ANKERLIG POWER STATION CONVERSION AND INTEGRATION PROJECT, WESTERN CAPE PROVINCE
|
|
|
- Corey Small
- 10 years ago
- Views:
Transcription
1 ANKERLIG POWER STATION CONVERSION AND INTEGRATION PROJECT, WESTERN CAPE PROVINCE DRAFT ENVIRONMENTAL MANAGEMENT PLAN (EMP): ADDENDUM TO THE ENVIRONMENTAL MANAGEMENT PLAN (EMP) FOR THE ANKERLIG OPEN CYCLE GAS TURBINE POWER STATION IN THE ATLANTIS AREA, WESTERN CAPE PROVINCE (REVISION 1 OF THE EMP DATED SEPTEMBER 2007) Submitted as part of the EIA Report October 2008 Prepared for Eskom Holdings Ltd Eskom Generation & Eskom Transmission PO Box 1091 Johannesburg 2000 Prepared by Savannah Environmental (Pty) Ltd PO Box 148 Sunninghill 2175
2
3 PROJECT DETAILS DEAT Reference No. : 12/12/20/1014 (power station conversion) 12/12/20/1037 (transmission power line) Title : Environmental Impact Assessment Process Draft Environmental Impact Assessment (EIA) Report: Proposed Ankerlig Power Station Conversion and Transmission Integration Project, Western Cape Province Authors : Savannah Environmental (Pty) Ltd Jo-Anne Thomas & Karen Jodas Sub-consultants : Demos Dracoulides & Associates MetroGIS Southern Hemisphere Consulting & Development Consultants Nick Helme Botanical Surveys Department of Botany & Zoology, Stellenbosch University Archaeology Contracts Office, Department of Archaeology: University of Cape Town Arup (Pty) Ltd Sustainable Futures ZA Client : Eskom Holdings Limited (Eskom Generation Division) Report Status : Draft EMP (Addendum to the Ankerlig Open Cycle Gas Turbine Power Station EMP) submitted as part of the Environmental Impact Assessment Report When used as a reference this report should be cited as: Savannah Environmental (2008) Draft Environmental Management Plan (Addendum to the Ankerlig Open Cycle Gas Turbine Power Station EMP): Proposed Power Station Conversion and Integration Project in the Western Cape Province for Eskom Holdings Limited for Eskom Holdings Limited COPYRIGHT RESERVED This technical report has been produced for Eskom Holdings Limited. The intellectual property contained in this report remains vested in Savannah Environmental. No part of the report may be reproduced in any manner without written permission from Savannah Environmental (Pty) Ltd or Eskom Holdings Limited. Project Details Page i
4 DEFINITIONS AND TERMINOLOGY The following should be read in conjunction with the Glossary of Terms and Abbreviations section of the Ankerlig Open Cycle Gas Turbine Power Station EMP (refer to page 2 of Ankerlig Power Station EMP). Cumulative impacts: Impacts that result from the incremental impact of the proposed activity on a common resource when added to the impacts of other past, present or reasonably foreseeable future activities (e.g. discharges of nutrients and heated water to a river that combine to cause algal bloom and subsequent loss of dissolved oxygen that is greater than the additive impacts of each pollutant). Cumulative impacts can occur from the collective impacts of individual minor actions over a period of time and can include both direct and indirect impacts. Direct impacts: Impacts that are caused directly by the activity and generally occur at the same time and at the place of the activity (e.g. noise generated by blasting operations on the site of the activity). These impacts are usually associated with the construction, operation or maintenance of an activity and are generally obvious and quantifiable. Endangered species: Taxa in danger of extinction and whose survival is unlikely if the causal factors continue operating. Included here are taxa whose numbers of individuals have been reduced to a critical level or whose habitats have been so drastically reduced that they are deemed to be in immediate danger of extinction. Endemic: An "endemic" is a species that grows in a particular area (is endemic to that region) and has a restricted distribution. It is only found in a particular place. Whether something is endemic or not depends on the geographical boundaries of the area in question and the area can be defined at different scales. Environmental management: Ensuring that environmental concerns are included in all stages of development, so that development is sustainable and does not exceed the carrying capacity of the environment. Indirect impacts: Indirect or induced changes that may occur as a result of the activity (e.g. the reduction of water in a stream that supply water to a reservoir that supply water to the activity). These types of impacts include all the potential impacts that do not manifest immediately when the activity is undertaken or which occur at a different place as a result of the activity. Definitions and Terminology Page ii
5 Interested and Affected Party: Individuals or groups concerned with or affected by an activity and its consequences. These include the authorities, local communities, investors, work force, consumers, environmental interest groups and the general public. Red data species: Species listed in terms of the International Union for Conservation of Nature and Natural Resources (IUCN) Red List of Threatened Species, and/or in terms of the South African Red Data list. In terms of the South African Red Data list, species are classified as being extinct, endangered, vulnerable, rare, indeterminate, insufficiently known or not threatened (see other definitions within this glossary). Significant impact: An impact that by its magnitude, duration, intensity or probability of occurrence may have a notable effect on one or more aspects of the environment. Definitions and Terminology Page iii
6 TABLE OF CONTENTS PAGE CHAPTER 1: OVERVIEW OF THE PROJECT Description of the Proposed Project Description of the proposed Power Station Conversion Potential Environmental Impacts associated with the Proposed Power Station Conversion Description of the proposed Transmission Integration Project Potential Environmental Impacts associated with the Proposed Transmission Integration Project...5 CHAPTER 2: PURPOSE & OBJECTIVES OF THE EMP ADDENDUM Purpose of the EMP and associated Addendums Structure of the Addendum to the EMP Project Team CHAPTER 3: MANAGEMENT PLAN: PLANNING & DESIGN Goal for Planning Objectives for Planning OBJECTIVE: To ensure that the planning of the project responds to the identified environmental constraints and opportunities OBJECTIVE: To ensure adequate regard has been taken of landowner concerns along the power line alignment and that these are appropriately addressed CHAPTER 4: MANAGEMENT PLAN: CONSTRUCTION Overall Goal for Construction Objectives for Construction OBJECTIVE: maintain the construction noise levels around the power station site within acceptable levels and minimise the impact on residential areas and communities OBJECTIVE: Management of dust and emissions to air OBJECTIVE: Protection of sensitive areas, vegetation and faunal habitats OBJECTIVE: Protection of sites of heritage value OBJECTIVE: To ensure all construction activities/practices/procedures are undertaken with the appropriate level of environmental awareness to minimise environmental risk, in line with the specifications of the EMP CHAPTER 5: MANAGEMENT PLAN: OPERATION AND MAINTENANCE Overall Goal for Operation Objectives for Operation and Maintenance OBJECTIVE: Maintain the noise levels around the power station site within acceptable levels and minimise the impact on residential areas and communities.. 29 OBJECTIVE: Management of dust and emissions to air OBJECTIVE: Minimisation of visual impacts OBJECTIVE: Protection of vegetation and faunal habitats OBJECTIVE: Protection of avifauna Table of Contents Page vi
7 OVERVIEW OF THE PROJECT CHAPTER Description of the Proposed Project Eskom Holdings Limited (Eskom) is investigating the conversion of the nine Open Cycle Gas Turbine (OCGT) units at the existing Ankerlig Power Station (located in Atlantis Industria) plant to a Combined Cycle Gas Turbine (CCGT). This would increase the generating capacity of this existing power station by a maximum capacity of 720 MW. The proposed conversion would involve the addition of Heat Recovery Steam Generators (HRSG) to generate steam, and steam turbines and generators to the existing gas turbine plant (essentially adding a steam cycle to the existing gas cycle), and would be established on the same site as the existing Ankerlig Power Station. Eskom is also proposing the construction of a 400kV transmission power line between the Ankerlig Power Station and the already authorised Omega Substation (to be located on the Farm Groot Oliphantskop 81) to integrate the additional power generated at Ankerlig Power Station into the national electricity grid. The Ankerlig Power Station conversion and associated transmission integration project can be seen as a third phase of the original Atlantis OCGT power station project. The construction of the initial OCGT units (i.e. the four units now in operation) was the first phase of the project. The second phase of the project (currently under construction) involves the expansion (capacity increase) of the power station by adding another five OCGT units, four fuel tanks and a switchyard to the power station Description of the proposed Power Station Conversion The existing Ankerlig OCGT Power Station is located on the Remainder of Farm No 1395 in the Atlantis Industrial Township, which is located ~40 km from the Cape Town city centre. The Ankerlig OCGT Power Station consists of nine OCGT units (i.e. four existing OCGT units, plus an additional five OCGT units currently under construction) each with a nominal capacity of approximately 150 MW, resulting in a total nominal capacity of approximately MW for the power station. Each OCGT unit consists of one gas turbine driving an electric generator. The concept of converting the OCGT units to CCGT units is to utilise the heat energy from the exhaust of the gas turbine to create steam in the Heat Recovery Steam Generator (HRSG), to drive a steam turbine, instead of this heat energy being exhausted and lost to the atmosphere (as is the current scenario). Conversion of the units to CCGT is therefore based on increased cycle efficiency. Overview of the Project Page 1
8 Simply stated, this can be achieved through the following (and is illustrated in Figure 1.1):» When the hot gas exits the gas turbine as exhaust gas, it has a temperature of up to 600 C. This heat energy is transferred to water in the heat recovery steam generator, instead of being exhausted to the atmosphere.» The heat is used to generate steam (water vapour), which powers the steam turbine to produce mechanical energy.» The resulting mechanical energy is transferred to a generator, where it is converted into electricity. Figure 1.1: Simplified schematic illustrating the CCGT conversion process and components Conversion of the units to CCGT is undertaken to increase cycle thermal efficiency. It is estimated that each converted unit will produce approximately 80 MW additional capacity, i.e. approximately 50% more than a standard OCGT unit. Therefore, an additional 9 x 80 MW increase in capacity (approximately 720 MW total) is foreseen from the OCGT to CCGT conversion. The total nominal capacity of the Ankerlig Power Station will therefore increase to approximately MW. The proposed conversion will be on the site of the existing Ankerlig Power Station, and will not require any additional land take outside of the existing power station boundaries (refer to Figure 1.2). Overview of the Project Page 2
9 Figure 1.2: Aerial photograph of the Ankerlig Power Station site showing the existing power station infrastructure the power station expansion site, as well as the areas for the placement of infrastructure associated with the proposed power station conversion Overview of the Project Page 3
