the PSDH Project as possible. During the tender stage sub-contractors will be made aware of the specific environmental requirements for working on site and for identifying and dealing with specific environmental issues associated with their work packages. The environmental requirements for the project are outlined in the Volume 2 tender documentation sent out to all subcontractors. General site environmental requirements will be re-iterated during start up meetings and during the initial inductions. Sub-contractor s performance and commitment to sustainability and environmental management will be monitored through the information gathered for the environmental reports. Specific reporting and environmental control requirements will be identified in the environmental method statements when necessary. Toolbox talks will be provided to all site operatives to cover the requirements of the Project Environmental Plan and Procedures. These will be tailored to specific site activities. All management staff will be briefed on the requirements of the Project Environmental Plan and associated Environmental procedures The Project Environmental Plan will be made available on the Project Network Server and 4-Projects extranet. Formal training will be carried out for selected members of the design and construction teams as part of ongoing corporate training Communication with the Client s Sustainability and Environmental Team To be confirmed on direct from John Laing Partnership and the requirements of Croydon Council Communication with the Public A construction hotline number (an 0800 number will be allocated prior to commencement on site) is displayed at local authority offices and around the site s boundaries for information and complaint purposes. All complaints and enquiries are logged. Should a complaint be received that relates to a deviation away from an agreed method of works and has caused substantiated nuisance to the neighbourhood and surrounding businesses and residents then an NCR (non-conformance report) will be raised in line with Sir Robert McAlpine Ltd company procedure AP 25) Liaison with External Parties Liaison will be made on a regular basis with the following external parties: Environment Agency (EA) Environmental Health Officer (EHO) for Croydon Council Thames Water (TW) Representatives from neighbouring offices and library

7 CCURV PSDH Page 7 of TRAINING All personnel on site will receive a site induction which will include basic environmental information. Additionally all staff will receive environmental training appropriate to their role. A training matrix identifying staff and training topics is identified in Appendix 4 and will act as a guide to the delivery of environmental training on the project. This will be updated for the different stages over the project duration and linked to the aspects and impacts risk matrix for the different construction stages. Subcontractors will receive environmental training as appropriate to their level of impact and activity risk on the environment. A toolbox talk will be issued to subcontractors on a regular basis.

8 CCURV PSDH Page 8 of 21 2 PART 2 ENVIRONMENTAL MANAGEMENT 2.1 ENVIRONMENTAL CONDITIONS OF SITE Issue Site History Ground contamination Archaeology Ecology Surface and Ground Water Resources Residential and Commercial areas Permits, Licences and Consents. Specific Considerations and Constraints The site is currently used as council offices with associated car parking. From 1896 to early 1960s the land use was residential with recreational buildings off site. From 1960s the site was used for council offices. There has been significant development of the surrounding areas since Possible contamination in made ground and natural strata, ( 2m bgl) The site is underlain by Thanet Sands overlying white chalk subgroup. Variable thickness of made ground and possibly River Terrace Deposits are also expected to overlie the natural strata. The likelihood of widespread soil contamination is low. The basement construction of the current building would have removed any contaminated soils within the footprint. Residual contaminants if encountered will be restricted to previously unexcavated ground. TBC unlikely to have a high archaeological significance due to previous land use and basement construction No Statutory protected sites within 2km of the site Site is of low ecological value with the exception of scattered trees to the south of the site which have a possibility of providing habitat for some birds and invertebrates. Site is in a Zone 1 Groundwater Protection Zone. No surface water courses, ground water expected to be found below 11m bgl Nearest groundwater abstraction is 167m NW at Surrey Street Pumping Station The overall risk associated with the water environment is considered to be moderate to low. Surrounding area is predominantly commercial offices including the neighbouring Council office buildings and library and various shops and restaurants to the north of the site. TBC a Section 61 may be applied for to cover the demolition and piling works upon discussion with Croydon Council. Referenced Document EPR Stage D report Faber Maunsell / Aecom Geotechnical and Geo-environmental Desk Study Report July 2008 Aecom Stage D Figure 3 Conceptual Geoenvironmental model Existing development Faber Maunsell / Aecom Geotechnical and Geo-environmental Desk Study Report July 2008 MoLAS reports - TBC Capita Lovejoy Public Realm Soft Landscaping Masterplan 4783-T-101 EPR Tree Protection Plan Feb 09, 4783TR02 Rev E Faber Maunsel (Aecom) Phase 1 Habitat Survey Report Feb 09 Aecom Stage D Faber Maunsell / Aecom Geotechnical and Geo-environmental Desk Study Report July 2008 Faber Maunsel (Aecom) External Noise Assessment August 08 Faber Maunsel (Aecom) Air Quality Assessment March 09 Croydon Council Code of Construction Practice 2.2 ENVIRONMENTAL REQUIREMENTS This PEP takes consideration of the following documents; BREEAM Offices 2006 Croydon Council Codes of Practice for Demolition and Construction Sites Considerate Constructors Scheme

9 CCURV PSDH Page 9 of KEY PROJECT CONSTRUCTION PHASES & ENVIRONMENTAL ASPECTS The table below identifies the main construction activities for the initial year of construction and associated environmental aspects. The activity list will be updated as the construction programme progresses, however a complete construction programme can be found on the Project Network Server (P:drive). Activity Timeframe Environmental Aspect Demolition Jan 2010 June 2010 Noise, vibration, dust, waste, contaminaton Piling Works July 2010 Jan 2011 Noise, Waste, Water, Ground Contamination Basement Construction Dec 2010 June 2011 Noise, Waste, Ground Contamination, Water Superstructure Concrete May 2010 Jan 2012 Noise, Waste, Dust, Water runoff External Cladding Sept 2011 May 2012 Noise, Waste Atrium Glazing Nov 2011 March 2012 Noise, Waste, Core Finishes Oct 2011 Sept 2012 Noise, Waste, Main Building CAT A Fit Out Aug 2011 Aug 2012 Waste, Air Quality Main Building CAT B Fit Out Dec 2011 Nov 2012 Waste, Air Quality External works (including soft/hard landscaping) July 2012 Dec 2012 Noise, Water, Waste, Ground Contamination. The environmental impacts and aspects are covered by full environmental risk assessments (ERAs) as per the Sir Robert McAlpine EMS procedure EMP 03 where ERA s are completed for each work package. Further details are in section below. 2.4 CONSENTS AND NOTIFICATIONS Applicable consent and or notification requirements, as well as the information required for obtaining and complying with them will be detailed here when information is available. This is reviewed on a regular basis in conjunction with the review of EMP02 (see section below). 2.5 SIR ROBERT M C ALPINE ENVIRONMENTAL MANAGEMENT SYSTEM Project Control Plan LSE-PCP-145 outlines the Quality Management System procedures and Health & Safety procedures to be implemented. Sir Robert McAlpine Ltd has an ISO14001 certified Environmental Management System. The following Company Environmental Management System Procedures shall be implemented: AP 22 Method Statement AP 22 defines the methodology for the method of preparation, format, presentation, review, revision and administration of method statements in order to control work activities adequately. Environmental risk assessments (as outlined in EMP03, see below) are to be included within method statements to ensure that any potential risks to the environment have been identified and can be eliminated/mitigated by adequate control measures AP 23 Document and Data Control AP 23 defines the system to be used to control all incoming and outgoing documents, along with their archive storage, content, review and disposal. Details are included in the Document Control Method Review completed for each project AP 25 Non-Conformance Control AP25 identifies the procedure for documenting non conformances and non conforming products and services AP 45 Environmental Assessment AP45 defines the system to be used and the items to be considered when carrying out an environmental assessment of construction works for a project. It includes a comprehensive checklist to help ensure that all relevant aspects are adequately addressed.

