Standard: Distribution Design Manual Vol 4 Underground Cable Distribution

Size: px
Start display at page:

Download "Standard: Distribution Design Manual Vol 4 Underground Cable Distribution"

Transcription

1 Standard: Distribution Design Manual Vol 4 Underground Cable Distribution Standard Number: HPC-5DC

2 Document Control Author Name: Anthony Seneviratne Position: Standards Engineer Document Owner (May also be the Process Owner) Name: Justin Murphy Position: Manager Power System Services Approved By * Name: Justin Murphy Position: Manager Power System Services Date Created/Last Updated June 2014 Review Frequency ** 3 yearly Next Review Date ** June 2017 * Shall be the Process Owner and is the person assigned authority and responsibility for managing the whole process, end-to-end, which may extend across more than one division and/or functions, in order to deliver agreed business results. ** Frequency period is dependent upon circumstances maximum is 5 years from last issue, review, or revision whichever is the latest. If left blank, the default shall be 1 year unless otherwise specified. Revision Control Revision Date Description A 17/06/2014 Initial Document STAKEHOLDERS The following positions shall be consulted if an update or review is required: Manager Engineering Services Manager Assets Management Services NOTIFICATION LIST The following shall be notified if an update or review is required Engineering & Projects Operations Page 2 of 47 Print Date: 18/12/2013

3 TABLE OF CONTENTS FOREWORD INTRODUCTION General Design Objectives DESIGN PROCESS AND INPUTS Safety in Design Network Requirements Planning Equipment Installation Requirements Cable Route Termites Equipment Location Equipment Compatibility Environmental and Approval Management ELECTRICAL EQUIPMENT USED FOR UDS INSTALLATIONS Medium Voltage Ring Main Unit (RMU) Switchgear Outdoor RMU Kiosks Indoor RMUs MV Cables, Joints and Terminations MV Feeder Cables MV Transformer Cables MV Cable Joints MV Terminations Non-Loadbreak Terminations Load break Terminations Types of Substations Modular Packaged Substations (MPS) Non MPS Arrangements Customer Owned Substations Single Phase Padmount Transformers kva Single Phase (SPUDS) Transformer kva Rural Underground Transformer Service Pillars LV Cables, Joints and Terminations Page 3 of 47 Print Date 23/06/2014

4 3.5.1 LV Feeder Cables: LV Service Cable LV Street Light Cables Other LV Cables LV Cable Joints/Terminations VOLTAGE REGULATION Voltage Tolerance Limits Statutory Voltage Tolerance Limits Voltage Drop Criteria Effect of Different Load Cycles Voltage Drops and Line Currents in LV Feeders General Effect of Load Unbalance Voltage Drops/Line Currents in Meshed Networks Voltage Drop Limits for LV Networks MV Voltage Regulation Design Approach Computer Modelling Voltage Control Equipment UNDERGROUND DISTRIBUTION SCHEMES (UDS) Design Procedure Transformers Initial Requirements Transformer Selection Mixed Loads Example Regions other than Esperance LV Network Design Primary Aim Challenge for Network Designers Use of Computer Packages Aspects of Electrical Design Determination of Cable Size Selection of LV Feeder Routes Proximity to Loads Utilisation/Loading Typical Route Lengths Page 4 of 47 Print Date 23/06/2014

5 5.3.8 Interconnection with Other Feeders Pillar/Cabinet Positioning and Alignment Other Considerations Typical Design Issues MV Design MV Cable Requirements MV Network Systems Radial Feeder System Ring Main System Hybrid System Satellite Substations Automation Design Outputs Outputs - MV/LV Layouts Outputs - Cable Ducts DETERMINATION OF RECOMMENDED LOAD DEMAND VALUES Estimation of Load Demand Effect of Load Diversity on Maximum Demand Residential Load ADMDs Determination of ADMD when standard values are not used Non-Residential Load Demands Residential Lot Classification LV FEEDER PROTECTION Introduction Feeder Protection Policy LV Fuse Selection Policy Prescribed Fuse Sizes (MV and LV) Maximum Lengths of LV Feeders General Equivalent Length of LV Feeders Feeder Equivalent Length Calculation Maximum Equivalent Lengths What if the Maximum Allowable Length is Exceeded? Calculation of Fault Currents at End of LV Feeders Fault Current Ready Reckoner Typical LV Fuse Time-Current Characteristics Page 5 of 47 Print Date 23/06/2014

6 8 INSTALLATION REQUIREMENTS STREET LIGHTING APPENDIX A REVISION INFORMATION APPENDIX B CURRENT RATING OF UNDERGROUND CABLES B.1 Continuous Current Rating B.1.1 Rating Factors for depth of laying direct in the ground B.1.2 Rating Factors for depth of laying direct in a duct B.1.3 Rating Factors for variation in Thermal Resistivity (3 core cables laid directly in the ground) B.1.4 Rating Factors for variation in Thermal Resistivity (1 core cables laid directly in the ground) B.1.5 Rating Factors for variation in Thermal Resistivity (3 core cables laid in duct buried in the ground) B.1.6 Rating Factors for variation in Thermal Resistivity (1 core cables laid in duct buried in the ground) B.1.7 Rating Factors for Variation in Ambient Temperature B.1.8 Rating Factors for Variation in Ground Temperature Page 6 of 47 Print Date 23/06/2014

7 FOREWORD This volume is one in a series of five volumes, which together, form the Horizon Power Distribution Design Manual. The DDM is intended to be a comprehensive reference manual for distribution design work carried out by professional engineers and technical support staff. The five volumes are: Volume 1: Quality of Electricity Supply Volume 2: Low Voltage Aerial Bundled Cable Volume 3: Supply to Large Customer Installations Volume 4: Underground Residential Distribution (URD) Volume 5: Overhead Bare Conductor Distribution The DDM will also serve to initiate "newcomers" to distribution work in Horizon Power without them having to start from scratch. It serves to establish "standards" for design work to ensure that we get the best value from our facilities - not only in terms of initial cost, but also in terms of component availability, length of service life and cost-effective maintenance. In addition to this, the DDM will also serve as a teaching aid for courses run by Horizon Power. This volume describes the engineering process involved in designing and providing electricity supplies using underground cables. It describes the design process in detail, making use of standardised design information for use with routine work. Page 7 of 47 Print Date 23/06/2014

8 1 INTRODUCTION 1.1 General This document describes the engineering process involved in designing distribution underground networks. These networks typically originate from Zone substations as medium voltage feeders and are stepped down to low voltage networks through distribution transformers. Low voltage distribution networks then transmit power to customer installations, though some customers are supplied directly from the medium voltage networks. Although, underground cables do not account for a significant proportion of Horizon Power's networks at present, Horizon Power's policy mandates underground power supplies in all sub divisions including residential, rural residential, commercial and industrial. There are variations to this policy in the case of larger lot sizes greater than 10 hectares, which can be found in Horizon Power s Underground Distribution Schemes Manual. Underground assets are capital intensive, both for Horizon Power and its customers and they need to be properly designed and constructed. It is imperative that a high level of engineering is put into their designs, particularly because cables are buried and are not visible. Effort expended during design could avoid unnecessary expenses and ensure that the requirements (Horizon Power's and its customers ) are catered for. Each cable network may require different design considerations, configurations, layouts, etc. As such, there may be many different ways to approach a design. The information contained in this manual will assist the designer to develop a structured design approach, and ensure that the optimum configuration is selected at all times. 1.2 Design Objectives The objectives of underground cable design are to: a) Reduce cost to customers; b) Reduce life cycle costs; c) Provide greater durability, with due consideration to location in rocky, saline and marshy soils; d) Ensure safety of workers and the general public (safety in design); e) Promote environmental compatibility; f) Ensure electromagnetic field compatibility; g) Promote public acceptance (e.g. easements); and h) Attain and exceed the required supply quality and reliability standards. Page 8 of 47 Print Date 23/06/2014

9 The following factors are to be considered before the design can commence: a) Potential number of customers and total load; b) Estimation of potential load growth; c) Availability and/or requirement for interconnections; d) Selection of voltage for line operation; e) Size and location of loads (Bulk supply, transformers); f) Selection of route; g) Length of cable route; and h) Life cycle costs. Note: The size and type of cable to be used will be dictated by the capacity (load) to be carried by the cable during its lifetime together with voltage drop, thermal rating and fault rating considerations. Page 9 of 47 Print Date 23/06/2014