10 The primary components of the conversion project include the following:» A heat recovery steam generator (HRSG) will be added to the gas turbine to recover waste heat, to drive the steam turbine cycle. In principle, a HRSG is associated with a gas turbine. One HRSG can be linked to 2 or 3 OCGT units.» A condenser which converts exhaust steam from the steam turbine back into water through a cooling process.» Depending on the configuration, a bypass stack for the CCGT, anticipated to be approximately 60 m in height will be associated with each HRSG.» Water treatment plant (for treatment of potable water and production of demineralised water (for steam generation). A waste disposal system for the effluent from this water treatment system will be required.» Dry-cooled technology consisting of a system of air-cooled condenser fans situated in fan banks approximately between m above ground.» Additional fuel storage facilities and associated off-loading and other related infrastructure to cater for the increased fuel requirements associated with the higher load factor (i.e. longer operating hours or a mid-merit operating regime 1 ).» An elevated water tank, approximately 20m high, with a holding volume of approximately 2.5 million litres (i.e. water storage for approximately 5 days of operation). It is important to note that the plant can use liquid fuel or natural gas as fuel. It is envisaged that the CCGT units would initially be diesel-fired, until such time that natural gas becomes available, if it becomes available Potential Environmental Impacts associated with the Proposed Power Station Conversion All components of the proposed power station conversion project will be on the site of the existing Ankerlig Power Station, and will not require any additional land take outside of the existing power station boundaries. Potential impacts associated with the proposed power station conversion project are expected to occur during both the construction and operational phases. In general, impacts are expected to be similar to those associated with the initial phases of the power station project (i.e. the initial 4 OCGT units currently in operation, and the additional 5 OCGT units currently under construction). New impact sources associated with the power station conversion project would include:» Visual impacts as a result of the additional infrastructure associated with the conversion project to be added onto the existing power station (i.e. the heat recovery steam generator (HRSG), the 60 m high stacks, the 25 m - 30 m high aircooled condensers, the additional fuel storage tanks and the water reservoir). 1 Mid-merit capacity is during the daytime from about 6 am to about 10 pm on weekdays. Overview of the Project Page 4
11 » Air quality impacts associated with the construction phase (dust) and the operational phase (emissions from the power station).» Noise impacts associated with the existing OCGT units as well as the additional CCGT components to be added onto the existing power station (i.e. air filters, the gas compressor, the gas turbine, the generator, the electricity transformers, the fans associated with the stacks, the heat recovery equipment, the steam generator, the steam turbine and the air-cooled condenser system associated with the drycooling system).» Impacts on the social environment as a result of the creation of employment opportunities, influx of workers to the area, traffic movements, and impacts on sense of place.» Traffic and transportation impacts associated with the transportation of additional fuel to the power station site as a result of the need to operate the power station at a higher load factor (i.e. for longer hours) than is currently the case. No environmental fatal flaws have been identified to be associated with the proposed power station conversion project. It was concluded that the impacts could be successfully mitigated through the implementation of the management measures detailed in Ankerlig OCGT Power Station EMP (Revision 1 dated September 2007) as well as this addendum to the approved EMP Description of the proposed Transmission Integration Project A 400kV transmission power line is required to be constructed between the Ankerlig Power Station and the Omega Substation (authorised but not yet constructed, and to be located on the Farm Groot Oliphantskop 81) to integrate the additional power generated at this power station to the national electricity grid. The existing substation (high voltage (HV) yard) at the Ankerlig Power Station will be utilised, and no additional infrastructure or expansion of this HV yard is required to accommodate the new transmission power line. From the specialist studies undertaken in the Environmental Impact Assessment (EIA), It is concluded that the adoption of Alternative A (refer to Figure 1.3) would have the lower impact on the overall environment. In addition, this alternative is preferred from a technical perspective as it would allow for future power lines exiting the Koeberg Nuclear Power Station site Potential Environmental Impacts associated with the Proposed Transmission Integration Project Potential impacts associated with the proposed transmission power line are expected to occur during the construction and operational phases, and have been identified to include: Overview of the Project Page 5
12 » Impacts on flora and fauna as a result of the disturbance of habitats within the power line servitude and at tower footprints.» Impacts on heritage sites as a result of disturbance or destruction during the construction phase, as well as due to visual impacts on heritage sites.» Visual impacts on the surrounding area.» Impacts on the social environment as a result of the creation of employment opportunities, influx of workers to the area, impacts on land use, and impacts on sense of place. No environmental fatal flaws have been identified to be associated with the proposed transmission integration project, provided the nominated preferred alternative is implemented. It was concluded that the impacts could be successfully mitigated through the implementation of the management measures detailed in Ankerlig OCGT Power Station EMP (Revision 1 dated September 2007) as well as this addendum to the approved EMP. Overview of the Project Page 6
13 Figure 1.3: Locality map indicating the nominated preferred alternative for the Ankerlig-Omega 400kV transmission power line Overview of the Project Page 7
14 PURPOSE & OBJECTIVES OF THE EMP ADDENDUM CHAPTER 2 An Environmental Management Plan (EMP) provides a link between the impacts predicted and mitigation measures recommended within the EIA report, and the implementation activities of a project to ensure that these activities are managed and mitigated so that unnecessary or preventable environmental impacts do not result. Eskom have an approved EMP in place for the construction, operation and maintenance activities associated with the Ankerlig OCGT Power Station (refer to the EMP (Revision 1 dated September 2007)). This EMP is currently successfully utilised and in force at the operational 4 units of the OCGT power station (and associated 400 kv transmission power lines), and on the construction site for the additional 5 units. Regular compliance audits to the EMP requirements are undertaken by the Environmental Control Officer and an external auditor. As such, it is not deemed necessary to reiterate all the specifications of this approved EMP which are currently being applied to all components of the bigger Ankerlig OCGT Power Station project, and therefore this addendum to the approved EMP has been prepared to specifically address the potential impacts resulting from the power station conversion and transmission integration project only Purpose of the EMP and associated Addendums The purpose of the Ankerlig OCGT Power Station EMP (Revision 1 dated September 2007) as well as this addendum to the approved EMP is to assist in ensuring continuous improvement of environmental performance, reducing negative impacts and enhance positive effects during the construction and operation of the project. An effective EMP is concerned with both the immediate outcome as well as the long-term impacts of the project. The draft EMP has the following objectives:» To outline mitigation measures, and environmental specifications which are required to be implemented for the planning, construction, rehabilitation and operation/maintenance phases of the project in order to minimise the extent of environmental impacts, and to manage environmental impacts associated with the project.» To identify measures that could optimise beneficial impacts.» To ensure that the construction and operation phases do not result in undue or reasonably avoidable adverse environmental impacts, and ensure that any potential environmental benefits are enhanced.» To ensure that all environmental management conditions and requirements as stipulated in the Environmental Authorisation (once issued) are implemented throughout the project life-cycle. Purpose & Objectives of the EMP Page 13
15 » To ensure that all relevant legislation (including national, provincial and local) is complied with during the construction and operation phases» To identify entities who will be responsible for the implementation of the measures and outline functions and responsibilities.» To propose mechanisms for monitoring compliance, and preventing long-term or permanent environmental degradation.» To facilitate appropriate and proactive response to unforeseen events or changes in project implementation that were not considered in the EIA process. This addendum to the approved EMP has been developed as a set of environmental specifications (i.e. principles of environmental management) which are appropriately contextualised to provide clear guidance in terms of the implementation of these specifications for the proposed project. This EMP addendum for the proposed Ankerlig Power Station conversion and transmission integration project has been compiled in accordance with Section 34 of the EIA Regulations and will be further developed in terms of specific requirements listed in any authorisations issued for the proposed project. It should be noted that since this addendum to the EMP is part of the EIA process undertaken for the proposed project, it is important that this document be read in conjunction with the Scoping Report (March 2008) and EIA Report (September 2008). This will contextualise the EMP addendum. This addendum to the approved EMP must be read in conjunction with the relevant sections and appendices of the Ankerlig OCGT Power Station EMP (Revision 1 dated September 2008) Structure of the Addendum to the EMP Several procedures are necessary for Eskom to achieve environmental compliance for the Ankerlig Power Station and transmission integration project. These are described in further detail within the Ankerlig OCGT Power Station EMP (Revision 1 dated September 2008). In order to ensure site-specific compliance associated with the proposed power station conversion and transmission integration, this EMP addendum includes the statement of an over-arching environmental goal, as well as lists a number of objectives in order to meet this goal. The management plan has been structured in table format in order to show the links between the goals for each phase and their associated objectives, activities/risk sources, mitigation actions monitoring requirements and performance indicators. A specific environmental management plan table has been established for each environmental objective. The information provided within the EMP table for each objective is illustrated below: Purpose & Objectives of the EMP Page 14