10 CCURV PSDH Page 10 of AP 46 Performance Measurement and Continuous Improvement AP 46 defines the system to be used to generate sub-contractor and consultant Key Performance Indicators (KPI s) and how they will be used in the SRM Continuous Improvement Program EMP 02 Environmental Legislation EMP02 defines the controls to be adopted for the identification of current environmental legislation relevant to the construction operations. This includes a comprehensive checklist to enable Project Management to assess the impact of pertinent legislation on the works and determine specific action plans. A Register of Environmental Legislation shall be completed by the Environmental Advisor covering legislation associated with (i) Noise & Vibration, (ii) Dust & Air Pollution, (iii) Contaminated Land, (iv) Spoil & Waste, (v) Built Heritage, (vi) Water and (vii) Ecology. It will identify how the legislation affects the Company / Project and what controls and action plans are required to ensure compliance. The Register will be subject to reviews to reflect any changes to legislation as advised by the Company Environmental Manager. It will be kept on the network project drive and issued to the project management team. Surveillances of best practice on site and the specific applicable legislation will take place on a quarterly basis or following legislation updates from the Company Environmental Manager EMP 03 Environmental Risk Assessments EMP03 defines the methods to be used to evaluate the environmental Aspects and Impacts that the project places upon its surroundings during the works. It includes the process of identifying possible preventative measures (and associated residual risk assessments). Environmental Risk Assessments shall be completed by the Environmental Advisor and Package Manager for each work package. Environmental Risk Assessments will be kept on the network project drive and issued to the project management team. In addition to individual work package based environmental risk assessments, a generic register has been developed for the CCURV works to provide a summary of significant environmental aspects and impacts. This will be kept on the network server and made available to subcontractors upon start up to provide an overview of environmental issues and risks EMP 04 Project Environmental Plans EMP04 defines the requirements for the preparation and control of Project Environmental Plans (PEP) (ie:- this document), including subsequent revisions. The Project Environmental Plan is a live document and will be reviewed and amended as necessary during the course of the project, e.g. to take into account of changes to site activities. The layout of this PEP differs from the EMP 04 suggestion although it contains all the required information as per EMP04. The table below indicates which sections of this plan comply with the layout of EMP04: EMP04 Typical Index Content Heading Reference within this Environmental Plan 1.0 Purpose 1.1 Purpose and Scope 2.0 Employer s Environmental Requirements 2.2 Environmental Requirements 3.0 Key Project Environmental Data 2.1 Environmental Conditions of Site 4.0 Contact Details and Responsibilities 1.6 Communication and Liaison 5.0 Environmental Training and Awareness 1.7 Training 6.0 Company Environmental Policy, Objectives and Targets 1.2 General Statement of Company Policy 1.5 Environmental Objectives and Targets 7.0 Environmental Management System 2.3 Sir Robert McAlpine Environmental Management Systems 8.0 Environmental Review and Risk Assessment EMP 03 Environmental Risk Assessment 9.0 Site Specific Environmental Control Procedure 3 Part 3 Site Specific Controls 10.0 Monitoring and Reporting Environmental 4 Part 4 Monitoring and Reporting Matters 11.0 Environmental Preparedness and Emergency 5 Part 5 Emergency Response Planning 12.0 Other Measures 3 Part 3 Site Specific Controls

11 CCURV PSDH Page 11 of 21 The Environmental Management System Procedures are supported by the following Environmental Procedures Health Hazards :- EP 01 Contaminated Ground; EP 02 COSHH; EP 03 Control of Noise; EP 04 Dust Control; EP 05 Wet Concrete; EP 06 Asbestos: EP 07 Waste EMP 06 Emergency Preparedness EMP 06 outlines the procedure and best practice for dealing with environmental emergencies. In particular the document provides guidance on: Planning for an Emergency Storage of Liquids Depot Drainage Spills and Spill Kits Training Waste Dust and Noise The site specific controls for dealing with environmental emergencies and pollution prevention are covered in section 5 (Emergency Response) in this document. All environmental procedures, including this plan, can be found on the Project Network Server (P: drive) under Environment and the folder entitled EMS or 4-Projects extranet local network drive.

12 CCURV PSDH Page 12 of 21 3 Part 3 SITE SPECIFIC CONTROLS The controls described below apply to all personnel associated with the PSDH Project including Sir Robert McAlpine Ltd staff, sub-contractors, suppliers and third parties; and all activities and operations associated with the project. Controls will be defined in more detail as the programme and site layout changes and progresses. 3.1 AIR QUALITY AND DUST Particulates from dust caused during construction along with exhaust emissions from construction plant are the main impacts on air quality. Best Practicable Means (BPM) will be used to ensure that dust does not cause nuisance. Where dust is considered to be a risk during a specific site activity, mitigation measures will be included in the task-specific method statement for the work. Construction plant will be well maintained and operated to minimise emissions to air. The Environmental Advisor will brief operatives on good practice and will carry out regular inspections to ensure that BPM is employed across the project. 3.2 WATER The site is in a Zone 1 Groundwater Protection Zone. Before demolition commences the design team will liaise with the Environment Agency and Thames Water to clarify any implications with the Zone 1 status and the foundation design Foul and Surface Water During construction, best practice measures will be undertaken to ensure that surface and groundwater is managed to avoid risk of pollution. Environment Agency pollution prevention guidelines (PPG s) and guidance issued by CIRIA will be adhered to and communicated to staff as appropriate. These include the following: Fuel, oil and chemicals will be stored in locations away from drains and watercourses and in compliance with the Oil Storage Regulations. Plant and vehicles will be maintained in good working order to prevent oil leaks and drip trays will be used under static plant. Emergency spill kits will be provided in strategic locations around each work area and project personnel will be trained in their use. A site drainage plan identifying the construction/compound drainage runs (and in accordance with PPG 21) will be developed and then posted around the site notice boards and will be available as Appendix 9 for information. This will be based on the Faber Maunsel Proposed Drainage Layout drawing, /CL(5)/ Groundwater It is anticipated that the excavations will encounter perched / shallow groundwater in the superficial deposits and the groundwater table within the White Chalk major aquifer. It is also expected that there will be quantities of groundwater inflow from the base of the excavation. The Environment Agency and Thames Water will be consulted and the necessary consents obtained for any dewatering and abstraction activities. Monitoring and records will be kept of water discharged from excavations Water Monitoring The Environment Team will undertake regular inspections of water management and discharges. Unless otherwise stipulated as a consent condition, the frequency of inspections will be decided by the Environment Team in consultation with the Construction Manager taking account of the specific circumstances of the discharge, the construction activities and the ground and/or weather conditions prevailing at the time. 3.3 NUISANCE (NOISE / VIBRATION)

13 CCURV PSDH Page 13 of 21 Noise and Vibration caused by site activities will be controlled as far as is reasonably practicable so that surrounding residential and commercial receptors are protected from excessive levels arising from the construction process Hours of Work Permitted hours of work throughout the duration of the project are in accordance with the Croydon City Council Code of Construction Practice and Planning Conditions and are restricted to: Monday to Friday Saturday There will be no working on Sunday s with the exception of abnormal deliveries and erecting Tower Cranes. In the event of unusual activities or events that can be anticipated, these will be notified to the relevant EHO and to the relevant sensitive receptors wherever possible. The relevant activities will be determined by agreement with the relevant local authority and will include: Noisy activities, including piling operations Necessary night time, weekend or evening working; Road or footpath closures / diversions and movements of wide loads; Tower crane services and erections; Activities that are deemed to require monitoring by the local authority Noise and Vibration Monitoring Baseline monitoring will be undertaken during enabling works. Historical baseline monitoring results appropriate to the construction zone will be requested from the client. Monitoring will be carried out during mobilisation of the first work packages to compare with the enabling works results. Noise and Vibration monitoring will be carried out regularly, as well as in response to requests/complaints/section 61 requirements and / or any new activities that have the potential to generate significant noise. (NB: All complaints and requests are recorded and dealt with as quickly as possible) Monitoring will be carried out on the construction site boundary. Positions to be monitored will be assessed with regards to the works currently being carried out on site and their proximity to sensitive receptors. Monitoring is carried out by a competent person trained in the use of the equipment and with an understanding of the relevant legislation, action levels and potential environmental issues related to the creation of noise and vibration. Equipment used in monitoring will include Type 1 integrated hand held noise monitor, permanent type 1 sound level meters and a Vibrok Standard Vibration Model for vibration sampling. Equipment is calibrated in accordance to Procedure AP29. The Vibrok Vibration Model will be calibrated off site by the manufacturers on a yearly basis. The hand held and continuous sound level meter will be calibrated before each use with a calibrator. These devices also undergo periodic off-site calibration checks in accordance with the manufacturer s recommendations. Recorded results will be downloaded from the equipment to the project networked drive (within the Environment folder) and collated into tabled databases. These results will be made available upon request and in monthly reporting. Best practical means will be employed at all times to ensure that all aspects of the works minimise potential noise and vibration as described in the Construction Code of Practice. 3.4 CONTAMINATED GROUND The likelihood of widespread contamination is expected to be low given the extent of the previous development s basement and historical site use. However environmental management practices will be adopted to prevent potential impacts associated with cross contamination, segregation of potentially contaminated hot spots, dust generation and surface water run off as examples Monitoring Method statements that cover excavated material will include the possibilities of finding contamination and the mechanisms for dealing with it.