10 2 DESIGN PROCESS AND INPUTS This section covers the various considerations and inputs needed as part of design. The steps involved in the design of an underground cable network will depend on the individual project and the context in which the design is performed. It is an iterative process, with the designer making some initial assumptions, e.g. cable type and rating, which may later be adjusted as the design is checked and gradually refined. Delivering an optimum arrangement that meets all constraints as the final outcome. Horizon Power mainly uses underground cable simulation software to aid the design process. 2.1 Safety in Design Whenever design work is undertaken to construct new distribution network assets, or modify existing assets, demonstration of due diligence with respect to safety is required. This must cover the full life cycle of the asset that is created or the remaining life of the modified asset and thought about early in the design stage. The essential elements covering a designer s responsibility in ensuring the safety of the asset during its life cycle are addressed in the document, Guideline Safety in Design - HPC-2DC Network Requirements Design shall take into account both present and future network requirements. This information is typically covered in the relevant planning report, design specification and equipment specifications Planning For new distribution networks or extension to existing distribution networks, planning is carried out during concept development stage. Details covered in the planning reports that need to be considered include but not limited to: a) Load size; b) Load distribution centres; c) Load cycle; d) Nature of load; e) Required transfer capacity; f) Potential interconnection point; and g) Automation requirements Equipment Design specification and equipment specifications play a role in capturing requirements that need to be addressed during design. This includes the following: a) Equipment and cable rating for normal load, emergency load and for fault conditions (selection of medium voltage cables as feeders based on continuous current rating is covered in Appendix A ); b) Equipment or cable operating conditions (e.g. Broome versus Esperance); Page 10 of 47 Print Date 23/06/2014

11 c) Network tolerance limits (e.g. statutory voltage tolerance limits); d) Standard installation requirements (refer to clause 2.3); and e) Protection grading requirement. In special cases, there may also additional requirements such as: i. Customer request for a higher security supply; and ii. Coordination with road lighting design 2.3 Installation Requirements Installation condition has a significant impact on the overall technical design of an underground distribution network. Factors that must be considered by designer include but not limited to the following: a) Ambient air and ground temperature; b) Soil type and terrain such as: sandy, rocky, water table, etc.; c) Soil or backfill thermal resistivity; d) Cable installation arrangement (i.e. numbers of circuit within same easement, use of conduit, installation depth, etc.); e) Space requirement for installation of ground mounted equipment; f) Termites activity; g) Environmental risk such as fire, flood, acid sulphate soil and erosion; h) Pollution such as dust, salt and noise; i) Proximity to other utility assets and congestion level from existing services; j) Proximity to metallic/conductive structures; k) Proximity to occupiable structures; and l) Soil salinity Cable Route Evaluate the terrain to determine issues with ground. For example, suppose a medium voltage underground cable is to be constructed to supply a customer remote from a zone substation, and the line route traverses an area of rock, it would seem prudent for the designer to consider the issues involved in embedding cables in rock and the associated cost Termites Termite protection must be installed in all areas prone to termite attack Equipment Location Equipment must be suitable for the environment in which it operates. For example, a ground mounted transformer with open bushings may not be suitable for use outside a cement plant or quarry, where the build-up of fly-ash or dust may lead to nuisance tripping or a disproportionately high level of maintenance. Others include mines sites, with open air blasting, etc. Page 11 of 47 Print Date 23/06/2014

12 The location of ground mounted substations and other equipment shall take into consideration access, fire separation, touch and step potential, and other related issues. (Refer to Substation Installation Technical Requirements HPC-9DJ and Distribution Line Earthing Standard HPC-9DC ). 2.4 Equipment Compatibility Standard equipment shall be used as much as possible. In certain cases however, use of non- standard equipment may be required to deliver the required outcome or to deliver the most cost-effective solution. In such cases, equipment compatibility must be considered. Where unusual conditions or other circumstances warrant using alternative equipment the disadvantages in terms of readily available replacements and operational issues must be considered. Cable accessories such as joints and terminations for example, can only be used for cables within a certain size range. Other factors that need to be considered include but not limited to: a) Equipment s rated voltage b) Equipment s normal load and fault rating In cases where non-standard equipment is required as part of the design, the designer should seek formal approval from the Standards Group prior to proceeding with the final design. 2.5 Environmental and Approval Management Environmental sensitive areas, land usage, condition and ownership issues along a cable installation route can have a significant impact on the overall project cost and timeline. Relevant factors that need to be considered by designers include but not limited to the following: a) Aboriginal heritage sites or areas; b) Area with bio-security weeds, pests and disease spread risk (i.e. dieback disease); c) Threatened ecological communities, sites with declared rare flora and fauna; d) Land with native title; e) Protected wetlands; f) Waste management areas; and g) Registered and/or private lands. Prior approvals are typically required to perform work at or close to these sites. Where vegetation clearing is required, a permit shall also be obtained prior to proceeding with the clearing. Current statutory processes require a range of approvals to be obtained prior to commencement of works. Due to the time taken to obtain these approvals, these issues must be considered at the commencement of a project. As per the Western Australian Distribution Connections Manual (WADCM Section 6.12) environmental and heritage impacts must be investigated and managed by the applicant for power supply and their agent. Page 12 of 47 Print Date 23/06/2014

13 3 ELECTRICAL EQUIPMENT USED FOR UDS INSTALLATIONS 3.1 Medium Voltage Ring Main Unit (RMU) Switchgear 22 kv and 33 kv RMU switchgear is used for switching of the medium voltage network. They are used as a "standalone" kiosk or incorporated into a RMU integrated package substation (only option is currently available as a packaged substation). 11 kv networks shall make use of 22 kv switchgear Outdoor RMU Kiosks The commonly used outdoor RMU combinations at 22 kv and 33 kv are: a) 2 switches plus 1 fuse switch (2+ 1); b) 2 switches plus 2 fuse switches (2+2); c) 2 switches plus 3 fuse switches (2+3) only at 22 kv; d) 3 switches plus 0 fuse switches (3+0); e) 3 switches plus 1 fuse switch (3+1); f) 3 switches plus 2 fuse switches (3+2); and g) 4 switches plus 0 fuse switches (4+0); 22 kv and 33 kv RMUs are incorporated into either 3, 4 or 5 way kiosks (e.g. 2+2). RMUs are installed in a freestanding aluminium kiosk mounted on a steel frame. This steel frame is buried in the ground to provide a firm foundation and allows easy access to the cables and terminations below the switchgear Indoor RMUs Indoor compounds comprising brick enclosures with roof are used to house RMUs and transformers. They are generally used to cater for larger loads (> 630 kva). Extensible and non-extensible MV RMUs are also installed within buildings owned by customers. 3.2 MV Cables, Joints and Terminations MV Feeder Cables (a) 3 x 1 core, 95 mm 2, 185 mm 2, 400 mm 2 aluminium and 240 mm 2 copper XLPE insulated, PVC/HDPE sheathed cables are used on 22 kv networks. (b) 3 x 1 core, 185 mm 2 aluminium and 240 mm 2 copper XLPE insulated, PVC/HDPE sheathed cables are used in 33 kv networks MV Transformer Cables (a) 3 X1 core, 35 mm 2 aluminium XLPE insulated, PVC/HDPE sheathed, cables are use on 22 kv systems (b) 3 X 1 core 50 mm 2 aluminium XLPE insulated, PVC/HDPE sheathed, cables are use on 33 kv systems Page 13 of 47 Print Date 23/06/2014

14 3.2.3 MV Cable Joints Currently, all MV straight-through joints, including transition types, use heat shrink materials, except where otherwise approved. All cable joints shall be installed in accordance with details outlined in the Underground Cable Installations Manual: HPC- 5DJ , and the manufacturer's instructions supplied with joint kits. Where not published in specific detail clarification shall be sought from the supplier. In any case, sound engineering practice shall be used MV Terminations All pole top cable terminations and some transformer terminations use heat shrink materials, except where otherwise approved. Separable insulated connectors (non-ioad break type) are used for terminations on transformers (satellite and ringmain), Modular Packaged Substations (MPS), small single phase pad mount transformers (SPUDs) and ringmain switchgear with integral bushings Non-Loadbreak Terminations The MV connectors, bushings and apparatus used in Horizon Power's underground system are shown in table below: Type of Connector Connector Function Non-Load Bushing Non-Load Elbow break break Mounted on the MV side of transformer to connect cables Terminates the XLPE cable to allow connection with the MV bushing Dead-End Plug Dead-End Receptacle Used to protect the non load break elbow when it is not connected to a transformer bushing Used to protect the transformer bushing when there is no non load break elbow connected to it Load break Terminations Load break terminations are currently not used by Horizon Power. 3.3 Types of Substations Horizon Power may require that the supply arrangement to an installation be via a particular "type" of substation, i.e.: "District" Substation (With LV street feeds to/from the substation); "Sole Use" Substation (With no LV street feeds); or "Customer Owned" Substation (Supplied at distribution MV voltage levels). Page 14 of 47 Print Date 23/06/2014