16 OBJECTIVE: Description of the objective, which is necessary in order to meet the overall goals; these take into account the findings of the environmental impact assessment specialist studies Project component/s Potential Impact Activity/risk source Mitigation: Target/Objective List of project components affecting the objective Brief description of potential environmental impact if objective is not met Description of activities which could impact on achieving the objective Description of the target; include quantitative measures and/or dates of completion Mitigation: Action/control Responsibility Timeframe List specific action(s) required to meet the Who is responsible Time periods for mitigation target/objective described above. for the measures implementation of measures Performance Indicator Monitoring Description of key indicator(s) that track progress/indicate the effectiveness of the management plan. Mechanisms for monitoring compliance; the key monitoring actions required to check whether the objectives are being achieved, taking into consideration responsibility, frequency, methods and reporting 2.3. Project Team Jo-Anne Thomas, the principle author of this addendum to the Environmental Management Plan, is a registered Professional Natural Scientist (in the practice of environmental science) with the South African Council for Natural Scientific Professions. She has extensive knowledge and experience in environmental impact assessment and environmental management, having being involved in EIA processes over the past ten (10) years. Purpose & Objectives of the EMP Page 15
17 MANAGEMENT PLAN: PLANNING & DESIGN CHAPTER Goal for Planning Overall Goal for Planning: Undertake the planning phase of the Ankerlig Power Station conversion and Transmission Integration Project in a way that:» Ensures that the planning of the project components responds to the identified environmental constraints and opportunities.» Ensures that adequate regard has been taken of landowner concerns and that these are appropriately addressed through planning and design (where appropriate and possible).» Ensures that the best environmental options are selected for the required construction and operation activities associated with the project.» Enables the required construction activities to be undertaken without significant disruption to other land uses in the area. This addendum to the approved EMP must be read in conjunction with the relevant sections and appendices of the Ankerlig OCGT Power Station EMP (Revision 1 dated September 2008) Objectives for Planning In order to meet this goal, the following objectives have been identified, together with necessary actions and monitoring requirements. OBJECTIVE: To ensure that the planning of the project responds to the identified environmental constraints and opportunities Once the final transmission power line alignment has been negotiated, surveyed and pegged, a walk-through survey must be undertaken by a suitably qualified heritage specialist in order to determine whether any heritage sites of significance would be impacted by the proposed power line towers. The findings of this specialist survey must be incorporated into this EMP, such that it is updated to include site-specific information which must be incorporated into the construction and operation phases of the project. From the studies undertaken, it was concluded that walk-through surveys by an ecologist and ornithologist are not required as this would not add any significant value to the outcomes of the EIA process. EMP: Planning and Design Page 16
18 Project Project components affecting the objective: component/s» CCGT gas turbine units, water reservoir, fuel storage tanks and lighting structures» Power line towers» access roads Potential Impact» Design fails to respond optimally to the environmental consideration» Power line route that degrades environment unnecessarily, particularly with respect to visual aesthetics, loss of indigenous flora, erosion, and impacts on local communities/residents» Unacceptable noise and air emissions from power station components» Potential exposure to and visual impact on observers travelling along the Dassenberg Road Activities/risk sources» Alignment of power line and positioning of towers and access roads within the approved power line corridor» Positioning of the power station components within the Ankerlig Power Station footprint» Establishment of power station components within the Atlantis Power Station footprint alongside Dassenberg Road Mitigation: Target/Objective» To ensure that the design of the project components respond to the identified environmental constraints and opportunities» To ensure selection of best environmental option for the power station conversion and alignment for the power line» To shielding the project infrastructure in order to not visually impose on road users on Dassenberg Road. Mitigation: Action/control Responsibility Timeframe Undertake appropriate pre-construction planning, including a master plan indicating site layout, infrastructure placement (away from the Dassenburg Road) and the potential vegetated berm. Ensure that appropriate planning is undertaken regarding the placement of any additional lighting structures and that light fixtures are designed such that they only illuminate areas inside the power station facility. In order to reduce the overall noise and air emissions to acceptable levels, final design of equipment will ensure the level of noise and air emissions from the plant must be limited to levels guaranteed by the contractor. Noise mitigation measures to include in design include: Increased boiler casing thickness. Stack exit silencer and transition barrier. Pumps inside enclosure. Steam turbine inside high STC enclosure. Low noise fans with inlet and exit silencers and Eskom/landscape Pre-construction architect/engineer Eskom/lighting Design engineer Eskom/design Design engineer Eskom/design Design engineer EMP: Planning and Design Page 17
19 Mitigation: Action/control Responsibility Timeframe larger footprint Additional infrastructure on the power station site (such as the water reservoir and fuel storage tanks) should be set back (further away) from the road as far as possible The viability of the construction of a 5 to 10 m tall vegetated screening berm between the Dassenburg Road and the power station site should be investigated. Undertake negotiations with affected landowners within the approved power line corridor and agree on landowner-specific conditions for construction and maintenance Undertake a detailed geotechnical survey of the proposed transmission line tower positions in order to fully understand the soils in terms of founding conditions and erosion potential Consider planning and design level mitigation measures recommended by the specialists. The realignment of the preferred power line alignment to facilitate the crossing of the R303 adjacent to (in closer proximity to) the existing power lines, should this be technically feasible. Ensure that bird-friendly power line tower and conductor designs are used. Ensure that no towers or tracks are placed in the wetland areas indicated in the High sensitivity patches in southern half of the power line alignment (as indicated in the EIA Report). Balance technical and financial considerations against environmental constraints and opportunities in finalising the design of key elements (such as the power station components (in terms of noise and air emission mitigation), tower design and required (servitude width). Ensure that any new access road required for accessing the power line are designed to allow for the natural flow of water where required. Crossing of eroded areas on access routes to the power line servitude shall be thoroughly planned and installed according to design and contract specifications. Eskom/design Design engineer Eskom/design Design engineer Negotiator Planning Phase Eskom Design Phase Engineering Design Design Phase Consultant Eskom Transmission Design Phase design team Eskom Transmission Design Phase design team Eskom Transmission Design Phase design team Eskom Tender Design & Design Phase Engineering Design Design Phase Consultant Performance Indicator» Design meets objectives and does not degrade the environment» Design and layouts etc respond to the mitigation measures and recommendations in the EIA report. EMP: Planning and Design Page 18
20 » Final installed power station components minimises any negative environmental impacts and maximises any benefits.» Final surveyed route alignment minimises any negative environmental impacts and maximises any benefits. Monitoring» Ensure that the design implemented meets the objectives and mitigation measures in the EIA report through review of the design by the Project Manager and Environmental Control Officer (ECO) prior to the commencement of construction. OBJECTIVE: To ensure adequate regard has been taken of landowner concerns along the power line alignment and that these are appropriately addressed Transmission power lines are constructed and operated within a servitude (55 m wide for 400kV lines) that is established along the entire length of the power line, and for which the affected landowner is appropriately compensated. Within this servitude, Eskom has certain rights and controls that support the safe and effective operation of the power line. The negotiation process for this servitude is undertaken by Eskom directly with the appropriate landowner and culminates in the signing of a servitude agreement. Here Eskom enters into a legal agreement with the landowner. The agreements will detail such aspects as the exact location and extent of the servitude, and access arrangements and maintenance responsibilities, as well as any specific landowner requirements for construction and maintenance of the power line, as well as regarding rehabilitation measures. Project Project components affecting the objective: component/s» Power line» access roads Potential Impact» Landowners impacted by proposed alignment of the power line, positioning of towers and access road/s» Impacts on current and future land use activities Activities/risk» Positioning of towers and access roads sources» Alignment of power line and placement of towers within the approved corridor Mitigation:» To ensure adequate regard has been taken of concerns of affected Target/Objective and surrounding landowners and that these are appropriately addressed Mitigation: Action/control Responsibility Timeframe Initiate negotiations with landowners timeously. Eskom Lands and Initiate once EMP: Planning and Design Page 19
21 Mitigation: Action/control Responsibility Timeframe Address reasonable expectations/requests of Rights Environmental landowners, where possible. Authorisation obtained. Finalised prior to construction. Avoid the resettlement and/or displacement of Eskom Lands and Planning phase households as far as possible. If resettlement is Rights unavoidable, residents shall be sufficiently compensated and assisted with the relocation process (if required). Performance Indicator» Landowners should be satisfied with the outcome of the negotiations process.» Landowners should be afforded reasonable and appropriate rights/access. Monitoring» Not applicable EMP: Planning and Design Page 20
22 MANAGEMENT PLAN: CONSTRUCTION CHAPTER Overall Goal for Construction Overall Goal for Construction: Undertake the construction phase in a way that:» Ensures that construction activities are properly managed in respect of environmental aspects and impacts.» Enables the construction activities to be undertaken without significant disruption to other land uses in the area, in particular with regard to noise impacts, farming practices, traffic and road use, and effects on local residents.» Minimises the impact on the vegetation and habitats within the area.» Minimises the impact on the archaeological and historical value of the area, and where possible adds to the archaeological record of this area.» Minimises impacts on birds and terrestrial fauna within the study area. This addendum to the approved EMP must be read in conjunction with the relevant sections and appendices of the Ankerlig OCGT Power Station EMP (Revision 1 dated September 2008). This addendum relates only to activities associated with the Ankerlig Power Station Conversion and Transmission Integration Project. Generic environmental specifications and guidelines included within this approved EMP are not repeated here Objectives for Construction In order to meet the goals, the following objectives have been identified, together with necessary actions and monitoring requirements. OBJECTIVE: maintain the construction noise levels around the power station site within acceptable levels and minimise the impact on residential areas and communities Project» Construction activities during the construction phase component/s Potential Impact» Noise impacts on surrounding areas Activity/risk source» Construction activities, i.e. excavating, loading and unloading of trucks, piling, material transport, general building activities, etc. Mitigation: Target/Objective» Minimise noise impacts during the construction phase EMP: Construction Page 21