14 CCURV PSDH Page 14 of 21 Testing and analysis will be carried on samples of excavated materials as defined by the Geotechnical and Geo-environmental Desk Study Reports and the Ground Investigations reports by Faber Maunsel / Aecom. The test results will determine if the excavated material are contaminated and will need appropriate disposal (in line with the requirements of Duty of Care and the Site Waste Management Plan) or if the excavated material is classified as uncontaminated it can be either re-used or sent off site. 3.5 ECOLOGY An Environmental Impact Assessment and subsequent ecological surveys have been carried out on the site and near vicinity. Reference is made to the Faber Maunsell Phase 1 Habitat Survey February 2009 which identifies that the site is of low ecological value with the exception of the scattered trees which are designated to be kept throughout the development. These will be identified on the Environmental Constraints Plan Scope of Ecological Issues Trees to be retained on site are indicated by the drawing Tree Protection Plan 4783-TR-02. These will be protected throughout the duration of the works. Best practice will be carried out including: Keeping vehicles and plant away from trees and vegetation to be protected Temporary fencing and demarcation around protected tress Materials and spoil will not be stored within protected area or under tree canopy No cutting or damage to roots greater than 25mm in diameter within the protected area Any backfilling to be carried out with care to ensure roots are not damaged and compact backfill lightly Ecological Monitoring Regular monitoring will be undertaken throughout the construction phase of the project to ensure that impacts on ecology are minimised. Method statement briefings and toolbox talks will be provided to all personnel involved in activities that have the potential to have a significant ecological impact. In the event that a protected species or habitat is discovered during construction, works will stop and expert advice will be sought on how to proceed. This will be treated as an environmental near miss or incident and be reported to the client and statutory bodies, as required. 3.6 ARCHAEOLOGY Following advice from MoLAS and based on findings and recommendations from their Archaeological report (TBC) it will be determined what level of surveys are required given that the project is on a previously developed site. However, if archaeological remains are discovered during construction, works will stop and expert advice will be sought on how to proceed. This will be treated as an environmental near miss or incident and be reported to the client and statutory bodies, as required. 3.7 MATERIAL USE / WASTE MINIMISATION Specification In the design stages studies will be carried out into the Embodied Energy of the components of the project. Additional work may be carried out to estimate and calculate the carbon savings associated with different design solutions and compared with other similar size projects. Further work will be carried out in the next stage of design to ensure that the materials specified and procured have as low embodied impact as feasibly possible (maintaining the required structural requirements and enabling the project to be completed within the set built program). The Sustainability Tracker Schedule (Appendix 7) will be used to record material considerations and discussions with suppliers and the design team and client to obtain materials that have environmental or sustainability benefits such as; Low embodied energy; Recycled content; The ability to be easily demountable and or reused / recycled after end of design life; Minimal transportation to site;

15 CCURV PSDH Page 15 of 21 Minimal wastage in production, transportation to site and in construction; Sourced from sustainable sources with chain of custody documentation (especially relevant for timber products) Recycled Content There is potential to use WRAP Net Waste Toolkit for Recycled Content to determine the opportunities for increasing the recycled content of materials from good to best practice and gaining a Recycled Content by Value for the PSDH project Site Waste Management Plan A Site Waste Management Plan has been developed as a separate stand alone document subject to its own review process. This is in accordance with the DEFRA Guidance, Site Waste Management Plan Regs (2008), the Sir Robert McAlpine Procedure EMP 05 and the requirements of the client and Croydon City Council. Opportunities for designing out waste in the first instance, using materials with a recycled content, reuse and recycling will be progressed through workshops with the design team and subcontractors. Monthly waste returns will be complied for all waste produced on site. 3.8 ENERGY The project will actively strive to monitor and minimise energy during the construction phase. This will be achieved through: Regular maintenance of plant to ensure equipment is running efficiently, minimizing nuisance and avoiding pollution. Switching off plant when not in use rather than running idle. Use of energy efficient lighting. Investigation into potential for renewable energy units for the welfare units and temporary offices such as solar thermal units for hot water Procuring energy saving office equipment. Training of office staff and site operatives in energy efficiency Monitoring Where possible, meters will be installed to monitor energy used in the offices and welfare cabins. Contractors and sub-contractors will record their delivery mileage and fuel uses which can be converted into associated CO TRAFFIC AND LOGISTICS The site will receive deliveries, materials and plant in accordance with the Construction Logistics Plan. Wheel wash facilities will be located in appropriate positions at the site exits and their location will be indicated in the Environmental Constraints Plan as identified in Appendix PROCUREMENT AND SUPPLY CHAIN Procurement Strategy The Environmental and Sustainability requirements of the CCURV are included in the Environmental section of the Volume 2 of the Sub Contracts. The attendance schedules will also be amended appropriate to the environmental issues associated with a particular package. The main environmental issues associated with each work package will be identified on a work package environmental schedule and made available to the project Commercial Team. Sub-Contractors are asked to complete an Environmental Compliance Schedule (Appendix 8) at tender stage to indicate their environmental management systems and contributions to environmental issues. Post tender, Sub-Contractors are also asked to complete Package Waste Schedules as part of the SRM Site Waste Management Plan. This indicates the type and quantity of waste likely to be produced on site.

16 CCURV PSDH Page 16 of 21 Environmental and Sustainability requirements and issues will be discussed in the Post Tender Interviews and the actions and responses minuted within those meetings. A member of the Environmental Team will be present where appropriate Supply Chain and Material Choice It is recognised that those with a responsibility for supply, specifying and procurement are required to work together to identify options and seek alternatives for consideration and evaluation. Potential areas for more sustainable alternatives include: Alternative suppliers, including more proven ethical supplier Alternative technical specifications, including more easily recycled or dismantled for recovery at end of life Alternative material content including higher recycled content Alternative performance specifications Alternative material sources Alternative construction / installation methods Alternative transport requirements Discussions with the design team and client will identify options for various work packages and materials and the outcomes will be investigated by the relevant members of the team (Package Manager s, Sub-Contractors, Commercial department)