15 Consideration may also be given to installing a pad-mount or Modular Package Substation (MPS) in lieu of the more common brick enclosure substations. There may be cost advantages as well as land/space advantages with this option. The decision as to which type is selected depends on several factors, including: a) Size of customer's load; b) Location of customer's load centre on the property, and distance of the same from the street boundary; c) Type and nature of loads within the installation (disturbing, passive, etc.); d) Nature of Horizon Power's existing distribution network and loading levels on other substations in the vicinity; e) Horizon Power's need to connect LV street feeds to/from the substation; f) Fire separation requirements LV street feeds may be required to/from a substation for the following reasons: a) The customer requires a "back-up" LV supply to the installation; b) There will be future developments and load growth in the immediate area; c) The customer's load is expected to increase in the future; d) Ease of maintaining equipment in the substation (e.g. with street feeds into the substation, the customer's load can be partly met while the MV switchgear is being maintained); etc Modular Packaged Substations (MPS) a) A MPS comes complete with a single transformer and LV switchgear. It is housed in a self contained metal enclosure and is installed on an inverted, direct buried concrete culvert. If MV switchgear is required, this is also housed in a self-contained metal enclosure which is installed adjacent to the transformer on a direct buried steel mounting frame. b) MPS s are used only as District Substations. They are not used as Sole Use substations and are not fire rated. c) MPS is the preferred arrangement for a District substation with a maximum load of 630 kva after allowing for future load growth, and where there is no requirement for the substation to be fire rated Non MPS Arrangements a) A Non MPS arrangement comprises a combination of one or more transformers plus LV switchgear and MV switchgear as required. Each of these items is a separate component housed in a self contained metal enclosure. The transformer is installed on an inverted, direct buried concrete culvert. The LV and MV switchgear enclosures are installed on direct buried steel mounting frames. b) Non MPS components are not installed as a single package. They can be installed either as a cluster substation or in a fire rated enclosure (see Section 6). In the latter case, the culvert and switchgear mounting frames are not required. Page 15 of 47 Print Date 23/06/2014

16 c) Non MPS arrangements can comprise multiple transformers, with 1000 kva being the largest individual transformer size. They can be used as both District and Sole Use substations. A Non MPS arrangement shall be used where; A Sole Use substation is required; or Multiple transformers are required; or The maximum load is greater than 630 kva after allowing for future load growth; or The substation is to be fire rated Customer Owned Substations Typically, for loads greater than 4 MVA, a Customer Owned substation shall be provided. Neither the MPS nor the Non MPS arrangements are suitable for Customer Owned Substations. Horizon Power shall provide extensible MV switchgear necessary for connection to the network. The equipment shall be installed in a switch room constructed by the customer, along with the customer s own MV switchgear (See DSM-3-22 for details). Where a customer s load is less than 4 MVA, MV outdoor ground mounted switchgear can be considered. (See DSM-3-23 for details). A Customer Owned Outdoor Ground Mounted Substation cannot be upgraded for loads above 4 MVA. In the event that the customer s load increases above 4 MVA, the substation shall be converted to a MV Indoor Ground Mounted Substation, which will require a switch room to be built. In areas with overhead networks only, MV outdoor aerial mounted switchgear may be used (See DSM-3-24 for details) Single Phase Padmount Transformers The padmount single phase transformer is available in both 10 kva and 25 kva units for 12.7 kv Single Wire Earth Return (SWER) operation or for 22 kv "Two Phase" operation. The transformers are supplied configured for 240 volts, but can be re-configured to 480 volts for "sole use" applications kva Single Phase (SPUDS) Transformer The transformer is mounted on a hot-dipped galvanised steel base. The HV side of the transformer is equipped with either 2, 3 or 4 x 200 A tapered bushings which allow connection with separable non loadbreak elbow connectors. An internal, oil-immersed HV fuse is fitted inside the transformer tank. The unit is fitted with an externally operated, off-load tap-changer with steps of 0, ±2.5% and ±5.0%. The LV feeder cables, outgoing from the LV compartment, are protected by one "Red Spot" fuse (100 Amp) for 240 V or two "Red Spot" fuses (63 Amp) for 480 V. For further information refer to SPUDS design and operation manual. Page 16 of 47 Print Date 23/06/2014

17 kva Rural Underground Transformer The transformer is mounted on a concrete base. The HV side of the transformer is equipped with 2 x 200 A tapered bushings which allow connection with separable non-loadbreak elbow connectors. An internal, oil-immersed HV fuse is fitted inside the transformer tank. The unit is fitted with an externally operated, off-load tap-changer with steps of 0, ±2.5% and ±5.0%. The outgoing mains from the LV compartment, are protected by one "Red Spot" fuse (50 Amp) for 240 V or two "Red Spot" fuses (32 Amp) for 480 V. 3.4 Service Pillars Customer service pillars facilitate the connection of house services, customer bulk supply cables or interconnections of main LV street cables. In dusk to dawn street lighting areas, some may also provide supplies to streetlights. The service pillars are of a dark-green, polyurethane construction, with base partly buried in the ground. Figure 3-1 shows typical pillars. Figure 3.1 Typical Pillars There are two types of service pillar: 1) "Mini" Pillar (with tunnel terminal blocks): Tunnel block accepts up to 5 outgoing circuits (to 35 mm 2 copper cable), usually connected as follows: Pillar on cable side of road: Connect incoming 3 core 25 mm 2 cable from LV feeder; and Connect outgoing 2 x 3 phase or 2 x 1 phase services; and outgoing 3 core 25 mm 2 road crossing service cable Page 17 of 47 Print Date 23/06/2014

18 Pillar on other side of road: Connect incoming 3 core 25 mm 2 road crossing service cable; and Connect outgoing 2 x 3 phase or 2 x 1 phase house services 2) Universal" Pillar (with links and tunnel terminals): The universal pillar can be used as: an "interconnector" pillar with provision for solid links, to form a normally open or closed network point. a location to reduce the size of LV cable; to service a large single load (e.g. multiple dwelling lot) with LV HRC fuses (J type) to 315 A The universal pillar also contains tunnel terminals for service cables, as per "mini" pillar. Note: both "mini" pillars and "universal" pillars have provision for a fused terminal for an adjacent lighting column. 3.5 LV Cables, Joints and Terminations LV Feeder Cables: (a) 120 mm 2, 3 core, solid Aluminium conductor, Copper screened neutral (Wave Wound), 0.6/1 kv, XLPE insulated, PVC sheathed (b) 185 mm 2, 3 core, solid Aluminium conductor, Copper screened neutral (Wave Wound), 0.6/1 kv, XLPE insulated, PVC sheathed (c) 240 mm 2, 3 core, solid Aluminium conductor, Copper screened neutral (Wave Wound), 0.6/1 kv, XLPE insulated, PVC sheathed (d) 630 mm 2, 1 core, solid Aluminium conductor, Copper screened neutral (Wave Wound), 0.6/1 kv, XLPE insulated, PVC sheathed LV Service Cable 25 mm 2, 3 core, solid Copper conductor, Copper screened neutral (Wave Wound), 0.6/1 kv, XLPE insulated, PVC sheathed LV Street Light Cables Single core 10 mm 2 and 16 mm 2 stranded copper, XLPE insulated, helical copper wire neutral screen, PVC sheathed Other LV Cables For minor branch and road crossing services use: 25 mm 2, 3 core, solid Copper conductor, Copper screened neutral (Wave Wound), 0.6/1 kv, XLPE insulated, PVC sheathed cable. Page 18 of 47 Print Date 23/06/2014

19 3.5.5 LV Cable Joints/Terminations There are many variations of joints and terminations being used which are summarised below: 1) feeder cable straight through and breeches joints; 2) feeder cable to service cable tee joints; 3) feeder cable pole terminations (to bare and LV ABC overhead conductors); 4) feeder cable termination at universal pillar; 5) feeder cable termination at fused switch; 6) service/street light cable termination at mini pillar; 7) service/street light cable terminations (to bare and LV ABC overhead conductors); and 8) service/street light cable straight through and tee joints. Page 19 of 47 Print Date 23/06/2014

20 4 VOLTAGE REGULATION 4.1 Voltage Tolerance Limits Statutory Voltage Tolerance Limits Horizon Power declares the voltage level at a customer s point of supply as within ± 6% of the nominal 240 V single phase and ± 6% of the nominal 415 V three phase. As such, the maximum and minimum phase-to-neutral voltage levels at any point of supply on the LV network shall be within 225 V and 254 V for single phase supplies and within 390 V and 440 V for three phase supplies (under normal network conditions). In accordance with AS , Horizon Power expects to adopt the new voltage standard 230 V +6%, -10% for single phase and 400 V +6%, -10% for three phase supplies sometime in the future. When planning and designing a residential distribution network, the designer has to ensure that the voltages at any point of supply on the network will be within the statutory voltage tolerance limits, under normal network conditions. 4.2 Voltage Drop Criteria Impedance in each of the following components of the distribution system leads to voltage drop: 1) Medium Voltage Feeder; 2) Distribution Transformer; 3) Low Voltage Network; 4) Customer Service Leads/Cables. After a distribution system has been constructed, there are only two locations where voltage levels can be adjusted: a) at the zone substation (bus-bar voltage set-point and the use of Line Drop Compensators), and b) at the distribution transformers (off load tap changers). It is therefore important that the non-adjustable parts of the system be designed adequately to fully utilise the voltage control equipment at these locations to keep the customers voltages within the statutory voltage tolerance limits. Table 4.1: - Voltage Drop Limits with respect to nominal voltage Non-Adjustable System Components Maximum Voltage Drop Limits Medium Voltage Feeder 5.0% Distribution Transformer 4.0% Low Voltage Network 5.0% Customer Service Cable 2.0% Thus to compensate for voltage drops caused by components in Table 4.1, the Automatic Voltage Regulator (AVR), Line Drop Compensator (LDC) and distribution transformer taps are set accordingly. Page 20 of 47 Print Date 23/06/2014

