1 US GoM EPS FPSO OPERATORS PERSPECTIVE C. Mastrangelo & J. Daniel FPSO Research Forum - April 25th 2007 Theme Disconnectable FPSOs

2 TOPICS Operator objectives Safety Regulatory Environment Concept Selection Process FPSO Disconnectable Permanent Moored Internal Turret Design Premise Conclusion

3 OPERATOR OBJECTIVES SAFETY During design, Fabrication, Installation AND Operations: 1. Safety of Life 2. Safety of Environment 3. Safety of Asset Compliance with Local Regulations Minimum Overall Cost On schedule Optimize Production

4 WORLDWIDE FPU FLEET 1Q 2007 FPSO AND SEMI FPU FLEET PETROBRAS PETROBRAS WORLD WIDE IN OPERATION IN OPERATION # OF UNITS PERCENT OF WORLD FLEET # OF UNITS FPSO % SEMI % TLP SPAR FPSO & SEMI TOTAL % TOTAL FLEET % Quest Database 2007

5 SAFETY:ENVIRONMENT EIS RESULTS ON SPILLS MMS EIS 2001 pg.xv Based on the risk assessment, the risk of spills unique to FPSOs operations in the GoM is low risk of oil spills during offloading from the FPSO to the shuttle tanker is similar to that for lightering operations in the GOM, where there is a history of low spill frequency and small spill volumes. NOTE: Petrobras performed more than 3000 offloads in Brazilian waters with no spills

6 SAFETY:ENVIRONMENT EIS RESULTS ON SPILLS OF TOTAL FPSO SYSTEM RISK: SPILL IS 5% Approximately 94.4 percent of the volume of potential FPSO-unique spills is likely to be due to the transfer of oil from the FPSO to the shuttle tanker and from the shuttle tanker transit to shore percent of the volume of potential FPSO-unique spills is likely to be from shuttle tankers near port percent of the volume of potential FPSO-unique spills is likely to be from shuttle tankers in transit to port. 1.8 percent of the volume of potential FPSO-unique spills is likely to be from the transfer of oil from the FPSO to the shuttle tanker. However, this volume is comprised entirely of the smaller spill sizes (<1,000 barrels). 95% OF TOTAL RISK IS SIMILAR TO RISK OF OTHER DEEP WATER FLOATING PRODCUTION UNITS

7 REGS: FPSO REGS FOR US GoM Existing US Regulations are not entirely applicable to FPSOs. Several Operators have considered FPSO production systems, but only the Petrobras operated Cascade / Chinook field FPSO was submitted and the concept approved by regulators. Gaps exist in the concepts accepted by regulators. New concepts have to be justified prior to use in the GoM.

8 REGS: CONCEPTS VIEWED AS NEW TO US GoM For Cascade and Chinook: FPSO Disconnectable Turret FPSO Tandem Offloading Free Standing Hybrid Riser Some Optional New Concepts: Torpedo Piles (Petrobras Patent) Polyester Ropes (First GoM FPSO mooring with Polyester ropes)

9 Cascade Chinook CONCEPT OVERVIEW Cascade /Chinook Non DP-Internal Turret fully moored Disconnectable FPSO Producing from two fields 250 miles from New Orleans Shuttle Vessel FPSO 5 FSHR 4 Production 1 Gas Export line 4 Catenary Umbilicals Tandem Offloading Gas Export Pipeline Gas Export FSHR Dual PIP Production FSHR Flowlines Power Umbilical Boosting Tree Dual Flowlines Pump 4-Slot Manifold Boosting Pump Tree Control Umbilical

10 WHY AN FPSO? Items that drove selection to FPSO: Lack of Infrastructure EWT and EPS function Favorable CAPEX and OPEX Schedule driven project Versatility Reliability More than Adequate Deck Capacity

11 WHY DISCONNECTABLE SYSTEM? Mitigates risk to life and environment. FPSO disconnects and sails out of harm s way. Rapid build up of production if wells available Reduces potential production downtime by preventing storm damage. Capable of leaving for shore for unforeseen maintenance or repairs. Mooring System Design Criteria limit known. (design for known vs. unknown)