17 CCURV PSDH Page 17 of 21 Part 4 MONITORING AND REPORTING 4.1 INSPECTIONS AND AUDITS The following audits and monitoring will occur on a regular basis and as required: Regular site surveillances to check environmental good practice & compliance with EMS; Regular surveillances of sub contractors methods and processes (including supply chain audits) by SRM; Compliance audits and inspections by Client Environment Team; In-house BREEAM audits to ensure credits have been maintained; & National Considerate Constructors Scheme audits. The Non Conformance Report (NCR) process will be used when this PEP has not been complied with or for a breach of recognised best practice. 4.2 REPORTING Sub-Contractor Reporting Sub-contractors are required at tender stage to agree to report monthly, as a minimum on: Conformance with the site waste management plan. Conformance with the Considerate Constructors Scheme Site Energy usage, Transport Energy usage, modes of transport, weights consigned Any work package specific requirements The information supplied by the sub-contractors will be complied in the monthly environmental reports which will in turn comprise of: Any incidents or NCR s raised Liaison with external parties Key environmental issues Environmental data noise, vibration & dust monitoring results - Energy consumption & CO 2 emissions from site - Fuel consumption & CO 2 emissions for transportation - Waste volumes & disposal routes Client and External Party Reporting To be developed following discussion with John Laing Partnership SRM and Head Office Monthly Reporting Monthly reports will be issued to the Regional Environmental Advisor typically on the following topics which are then sent to SRM head office; EA Interaction and incidents reported Environmental Incidents Not Reportable to EA Training Carried Out; Update on Company Environmental Objectives ; Waste figures and quantities removed from site with destination Total Gas / Electricity / Water used (including site and offices); Type and Quantity of Materials brought to site with a Recycled Content; Good Practice / Ideas Being Adopted. Environmental KPIs (as part of the SRM Quality reporting system- AP46) will be assessed monthly for each subcontractor by the Package Manager with assistance from the Environmental Team. The KPI score will be assessed by using the environmental criteria included on the Company KPI database and a combination of weekly site surveillances, site observations and compliance with the requirements of this PEP. Internal monthly reports will include a summary of inspections, surveillances and nuisance monitoring reports. Nuisance monitoring reports including the downloaded data from monitoring equipment will be saved onto the Project server and made available to the client on a regular basis Sustainability Tracking Schedule The Sustainability Tracking Schedule (Appendix 7) records the sustainability ideas considered by the team throughout design, procurement and construction. It records the idea / suggestions environmental and sustainability benefit as well as any financial implications and whether there are barriers to

18 CCURV PSDH Page 18 of 21 implementing it. Ideas which are not implemented or taken forward will still be recorded for future reference. Where ideas present alternative solutions or materials which would appear to offer potential for a more sustainable solution, a shortlist of alternatives can be prepared. Depending on the work package this may be done in conjunction with the suppliers and sub contractors. Where the alternatives offer disadvantages that are likely to be a significant departure from the design/technical specification, the option may be discounted at this stage, for example, a recycled product that will not meet the strength or aesthetic requirements. The potential technical and commercial risks associated with the more sustainable options should be identified, and recommended alternatives should be proposed for further consideration. Issues which require a more thorough explanation will be subject to a lessons learnt exercise which will be linked to the Tracking Schedule. The Sustainability Tracker will be reviewed and updated on a regular basis following on from internal meetings and discussions. The Sustainability Tracker can be found on the Project Network Server (S: drive) within the Environment folder.

19 CCURV PSDH Page 19 of 21 Part 5- EMERGENCY RESPONSE The Environmental Emergency Response Controls are set out to; Establish the emergency response management procedure for the CCURV project. Outline the controls for any uncontrolled spillages or unforeseen emissions or events which effect 3 rd Parties. State the measures applicable to the project under the requirements of company procedure EMP 06 Emergency Preparedness. Ensure all project activities comply with applicable statutory United Kingdom and European Legislation, the Code of Construction Practice, and client requirements and statutory approvals including the Section 106 Agreement and Planning Conditions. 5.1 DEFINITIONS For the purpose of implementing the PEP the following definitions apply. Incident: An uncontrolled and unexpected release of a substance with the potential to pollute air, land and water resources but that can be contained and mitigated against using on-site equipment. Emergency incident: An incident where the effects of the event cannot be controlled (e.g. breakout from processes involving bentonite or large spillages of hazardous materials) and outside assistance from external bodies (Environment Agency) is required to bring it under control. Major incident: A situation where any of the following have occurred; An emergency incident A breach of legislation is identified by Sir Robert McAlpine Ltd, client or third parties. Enforcement action is issued by a regulator (e.g. a section 60 notice) 5.2 CONTROL MEASURES The following control measures will be adopted as illustrated in the flow chart below (drawing 1, 5.2) Sensitive receptors and pollution prevention measures are illustrated in the Environmental Constraints Plan (Appendix 5). When an incident is able to be controlled by facilities on site, and no intervention is required from a third party or a statutory authority then controls should be implemented, the incident cleaned up and reported in the site diary. All incidents will be recorded. 5.3 REPORTING Where an environmental incident occurs that has been dealt with in a manner which follows best practice and poses no further threat to the environment an entry will be made in the environmental incident log (Appendix 8) to record the issue. The environmental incident log will also be used to identify any trends in environmental incidents. A non-conformance report shall also be raised in accordance with company procedure AP25. The NCR should report the following: Date & Time of incident Works involved & responsible sub-contractor (s) Site location of incident Incident details (including type) Nearby receptors (drains, water run-off sumps, watercourses) Root causes Notified of incident & SRM employee notified Third parties contacted Remediation measures and any preventative actions Where an uncontrolled incident is classed as an emergency or a major incident the project Environmental Manager may wish to investigate the root causes, communication systems and issue a lessons learnt memo to the workforce concerned in addition to any NCR s that may have been raised. Where remedial works to contain an incident dictate that the works may run past consented working hours, the Environmental Health Officer will be contacted as soon as practically possible to inform them of the variation.

20 CCURV PSDH Page 20 of 21 Appropriate spill materials will be stored on site their position identified by signs. Other required emergency equipment will be stored on site and their position identified by posters and marked on drawings. (Environmental Constraints Plan, Appendix 5) Sub-contractors undertaking refuelling activities or using substances with the potential to pollute will be required to have spill materials available for use should a spill occur. Training should be given to these sub contractors on spill control measures. This procedure also relates to environmental emergencies relating to complaints raised from 3 rd parties that involve the statutory authorities whereby the NCR process will be followed. 5.4 TRAINING Training will be given on the emergency response procedure to sub-contractors as soon as possible to their commencement on site. Specific training on the use of spill kits will be given as appropriate. Spill control procedures and the adequacy of training will be tested by staging drills on a periodic basis and recording the findings on a surveillance register. Tool box talks will be given by the sub-contractor s foreman or works manager or by the Project Environmental team. This will be assessed depending on the works package and the stage of the project and the associated environmental risks present. Training records will be copied to the Environment Manager and HS3 forms will be completed for record keeping.

21 Drawing 1, Section 5.2 Environmental Incident Flow Chart M C Alpine Environmental Management System LSE Doc N o LSE-PEP-38 CCURV PSDH Page 21 of 21 Identify Problem & Stop Work Protect sensitive areas Apply Health & Safety controls (E.g. remove fire risk) Contain the spillage by bunds Treat the source of the spillage & implement control actions Can spillage be dealt with on site? NO? YES? Activate Emergency Response Procedure/notify stat. bodies Demarcate area & apply absorbents Clean up & reinstate area to previous state Record incident in Environmental Incident Log or site diary & notify Environmental Manager Ensure used spill materials are disposed of correctly with full duty of care. If required, await assistance prior to implementation of remedial action Demarcate area & apply absorbents Clean up & reinstate area to previous state Report Incident to Environmental Manager / Project Manager Raise NCR Record incident in Environmental Incident log

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot Construction Management Statement Residential development at Bywell House, St Mary s Hill, Ascot Parking of Vehicles of Site Personnel, Operatives and Visitors Site staff, visitors to the development and

More information

PROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON. Construction Management Plan

PROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON. Construction Management Plan PROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON Construction Management Plan May 2013 CONTENTS Page No: 1.0 INTRODUCTION 1 2.0 PROJECT ORGANISATION AND RESPONSIBILITIES 2 2.1 Client

More information

APPENDIX 4. Risk Tables

APPENDIX 4. Risk Tables APPENDIX 4 Tables Preliminary Qualitative Criteria The qualitative risk assessment criteria have been developed to identify key risks to the environment, society, heritage and business reputation. The

More information

1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY

1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY 1. GENERAL STATEMENT OF COMPANY HEALTH, SAFETY AND ENVIRONMENTAL POLICY Dumfries Timber Co. Ltd. is committed to comply with our legal duties in order to provide a safe and healthy working environment