21 With a 2% voltage drop assumed for customer service cables, coincident voltage drops, when taken together with zone substation LDC Buck/Boost and distribution transformer tap options are considered a reasonable balance to achieve: a customer s voltage at the meter panel between ± 6% of the nominal 240 V. Maintenance and Emergency Voltage Limits are shown in Table Effect of Different Load Cycles The majority of customers in a typical area will have similar, normal load patterns. Some, however, will have load patterns which vary and in extreme cases could be completely opposite to the normal pattern. These are usually single customer loads. Such loads of relatively small magnitude with respect to the total feeder load (or of relatively large magnitude with respect to the total distribution transformer load) can be catered for by adjusting the tap settings on the transformer supplying the load. Instances could also arise where a particular MV feeder load profile becomes dominant and masks the normal load profile of the remaining feeders on the zone substation. Such a feeder could influence the response of the LDC, to the detriment of the remaining feeders and their individual loads. This problem falls into network load modelling and is not dealt with in this manual. 4.3 Voltage Drops and Line Currents in LV Feeders General A three phase, four wire distribution system servicing a large proportion of single phase residential loads together with three phase commercial/industrial loads is subject to rapidly fluctuating currents. These currents produce corresponding rapidly fluctuating voltages on the system Effect of Load Unbalance It is inevitable that an imbalance between the line currents on the three phases of a feeder will occur if the feeder services a large number of single-phase loads (e.g. residential loads). This imbalance in the line currents leads to a current which flows in the neutral conductor, which adds to the voltage drop caused by the current flowing in the phase conductor. The voltage drop calculation (in LV DESIGN software) takes into account this added voltage drop caused by the load unbalance, as necessary Voltage Drops/Line Currents in Meshed Networks A Null Point is a point on the meshed portion of the network, through which no line current flows - the voltage drop from the transformer to either side of the null point is also the same. Page 21 of 47 Print Date 23/06/2014

22 In practice, the location of the null point in the meshed portion of the network can change as the loads on the meshed portion vary during the day. However, during times of peak load, the location of the null point would be approximately at the same position. The location of the null point in the meshed portion of the network signifies that the voltage drop from the transformer to either side of the null point is within the maximum allowable limit. Hence, once the location of the null point is known, the network can be assumed to be opened at this point and the cable sizes are appropriate to ensure that the voltage drop to the null point (and hence to all other points on the meshed portion of the network) remains within the maximum allowable limits Voltage Drop Limits for LV Networks One of the voltage drop criteria is that the maximum allowable voltage drop limit for the LV network is 5.0%. This translates to a phase-to-neutral voltage drop of 12 V between the transformer LV terminals and the Point of Supply of any load on the network. This limit, however, applies for normal or steady state conditions. In general, the network designer shall ensure that the design of the network conforms to the voltage drop limits shown in Table 4.2. Table Maximum Voltage limits for LV Networks Condition Voltage Limits (Phase to Neutral) % Volts Max (V) Min (V) Normal or Steady State ± Maintenance ± Emergency ± When designing the network, maintenance or emergency conditions must also be considered. Interconnection with adjacent networks is necessary to maintain the supply. 4.4 MV Voltage Regulation Design Approach The design approach is generally as follows: (a) Determine loads for maximum, lightly loaded and maintenance conditions. (b) For least cost option, check that voltage remains within limits for the various loads. (c) If voltage goes outside limits try various options. (d) Compare options to determine optimum solution Computer Modelling In many instances the cable electrical data is entered into a suitable computer program for analysis such as Horizon Power s Power Factory (Digsilent) program. This calculates the voltage variations for each option. The designer still needs to compare the options. Page 22 of 47 Print Date 23/06/2014

23 Voltage Control Equipment Some voltage control is built into the standard system equipment as follows: (a) Distribution Transformers: Out of service manual tap changes of ±2.5% and ±5%. (b) Zone Substation Transformers: Typically ±10%, ±13% or %. In urban areas it has been standard practice to utilise the above two measures only and choose appropriate conductor sizes and distribution transformer location/quantity to provide satisfactory voltage regulation. These are covered in Clause LV Network Design. Where longer lines are used it can become uneconomic to increase the conductor size. Additional forms of MV voltage control may become the lowest cost option. The three options usually considered are as follows: a) Capacitors -typically used for lines of moderate length (effective when permanently in service) b) Reactors - typically used for very long lightly loaded lines (effective when permanently in service) c) Regulator - can be used to raise or lower voltage (output voltage varies to suit load conditions) Page 23 of 47 Print Date 23/06/2014

24 5 UNDERGROUND DISTRIBUTION SCHEMES (UDS) 5.1 Design Procedure The Underground Distribution Schemes Manual (UDSM) sets out the procedure for a subdivision that is to be supplied with electricity from Horizon Power s network. The UDSM covers the policies, processes, practices, requirements and equipment that are relevant to designing underground distribution systems and it shall be referred to when designing Underground Distribution Schemes. The challenge for the designer is to produce the most economical selection of equipment, location and cable size that will adequately service the loads within the constraints of achieving Horizon Power s "quality of supply" objectives. (Refer to HPC-5DC : Distribution Design Manual Volume 1 Quality of Electricity Supply). Section 6 Determination of Recommended Load Demand Values, provides information about determining loads for underground distribution schemes. General steps involved in design are summarised below: 5.2 Transformers Initial Requirements Count the lots in the development from which the total number of transformers can be calculated (refer to HPC-3DC : Information Electrical Design for Distribution Networks: After Diversity Maximum Demand). Based on the number of lots to be serviced by a transformer, do a rough grouping of the lots and select tentative transformer locations. Relocate transformers after Step (b) to optimise loading on the LV distribution cables available. Identify non-residential loads such as pumps, shops, schools etc. Identify discrete or sole use transformer loads. The transformer substation should be located as near as possible to the electrical load centre of a group of lots in order to best balance the loads between feeders. This is achieved by locating the transformer close to road intersections and junctions. The designer must be prepared to regroup lots and change transformer locations as the design develops. Standard transformer ratings used by Horizon Power for underground distribution schemes are: i. 160 kva MPS and non MPS ii. 315 kva MPS and non MPS iii. 630 kva MPS and non MPS iv kva non MPS Note: The above transformers are available as indoor or outdoor units Page 24 of 47 Print Date 23/06/2014

25 5.2.2 Transformer Selection The designer must also be aware of other factors that may affect transformer selection and location unique to the subdivision under development, such as: 1) Isolated pockets of UDS that may be serviced from: Satellite substations; Spare capacity from adjacent non residential loads; and Spare capacity from adjacent separate developments. 2) Pockets never likely to be expanded and satisfactorily serviced from a 315 kva substation (i.e. no future 630 kva requirement). 3) Topographical features and ground conditions prohibiting installation. 4) Strategies adopted by developers for different schemes Mixed Loads If the full utilisation of Horizon Power assets is to be achieved then mixed loads are inevitable. Different peak load times for mixed loads must be taken into consideration when selecting transformer ratings or grouping of lots Example 1 How many residential lots can be supplied from a substation feeding a high school? Available information: School maximum demand is 220 kva (clause 6.3.2) School is supplied from a 315 kva transformer ADMD for Esperance is 3 kva Residential peak occurs between 5:30 and 6:30 PM. School load has been measured at 20% peak during domestic peak. Transformer kva = (No. of lots x ADMD) + (220 x 20%) Hence, No. of lots = {315 - (0.2 x 220)} / 3.0 = 90 lots now and ultimately No. of lots = {630 - (0.2 x 220)} / 3.0 = 195 lots with 630 kva transformer It appears that about 195 lots may be mixed with a high school load provided that a 630 kva transformer replaces the 315 kva transformer sometime in the future. However, the school peak occurs at 11:30 am when the domestic load has been measured at 50% maximum demand, Therefore, No. of lots = ( ) / 1.5 = 63 lots now and ultimately = ( ) / 1.5 = 273 lots with 630 kva transformer Page 25 of 47 Print Date 23/06/2014

26 An analysis of the above shows that certain options exist depending on the particular circumstance of the subdivision requirements. 1) 63 lots could be serviced now from a 315 kva substation to be upgraded later to a 630 kva substation. This would underutilise the 630 kva transformer unless, as is often the case, there was a requirement for spare capacity (up to 132 lots) at a later stage of development. 2) 195 lots could be serviced now from a 630 kva transformer saving the cost of upgrade but incurring additional capital costs and early transformation losses. In general, it may be prudent not to take advantage of the 120% overload capacity of the transformer. This allows for contingencies, common in mixed load applications Regions other than Esperance It is standard practice to install 630 kva transformers initially because the flat load profile due to air-conditioning allows little scope for cyclic rating use. 5.3 LV Network Design Primary Aim The primary aim when designing a LV network is to select and locate equipment that will adequately service both present and future customer loads and also satisfy the reliability and quality of supply standards stipulated by the Electricity Industry (Network Quality and Reliability of Supply) Code Challenge for Network Designers The challenge for any network designer is to avoid over/under design of the network. Over design is costly in terms of unnecessary capital investment, whilst under design leads to high losses, costly investigation and rectification of Quality of Supply related complaints. Extra effort expended in optimising the design of LV networks results not only in the efficient utilisation of capital costs but also impacts on the MV network, affecting the number and location of distribution transformers Use of Computer Packages Typically, the design studies and calculations are carried out using specially written computer programmes, for the more complex cases or where accurate results are required. Alternatively, manual calculations can sometimes be used, especially for simpler cases or where only estimates are required. LV DESIGN is a PC based computer program, written specifically for studying LV networks. It is particularly suited for underground distribution scheme designs, with distributed loads along the LV feeder. The program automatically accounts for load unbalance and diversity. However, it can also be used to calculate the voltage drops and line currents caused by large commercial loads. LV DESIGN can be used to investigate the impact of new large loads within residential estates, e.g. shopping centres, pumps, etc. Page 26 of 47 Print Date 23/06/2014