23 Mitigation: Action/control Responsibility Timeframe Regular maintenance of equipment and fitting of silencers where appropriate. Training of personnel to adhere to operational procedures that reduce the occurrence and magnitude of individual noisy events. Restricting noisy operation such as piling or rock breaking, etc. to daytime hours. Contractor in Duration of consultation with contract Specialist Contractor in Duration of consultation with contract Specialist Contractor Duration of contract Performance» No complaints regarding noise during construction activities Indicator» The measured noise levels around the boundary of the site to be less than 70 dba during day-time and 60 dba during night-time.» The noise levels in Avondale and Protea Park residential areas not to exceed 50 dba and 45 dba during daytime and night-time respectively, due to the power station operations. Monitoring» Biannual noise monitoring during construction lifespan on power station perimeter. The closest residential area to the site and at two selected locations outside the perimeter should also be included.» The noise monitoring should be performed in accordance with SANS and the report submitted to the appropriate authority.» An incident reporting system must be used to record nonconformances to the EMP. OBJECTIVE: Management of dust and emissions to air During the construction phase, limited gaseous or particulate emissions are anticipated from exhaust emissions from construction vehicles and equipment on-site, as well as vehicle entrained dust from the movement of vehicles on the construction site. Project Project components affecting the objective: component/s» Combined cycle units» Power line» Access roads Potential Impact» Dust and particulates from vehicle movement to and on-site, foundation excavation, access road construction and maintenance activities, temporary stockpiles, and vegetation clearing affecting the surrounding residents and visibility» Release of minor amounts of air pollutants (for example NO 2, CO, PM10 and SO 2 ) from vehicles and construction equipment Activities/risk» Clearing of vegetation and topsoil sources» Excavation, grading, scraping» Transport of materials, equipment and components on internal access EMP: Construction Page 22
24 Mitigation: Target/Objective roads» Re-entrainment of deposited dust by vehicle movements» Wind erosion from topsoil and spoil stockpiles and unsealed roads and surfaces» Fuel burning vehicle engines» To ensure emissions from all vehicles are minimised, where possible, for the duration of the construction phase» To minimise nuisance to the community from dust emissions and to comply with workplace health and safety requirements for the duration of the construction phase Mitigation: Action/control Responsibility Timeframe Access roads must be maintained to a manner that will ensure that dust from road or vehicle sources is not visibly excessive. Contractor Erection: during site establishment Maintenance: for duration of contract Appropriate dust suppressant must be applied on all Contractor Duration of exposed areas and stockpiles as required to contract minimise/control airborne dust. Haul vehicles moving outside the construction site Contractor Duration of carrying material that can be wind-blown must be contract covered. Speed of construction vehicles must be restricted, as Contractor Duration of defined by the SHE Representative. contract Burning or incineration of any materials on-site must be Contractor Duration of prohibited. contract Specific fire safety precautions must be implemented Contractor Duration of during welding activities associated with the CCGT units contract and power line construction. Disturbed areas must be re-vegetated as soon as Contractor At completion of practicable. the construction phase Vehicles and equipment must be maintained in a roadworthy Contractor Duration of condition at all times. contract If monitoring results or complaints indicate inadequate Contractor Duration of performance against the criteria indicated, then the source of the problem must be identified, and existing contract procedures or equipment modified to ensure the problem is rectified. Performance Indicator Monitoring No complaints from affected residents or community regarding dust or vehicle emissions Monitoring must be undertaken to ensure emissions are not exceeding the prescribed levels via the following methods: EMP: Construction Page 23
25 » Visual daily inspections of dust generation by construction activities throughout the construction phase. If considered necessary by the SHE Representative, dust gauges will be installed at nearby residences.» Immediate reporting by personnel of any potential or actual issues with nuisance dust or emissions to the Site Manager or SHE Representative.» A complaints register will be maintained, in which any complaints from residents/the community will be logged. Complaints will be investigated and, where appropriate, acted upon.» An incident reporting system will be used to record non-conformances to the EMP. OBJECTIVE: Protection of sensitive areas, vegetation and faunal habitats The construction of the additional fuel storage for the power station conversion and the proposed power line within the servitude requires the clearance of vegetation within the development footprint. Impacts on sensitive areas, vegetation and faunal habitats at the construction stage are expected to be mainly as a result of direct permanent loss of vegetation within the development footprint. In order to minimise impacts on flora, fauna and ecological processes, the development footprint and associated disturbance to topsoil should be limited. Project» Additional fuel storage footprint component/s» Power line tower footprints» Access roads Potential Impact» Localised loss of sensitive, protected and/or Red Data plant species» Damage to surrounding areas» Damage to/removal of Red Data plant species and sensitive faunal habitats» Disturbance to plant communities and habitats Activity/risk source» Clearing and levelling of additional fuel storage area footprint» Clearing of tower footprints, servitude centre line and access roads» Traffic to and from site during all phases of construction (i.e. from surveying to rehabilitation of an area)» Site preparation and earthworks» Excavation of foundations» Mobile construction equipment» Dumping or damage by construction equipment outside of demarcated construction areas Mitigation: Target/Objective» Minimise areas of impact adjacent to proposed fuel storage area and power line servitude to retain natural vegetation as far as possible» Store construction materials in low impact area» Implement monitoring programme EMP: Construction Page 24
26 Mitigation: Action/control Responsibility Timeframe Search and Rescue of certain translocatable, selected succulents and bulbs occurring in the fuel storage area is recommended. These are to be translocated to an area approved by the ECO. Contractor in consultation with Specialist & ECO Pre-construction Areas to be cleared shall be clearly marked in the field Contractor in Pre-construction, to eliminate unnecessary clearing and impact on flora consultation with site and faunal habitats is restricted. Specialist establishment & duration of contract Avoid the unnecessary removal of vegetation for the Contractor Site transmission power line servitude. establishment & duration of contract Limit access to the power line servitude along existing Contractor Site access roads. establishment & duration of contract Minimise the use of herbicides as far as possible. Where herbicides are required to be used, this shall be undertaken by a registered pest control operator in accordance with the relevant legislation. Unnecessary disturbance to areas outside of servitude and power station site shall be strictly controlled. Contractor Duration of contract Contractor Duration of contract Implement monitoring programme Ecologist, ECO Construction Compile rehabilitation programme for areas adjacent to servitude, and implement as soon as possible after construction is completed in an area. Contractor consultation ECO in with Construction phase The weed eradication programme detailed in Appendix Contractor in Duration of C of the approved EMP (September 2007) shall be consultation with contract implemented. ECO Performance Indicator» No disturbance outside of designated work areas.» Minimised clearing of existing/natural vegetation.» Limited impacts on areas of identified and demarcated sensitive habitats/vegetation.» Successful recovery of vegetation in servitudes and other disturbed areas post-construction phase Monitoring» Observation and monitoring of vegetation clearing activities by ECO throughout construction phase.» Supervision of all clearing and earthworks.» An incident reporting system must be used to record nonconformances to the EMP. EMP: Construction Page 25
27 OBJECTIVE: Protection of sites of heritage value Numerous fossil and archaeological sites have been recorded in the broader study area. No specific heritage surveys have been carried out for this project at this stage, as sufficient information was obtainable from existing information. Heritage sites can be negatively affected by disturbance of the land surface, destruction of significant structures and places as well as any action that will alter the feel and appearance of an historic place or building. Therefore, the construction of the transmission line could result in moderate impacts to the land surface during the construction phase but permanent changes in terms of visual impacts and changes to the feel of a landscape. Project List of project components affecting the objective: component/s» Power line towers» access roads Potential Impact» Heritage objects or artefacts found during construction are inappropriately managed or destroyed Activity/risk source» Site preparation and earthworks» Excavation of foundations» Construction equipment movement on site Mitigation: Target/Objective» To ensure that any heritage objects found on site are recorded and/or treated appropriately and in accordance with the relevant legislation Mitigation: Action/control Responsibility Timeframe Familiarise all staff and contractors with procedures for ECO/specialist Pre-construction dealing with heritage objects/sites. Should any finds be unearthed during construction activity, an archaeologist and Heritage Western Cape should be informed immediately. The relevant contact person at Heritage Western Cape is Ms Celeste Booth ( ). ECO Construction Project employees and any contract staff should maintain, at all times, a high level of awareness of the possibility of discovering heritage sites. Apply for sampling permits from SAHRA for work on any archaeological sites identified as needing intervention in other words any archaeological site that will be directly affected by the proposed transmission power lines, substation or access roads. In the event of a find of human remains: 1) leave the remains in place, nothing should be moved Eskom/Contractor Duration of contract Eskom/Contractor Duration of in consultation contract with Specialist Eskom/Contractor Duration of in consultation contract with Specialist EMP: Construction Page 26