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Plan POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN 1. Introduction This Pollution Incident Response Management Plan (PIRMP) has been prepared to describe the processes

More information

Construction Management Statement. Introduction. Contents

Construction Management Statement. Introduction. Contents Construction Management Statement Project Name Dee Point Primary School Introduction On all Morgan Sindall projects, the safety and welfare of all is of paramount importance. This document concentrates

More information

CHAPTER 24: ENVIRONMENTAL MANAGEMENT

CHAPTER 24: ENVIRONMENTAL MANAGEMENT Central Eyre Iron Project Environmental Impact Statement CHAPTER 24: ENVIRONMENTAL MANAGEMENT CHAPTER 24 ENVIRONMENTAL MANAGEMENT COPYRIGHT Copyright Iron Road Limited, 2015 All rights reserved This document

More information

VICTORIAN GOVERNMENT DEPARTMENT ENVIRONMENTAL MANAGEMENT SYSTEM MODEL MANUAL

VICTORIAN GOVERNMENT DEPARTMENT ENVIRONMENTAL MANAGEMENT SYSTEM MODEL MANUAL MODEL FINAL VERSION 1, MARCH 2003 ACKNOWLEDGMENTS This Manual is based on Environment Australia s Model EMS 1 and has been adapted for use by Victorian Government agencies by Richard Oliver International.

More information

Pollution & Noise from Demolition & Construction Sites

Pollution & Noise from Demolition & Construction Sites CONTROL OF Pollution & Noise from Demolition & Construction Sites N oi se Co ns tru ct io n MAY 2008 THE LONDON BOROUGH 3 CONTENTS Part 1 Introduction Page 1. Background 4 2. Purpose of the code 5 3.

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan This environmental management plan outlines Red Bus Services objectives and strategies for protecting the environment. This plan sets out how Red Bus Services intends to comply

More information

SMS0045 Construction Health and Safety Policy and Procedures

SMS0045 Construction Health and Safety Policy and Procedures SMS0045 Construction Health and Safety Policy and Procedures March 2015 Version 8 Please note that for projects utilising a CDM Co-ordinator under the transitional arrangements of CDM 2015 (between 6 April

More information

ANNEX 2 Emergency / Pollution Incident Response Plan

ANNEX 2 Emergency / Pollution Incident Response Plan ANNEX 2 Emergency / Pollution Incident Response Plan Volume 5 of 5 Appendix 21.1 Annex 2 EPIRP Page 1 of 9 1 WIND FARM CONSTRUCTION ENVIRONMENTAL EMERGENCY / POLLUTION RESPONSE PLAN... 3 1.1 Policy...

More information

SAFETY and HEALTH MANAGEMENT STANDARDS

SAFETY and HEALTH MANAGEMENT STANDARDS SAFETY and HEALTH STANDARDS The Verve Energy Occupational Safety and Health Management Standards have been designed to: Meet the Recognised Industry Practices & Standards and AS/NZS 4801 Table of Contents

More information

Proposed (Concrete Cutting And Drilling) Environmental Management Plan

Proposed (Concrete Cutting And Drilling) Environmental Management Plan SAMPLE ENVIRONMENTAL MANAGEMENT PLAN This EMP is designed for (Concrete Cutting and drilling), however you may insert your business activities with only minor changes needed. This EMP should become part

More information

13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM

13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM 13 ENVIRONMENTAL AND SOCIAL MANAGEMENT SYSTEM This ESIA has identified impacts (both positive and negative) to the physical, natural and socio-economic environments, as well as to community and worker

More information

Pollution Incident Response Plan

Pollution Incident Response Plan Pollution Incident Response Plan Introduction Schmidt Quarries is committed to ensuring all aspects of our quarrying activities comply with the environmental legislative requirements in NSW. This Pollution

More information

Site Layout & Traffic Plan

Site Layout & Traffic Plan Location Site address: Norbury Manor Business Enterprise College, Kensington Avenue, Thornton Heath, Croydon CR7 8BT. The new block will be constructed on the existing hard play area. The construction

More information

Pollution Incident Response Management Plan (PIRMP)

Pollution Incident Response Management Plan (PIRMP) Pollution Incident Response Management Plan (PIRMP) For NSW Ports For Construction of Berth 103 Stage 2 Extension WATERWAY CONSTRUCTIONS PTY LTD ABN 74 061 311 395 Po Box 290, Annandale NSW 2038 TELEPHONE:

More information

Environmental Site Inspection Checklist

Environmental Site Inspection Checklist Note : This form is designed for general use and may not be exhaustive. Modifications and additions may be necessary to suit individual projects and to address specific environmental issues and associated

More information

COMPANY NAME. Environmental Management System Manual

COMPANY NAME. Environmental Management System Manual Revision No. : 1 Date : DD MM YYYY Prepared by : Approved by : (EMR) (Top Management) Revision History Revision Date Description Sections Affected Revised By Approved By Table of Content 0.0 Terms and

More information

Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue

Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority

More information

SPECIFICATION NET LINE 1 - Wilkinson Street Diamond Crossing (WSDC) re-ballast

SPECIFICATION NET LINE 1 - Wilkinson Street Diamond Crossing (WSDC) re-ballast General Requirements: The existing fixed diamond crossing at the Armstrong Way / Wilkinson Street junction (NG7 7NW) has become contaminated with material from roadway run-off and requires re-ballasting

More information

Guideline for preparing an Environmental and Social Management Plan

Guideline for preparing an Environmental and Social Management Plan Guideline for preparing an Environmental and Social Management Plan NZ Transport Agency www.nzta.govt.nz Version 1: April 2014 ISBN 978-0-478-41934-4 (online) Copyright information This publication is

More information

How to comply with your environmental permit

How to comply with your environmental permit How to comply with your environmental permit 1 How to comply with your environmental permit We are the Environment Agency. We protect and improve the environment and make it a better place for people and

More information

Environmental guidelines for preparation of an Environment Management Plan

Environmental guidelines for preparation of an Environment Management Plan Environmental guidelines for preparation of an Environment Management Plan Environment Protection Authority MAY 2013 Australian Capital Territory, Canberra 2013 This work is copyright. Apart from any use

More information

Health, Safety and Environment Management System

Health, Safety and Environment Management System Health, Safety and Environment Management System For Bridgeport Energy Ltd Level 7, 111 Pacific Highway North Sydney 2011 June, 2010 DOCUMENT CONTROL Title: Document Number: Health, Safety and Environmental

More information

R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN

R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN LEND LEASE BUILDING PTY LIMITED ABN 97 000 098 162 R8000 NEW AIR COMBAT CAPABILITY (NACC) FACILITIES PROJECT, RAAF BASE WILLIAMTOWN HAZARDOUS SUBSTANCES DANGEROUS GOODS MANAGEMENT PLAN 3/12/2015 Revision

More information

THIS PAGE INTENTIONALLY LEFT BLANK

THIS PAGE INTENTIONALLY LEFT BLANK THIS PAGE INTENTIONALLY LEFT BLANK Construction Traffic Management Plan 2 Contents 1. Introduction... 4 1.1 Conditions of Consent... 4 2. Goals of the CTMP... 6 2.1 Objectives... 6 2.2 Predicted Construction

More information

ENVIRONMENTAL ASPECTS REGISTER (ISO 14001)

ENVIRONMENTAL ASPECTS REGISTER (ISO 14001) ENVIRONMENTAL ASPECTS REGISTER (ISO 14001) 1. Scope The scope of this Environmental Aspects Register covers the following operational areas: Aberdeen Region (A); Cumbernauld Region (C); Warrington Region

More information

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS Business Procedure HS Contract Management Document Number OHS-PROC-136 This document applies to the following site(s): Rockhampton Office Brisbane Office Tarong Site Barron Gorge Hydro PS Kareeya Hydro

More information

CONSTRUCTION SEQUENCE & PROGRAMME

CONSTRUCTION SEQUENCE & PROGRAMME CONSTRUCTION SEQUENCE & PROGRAMME 2 CONTENTS 1.0 Introduction 7 2.0 Key activities 8 2.1 Airport related activities 2.2 Construction of new roads and accesses 2.3 Earthworks zone a 2.4 Earthworks zone