27 GIS (Geospatial Information System) is one of Horizon Power's prime computer systems. Various distribution plant items are recorded in the system for most parts of the state, e.g. transformers, MV and LV cables and many other assets. Customer property boundaries are also recorded in the GIS database. GIS can be used by the designer to obtain information quickly about the existing supply system around a new proposed installation, from which, various supply alternatives can be considered. GIS can also be used to down-load information on the supply system onto Power Factory (Digsilent) for later analysis Aspects of Electrical Design The electrical design of distribution feeders generally involves the following aspects: 1) Estimation of load demands; 2) Selection of distribution transformer; 3) Planning of network layouts; 4) Calculation of Voltage Drops and Cable Currents; 5) Selection of cable sizes to satisfy the voltage drop and current capacity requirements; and 6) Selection of fuse/protection device (if applicable). These aspects are explained in the following sections Determination of Cable Size The size of LV cable is chosen to ensure that all of the following criteria are satisfied: 1) Voltage drops during peak network load times being within maximum allowable limits (and during minimum load times being within minimum allowable limits) - Refer to Section 4 2) De-rated current carrying capacity of cable being adequate so that load currents will be within the capacity, not only during steady state conditions, but during maintenance/emergency conditions when the LV network is interconnected with others (Refer to Appendix B); 3) Other cable current ratings (e.g. summer, winter) not being exceeded, wherever applicable ( Refer to Appendix B and cable manufacturers data); 4) Cable impedance satisfying the LV fuse/protection requirements (so that at times of fault at the end of the feeder, the fault current will be large enough to be seen by the LV fuse and hence, cleared in time to prevent damage to the cable ( Refer to Section 7) Selection of LV Feeder Routes When selecting LV feeder routes, the designer should take the following into account: Page 27 of 47 Print Date 23/06/2014

28 Proximity to Loads The feeder route should be chosen such that it will start to be loaded as close to the transformer as possible. This is facilitated by locating the transformer as close to heavy load centres as possible or as close to the centre of gravity of a group of loads. Feeder routes where the feeder only picks up loads after a considerable distance away from the transformer should be avoided (as this causes larger voltage drops than necessary in the initial part of the feeder) Utilisation/Loading LV feeder routes must be chosen such that the transformer will service the required number of loads determined on the basis of design load demand values (refer to Section 6 Determination of Recommended Load Demand Values and HPC-3DC Electrical Design for Distribution Networks: After Diversity Maximum Demand) Typical Route Lengths The length of a LV feeder affects the: 1) voltage drop on the feeder; and 2) fault current at the end of the feeder. Very long LV feeders should generally be avoided since this would only result in medium voltage drops than necessary, cause improper operation and lead to possible conductor burnouts. Designs may require up to 500 m route lengths. However, route lengths in excess of 400 m are unusual and may indicate poor substation location. Cable routes should be selected so that feeders start to pick up load as close to the substation as possible. This can be achieved by locating the substation close to the electrical load centre of a group of residential loads or non residential loads. Cable routes that pick up loads at significant distances from the substation entail substantial voltage drops to occur. This can impact adversely on conductor costs and losses Interconnection with Other Feeders If a transformer becomes unserviceable, its LV network has to be supplied by adjacent transformers until repairs can be effected or a replacement put into service. As such, the LV network should be provided with sufficient numbers of interconnecting points (e.g. via the use of removable solid links, fuse switches) to allow lateral interconnections between LV networks of adjacent transformers. When selecting LV routes, the designer should select routes which can assist in the provision and location of these interconnecting points, if possible. The interconnection criteria generally used by Horizon Power is to ensure that the backbone feeder of any transformer can be interconnected with other LV feeders from adjacent transformers, at least twice. If the number of interconnections cannot be provided due to certain constraints, the designer should consider using a smaller transformer size instead. Page 28 of 47 Print Date 23/06/2014

29 5.3.9 Pillar/Cabinet Positioning and Alignment When selecting the LV feeder route, the designer must also give consideration to the positioning of Pillars and Cabinets Other Considerations Sometimes, in order to mitigate the excessive voltage drops caused by large motor starting currents, it may be necessary to connect up large motors (e.g. large reticulation and sewerage pumps) via a dedicated LV feeder. A similar requirement may be called for to mitigate any interferences caused by potentially disturbing electrical loads to other customers on the same LV feeder, e.g. light industrial customers with arc-welders, thyristor controlled motor speed drives, large motors. On the other hand, from the nature of the load itself, or due to special requests from the customer for a more secure supply arrangement, certain loads may need to be serviced via dedicated LV feeders or from sole-use transformers (e.g. small hospitals, retirement villages, bulk cold food storages) Typical Design Issues When designing the LV feeder and street lighting, voltage drops with various cable sizes are calculated. If the voltage drop at the end of a radial LV feeder exceeds the prescribed limits the following alternative design choices are possible: a) Adjust lot grouping or change transformer boundaries b) Relocate the transformer to a site nearer the electrical load centre of the grouped lots. c) Upgrade cable size d) Check current flows against the current rating of the cables e) Check LV feeder protection fuse size 5.4 MV Design MV Cable Requirements When designing the MV layout, the shortest and most direct MV cable routes should be selected. If the design is for a large UDS: a) a detailed and comprehensive study of the existing and proposed MV feeders supplied from adjacent zone substations shall be carried out to determine the effect of the new load on the overall MV network and system security; b) in the overall area concept plan, the location of all the transformers and all existing MV mains adjacent to the subdivision (obtained from GIS) shall be marked; c) transformers that are to be supplied as "satellites" from the adjacent overhead MV mains and the transformers that are to be "ring main" Page 29 of 47 Print Date 23/06/2014

Distribution Substation Manual (DSM) Section I - Introduction

Distribution Substation Manual (DSM) Section I - Introduction (DSM) Section I - Introduction March 2007 Document release information Client Project name Western Power Distribution Substation Manual Document number 3463019 Document title Revision status Introduction

More information

ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1

ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1 ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1 Design and Planning Specification for New Low Voltage Installations for Housing Developments 1. SCOPE This appendix to ENA

More information

The electrical energy produced at the gen

The electrical energy produced at the gen 300 300 Principles of Power System CHAPTER CHAPTER 12 Distribution Systems General 12.1 Distribution System 12.2 Classification of Distribution Systems 12.3 A.C. Distribution 12.4 D.C. Distribution 12.5

More information

EARTHING AND BONDING AT SECONDARY SUBSTATIONS

EARTHING AND BONDING AT SECONDARY SUBSTATIONS DISTRIBUTION CONSTRUCTION MANUAL SECTION 4 - SUBSTATIONS ISSUE B SEPT 1996 4.4.4 EARTHING AND BONDING AT SECONDARY SUBSTATIONS 1 SCOPE This section of the Distribution Construction Manual lays down the

More information

How To Get A Power Line Extension

How To Get A Power Line Extension GUIDELINES FOR COMMERCIAL ELECTRIC SERVICE HOOKUP 1 Steps to Commercial Service Pay the Design Deposit Commercial Buildings: Up to 1, sq ft = $1,. 1, 5, sq ft = $2,. Over 5, sq ft = $3,. Commercial jobs

More information

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3

More information

Underground Commercial Electric Service

Underground Commercial Electric Service Underground Commercial Electric Service SCANA Corporation 2013 Revised: June 2013 Table of Contents SECTION PAGE I. Specification and Requirements 2 A. General B. Definition of Terms C. Company and Developer

More information

Network Standard Advice No. 1420C 9/6/2011

Network Standard Advice No. 1420C 9/6/2011 Network Standard Advice No. 1420C 9/6/2011 TO: Customers, Service Providers and Ausgrid Staff. Advisory Note on Changes to the Use of 11kV Cable Types. Introduction This Network Standard Advice (NSA) provides

More information

Networks. ESB Networks Ltd Basis of Charges for Connection to the Distribution System. Commercial and Customer Asset Management ESB Networks Ltd.

Networks. ESB Networks Ltd Basis of Charges for Connection to the Distribution System. Commercial and Customer Asset Management ESB Networks Ltd. Networks ESB Networks Ltd Basis of Charges for Connection to the Distribution System Revision Date: 14/01/20010 Revision No.: 1 Document No: DOC-10129-AXQ Issued by: ESB Networks Ltd Approved by : CER

More information

Undergrounding high voltage electricity transmission. The technical issues

Undergrounding high voltage electricity transmission. The technical issues Undergrounding high voltage electricity transmission The technical issues This is an interactive PDF document with clickable links from the contents to all sections and back and also to URL and email links.