28 Mitigation: Action/control Responsibility Timeframe 2) Cordon off the area 3) Call Ms Mary Leslie at SAHRA ( ) 4) Contact an archaeologist 5) Once an archaeologist has examined the find, the archaeologist/sahra should contact SA Police services and the state pathologist to report human remains 6) If the human remains are found to be a legitimate burial or a pre-colonial burial, an emergency exhumation permit will be issued by SAHRA or HWC 7) If a crime is suspected, a police docket will need to be opened. Performance» No disturbance of heritage sites outside of designated work areas. Indicator» All heritage items located are dealt with as per the legislative guidelines. Monitoring» Observation of excavation activities by ECO throughout construction phase.» Supervision of all clearing and earthworks.» Due care taken during earthworks and disturbance of land by all staff and any heritage objects found reported, and appropriate permits obtained from SAHRA prior to the disturbance or destruction of heritage sites.» An incident reporting system should be used to record nonconformances to the EMP. OBJECTIVE: To ensure all construction activities/practices/procedures are undertaken with the appropriate level of environmental awareness to minimise environmental risk, in line with the specifications of the EMP The environmental specifications are required to be underpinned by a series of Method Statements, within which the Contractors and Service Providers are required to outline how any identified environmental risks will practically be mitigated and managed for the duration of the contract. That is, the Contractor will be required to describe how specified requirements will be achieved through the submission of written Method Statements to the Site Manager (and ECO). A Method Statement is defined as a written submission by the Contractor in response to the environmental specification or a request by the Project Manager/Site Manager, setting out the plant, materials, labour and method the Contractor proposes using to conduct an activity, in such detail that the Project Manager/Site Manager is able to assess whether the Contractor's proposal is in accordance with the Specifications and/or EMP: Construction Page 27
29 will produce results in accordance with the Specifications. A Method Statement must cover applicable details with regards to:» Construction procedures» Materials and equipment to be used» Getting the equipment to and from site» How the equipment/material will be moved while on-site» How and where material will be stored» The containment (or action to be taken if containment is not possible) of leaks or spills of any liquid or material that may occur» Timing and location of activities» Compliance/non-compliance with the Specifications, and» Any other information deemed necessary by the Project Manager/Site Manager. The Contractor may not commence the activity covered by the Method Statement until it has been approved by the Site Manager/ECO (or as per the reporting structures in the Ankerlig OCGT Power Station EMP), except in the case of emergency activities and then only with the consent of the Site Manager. Approval of the Method Statement will not absolve the Contractor from their obligations or responsibilities in terms of their contract. EMP: Construction Page 28
30 MANAGEMENT PLAN: OPERATION AND MAINTENANCE CHAPTER Overall Goal for Operation Overall Goal for Operation: To ensure that the operation and maintenance of the Ankerlig Power Station Conversion and Transmission Integration Project does not have unforeseen impacts on the environment and to ensure that all impacts are monitored and the necessary corrective action taken in all cases. In order to address this goal, it is necessary to operate the proposed project in a way that:» Ensures that operation activities are properly managed in respect of environmental aspects and impacts.» Enables operation and maintenance activities to be undertaken without significant disruption to other land uses in the area, in particular with regard to noise impacts, farming practices, traffic and road use, and effects on local residents.» Minimises impacts on birds in the area. This addendum to the approved EMP must be read in conjunction with the relevant sections and appendices of the Ankerlig OCGT Power Station EMP (Revision 1 dated September 2008). This addendum relates only to activities associated with the operation and maintenance of the Ankerlig Power Station Conversion and Transmission Integration Project. Generic environmental specifications and guidelines applicable to the power station and power line operation and maintenance included within this approved EMP are not repeated here Objectives for Operation and Maintenance In order to meet the goal for operation and maintenance, the following objectives have been identified, together with necessary actions and monitoring requirements. OBJECTIVE: Maintain the noise levels around the power station site within acceptable levels and minimise the impact on residential areas and communities The results of the noise impact assessment undertaken as part of the EIA indicate that the potential impact of the power station conversion project on the overall noise levels in the noise-sensitive areas of Atlantis may be of Moderate significance. With the implementation of mitigation measures, this impact is expected to be of low significance. EMP: Operation and Maintenance Page 29
31 Project List of project components affecting the objective: component/s» Air filters» Gas compressor» Gas turbine» Generator» Electricity transformers» Fans associated with the stacks» Heat recovery equipment» Steam generator» Steam turbine» Air-cooled condenser system associated with the dry-cooling system Potential Impact» Increased noise levels in the surrounding areas, noise nuisance and sleep disturbance of the affected communities Activity/risk source» Power station components (as listed above) Mitigation: Target/Objective» To minimise noise levels generated by the facility as far as possible Mitigation: Action/control Responsibility Timeframe Regular maintenance of equipment shall be Eskom Operation undertaken throughout the operation of the power station Training of personnel to adhere to operational Eskom Operation procedures that reduce the occurrence and magnitude of individual noisy events. Implement the noise management and monitoring Eskom Operation plan as per the approved EMP (dated September 2007) Performance Indicator» The measured noise levels around the boundary of the site to be less than 70 dba during day-time and 60 dba during night-time.» The noise levels in Avondale and Protea Park residential areas not to exceed 50 dba and 45 dba during daytime and night-time respectively, due to the power station operations. Monitoring» Annual noise monitoring throughout the operational lifespan on the perimeter of the power station. The closest residential area to the site and at two selected locations outside the perimeter should also be included.» The noise monitoring should be performed in accordance with SANS and the report submitted to the appropriate authority. EMP: Operation and Maintenance Page 30
32 OBJECTIVE: Management of dust and emissions to air The main air pollution sources identified to be associated with the proposed power station conversion include:» The turbine combustion emissions during the normal operation phase.» The turbine combustion emissions during start-up and upset conditions. The exhaust emissions during normal operation, start-up and upset conditions could have a negative impact on the air quality of residential townships in close proximity to the power station. The type of emissions are not expected to change from those currently generated by the 9 OCGT units, since instead of being released into the atmosphere after the turbines, as the gases from the OCGT plant will pass through a heat recovery system and then be released. The only variations to the OCGT emissions will be the different release heights of the new stacks and the temperature of the emitted gases. These changes could have a small additional negative impact on potentially sensitive receptors in the vicinity of the power station. Project Project components affecting the objective: component/s» Converted power station units Potential Impact» Emissions from CCGT unit stacks Activities/risk» Operation of the power station sources Mitigation: Target/Objective» To ensure emissions are minimised, where possible, for the duration of the operation phase Mitigation: Action/control Responsibility Timeframe Implement stack heights at 60m or higher Eskom Operation Investigate additional mitigation measures to further Eskom Operation reduce nitrogen dioxide emissions Introduce natural gas as a fuel source as and when Eskom Operation available Implement the air pollution management plan as per the approved EMP (dated September 2007) Eskom Operation Performance Indicator» The measured hourly and annual nitrogen dioxide levels due to the power station s operations at local communities around the power station to be in compliance with South African ambient NO2 air quality standards» No complaints from affected residents or community regarding emissions EMP: Operation and Maintenance Page 31
33 Monitoring Monitoring will be undertaken to ensure emissions are not exceeding the prescribed levels via the following methods:» In-stack monitoring of emissions» Monitoring of nitrogen oxides at local communities» A complaints register will be maintained, in which any complaints from residents/the community will be logged. Complaints will be investigated and, where appropriate, acted upon.» An incident reporting system will be used to record non-conformances to the EMP. OBJECTIVE: Minimisation of visual impacts The primary area of potential visual impact of the CCGT units associated with the converted power station would occur along Dassenburg Road within a 200 m radius of the power station conversion and additionally constructed infrastructure. Other sources of visual impact include any additional lighting which may be associated with the power station conversion. The area of potentially high visual impact is indicated within a 500m buffer zone from the transmission power line. Project List of project components affecting the objective: component/s» CCGT units (~60 m high stacks)» Water storage tanks» Additional fuel storage tanks» power line and service road for power line servitude Potential Impact» Enhanced visual intrusion Activity/risk source» Size/scale of CCGT unit stacks (~60 m in height) and associated lighting» Power line Mitigation:» To minimise potential for visual impact Target/Objective» Minimise contrast with surrounding environment and visibility of the turbines to humans Mitigation: Action/control Responsibility Timeframe Ensure careful planning and sensitive placement of any Eskom/ lighting Erection and additional light fixtures, and ensure the fitment of covers engineer maintenance and shields designed to contain, rather than spread the light. Ensure timely maintenance of the CCGT units, ancillary Eskom Operation and infrastructure and the general surrounds of the property maintenance (gardens, access roads, etc.) in order to prevent the visual impact of degradation and perceived poor EMP: Operation and Maintenance Page 32