12 WHY PERMANENTLY MOORED? Disconnectable Turret / Dynamic Positioning Suitable for limited number of risers. Light mooring system for disconnected buoy Requires design for Emergency Disconnection Disconnectable Turret / Permanently Moored More flexible in number of risers. Permanent mooring system for disconnected buoy. Design for Planned Disconnection. Cascade / Chinook (5 FSHR & 4 umbilicals) DP light mooring 3X2 mooring lines. Non-DP Permanent Mooring 3X3 mooring lines.

13 OPTIONS FOR TURRET PERMANENTLY MOORED Disconnectable system configurations; Internal Turret / Submerged Buoy Turret Moored Submerged Buoy (STL / STP) Riser Turret Mooring (RTM) PAI evaluation shows: Limited difference in features and operations. All have several years operational experience. All are controlled disconnect & reconnect. All connection and disconnection is contained. All are considered suitable for use in the GoM.

14 INTERNAL TURRET / SUBMERGED BUOY Turret Access Structure Swivel Stack (red) Turret Decks Vessel Moonpool Submerged Buoy Mooring Lines Picture courtesy of SOFEC

15 Pictures courtesy of APL TURRET MOORED SUBMERGED BUOY

16 Picture courtesy of SBMAtlantia RISER TURRET MOORING (RTM)

17 WHY INTERNAL TURRET PREFERRED? Turret location adjusted for optimum location to minimize FPSO induced riser motions. (Location must ensure passive weathervaning.) Buoy does not travel through the wave /air interface during disconnection and connection. Reduced riser motions when disconnected, since the turret buoy submerged depth will be below the wave zone. Protected access to the top of turret buoy.

18 DESIGN PREMISE Process plant capable of producing in up to a 5yr Winter storm with a 1 yr Loop/Eddy condition. FPSO, Mooring and Utilities designed for 100yr Winter storm condition. Target: disconnect in <1 hr. at design wave height of 4.5 meters. (Riser excursion limit may govern some disconnects). Time to disconnect and sailing speed must be sufficient to move away from the path of a hurricane that may be born in the GoM.

19 EXAMPLE OF TURRET-BUOY INTERFACE Current Turret / Buoy interface has two (2) valves, a means for crude purge, blind flanges for isolation when buoy is disconnected. Location of Isolation Blind flanges To Closed Drain / Vent Purge Premise: Zero (0) Fluid Spill at Disconnect Fail Safe Actuator

20 POTENTIAL PLANNED DISCONNECT TIME LINE Production Stopped Cascade Chinook No Touch Period Up to 4 hrs. 5 Displace Production Fluids 2 Close Isolation Valve / Drain / Purge 1.5 Add Blinds Isolate Wells & Treat Trees Flush Well Jumpers Flush Subsea Pumps Prep Umbilical Connections Other Turret / Buoy preparations Prepare Vessel Propulsion System, etc. Displace Production Fluids Prep Buoy Connector 0.5 Flood Lower Turret 1.0 Disconnect Buoy Hours Production stopped anytime prior to 0 hrs. Unplanned would not include displacement of fluids.

21 CRITICAL WHAT IF? What if the primary disconnect system fails to disconnect? Safeguards to mitigate will be: Redundant disconnect system. Rigorous maintenance and testing program and design philosophy. On site testing w/o disconnect Appropriate SF in design. Design for Disconnect during Black-out. (Power from Emergency Generator)

22 CONCLUSION Disconnectable FPSOs provide a means to improve protection of life, environment and asset during GoM hurricanes All critical components of a disconnectable FPSO have been successfully proven in operations world wide EPS Disconnectable FPSO Can be considered a Reliable and Efficient Concept for the deep water fields in GoM Flexibility of a disconnectable FPSO facilitates the accommodation of uncertainties such as environment, fluid production, composition and deck loads.