More information

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz)

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz) 24 1. NETWORK CONFIGURATIONS definition Standard IEC 38 defines voltage ratings as follows: - Low voltage () For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information

Document No Amendment No Approved By Approval Date Review Date NS112 DESIGN STANDARDS FOR INDUSTRIAL AND COMMERCIAL DEVELOPMENTS

Document No Amendment No Approved By Approval Date Review Date NS112 DESIGN STANDARDS FOR INDUSTRIAL AND COMMERCIAL DEVELOPMENTS Network Standard NETWORK Document No Amendment No Approved By Approval Date Review Date : : : : : NW000-S0041 1 Chief Engineer 26/10/2015 13/04/2018 NW000-S0041 NS112 DESIGN STANDARDS FOR INDUSTRIAL AND

More information

Earthing Guidance Notes

Earthing Guidance Notes Central Networks Earthing Manual Section E2 Earthing Guidance Notes Version: 2 Date of Issue: September 2007 Author: Nigel Johnson Job Title: Earthing Specialist Approver: John Simpson Job Title: Head

More information

Modular Systems, PPMV, 2014 UniPack-G Glass Fiber Reinforced Polyester Compact Secondary Substation

Modular Systems, PPMV, 2014 UniPack-G Glass Fiber Reinforced Polyester Compact Secondary Substation Modular Systems, PPMV, 2014 UniPack-G Glass Fiber Reinforced Polyester Compact Secondary Substation Index News Introduction Applications & Segments Main Components Applicable Standards Technical characteristics

More information

INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION

INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION February 2013 NOTE: If conflict exists between St. Thomas Energy s Conditions of Service and this document, the Conditions

More information

Hyperlinks are Inactive

Hyperlinks are Inactive Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

3-PHASE LOW VOLTAGE NETWORK LOAD BALANCER : A COST EFFECTIVE SOLUTION TO LINE VOLTAGE VARIATIONS

3-PHASE LOW VOLTAGE NETWORK LOAD BALANCER : A COST EFFECTIVE SOLUTION TO LINE VOLTAGE VARIATIONS 3-PHASE LOW VOLTAGE NETWORK LOAD BALANCER : A COST EFFECTIVE SOLUTION TO LINE VOLTAGE VARIATIONS Pierre FRISTOT Olivier CONSTANT Catherine MONCET Omegawatt - France Omegawatt - France SDET - France pierre.fristot@omegawatt.fr

More information

MEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV.00 2012.4

MEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV.00 2012.4 CE - BF - C - en - REV.00 2012.4 APPLICATION CE-BF Switchbords up to 40.5 kv are designed for use in public and industrial distribution system up to 40,5KV for the operation and protection of lines, transformers,

More information

CONSTRUCTION STANDARD ELECTRIC OPERATIONS ORGANIZATION

CONSTRUCTION STANDARD ELECTRIC OPERATIONS ORGANIZATION Page 1 of 11 ****This Standard Supercedes BECo CS2.13-2.3 & ComElectric OH Construction Manual, System Grounding Section, drawings CGND, GRDSUM, and C2**** 1.0 Bill of Materials GROUNDING AND BONDING POLE-MOUNTED

More information

ScottishPower Distribution Cables & Equipment. Metal Theft

ScottishPower Distribution Cables & Equipment. Metal Theft ScottishPower Distribution Cables & Equipment Metal Theft April 2012 As an aid to deterring to metal theft this booklet has been put together to help identify the types of utility power cables and associated

More information

environment briefing02

environment briefing02 PRODUCED BY THE SAFETY, HEALTH & ENVIRONMENT GROUP OF THE ENERGY NETWORKS ASSOCIATION - JULY 2006 environment briefing02 transporting electricity Overhead Lines or Underground Cables? Introduction The

More information

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China ELECTRIC POWER DISTRIBUTION SYSTEMS F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China Keywords: Distribution system planning, Load characteristics, Subtransmission Lines, Distribution

More information

Chapter 1. Network Structures

Chapter 1. Network Structures Chapter 1 Network Structures Definition Standard IEC 60038 defines voltage ratings as follows: Low voltage (): for a phase-to-phase voltage of between 100 V and 1,000 V, the standard ratings are: 400 V

More information

Emirates Aluminium starts up World s first fully integrated power distribution system from ABB

Emirates Aluminium starts up World s first fully integrated power distribution system from ABB Reprint from Aluminium World 2009, Volume 2 Emirates Aluminium starts up World s first fully integrated power distribution system from ABB Emirates Aluminium (EMAL), a joint venture between Abu Dhabi s

More information

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Course No: E02-010 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education

More information

CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE

CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE 8.1 SYSTEM 8.1.1 Armoured, screened underground cables are used for control communication in electrified areas to limit induction effect. 8.2

More information

Indicative costs for replacing SWER lines

Indicative costs for replacing SWER lines WIT.3019.005.0002 Indicative costs for replacing SWER lines 28 th August 2009 Department of Primary Industries Parsons Brinckerhoff Australia Pty Limited ABN 80 078 004 798 SWER_Replacement_Options_Report_v1_0

More information

POWER NETWORKS. 2014-15 Electricity Network Tariffs and Charges and Future Price Trends

POWER NETWORKS. 2014-15 Electricity Network Tariffs and Charges and Future Price Trends POWER NETWORKS 2014-15 Electricity Network Tariffs and Charges and Future Price Trends August 2014 Power and Water Corporation Table of Contents 1 Business Characteristics... 3 2 2014 Network Price Determination...

More information

POWER NETWORKS. 2015-16 Electricity Network Tariffs and Charges and Future Price Trends

POWER NETWORKS. 2015-16 Electricity Network Tariffs and Charges and Future Price Trends POWER NETWORKS 2015-16 Electricity Network Tariffs and Charges and Future Price Trends July 2015 Power and Water Corporation 1 Table of Contents 1 Business Characteristics 3 2 2014 Network Price Determination

More information

Comparative study for cables and busbars

Comparative study for cables and busbars Comparative study for cables and busbars Preliminary considerations To compare the prices of two categories of product as different as traditional cables and busbars, it is necessary to make some preliminary

More information

Product overview brochure. ABB Medium Voltage Products Our one-stop approach for every medium voltage application

Product overview brochure. ABB Medium Voltage Products Our one-stop approach for every medium voltage application Product overview brochure ABB Medium Voltage Products Our one-stop approach for every medium voltage application Overview ABB meets every need for reliable, safe and energy-efficient medium voltage switchgear,

More information

FAQs-Main switchboard design criteria

FAQs-Main switchboard design criteria FAQs-Main switchboard design criteria Q: What is the Australian standard for main switchboards? Current Australian standard is AS/NZS 3439.1: 2002 originating from IEC 60439. The new series of standard

More information

12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting

12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting 12 SOLAR PHOTOVOLTAIC POWER by John Ware IT IS PLANNED for BS 7671:2008 to include a new Section 712 providing additional requirements for safety applicable to solar photovoltaic (pv) power supply systems.

More information

BL20A0501 Electricity distribution technology. Introduction Jarmo Partanen

BL20A0501 Electricity distribution technology. Introduction Jarmo Partanen BL20A0501 Electricity distribution technology Introduction Jarmo Partanen Introduction to ED Prof. Jarmo Partanen, D.Sc Jukka Lassila Topics of lectures Introduction to Electricity Distribution, 27.10

More information

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F TABLE OF CONTENTS Appendix F - Electrical Engineering Design Criteria F.1 Introduction...F-1 F.2 Codes and Standards...F-1 F.3 Switchyard and Transformers...F-1

More information

Executive summary 2. 1 Introduction 4

Executive summary 2. 1 Introduction 4 Flexible Networks for a Low Carbon Future Future Network Monitoring Strategy September 2015 Contents Executive summary 2 Glossary 3 1 Introduction 4 2 Fundamental principles of monitoring 5 2.1 LCT monitoring

More information

Engineering Recommendation G81 - Part 1: Design and Planning

Engineering Recommendation G81 - Part 1: Design and Planning PRODUCED BY THE ENGINEERING DIRECTORATE OF THE ENERGY NETWORKS ASSOCIATION Engineering Recommendation G81 - Part 1: Design and Planning Issue 2 Ammendment 1 January 2008 Framework for design and planning,

More information

All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations.

All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations. DIVISION 16 ELECTRICAL SECTION 16100 - ELECTRICAL PART 1 - GENERAL SCOPE All electrical work as shown on the drawings and as necessary to provide a complete electrical system. Include primary service,

More information

BASIC NEC CODE RULES AND DESIGN PRACTICE

BASIC NEC CODE RULES AND DESIGN PRACTICE BASIC NEC CODE RULES AND DESIGN PRACTICE Wire Ampacity and Size Circuit Breaker Size 1. Maximum loading for any branch circuit is 80% of rating of circuit for ampacity of wire for any load. NEC 220-2,

More information

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS Meher Capacitors offers reliable and innovative products and solutions in the fields of Reactive Power Compensation, Power Quality and Energy

More information

Distribution Design Manual

Distribution Design Manual 1 6 DESIGN PARAMETERS 4 6.1 Glossary and Definitions 4 6.2 Standard Voltages and Frequency 5 6.2.1 Transmission 5 6.2.2 Subtransmission 6 6.2.3 MV Distribution 6 6.2.4 LV Distribution 7 6.3 Point of Supply

More information

Gulf Cable & Electrical Ind. Co.