34 Mitigation: Action/control Responsibility Timeframe management Natural hues that compliment the natural environment Eskom Erection and (such as is currently the case) must be used to soften the maintenance general appearance of the power plant. Performance» Minimised visual intrusion on surrounding areas Indicator Monitoring» Ensure that adequate safety lighting is installed before construction is completed and are functional at all times OBJECTIVE: Protection of vegetation and faunal habitats Indirect impacts on vegetation during operation and maintenance activities could result from maintenance activities and the movement of people and vehicles along the power line servitude. Project List of project components affecting the objective: component/s» Power line servitudes and associated access roads Potential Impact» Disturbance to or loss of vegetation and/or habitats Activity/risk source» Movement of employee and visitor vehicles within and around site Mitigation:» To minimise impacts on flora and faunal habitats Target/Objective» To ensure and encourage plant regrowth in areas of post-construction rehabilitation Mitigation: Action/control Responsibility Timeframe Vehicle movements shall be restricted to designated Eskom Operation roadways No new roads shall be created Eskom Operation Existing roads shall be maintained to ensure limited Eskom Operation erosion and impact on areas adjacent to roadways. During maintenance activities, unnecessary Contractor in Duration disturbance to habitats shall be strictly controlled. consultation with contract Avoiding any sensitive habitats with maintenance Specialist vehicles must be ensured. No bushcutting may occur within the High and Eskom Operation Medium sensitivity sections of the servitudes (as detailed in the EIA Report). If it is proven essential, the maximum frequency permitted should be once every ten years. Implement the weed eradication programme as Eskom Operation of EMP: Operation and Maintenance Page 33
35 Mitigation: Action/control Responsibility Timeframe detailed in the approved EMP (September 2007) Ongoing, annual alien plant management must be Eskom Operation undertaken in the High and Medium sensitivity sections of the servitudes (as identified in the EIA Report). Methodology used must comply with DWAF methodology for control of Acacia saligna and Acacia cyclops. Key elements include: alien clearing must be undertaken by well trained teams using the right equipment; all stems must be cut by hand (not heavy machinery); all cut stumps must immediately (within 5 minutes) be painted with a suitable herbicide that contains a visible dye (in order to prevent resprouting, and to ensure that all stems are painted); no spraying of herbicide; cut stems must be neatly stacked at the outside edges of the servitudes, or preferably removed from the servitudes to an approved organic waste dump site. Performance» No further disturbance to vegetation Indicator» Continued improvement of rehabilitation efforts Monitoring» Observation of vegetation on-site by Site Manager» Annual monitoring by an independent consultant to ensure that alien vegetation is being cleared appropriately from the High and Medium sensitivity areas (as identified in the EIA Report), and to ensure that these areas are not being bushcut more than once every ten years. OBJECTIVE: Protection of avifauna Bird interactions with the power lines can be anticipated during the operation phase of the power lines. These are, however, well researched in the South African context (through the EWT and Eskom partnership). The main impacts expected are as a result of collisions with the earth wire and disturbance of bird species in the area. As a result of long-term monitoring, Eskom are in a position to make use of birdfriendly towers and conductor configurations for their power lines. A number of mechanisms exist through which birds are able to cause electrical faults. These include: EMP: Operation and Maintenance Page 34
36 » Bird streamer induced faulting, whereby the fault is caused by the bird releasing a streamer of faeces which can constitute an air gap intrusion between the conductor and the earthed structure.» Bird pollution, whereby a flashover occurs when an insulator string gets coated with pollutant, which compromises the insulation properties of the string.» Bird nests, which may cause faults through nest material protruding and constituting an air gap intrusion Project List of project components affecting the objective: component/s» power line Potential Impact» Loss of birds as a result of collision with the power line earth wire» Disturbance to bird species in the area as a result of maintenance activities» Impact of birds on quality of supply Activity/risk source» Overhead power line Mitigation: Target/Objective» Ensure bird-friendly towers are installed and maintained. Mitigation: Action/control Responsibility Timeframe Marking of the earth wires shall be undertaken on the Eskom / specialist Operation/ high risk sections of the power line with an maintenance appropriate, Eskom approved marking device according the Eskom guidelines. Bird Guards shall be installed on all self-supporting towers according to the existing Eskom guidelines in Eskom / specialist Operation/ maintenance order to prevent birds from perching in high-risk areas on the towers directly above live conductors. During maintenance activities, unnecessary Contractor in Duration of disturbance to habitats shall be strictly controlled. consultation with contract Avoiding any sensitive habitats with maintenance Specialist vehicles must be ensured. Performance Indicator» No additional disturbance to avifaunal populations along the length of the power line route» Continued improvement of avifaunal protection efforts Monitoring» Observation of avifaunal populations and incidence of injuries/death from collisions with the power line» Regular inspections to monitor casualties from collisions - delegate a suitable on-site monitor to assess avian mortality associated with the power lines. EMP: Operation and Maintenance Page 35
37
TRAFFIC MANAGEMENT PLAN
TRAFFIC MANAGEMENT PLAN For: The construction and operation of a Photovoltaic (PV) Facility in Dabenoris, South Africa Prepared for: Alternative Energy Solutions (Pty) Ltd PO Box 4939 Tygervalley, South
CHAPTER 24: ENVIRONMENTAL MANAGEMENT
Central Eyre Iron Project Environmental Impact Statement CHAPTER 24: ENVIRONMENTAL MANAGEMENT CHAPTER 24 ENVIRONMENTAL MANAGEMENT COPYRIGHT Copyright Iron Road Limited, 2015 All rights reserved This document
LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT
LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT Introduction The purpose of this Public Environmental Report (PER) is to provide the Government
Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot
Construction Management Statement Residential development at Bywell House, St Mary s Hill, Ascot Parking of Vehicles of Site Personnel, Operatives and Visitors Site staff, visitors to the development and
ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED PHASE 2 EXPANSION OF THE TRANSNET IRON ORE HANDLING FACILITY, SALDANHA
ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED PHASE 2 EXPANSION OF THE TRANSNET IRON ORE HANDLING FACILITY, SALDANHA BACKGROUND INFORMATION DOCUMENT 1 BACKGROUND Transnet Limited s (Transnet) existing
Environmental Guidelines for Preparation of an Environmental Management Plan
2013 Environmental Guidelines for Preparation of an Environmental Management Plan Environmental Management Division Environmental Protection Agency 3/13/2013 ENVIRONMENTAL GUIDELINES FOR PREPARATION OF
Environmental guidelines for preparation of an Environment Management Plan
Environmental guidelines for preparation of an Environment Management Plan Environment Protection Authority MAY 2013 Australian Capital Territory, Canberra 2013 This work is copyright. Apart from any use
CONSTRUCTION SEQUENCE & PROGRAMME
CONSTRUCTION SEQUENCE & PROGRAMME 2 CONTENTS 1.0 Introduction 7 2.0 Key activities 8 2.1 Airport related activities 2.2 Construction of new roads and accesses 2.3 Earthworks zone a 2.4 Earthworks zone
SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY
SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY 1.0 Conditions and requirements for permits A permit to use and develop the
APPENDIX 4. Risk Tables
APPENDIX 4 Tables Preliminary Qualitative Criteria The qualitative risk assessment criteria have been developed to identify key risks to the environment, society, heritage and business reputation. The
6 CONSIDERATION OF ALTERNATIVES
6 CONSIDERATION OF ALTERNATIVES 6.1.1 Schedule 4 of the Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2011 sets out the information for inclusion in Environmental Statements
Devonport EfW CHP Facility. CEMP Proposal for Non Destructive Testing Activities. 1. Introduction
Devonport EfW CHP Facility CEMP Proposal for Non Destructive Testing Activities. 1. Introduction This application is issued in compliance with the principles of the approved Construction Environmental
Proposed Terms of Reference for EIA studies
1 Proposed Terms of Reference for EIA studies Base line data collection will be collected for the Post-Monsoon season 2016 (September to November 2016) in study area and 10 kms radius from project site.
23.1 RENEWABLE ENERGY
Proposed Hastings District Plan as Amended 23.1 Renewable Energy 23.1 RENEWABLE ENERGY 23.1.1 INTRODUCTION The use of energy is of fundamental importance to the function and development of our society.
Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014
Guideline: Works that interfere with water in a watercourse watercourse diversions September 2014 This publication has been compiled by the Department of Natural Resources and Mines. State of Queensland,
National Planning Policy for Waste
National Planning Policy for Waste October 2014 Department for Communities and Local Government Crown copyright, 2014 Copyright in the typographical arrangement rests with the Crown. You may re-use this
4 Alternatives and Design Evolution
4 Introduction 4.1 This Chapter describes the considerations and constraints influencing the siting, layout and massing of the Development. It also describes the main alternatives to the Development that
CALDER PARK PROJECT STAGE 1. EPBC Act Approval Compliance Report (EPBC 2012/6439)
CALDER PARK PROJECT STAGE 1 EPBC Act Approval Compliance Report (EPBC 2012/6439) Prepared for: METRO TRAINS MELBOURNE Level 28, 80 Collins Street, Melbourne, VIC 3000 Prepared by: Kellogg Brown & Root
8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP
8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP 8.1 INTRODUCTION Mitigation measures, monitoring and other follow-up actions identified in Chapter 7 (Environmental Effects Assessment and Mitigation)
Development proposals will require to demonstrate, according to scale, type and location, that they:-
Appendix 2 : Relevant Development Plan Policies Angus Local Plan Review 2009 Policy S1 : Development Boundaries (a) Within development boundaries proposals for new development on sites not allocated on
1. Purpose and scope. 2. SEPA's role in hydropower and planning
Page no: 1 of 10 1. Purpose and scope 1.1 The purpose of this note is to provide guidance on the approach that we will take when dealing with hydropower development management consultations. We welcome
How To Conduct An Environmental Impact Assessment
Proposed Terms of Reference for EIA studies 1. Introduction The proposed expansion of Bulk Drugs & Intermediates manufacturing unit by M/s. Sri Krishna Pharmaceuticals Limited (Unit V). is located at Plot
GENERAL SPECIFICATION
R64 - PAVEMENT MARKING August 1996 GENERAL SPECIFICATION G10 CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN Date JUNE 2012 Department 1 DOT Spec R64 of Infrastructure, Energy and Resources Index DEPARTMENT
Birmingham City University / Students Union Aspects and Impacts Register. Waste. Impacts description
Birmingham City University / Students Union and Impacts Register Waste Production of non - hazardous waste Production of hazardous waste Storage of non - hazardous waste Potential for waste to be disposed
Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan
Triton Knoll Offshore Wind Farm Limited Electrical System Outline Traffic Management Plan October 2014 RWE Innogy UK Triton Knoll TMP Copyright 2014 RWE Innogy UK Ltd All pre-existing rights reserved.