More information

CONTRACTOR SAFETY MANAGEMENT PROCEDURE

CONTRACTOR SAFETY MANAGEMENT PROCEDURE CONTRACTOR SAFETY MANAGEMENT PROCEDURE Version 1.0 TRIM file number Short description Relevant to Authority Responsible officer Responsible office Date introduced July 20, 2015 Date(s) modified June 11,

More information

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES INTRODUCTION What is a Construction Management Plan? The City of Vincent requires careful management of construction involving excavation and retention

More information

Development proposals will require to demonstrate, according to scale, type and location, that they:-

Development proposals will require to demonstrate, according to scale, type and location, that they:- Appendix 2 : Relevant Development Plan Policies Angus Local Plan Review 2009 Policy S1 : Development Boundaries (a) Within development boundaries proposals for new development on sites not allocated on

More information

Environmental Incident Response Procedure. Newcastle Gas Storage Facility Document Number: NGSF-PSV-NAS-EN-PLN-0024

Environmental Incident Response Procedure. Newcastle Gas Storage Facility Document Number: NGSF-PSV-NAS-EN-PLN-0024 Environmental Incident Response Procedure Newcastle Gas Storage Facility Document Number: NGSF-PSV-NAS-EN-PLN-0024 Environmental Incident Response Procedure Document Number: NGSF-PSV-NAS-EN-PLN-0024 Version:

More information

PPG21. Pollution Prevention Guidelines. pollution incident response planning: PPG 21. 1. Introduction

PPG21. Pollution Prevention Guidelines. pollution incident response planning: PPG 21. 1. Introduction PPG21 February 2004 Environmental Alliance working together Pollution Prevention Guidelines pollution incident response planning: PPG 21 These guidance notes have been drawn up to assist those developing

More information

CONSTRUCTION TRAFFIC MANAGEMENT PLAN Issue 2, V5, 11/11/13

CONSTRUCTION TRAFFIC MANAGEMENT PLAN Issue 2, V5, 11/11/13 Note: Please refer to the end of this document for guidance notes about completing this form Q1. What is the full postal address of the site? Your response Q2. Planning reference and revision number (if

More information

Demolition & Construction Management Plan

Demolition & Construction Management Plan Demolition & Construction Management Plan 72 76 Cadogan lane SW1 Demolition & Construction Management Plan Issue Date: March 2013 Contents: 1.0 Introduction 1.1 Objectives of the Plan 1.2 Project Overview

More information

WASTE Application Form - Dublin Waste to Energy SECTION J ACCIDENT PREVENTION & EMERGENCY RESPONSE

WASTE Application Form - Dublin Waste to Energy SECTION J ACCIDENT PREVENTION & EMERGENCY RESPONSE SECTION J ACCIDENT PREVENTION & EMERGENCY RESPONSE Describe the existing or proposed measures, including emergency procedures, to minimise the impact on the environment of an accidental emission or spillage.

More information

Birmingham City University / Students Union Aspects and Impacts Register. Waste. Impacts description

Birmingham City University / Students Union Aspects and Impacts Register. Waste. Impacts description Birmingham City University / Students Union and Impacts Register Waste Production of non - hazardous waste Production of hazardous waste Storage of non - hazardous waste Potential for waste to be disposed

More information

ENVIRONMENTAL POLICY & MANAGEMENT SYSTEM GUIDE

ENVIRONMENTAL POLICY & MANAGEMENT SYSTEM GUIDE ENVIRONMENTAL POLICY & MANAGEMENT SYSTEM GUIDE 1 Statement of Intent Corps Security aims to create and maintain through staff awareness, the highest level of environmental responsibility. We regard the

More information

Environmental Management System

Environmental Management System Environmental Management System Heron Island Research Station (HIRS) Environmental Noise Program 1. Scope The Environmental Noise Program is limited to the following noise sources: Machinery owned by the

More information

CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP)

CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP) CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP) [Colston Budd Hunt & Kafes Pty Ltd AS AMENDED BY City of Sydney] 23 March 2010 1. PREAMBLE 1.1 This document constitutes the Demolition and Traffic Management

More information

Howard Primary School Construction Management Plan

Howard Primary School Construction Management Plan 2.1 Introduction Howard Primary School Construction Management Plan The Howard Primary school project covers the construction of a new three storey block next to a live school and includes alterations

More information

Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan

Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan Triton Knoll Offshore Wind Farm Limited Electrical System Outline Traffic Management Plan October 2014 RWE Innogy UK Triton Knoll TMP Copyright 2014 RWE Innogy UK Ltd All pre-existing rights reserved.

More information

Environmental Guidelines for Preparation of an Environmental Management Plan

Environmental Guidelines for Preparation of an Environmental Management Plan 2013 Environmental Guidelines for Preparation of an Environmental Management Plan Environmental Management Division Environmental Protection Agency 3/13/2013 ENVIRONMENTAL GUIDELINES FOR PREPARATION OF

More information

WHS Contractor Management Procedure

WHS Contractor Management Procedure Wudinna District Council 1. Overview Wudinna District Council as part of its commitment under its Policy recognises its obligation to: Ensure, so far as is reasonably practicable, the health and safety

More information

BEHANS LAND RESTORATION LIMITED RESTORATION OF FORMER QUARRY BLACKHALL, CO. KILDARE OUTLINE CONTINGENCY PLAN MAY 2008

BEHANS LAND RESTORATION LIMITED RESTORATION OF FORMER QUARRY BLACKHALL, CO. KILDARE OUTLINE CONTINGENCY PLAN MAY 2008 BEHANS LAND RESTORATION LIMITED RESTORATION OF FORMER QUARRY BLACKHALL, CO. KILDARE OUTLINE CONTINGENCY PLAN MAY 2008 JBA Prepared by : John Barnett and Associates / SLR Consulting 7 Dundrum Business Park

More information

Galloper Wind Farm Project. Traffic Management Plan May 2013 Draft v1 Document Reference GWF/TMP/100513. Galloper Wind Farm Limited

Galloper Wind Farm Project. Traffic Management Plan May 2013 Draft v1 Document Reference GWF/TMP/100513. Galloper Wind Farm Limited Galloper Wind Farm Project Traffic Management Plan May 2013 Draft v1 Document Reference GWF/TMP/100513 Galloper Wind Farm Limited Document title Galloper Wind Farm Project Traffic Management Plan Status

More information

Construction Management Plan Template

Construction Management Plan Template Plan Template Planning Permit Number:... Date Planning Permit Issued:... Approval Stamp (Office Use only): Standard Plan Template Project details Company Operational Details.. Directors Name Company Name

More information

University Arms Hotel, Cambridge

University Arms Hotel, Cambridge Traffic Management Plan For University Arms Hotel, Cambridge Prepared By: James Batterbee Number: M1342 / Rev B Date: 29 th August 2014 CONTENTS: (1) INTRODUCTION (2) VEHICLE ACCESS & EGRESS AND PEDESTRIAN

More information

Generic ISO 14001 EMS Templates. User Manual

Generic ISO 14001 EMS Templates. User Manual Generic ISO 14001 EMS Templates (ISO 14001 : 2004 version) User Manual ACT PLAN CHECK DO September 2005 Generic ISO 14001 EMS Templates User Manual Contents Contents of this User Manual ISO 14001 Environmental

More information

Communication of Health and Safety Policy and Information

Communication of Health and Safety Policy and Information Modules 1 4 1. Communication of Health and Safety Policy and Information 2. Allocation of Responsibility/Accountability for Health and Safety 3. Purchasing Controls 4. Contractors Communication of Health

More information

Hazard/Incident Recording, Reporting and Investigation

Hazard/Incident Recording, Reporting and Investigation Hazard/Incident Recording, Reporting and Investigation Power and Water Corporation Procedure 1 Purpose... 1 2 Scope... 1 3 References... 2 4 Roles and Responsibilities... 2 5 Definitions... 6 6 Records...