Gulf Cable & Electrical Ind. Co. CONTENTS INTRODUCTION PRODUCT RANGE I PRODUCT DATA TABLES XLPE INSULATED 600/1000V CABLES Two Core Cables CU/XLPE/PVC/LC/PVC/SWA/PVC 1 Three Core Cables CU/XLPE/PVC/LC/PVC/SWA/PVC 2 Four Core Cables CU/XLPE/PVC/LC/PVC/SWA/PVC

More information

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 SHE Transmission 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 Summary This paper presents SHE Transmission s views and approach on the impact of transmission losses on the transmission

More information

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,

More information

www.klmtechgroup.com TABLE OF CONTENT

www.klmtechgroup.com TABLE OF CONTENT Page : 1 of 13 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia ELECTIRAL GROUNDING TABLE OF CONTENT

More information

Unified requirements for systems with voltages above 1 kv up to 15 kv

Unified requirements for systems with voltages above 1 kv up to 15 kv (1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements apply to

More information

A Review of Engineering Recommendations P15, P17 and P27 (Transformers, Cables and Overhead Lines)

A Review of Engineering Recommendations P15, P17 and P27 (Transformers, Cables and Overhead Lines) A Review of Engineering Recommendations P15, P17 and P27 (Transformers, Cables and Overhead Lines) DOCUMENT NUMBER CLNR-L263 AUTHORS David Miller, Northern Powergrid Duncan Yellen and Daniel Hollingworth,

More information

POWER CORPORATION Requirements for Distribution Wires Access

POWER CORPORATION Requirements for Distribution Wires Access POWER CORPORATION Requirements for Distribution Wires Access Contact Information: ENMAX Power Corporation 8820 52 St SE Phone: 514-3700 Calgary, Alberta Fax: 514-3719 T2C 4E7 Version 3.0 January 2005 i

More information

Electric Power Distribution

Electric Power Distribution Electric Power Distribution A S Pabla Consulting Engineer and Former Chief Engineer Punjab State Electricity Board McGraw-Hill New York Chicago San Francisco Lisbon London Madrid Mexico City Milan New

More information

Electrical Grounding. Appendix C

Electrical Grounding. Appendix C Appendix C Electrical Grounding Low-Voltage Equipment Grounding The most frequently cited Office of Safety and Health Administration (OSHA) electrical violation is improper occupational grounding of equipment

More information

Screened cable and data cable segregation

Screened cable and data cable segregation December 2007 Screened cable and data cable segregation Can an armoured power cable be considered a screened cable and how does this relate to power and data cable segregation? The short answer is yes;

More information

Western Australian Distribution Connections Manual. Document Control

Western Australian Distribution Connections Manual. Document Control 2015 Document Control Endorsement/Approvals Approved by Approved by Name Title Signature Justin Murphy Andy Kondola Manager Asset Management Services Horizon Power Head of Function Network Policy & Standards

More information

REB 1 REB 3 REB 5 REB 6 REB 8 REB 10 REB 12 REB 16

REB 1 REB 3 REB 5 REB 6 REB 8 REB 10 REB 12 REB 16 REB 1 REB 3 REB 5 REB 6 REB 8 REB 10 REB 12 REB 16 Manually Operated Electronic Speed Controller Single Phase For all applications using suitably specified single-phase induction motor fans 1 GENERAL The

More information

RCP2 Portfolio Overview Document

RCP2 Portfolio Overview Document RCP2 Portfolio Overview Document Portfolio: Expenditure Class: Base Capex Expenditure Category: Grid Replacement & Refurbishment As at date: 15 November 2013 Expenditure Forecast Real 2012/13 NZ$ (m) 2015-2016

More information

PLEASE NOTE. For more information concerning the history of these regulations, please see the Table of Regulations.

PLEASE NOTE. For more information concerning the history of these regulations, please see the Table of Regulations. PLEASE NOTE This document, prepared by the Legislative Counsel Office, is an office consolidation of this regulation, current to August 1, 2013. It is intended for information and reference purposes only.

More information

Electricity Service Standards

Electricity Service Standards CODE OF PRACTICE Electricity Service Standards Revised August 2015 Contents 1. Preface... 1 Format... 1 2. Application and Objectives... 2 3. Service Standards... 3 3.1 General... 3 3.2 Particular... 3

More information

Step Voltage Regulators

Step Voltage Regulators Step Voltage Regulators Don Wareham Field Application Engineer Today s Agenda Introduction Voltage Regulator theory Voltage Regulator application considerations Installation and proper bypassing Wrap-up/questions

More information

SOLAR PV STANDARD ELECTRICAL PLAN Microinverter Systems for Single Family Dwellings

SOLAR PV STANDARD ELECTRICAL PLAN Microinverter Systems for Single Family Dwellings *** Provide this document to the inspector along with ALL system installation instructions *** Project Address: Scope: Standard plan for the installation of grounded microinverter solar PV systems, not

More information

Comparison of GIS and AIS systems for urban supply networks

Comparison of GIS and AIS systems for urban supply networks Comparison of GIS and AIS systems for urban supply networks Studies carried out by ABB show that for urban supply networks the combination of HV gas-insulated switchgear (GIS) and HV cable has important

More information

Considering UNDERGROUND. tampaelectric.com

Considering UNDERGROUND. tampaelectric.com Considering UNDERGROUND Electric Service? tampaelectric.com INTRODUCTION The majority of Tampa Electric s customers receive their electric service through overhead construction, which is the standard type

More information

Power Voltage Transformers for Air Insulated Substations. THE PROVEN POWER.

Power Voltage Transformers for Air Insulated Substations. THE PROVEN POWER. Power Voltage Transformers for Air Insulated Substations THE PROVEN POWER. Introduction Trench Power Voltage Transformers (Power VTs) combine the attributes of an inductive voltage transformer with the

More information

16 West Coast Regional Plan

16 West Coast Regional Plan 16 West Coast Regional Plan 16.1 Regional overview 16.2 West Coast transmission system 16.3 West Coast demand 16.4 West Coast generation 16.5 West Coast significant maintenance work 16.6 Future West Coast

More information

AMSC s Superconductor Cable Technologies for Electric Utilities

AMSC s Superconductor Cable Technologies for Electric Utilities International Workshop 2014 AMSC s Superconductor Cable Technologies for Electric Utilities Michael Ross, P.E. Managing Director of Superconductor Power Systems AMSC Corporate Facts Headquartered in MA,

More information

Size template. Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer

Size template. Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer Size template Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer The average system size has doubled since 2010 Key Network Issues Reverse power on up to 12 off 11 kv feeders

More information

SELECTION OF FINAL CIRCUIT PROTECTION

SELECTION OF FINAL CIRCUIT PROTECTION SELECTION OF FINAL CIRCUIT PROTECTION By Phil Williams, Product Marketing Manager, Power Distribution Components, Eaton Executive summary The selection of devices for final circuit protection in electrical

More information

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering Title 20 PUBLIC SERVICE COMMISSION Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES Chapter 02 Engineering Authority: Public Utility Companies Article, 2-121, 5-101 and 5-303, Annotated Code of Maryland.

More information

WA Electrical Requirements

WA Electrical Requirements WA Electrical Requirements Issued by the Director of Energy Safety January 2014 Preface Energy Safety Division (EnergySafety) of the Department of Commerce, following consultation with network operators

More information

Code of Practice Electricity transmission and distribution asset management. February 2009

Code of Practice Electricity transmission and distribution asset management. February 2009 Code of Practice Electricity transmission and distribution asset management February 2009 CONTENTS 1 PREFACE...4 2 APPLICATION AND OBJECTIVES...5 3 SCOPE...6 4 DEFINITIONS...7 5 DESIGN AND CONSTRUCTION...11

More information

Emergency Telephone Systems

Emergency Telephone Systems Standard Issued Date: 22 May 2014 Important Warning This document is one of a set of standards developed solely and specifically for use on the rail network owned or managed by the NSW Government and its

More information

LV MCC LOW VOLTAGE SWITCHGEAR MOTOR CONTROL CENTRE PRODUCT GUIDE

LV MCC LOW VOLTAGE SWITCHGEAR MOTOR CONTROL CENTRE PRODUCT GUIDE LV MCC LOW VOLTAGE SWITCHGEAR MOTOR CONTROL CENTRE PRODUCT GUIDE 380/415/690 Volt AC 50/65/80/100 ka 1. Product Guide Low Voltage Motor Control Centre CONTSTRUCTION Continuous "poured in place" gasket

More information

4 IX D N E P P A Installation methods Current-carrying capacity and voltage drop for cables Reference method IET Wiring Matters

4 IX D N E P P A Installation methods Current-carrying capacity and voltage drop for cables Reference method IET Wiring Matters 8 Appendix 4 of BS 7671 by Mark Coles Appendix 4, Current-carrying capacity and voltage drop for cables and flexible cords, has seen significant changes with the publishing of BS 7671:2008. This article

More information

Presentation to CIGRE Next Generation Network. Visit of Seine substation

Presentation to CIGRE Next Generation Network. Visit of Seine substation Presentation to CIGRE Next Generation Network Visit of Seine substation Projet Seine 30 août 2012 Contents 0. Presentation of RTE 1. Power supply of «Ile-de-France» and Paris 2. 225 kv Paris substations

More information

Federal Wage System Job Grading Standards for Electric Power Controlling, 5407. Table of Contents

Federal Wage System Job Grading Standards for Electric Power Controlling, 5407. Table of Contents Federal Wage System Job Grading Standards for Electric Power Controlling, 5407 Table of Contents WORK COVERED... 2 WORK NOT COVERED...2 TITLES... 2 GRADE LEVELS... 2 SPECIAL ADDITIONAL RESPONSIBILITIES...