Draft New Museums Site Development Framework Supplementary Planning Document SUSTAINABILITY APPRAISAL SCREENING REPORT
Draft New Museums Site Development Framework Supplementary Planning Document SUSTAINABILITY APPRAISAL SCREENING REPORT MAY 2015 1 Contents 1 INTRODUCTION 3 2 DRAFT NEW MUSEUMS SITE SPD 4 3 STRATEGIC ENVIRONMENTAL
2x800 MW Thermal Power Project Near Village Paraspani, Tehsil Pathargama, Godda- District By Adani Power (Jharkhand) Limited
(IV) Proposed Terms of Reference for EIA Studies Project Category Project Proponent Location Paraspani Thermal Power Plant (2x800 MW) Coal based Thermal Power Project A [1(d) Thermal Power Plant 500 MW]
TERMS OF REFERENCE FOR SCOPING OF EIA STUDY
TERMS OF REFERENCE FOR SCOPING OF EIA STUDY Ours project is a proposed large scale unit and categorized as 5(h)-B as per the EIA notification 2006 of MoEFCC, New Delhi and subsequent amendments. Looking
Sec. 22a-1a page 1 (4-97)
Department of Environmental Protection Sec. 22a-1a page 1 (4-97) TABLE OF CONTENTS Connecticut Environmental Policy Act Definitions... 22a-1a- 1 Determination of sponsoring agency.... 22a-1a- 2 Determination
Environmental Impact Assessment Ordinance (Cap. 499) Environmental Impact Assessment Report Sludge Treatment Facilities
40/F, Revenue Tower, 5 Gloucester Road, Wan Chai, Hong Kong 香 港 灣 仔 告 士 打 道 5 號 稅 務 大 樓 40 樓 ACE-EIA Paper 2/2009 For advice Environmental Impact Assessment Ordinance (Cap. 499) Environmental Impact Assessment
Planning requirements for heliports and helicopter landing sites
Practice Note 75 December 2012 Planning requirements for heliports and helicopter landing sites The purpose of this practice note is to: 1. Explain how helicopter activity is regulated by the planning
DEPARTMENT OF ENVIRONMENTAL QUALITY Environmental Assessment
DEPARTMENT OF ENVIRONMENTAL QUALITY Environmental Assessment Water Protection Bureau Name of Project: Applicant: Ueland Land Development LLC Type of Project: Proposed discharge of treated domestic wastewater
CLEAN GREEN & SUSTAINABLE NS1439215
CLEAN GREEN & SUSTAINABLE NS1439215 1 Contents 2 Introduction Strategic Alignment 1 - Energy Efficiency 2 - Water Management 3 - Fleet and Plant Management 4 - Carbon Offsets 5 - Waste Management Everything
WORKING IN CONFINED SPACES GUIDELINES
WORKING IN CONFINED SPACES GUIDELINES Contents 1 Introduction... 2 2 Scope... 2 3 Definitions... 2 4 Responsibilities... 3 4.1 Permit Authoriser... 3 4.2 Permit Receiver... 3 4.3 Responsible UOW Officer...
Environment Impact Assessment of Thermal Power Plant for Sustainable Development
International Journal of Environmental Engineering and Management. ISSN 2231-1319, Volume 4, Number 6 (2013), pp. 567-572 Research India Publications http://www.ripublication.com/ ijeem.htm Environment
Finance, Mining & Sustainability. The Gamsberg Zinc Project South Africa
Finance, Mining & Sustainability The Gamsberg Zinc Project South Africa Project Summary Discovered in 1971 Anglo American purchased 33% interest in 1974 and increased interest to 100% in 1998 Feasibility
Construction Traffic Management Plan
Introduction This (CTMP) has been prepared in order to discharge Condition 20 of planning permission ref 07/02879/EFUL for the enabling site works associated with the wider Bath Western Riverside development.
9.0 Project Follow-Up Measures and Monitoring
9.0 This section details the follow-up measures and monitoring program that the Kruger and/or the Contractor will carry out in relation to the Project. The monitoring program has been designed to ensure
Proposed General Plan Update Goals, Policies, and Implementation Actions
Proposed General Plan Update Goals, Policies, and Implementation Actions The construction and maintenance of infrastructure is necessary to support existing and planned land uses and to achieve Environmental
APPENDIX 7 : PHYSICAL CULTURAL RESOURCES MANAGEMENT PLAN
APPENDIX 7 : PHYSICAL CULTURAL RESOURCES MANAGEMENT PLAN Contents 1.0 Introduction... 2 1.1 Definitions... 3 1.2 Purpose / Goals of the Plan... 3 1.3 Timing... 3 1.4 EMP Framework... 3 1.5 Plan Revision,
ENVIRONMENT ACT PROPOSED TERMS OF REFERENCE FOR PUBLIC REVIEW AND COMMENT NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS
ENVIRONMENT ACT PROPOSED TERMS OF REFERENCE FOR PUBLIC REVIEW AND COMMENT NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS Beaver Bank Bypass Highway 101 to the Beaver Bank Road Halifax County,
Role of the Environmental Management Representative (EMR)
Legacy Way Project Role of the Environmental Management Representative (EMR) What is Legacy Way The project consists of the following key elements: Two 4.2 km road tunnels connecting the Western Freeway
Pollution Incident Response Management Plan
Pollution Incident Response Management Plan POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN 1. Introduction This Pollution Incident Response Management Plan (PIRMP) has been prepared to describe the processes
PROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON. Construction Management Plan
PROPOSED RESIDENTIAL DEVELOPMENT LAND OFF MACCLESFIELD OLD ROAD, BUXTON Construction Management Plan May 2013 CONTENTS Page No: 1.0 INTRODUCTION 1 2.0 PROJECT ORGANISATION AND RESPONSIBILITIES 2 2.1 Client
THIS PAGE INTENTIONALLY LEFT BLANK
THIS PAGE INTENTIONALLY LEFT BLANK Construction Traffic Management Plan 2 Contents 1. Introduction... 4 1.1 Conditions of Consent... 4 2. Goals of the CTMP... 6 2.1 Objectives... 6 2.2 Predicted Construction
sustainability report
sustainability report Sustainable development In the midst of turbulent macro-economic conditions adversely impacting the coal sector, we maintain our focus on building a business that has a viable, long-term
Management of Contractors and Suppliers Procedure
Management of Contractors and HSE P1101 Table of Content 1 DOCUMENT CONTROL... 2 2 PURPOSE... 3 3 SCOPE... 3 4 DEFINITIONS... 3 5 ROLES AND RESPONSIBILITIES... 5 6 PROCESS DETAILS... 9 6.1 Confirm Need
PROPOSED TERMS OF REFERENCE
PROPOSED TERMS OF REFERENCE ABOUT THE PROJECT: Rampura Marble Mine (ML No.- 420/91) is proposed by M/s Continental Minerals Pvt. Ltd. The Mine Lease area consists of 3.0 ha, which is located at Khasra
Liquid Effluent Treatment Plant (LETP) Land Clean-Up
Liquid Effluent Treatment Plant (LETP) Land Clean-Up Frequently Asked Questions What is proposed? Magnox Ltd is proposing to remove the redundant Liquid Effluent Treatment Plant (LETP) at Harwell and to
ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED NEW COAL-FIRED POWER STATION IN THE LEPHALALE AREA, LIMPOPO PROVINCE
ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED NEW COAL-FIRED POWER STATION IN THE LEPHALALE AREA, LIMPOPO PROVINCE FOCUS GROUP MEETING 10 MARCH 2006 09:30 KUMBA RESOURCES OFFICES, PRETORIA DRAFT
American Forest Foundation (AFF) 2010-2015 Standards of Sustainability for Forest Certification
American Forest Foundation (AFF) 2010-2015 Standards of Sustainability for Forest Certification Standards Prologue The American Forest Foundation s (AFF) 2010-2015 Standards of Sustainability for Forest
Ingredion ANZ Pty Ltd
Ingredion ANZ Pty Ltd 170 Epping Road, Lane Cove, NSW 2066 EPL: 518 Page 1 of 8 1. Purpose and Background POLLUTION INCIDENT RESPONSE The purpose of this Pollution Incident Response Management Plan (PIRMP)
2015 AVAGO 2D SEISMIC SURVEY ENVIRONMENTAL MANAGEMENT PLAN SUMMARY
ENVIRONMENTAL MANAGEMENT PLAN SUMMARY TABLE OF CONTENTS 1. INTRODUCTION... 3 2. DESCRIPTION OF ACTIVITY... 4 3. DESCRIPTION OF THE ENVIRONMENT... 4 4. DESCRIPTION OF THE ACTIVITY IN RELATION TO THE ENVIRONMENT...