More information

SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING

SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING 1 TABLE OF CONTENTS 1.0 Introduction and Purpose 3 2.0 Description of Work 3 3.0 Site Supervisor/Foremen Responsibilities 4 4.0 Equipment

More information

Wellington Inner City Improvements National War Memorial Park (Pukeahu) Certification Review

Wellington Inner City Improvements National War Memorial Park (Pukeahu) Certification Review Wellington Inner City Improvements National War Memorial Park (Pukeahu) Air Quality (Dust) Certification Review 22 November 2012 [CAQMP1 TR] Prepared in association with: Document produced by: Apecx PO

More information

Devonport EfW CHP Facility. CEMP Proposal for Non Destructive Testing Activities. 1. Introduction

Devonport EfW CHP Facility. CEMP Proposal for Non Destructive Testing Activities. 1. Introduction Devonport EfW CHP Facility CEMP Proposal for Non Destructive Testing Activities. 1. Introduction This application is issued in compliance with the principles of the approved Construction Environmental

More information

Principal Designer Guidance

Principal Designer Guidance Principal Designer Five or more employees 1 CONTENTS INTRODUCTION 3 Further reading / additional resources 3 QUESTION 1: POLICY AND ORGANISATION 4 4 4 QUESTION 2: ARRANGEMENTS/PROCEDURES FOR HEALTH AND

More information

Construction Site Set Up Requirements

Construction Site Set Up Requirements Process Code Number Revision COP A 035 B Document Title Construction Site Set Up Requirements B 1/11/10 SRC SAT DH Final A 1/10/10 SRC MI Draft comment Rev. Date Prepared Reviewed Approved Detail/Comment

More information

THE TOWN AND COUNTRY PLANNING ACT 1990 Grant of Planning Permission

THE TOWN AND COUNTRY PLANNING ACT 1990 Grant of Planning Permission Civic Offices Havant Hampshire PO9 2AX Tel (023)9247 4174 Fax(023)9244 6588 DX50005 Havant www.havant.gov.uk To: ADP Architects Ltd Richmond Court 94 Botley Road Park Gate Southampton, Hants SO311BA For:

More information

Site waste it s criminal A simple guide to Site Waste Management Plans

Site waste it s criminal A simple guide to Site Waste Management Plans Site waste it s criminal A simple guide to Site Waste Management Plans Introduction 10m tonnes of construction products are wasted every year, at a cost of 1.5 billion Much of this site waste is harmful

More information

Construction Logistics Plan Guidance

Construction Logistics Plan Guidance Construction Logistics Plan Guidance For planners MAYOR OF LONDON Transport for London Section 1 Introduction Contents Section 1 Introduction 3 Section 2 Policy background 6 Section 3 Typical contents

More information

TRAFFIC MANAGEMENT PLAN

TRAFFIC MANAGEMENT PLAN TRAFFIC MANAGEMENT PLAN For: The construction and operation of a Photovoltaic (PV) Facility in Dabenoris, South Africa Prepared for: Alternative Energy Solutions (Pty) Ltd PO Box 4939 Tygervalley, South

More information

1. Purpose and scope. 2. SEPA's role in hydropower and planning

1. Purpose and scope. 2. SEPA's role in hydropower and planning Page no: 1 of 10 1. Purpose and scope 1.1 The purpose of this note is to provide guidance on the approach that we will take when dealing with hydropower development management consultations. We welcome

More information

Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF)

Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF) Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF) Technical Guideline Audit and Inspection Version 2.0 February 2012 Table of Contents 1. Introduction... 3 2. Definitions... 3 3. Internal Audit... 3 3.1

More information

National Planning Policy for Waste

National Planning Policy for Waste National Planning Policy for Waste October 2014 Department for Communities and Local Government Crown copyright, 2014 Copyright in the typographical arrangement rests with the Crown. You may re-use this

More information

Compliance Audit Handbook

Compliance Audit Handbook Compliance Audit Handbook This Compliance Audit Handbook has been produced by the Compliance and Assurance Section of the Department of Environment and Conservation NSW (DEC). For technical information

More information

Considerate Constructors Scheme Site Manager s Guide

Considerate Constructors Scheme Site Manager s Guide Considerate Constructors Scheme Site Manager s Guide Started in 1997, the Considerate Constructors Scheme was set up by the UK construction industry to improve its image. The Scheme is a non-profit-making,

More information

Contractor Environment, Health and Safety Management Plan

Contractor Environment, Health and Safety Management Plan EHSMS10 Contractor and Supplier EHS Management Contractor Environment, Health and Safety Management Plan Purpose Guidelines Record Keeping This template provides an example to Santos Contractors of the

More information

Helical Bar - Environmental Management System. January 2014

Helical Bar - Environmental Management System. January 2014 Helical Bar - Environmental Management System January 2014 Contents 1 Introduction... 1 1.1 Overview... 1 2 Environmental aspects and impacts register... 2 2.1 Definitions... 2 2.2 Register of environmental

More information

Environmental Policy. JRI Orthopaedics Limited

Environmental Policy. JRI Orthopaedics Limited JRI Orthopaedics Limited October 2014 Contents Clause 1. Policy Statement 1 2. Who is covered by the policy? 2 3. Organisation and Responsibilities 2 4. Training and Communication 3 5. Suppliers and Customers

More information

APPENDIX O. Spill Prevention and Emergency Response Plan. G3 Terminal Vancouver Port Metro Vancouver Project Permit Application APPENDIX O

APPENDIX O. Spill Prevention and Emergency Response Plan. G3 Terminal Vancouver Port Metro Vancouver Project Permit Application APPENDIX O APPENDIX O Spill Prevention and Emergency Response Plan APPENDIX O G3 Terminal Vancouver Port Metro Vancouver Project Permit Application G3 TERMINAL VANCOUVER: PORT METRO VANCOUVER SPILL PREVENTION AND

More information

ALLEGANY WIND POWER PROJECT CONSTRUCTION SPILL PREVENTION PLAN

ALLEGANY WIND POWER PROJECT CONSTRUCTION SPILL PREVENTION PLAN ALLEGANY WIND POWER PROJECT CONSTRUCTION SPILL PREVENTION PLAN Best Management Practices (BMPs) will be implemented during construction of the Allegany Wind Power Project to prevent and contain spills.

More information

Guide Document for Development of WHS Management Plans

Guide Document for Development of WHS Management Plans DISCLAIMER: THIS DOCUMENT IS PROVIDED AS GUIDANCE TO ASSIST CONTRACTORS IN MEETING THEIR OBLIGATIONS UNDER THE WHS LAW AND NTG CONTRACTS. NTG DOES NOT ACCEPT ANY RESPONSIBILITY FOR THE CONTENTS OF CONTRACTORS

More information

MAGB HEALTH, SAFETY AND ENVIRONMENT GROUP POLLUTION INCIDENT RESPONSE PLAN

MAGB HEALTH, SAFETY AND ENVIRONMENT GROUP POLLUTION INCIDENT RESPONSE PLAN MAGB HEALTH, SAFETY AND ENVIRONMENT GROUP POLLUTION INCIDENT RESPONSE PLAN SCOPE: This guidance sets out best practice for producing a Pollution Incident Response Plan to deal with an environmental incident

More information

Benchmark OHS Consulting Pty Ltd Self Assessment WHS Audit Tool

Benchmark OHS Consulting Pty Ltd Self Assessment WHS Audit Tool Benchmark OHS Consulting Pty Ltd Self Assessment WHS Audit Tool This WHS Auditing System Tool is to be used as a self-assessment of YOUR COMPANY compliance with AS 4801 and the Work Health and Safety Act

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Pentarch PTY LTD Answerth Drive Oaklands, NSW Table of Contents 1. Description and Intended Use... 4 1.1. Overview... 4 1.2. Objectives... 4 1.3. Criteria...