More information

ESB Networks Ltd Statement of Charges

ESB Networks Ltd Statement of Charges ESB Networks Ltd Statement of Charges Revision Date: 9/2014 Revision No.: 11 Document No: DOC-101209-AXR Issued by: ESB NETWORKS LTD Approved by : CER Effective Date: 01/10/2014 Commercial and Renewable

More information

Approved Meter Sockets and Cabinets

Approved Meter Sockets and Cabinets Single Unit Residential Guide 1 PHASE, 120/240 VOLT S METERING (Metering sockets and cabinets are supplied by Customer). Outdoor meter mounting height is 1730 mm ( 5 8 ) to center of meter ± 100 mm ( 4

More information

Table of Contents. TransformerIQ FAQs 1

Table of Contents. TransformerIQ FAQs 1 [12/12] FAQs Table of Contents FAQ 1. What size transformer will TransformerIQ monitor?... 2 FAQ 2. Are there different TransformerIQ versions?... 2 FAQ 3. How are the units powered?... 2 FAQ 4. What is

More information

FIXED CHARGE: This is a cost that goes towards making the service available, including

FIXED CHARGE: This is a cost that goes towards making the service available, including ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer

More information

Unarmored Variable Frequency Drive (VFD) Cable Termination Guide

Unarmored Variable Frequency Drive (VFD) Cable Termination Guide Authorized Distributor Unarmored Variable Frequency Drive (VFD) Cable Termination Guide Be Certain with Belden A Step-by-Step Look at the Connection/Termination of Unarmored VFD Cables Terminating Unarmored

More information

BUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE

BUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE BUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE Toll Free Telephone Numbers Residential Services 800.454.3853 Commercial Services 800.653.5307 Utility Locating Company N.C. 800.632.4949 S.C. 888.721.7877

More information

Does your new building

Does your new building Does your new building need electricity? To save you time and money, talk to us early about your power supply. Our equipment will occupy ground space on your property. You need to consider the size and

More information

HPS Universal. Single and Three Phase Potted. Buck-Boost Transformers. Buck-Boost Applications & Standard Specification... 80

HPS Universal. Single and Three Phase Potted. Buck-Boost Transformers. Buck-Boost Applications & Standard Specification... 80 Buck-Boost Transformers Single and Three Phase Potted Buck-Boost Transformers Buck-Boost Applications & Standard Specification... 80 Selecting Buck-Boost Transformers... 81 Single Phase Selection Tables...

More information

ACTIV-8 PLUS Insulated Conductor Bar

ACTIV-8 PLUS Insulated Conductor Bar ACTIV-8 PLUS Insulated Conductor Bar A product made in Australia www.conductix.com.au ACTIV-8 PLUS ACTIV-8 is the most widely used and stocked conductor rail in use in Australia. It was designed by Conductix

More information

A product made in Australia. Insulated Conductor Rail ACTIV-8 PLUS

A product made in Australia. Insulated Conductor Rail ACTIV-8 PLUS A product made in Australia Insulated Conductor Rail ACTIV-8 PLUS ACTIV-8 PLUS The Industry Standard in Conductor Rails ACTIV-8 is the most widely used and stocked conductor rail in use in Australia. It

More information

11. Assessment of service 12. S-phase supply 13. Water heaters NORTHERN TERRITORY OF AUSTRALIA ELECTRICITY BY-LAWS T ABLE OF PROVISIONS

11. Assessment of service 12. S-phase supply 13. Water heaters NORTHERN TERRITORY OF AUSTRALIA ELECTRICITY BY-LAWS T ABLE OF PROVISIONS NORTHERN TERRITORY OF AUSTRALIA ELECTRICITY BY-LAWS T ABLE OF PROVISIONS By-law PART I - PRELIMINARY 1. Citation 2. Repeal 3. Interpretation 4. Qualifications of inspector PART II - INSPECTORS PART III

More information

Cable/Conduit Conversion

Cable/Conduit Conversion Cable/Conduit Conversion Busway can be used in many applications where cable and conduit are more commonly used. The question arises, Why use busway instead of conventional cable and conduit? Benefits

More information

3. TYPES OF SERVICE AVAILABLE. 3.1 Scope

3. TYPES OF SERVICE AVAILABLE. 3.1 Scope 3. TYPES OF SERVICE AVAILABLE 3.1 Scope UI supplies 60 hertz, alternating current with different voltage and ampere ratings. Not all voltage and ampere ratings are available throughout the entire service

More information

BC Hydro. Electric Distribution System Cost of Service Study

BC Hydro. Electric Distribution System Cost of Service Study BC Hydro Electric Distribution System Reimer Consulting Group Inc. Arnie Reimer May 7, 2010 Table of Contents 1. Executive Summary... 3 2. BC Hydro Electric Distribution System... 4 2.1. General Description...

More information

Building Electrical Infrastructure

Building Electrical Infrastructure Building Electrical Infrastructure Industrial & Commercial Connections, Industrial / Urban Residential Development, Asset Relocation, Street Lighting Our Company Our vision is to combine electrical engineering

More information

CHAPTER 4 UTILITY SYSTEMS ELECTRICAL. Utility Systems Electrical. Main Panel

CHAPTER 4 UTILITY SYSTEMS ELECTRICAL. Utility Systems Electrical. Main Panel CHAPTER 4 UTILITY SYSTEMS ELECTRICAL Utility Systems Electrical The electrical supply to your home begins outside, where you will see either an overhead feed and piping down the side of your home or (if

More information

TECHNICAL BRIEF. Commercial PV in Australia and New Zealand Using the Enphase Microinverter System

TECHNICAL BRIEF. Commercial PV in Australia and New Zealand Using the Enphase Microinverter System TECHNICAL BRIEF Commercial PV in Australia and New Zealand Using the Enphase Microinverter System 2015 Enphase Energy Inc. All rights reserved May 2015 Table of Contents Commercial PV in Australia and

More information

Power products and systems. Intelligent solutions for power distribution Zone concept

Power products and systems. Intelligent solutions for power distribution Zone concept Power products and systems Intelligent solutions for power distribution Zone concept Securing continuous power supply ABB is one of the world's leading power and automation technology companies whose products,

More information

Short Circuit Current Calculations

Short Circuit Current Calculations Introduction Several sections of the National Electrical Code relate to proper overcurrent protection. Safe and reliable application of overcurrent protective devices based on these sections mandate that

More information

Trade of Electrician. Three-phase Distribution Boards And Socket Circuits

Trade of Electrician. Three-phase Distribution Boards And Socket Circuits Trade of Electrician Standards Based Apprenticeship Three-phase Distribution Boards And Socket Circuits Phase 2 Module No. 2.3 Unit No. 2.3.2 COURSE NOTES Created by Charlie Walsh - Athlone TC Revision

More information

Cables, Cable Laying & Accessories Manual

Cables, Cable Laying & Accessories Manual Distribution Business Cables, Cable Laying & Accessories Manual Database ref: File Ref: Title Page & Revision Log For Cables & Access v4 - Nov 2003.doc Manual Name: Cables & Accessories Manual Version

More information

Respecting the environment

Respecting the environment MAIN FEATURE CHAPTER I RESEARCH WITH AN EYE ON THE FUTURE Respecting the environment Low power losses and a lesser visual impact on the landscape make Gas-Insulated Lines (GIL) a very environmentally friendly

More information

Primary and Secondary Electrical Distribution Systems

Primary and Secondary Electrical Distribution Systems Primary and Secondary Electrical Distribution Systems Critical Facilities Round Table 12th Quarterly Membership Meeting June 2, 2006 David D. Roybal. P.E. Eaton Electrical Cutler-Hammer Products Utility

More information

Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation

Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation Medium Voltage (MV) & High Voltage (HV) Training Module 6 Date of the presentation Electrical System Basics MV vs. HV - Definitions Differences between USA and the rest of the world IEC define a high voltage

More information

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES 1. Acceptance of Electricity Service By establishing or requesting a POD or by continuing an

More information

Part 1 System Modeling & Studies for Existing Systems

Part 1 System Modeling & Studies for Existing Systems Part 1 System Modeling & Studies for Existing Systems Operation Technology, Inc. Copyright 2009 Result of rapid release of energy due to an arcing fault between two conductors. Bus voltages > 208V Temperatures

More information