AESTHETIC AND NOISE CONTROL REGULATIONS
AESTHETIC AND NOISE CONTROL REGULATIONS 801. INTRODUCTION The rules and regulations in this section are promulgated to control aesthetics and noise impacts during the drilling, completion and operation
ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS
ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS PREPARED BY: DEPARTMENT OF ENVIRONMENT AND LANDS INDUSTRIAL ENVIRONMENTAL ENGINEERING DIVISION APRIL 16, 1992 - TABLE OF
Environmental Management Plan
Environmental Management Plan ENVIRONMENTAL MANAGEMENT PLAN An Environmental Management Plan is prepared for construction phase, post construction phase (commissioning & operation) and for post project
Appendix C. Municipal Planning and Site Restoration Considerations
Appendix C Municipal Planning and Site Restoration Considerations 67 68 Appendix C - Municipal Planning and Site Restoration Considerations This appendix contains best practice standards for site planning
approval of matters specified in conditions; and The Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013
Application for: planning permission; planning permission in principle; further applications; approval of matters specified in conditions; and mineral workings (if the planning authority do not have a
ENVIRONMENT MANAGEMENT PLAN
ENVIRONMENT MANAGEMENT PLAN LIMESTONE 1. INTRODUCTION: The proposed Bagdhara Limestone area, near Village- Bagdhara, Taluka- Jamjodhpur and District-Jamnagar, Gujarat has been granted to Dipakkumar Anantray
INFRASTRUCTURE, FLOOD PROTECTION AND REMEDIATION. Infrastructure Flood Protection Remediation Policies
INFRASTRUCTURE, FLOOD PROTECTION AND REMEDIATION Infrastructure Flood Protection Remediation Policies DRAFT POOLBEG PLANNING SCHEME 196 FIGURE 9.1: UTILITIES WAYLEAVES Electricity Cables 8m Wayleave for
Attended Noise Monitoring - Quarter Ending December 2013
Big Island Mining Pty Ltd Majors Creek Road Majors Creek Version: Page 2 PREPARED BY: ABN 29 001 584 612 Units 7-8, 26-28 Napier Close Deakin ACT 2600 Australia (PO Box 9344 Deakin ACT 2600 Australia)
STATEMENT OF RON HUNTSINGER NATIONAL SCIENCE COORDINATOR BUREAU OF LAND MANAGEMENT U.S
STATEMENT OF RON HUNTSINGER NATIONAL SCIENCE COORDINATOR BUREAU OF LAND MANAGEMENT U.S. DEPARTMENT OF THE INTERIOR BEFORE THE HOUSE APPROPRIATIONS SUBCOMMITTEE ON INTERIOR, ENVIRONMENT AND RELATED AGENCIES
Proposed (Concrete Cutting And Drilling) Environmental Management Plan
SAMPLE ENVIRONMENTAL MANAGEMENT PLAN This EMP is designed for (Concrete Cutting and drilling), however you may insert your business activities with only minor changes needed. This EMP should become part
PROPOSED TERMS OF REFERENCE
Annexure-IV PROPOSED TERMS OF REFERENCE 1.0 Proposed Scope of Work for EIA Study The components of the EIA study include: Detailed description of all elements of the project activities (existing and proposed
Beseck Switching Station Inspection
Page 1 of 5 Docket No. 272 Development and Management Plan Inspection The Connecticut Light and Power Company Certificate of Environmental Compatibility and Public Need for the construction of a new 345-kV
The purpose of this meeting is to inform the public of the updates to the project, and to get input before the finalization of the project.
The purpose of this meeting is inform the public of the updates the project, and get input before the finalization of the project. The following panels describe the purpose and hisry of the project, along
Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS
Business Procedure Traffic Management Document Number OHS-PROC-130 This document applies to the following sites: All Sites Rockhampton Office Brisbane Office Tarong Site Barron Gorge Hydro PS Kareeya Hydro
PROPOSED TOR FOR EIA STUDY
JAWAHARPUR VIDYUT UTPADAN NIGAM LIMITED 2x660 MW JAWAHARPUR THERMAL POWER PROJECT JAWAHARPUR, DISTRICT ETAH, UTTAR PRADESH PROPOSED TOR FOR EIA STUDY SEPTEMBER- 2015 DESEIN PRIVATE LIMITED CONSULTING ENGINEERS
Top Technology for Industry, Agriculture, Business and Communities
Top Technology for Industry, Agriculture, Business and Communities CHP The Technology with a Potential for Saving Energy Combined Heat and Power (CHP) is a highly efficient technology for the conversion
5.0 ENVIRONMENTAL IMPACT ASSESSMENT METHODS
5.0 ENVIRONMENTAL IMPACT ASSESSMENT METHODS The methods that are used to conduct the environmental impact assessment (EIA) of the Project are described in this section. The EIA uses a methodological framework
Gas to the West INFORMATION LEAFLET. gastothewest.com. [email protected]. www
Gas to the West INFORMATION LEAFLET 0800 975 2322 gastothewest.com @ [email protected] Gas to the West 1. INTRODUCTION This Gas to the West Project is a major energy infrastructure project to extend
Environmental Incident Classification and Reporting
Environmental Incident Classification and Reporting 9TP-PR-105/13.0 Procedure Applicable to Transport Projects Quality Management System Status: Approved Version: 13.0 Branch: Business unit: Planning and
Storm Water Management Requirements for Construction Projects Less than One Acre
Storm Water Management Requirements for Construction Projects Less than One Acre Purpose: UC Irvine s Phase II Small MS4 Storm Water Permit requires construction projects less than one acre in size to
Eskom Transmission. Hydra-Perseus Environmental Management Plan. Construction and Operational Environmental Management Plan
Eskom Transmission Hydra-Perseus Environmental Management Plan Construction and Operational Environmental Management Plan J27220 VOLUME I : ESKOM HYDRA-PERSEUS TRANSMISSION LINES CONSTRUCTION ENVIRONMENTAL
Guide to agrichemical use in Resource Management Plans Northland Region as at October 2011
Guide to agrichemical use in Resource Management Plans Northland Region as at October 2011 Northland Regional Air Quality Plan Note: This guide is intended to assist users and applicators understanding
Pollution & Noise from Demolition & Construction Sites
CONTROL OF Pollution & Noise from Demolition & Construction Sites N oi se Co ns tru ct io n MAY 2008 THE LONDON BOROUGH 3 CONTENTS Part 1 Introduction Page 1. Background 4 2. Purpose of the code 5 3.
The Pipelines Regulations, 2000
PIPELINES, 2000 P-12.1 REG 1 1 The Pipelines Regulations, 2000 being Chapter P-12.1 Reg 1 (effective April 1, 2000) as amended by the Statutes of Saskatchewan, 2014, c.21. NOTE: This consolidation is not
12.5: Generating Current Electricity pg. 518
12.5: Generating Current Electricity pg. 518 Key Concepts: 1. Electrical energy is produced by energy transformations. 2. Electrical energy is produced from renewable and non-renewable resources. 4. Electrical
Pollution Incident Response Plan
Pollution Incident Response Plan Introduction Schmidt Quarries is committed to ensuring all aspects of our quarrying activities comply with the environmental legislative requirements in NSW. This Pollution
Hackney Biomass Boiler Information Request Form
Hackney Biomass Boiler Information Request Form In common with other types of combustion appliances, biomass boilers are potentially a source of air pollution. Pollutants associated with biomass combustion
SECTION 02100 SITE PREPARATION
SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division
Guide Document for Development of WHS Management Plans
DISCLAIMER: THIS DOCUMENT IS PROVIDED AS GUIDANCE TO ASSIST CONTRACTORS IN MEETING THEIR OBLIGATIONS UNDER THE WHS LAW AND NTG CONTRACTS. NTG DOES NOT ACCEPT ANY RESPONSIBILITY FOR THE CONTENTS OF CONTRACTORS
COASTAL APPLICATION FOR A MAJOR SITING PERMIT
Frank M. Rabauliman Administrator Commonwealth of the Northern Mariana Islands OFFICE OF THE GOVERNOR Bureau of Environmental and Coastal Quality Division of Coastal Resources Management Gualo Rai Center
MLD: Domestic Maritime Transport Project
Environmental Monitoring Report Project Number: 37265 December 2010 MLD: Prepared by Japan Port Consultants Co., Ltd. Malé, Maldives For Ministry of Finance and Treasury Ministry of Transport and Communication
NON-TECHNICAL SUMMARY OF ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT FOR THE BAHCE WINDFARM PROJECT (135 MW)
Zorlu Plaza, 34310 Avcılar ISTANBUL / TURKIYE Tel: + 90 (212) 456-2300 Fax: +90 (212) 422-0099 www.zorlu.com.tr NON-TECHNICAL SUMMARY OF ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT FOR THE BAHCE WINDFARM
Tree Management Guidelines
Tree Management Guidelines Overview Tree Management Guidelines The trees that make up Brisbane s urban forest create much of our subtropical landscape character and biodiversity. Almost half of the city
LT McGuinness Site 10 Development, Wellington Waterfront. Construction Traffic Management Plan. 7 October 2014
LT McGuinness Site 10 Development, Wellington Waterfront Construction Traffic Management Plan 7 October 2014 TDG Ref: 12950 141007 ltm ctmp final report.docx LT McGuinness Site 10 Development, Wellington
Chapter 12: Impacts, Mitigation, Cumulative Impacts and Residual Effects
Chapter 12: Impacts, Mitigation, Cumulative Impacts and Residual Effects REnescience Northwich Quality Management Prepared by: Tom Dearing Senior Environmental Consultant 02/10/15 Reviewed & checked by:
Introduction to Waste Treatment Technologies. Contents. Household waste
Contents Introduction to waste treatment technologies 3 Section 1: The treatment of recyclable waste 4 Bulking facilities 5 Materials Reclamation Facility (MRF) 6 Reuse and recycling centres 8 Composting
Health & Safety Management System Manual
Health & Safety Management System Manual Document Information Document Number Description HSMSM This manual describes the Health & Safety Management System elements of the Integrated Management System
Environmental Management System
Environmental Management System Heron Island Research Station (HIRS) Environmental Noise Program 1. Scope The Environmental Noise Program is limited to the following noise sources: Machinery owned by the
Asbestos in Grounds Management Plan, Excelsior Public School, Castle Hill, NSW
Asbestos in Grounds Management Plan, Excelsior Public School, Castle Hill, NSW January 2013 NSW Public Works Parsons Brinckerhoff Australia Pty Limited ABN 80 078 004 798 Level 27, Ernst & Young Centre
Environmental Assessment Approval. Approval Date: Liverpool Wind Farm Liverpool Wind Energy Storage Project Inc.
Environmental Assessment Approval Approval Date: ocr 2 8 zols Liverpool Wind Farm Liverpool Wind Energy Storage Project Inc. Queens County, Nova Scotia The Liverpool Wind Farm (the Undertaking ), proposed
WHS Contractor Management Procedure
Wudinna District Council 1. Overview Wudinna District Council as part of its commitment under its Policy recognises its obligation to: Ensure, so far as is reasonably practicable, the health and safety