More information

Managing Contractor Health and Safety Risks Guidelines for Local Government

Managing Contractor Health and Safety Risks Guidelines for Local Government Managing Contractor Health and Safety Risks Guidelines for Local Government Acknowledgements This manual has been prepared by Noel Arnold & Associates Pty Ltd, occupational health and safety consultants

More information

HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM

HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM September 2011 OUR HEALTH, SAFETY AND ENVIRONMENT POLICY OUR PRINCIPLE OF DUE CARE We care about the wellbeing of our people and our impact on the environment.

More information

Safety Excellence Matrix

Safety Excellence Matrix Safety Excellence Matrix 1 = Performance just meets minimum standards 2 = Performance is satisfactory got the basics 3 = Performance is good going beyond the norm 4 = Performance is very good best practice

More information

Development Management Officer Report Committee Application. Summary

Development Management Officer Report Committee Application. Summary Development Management Officer Report Committee Application Summary Committee Meeting Date: 15 Dec 2015 Item Number: Application ID: Z/2014/0978/F Target Date: 31 st October 2014 Proposal: Single storey

More information

Environmental Incident Classification and Reporting

Environmental Incident Classification and Reporting Environmental Incident Classification and Reporting 9TP-PR-105/13.0 Procedure Applicable to Transport Projects Quality Management System Status: Approved Version: 13.0 Branch: Business unit: Planning and

More information

How to comply with your environmental permit Additional guidance for: Horizontal Guidance Note H6 - Environmental Management Systems

How to comply with your environmental permit Additional guidance for: Horizontal Guidance Note H6 - Environmental Management Systems How to comply with your environmental permit Additional guidance for: Horizontal Guidance Note H6 - Environmental Management Systems Published by: Environment Agency Rio House Waterside Drive, Aztec West

More information

Sydney Port Botany Terminal 3 Project Water Resource Management Plan

Sydney Port Botany Terminal 3 Project Water Resource Management Plan Civil Works Construction Contract Phase 1 1/8 Terms and Definitions The following terms, abbreviations and definitions are used in this plan: Terms Explanation SPBT3 Sydney Port Botany Terminal 3 CEMP

More information

LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT

LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT Introduction The purpose of this Public Environmental Report (PER) is to provide the Government

More information

CONSTRUCTION ENVIRONMENT MANAGEMENT PLAN. CLEARING AND CIVIL WORKS EPBC 2009/4796 and EPBC 2013/7032. July 2015

CONSTRUCTION ENVIRONMENT MANAGEMENT PLAN. CLEARING AND CIVIL WORKS EPBC 2009/4796 and EPBC 2013/7032. July 2015 CONSTRUCTION ENVIRONMENT MANAGEMENT PLAN CLEARING AND CIVIL WORKS EPBC 2009/4796 and EPBC 2013/7032 July 2015 Jandakot Airport Holdings Pty Ltd 16 Eagle Drive Jandakot WA 6164 Ref: Construction Environment

More information

IALN11006400 /05 01 19.06.13. FAO: The Planning Department The Royal Borough of Windsor and Maidenhead Town Hall, St. Ives Road Maidenhead SL6 1RF

IALN11006400 /05 01 19.06.13. FAO: The Planning Department The Royal Borough of Windsor and Maidenhead Town Hall, St. Ives Road Maidenhead SL6 1RF IALN11006400 /05 01 19.06.13 FAO: The Planning Department The Royal Borough of Windsor and Maidenhead Town Hall, St. Ives Road Maidenhead SL6 1RF Dear Sir / Madam Re: 12/02994 BCA Sports Hall Condition

More information

Health and Safety Management Standards

Health and Safety Management Standards Health and Safety Management Standards Health and Safety Curtin University APR 2012 PAGE LEFT INTENTIONALLY BLANK Page 2 of 15 CONTENTS 1. Introduction... 4 1.1 Hierarchy of Health and Safety Documents...

More information

INTEGRATED MANAGEMENT SYSTEM MANUAL IMS. Based on ISO 9001:2008 and ISO 14001:2004 Standards

INTEGRATED MANAGEMENT SYSTEM MANUAL IMS. Based on ISO 9001:2008 and ISO 14001:2004 Standards INTEGRATED MANAGEMENT SYSTEM MANUAL IMS Based on ISO 9001:2008 and ISO 14001:2004 Standards Approved by Robert Melani Issue Date 30 December 2009 Issued To Management Representative Controlled Y N Copy

More information

sustainability report

sustainability report sustainability report Sustainable development In the midst of turbulent macro-economic conditions adversely impacting the coal sector, we maintain our focus on building a business that has a viable, long-term

More information

Ingredion ANZ Pty Ltd

Ingredion ANZ Pty Ltd Ingredion ANZ Pty Ltd 170 Epping Road, Lane Cove, NSW 2066 EPL: 518 Page 1 of 8 1. Purpose and Background POLLUTION INCIDENT RESPONSE The purpose of this Pollution Incident Response Management Plan (PIRMP)

More information

HUGO BOSS ENVIRONMENTAL COMMITMENT. Our claim. Our approach

HUGO BOSS ENVIRONMENTAL COMMITMENT. Our claim. Our approach HUGO BOSS ENVIRONMENTAL COMMITMENT HUGO BOSS assumes responsibility for future generations. This entails that we also pursue our high standards for quality and performance in environmental protection.

More information

How To Write A Sustainable Resource Management Framework

How To Write A Sustainable Resource Management Framework FORTH REPLACEMENT CROSSING M9 Junction 1a Project Quality Plan: Volume 4 Sustainable Resource Management Framework Construction Issue RSMF 02: May, 2012 FORTH REPLACEMENT CROSSING M9 JUNCTION A1 SUSTAINABLE

More information

NAPCS Product List for NAICS 54162: Environmental Consulting Services

NAPCS Product List for NAICS 54162: Environmental Consulting Services NAPCS List for NAICS : Environmental Consulting Services National 1 Environmental consulting Providing objective information, advice, and guidance to clients concerning the preservation of air, water,

More information

APPLICATION for ISO Certification (All Standards)

APPLICATION for ISO Certification (All Standards) APPLICATION for ISO Certification (All Standards) Contents Section 1 General Information (Please complete this section for All standards) (Please complete ONLY the sections for the Standard(s) that you

More information

15 Guiding Principles

15 Guiding Principles Health, Safety, Environment and Corporate Social Responsibility 15 Guiding Principles 2013 Message from President and CEO 0 New Gold has a complementary portfolio of assets in different countries and cultures

More information

HYDROCARBON SPILLS PROCEDURE SIG-ENV-PR003

HYDROCARBON SPILLS PROCEDURE SIG-ENV-PR003 Page: 1 of 6 PROCEDURE SIG-ENV-PR003 Revision Approved Date Description 1 AV 01/04/99 New EP 2 AV 07/06/00 Revision of EP 3 AV 04/04/03 Revision of EP 4 Stuart Roseby DRAFT 5 Stuart Roseby 25/07/2005 Approved

More information

Subordinate Local Law No. 1.12 (Operation of Temporary Entertainment Events) 2015

Subordinate Local Law No. 1.12 (Operation of Temporary Entertainment Events) 2015 Redland City Council Subordinate Local Law No. 1.12 (Operation of Temporary Entertainment Events) 2015 Redland City Council Subordinate Local Law No. 1.12 (Operation of Temporary Entertainment Events)

More information

Flood Risk Assessment and Drainage Impact Assessment: Planning Guidance for Developers

Flood Risk Assessment and Drainage Impact Assessment: Planning Guidance for Developers Flood Risk Assessment and Drainage Impact Assessment: Planning Guidance for Developers Development and Regeneration Services Glasgow City Council 229 George Street Glasgow G1 1QU May 2011 1. Introduction...-

More information

Management of Contractors and Suppliers Procedure

Management of Contractors and Suppliers Procedure Management of Contractors and HSE P1101 Table of Content 1 DOCUMENT CONTROL... 2 2 PURPOSE... 3 3 SCOPE... 3 4 DEFINITIONS... 3 5 ROLES AND RESPONSIBILITIES... 5 6 PROCESS DETAILS... 9 6.1 Confirm Need

More information