23 US GoM EPS FPSO OPERATORS PERSECTIVE C. Mastrangelo & J. Daniel FPSO Research Forum - April 25th 2007 Theme Disconnectable FPSOs

24 DISCONNECT SIMULATION BUOY DISCONNECT SIMULATION FROM AN FPSO IN A 100 YR WINTER STORM. COURTESY OF DEEPSTAR. PREPARED BY TECHNIP.

HIPPS Application in the Gulf of Mexico. Christopher Lindsey-Curran BP Senior Subsea Engineer

HIPPS Application in the Gulf of Mexico. Christopher Lindsey-Curran BP Senior Subsea Engineer HIPPS Application in the Gulf of Mexico Christopher Lindsey-Curran BP Senior Subsea Engineer Agenda Introduction and background HIPPS overview Codes and standards System design Regulatory issues Conclusions

More information

Total Subsea Solutions

Total Subsea Solutions Total Subsea Solutions Total Subsea Solutions Developing new energy reserves, managing, and improving producing fields means an unprecedented number of technical challenges. In partnership with our customers,

More information

Offshore Structures. Offshore Drilling Equipment

Offshore Structures. Offshore Drilling Equipment Offshore Structures Offshore Drilling Equipment The drill string is lowered through a conduit (riser). The drill string consists of a drill bit, drill collar and drill pipe. Drill pipe sections are added

More information

SSP Offshore. Well Containment. April 2011

SSP Offshore. Well Containment. April 2011 SSP Offshore Well Containment April 2011 Well Containment - Points to Discuss 2 Lessons Learned in the Aftermath of the Deepwater Horizon Incident The Containment Solutions : Interim MWCS and the MCV solution

More information

Single Point Mooring System (SPM) for an Offshore LNG Terminal

Single Point Mooring System (SPM) for an Offshore LNG Terminal Single Point Mooring System (SPM) for an Offshore LNG Terminal GASTECH 2005, Session 7 - Technical Bilbao, March 15 th, 2005 Max Krekel Senior Naval Architect Bluewater Offshore Production Systems Neal

More information

2001/073 OFFSHORE TECHNOLOGY REPORT. Failure modes, reliability and integrity of floating storage unit (FPSO, FSU) turret and swivel systems HSE

2001/073 OFFSHORE TECHNOLOGY REPORT. Failure modes, reliability and integrity of floating storage unit (FPSO, FSU) turret and swivel systems HSE HSE Health & Safety Executive Failure modes, reliability and integrity of floating storage unit (FPSO, FSU) turret and swivel systems Prepared by AEA Technology Engineering Solutions for the Health and

More information

Subsea Technology. Alain Marion, Senior VP Assets & Subsea Technology. Investor Day in Brazil, October 4, 2011

Subsea Technology. Alain Marion, Senior VP Assets & Subsea Technology. Investor Day in Brazil, October 4, 2011 Subsea Technology Alain Marion, Senior VP Assets & Subsea Technology Investor Day in Brazil, October 4, 2011 Subsea Technology Technip s Commitment to Subsea R&D Technip Leadership Position Emerging Technologies

More information

Marine integrity monitoring Offshore oil and gas

Marine integrity monitoring Offshore oil and gas Marine integrity monitoring Offshore oil and gas Where will our knowledge take you? BMT has over 0 years experience in the design, procurement, integration and installation of monitoring systems worldwide.

More information

The Dalian Developer A new approach to oil spill response

The Dalian Developer A new approach to oil spill response The Dalian Developer A new approach to oil spill response Presenter: Jim O Sullivan, Vice President Technip USA National Ocean Industries Association Scottsdale, Arizona, October 18, 2012 Contents Introduction

More information

Design and Construction of LNG Regasification Vessel

Design and Construction of LNG Regasification Vessel Design and Construction of LNG Regasification Vessel GASTECH 2005 March 14 17, 2005 Bilbao, Spain Hochung Kim, JungHan Lee Daewoo Shipbuilding & Marine Engineering Co. Ltd. (DSME) Gastech 2005 Design and

More information

OFFSHORE FIELD DEVELOPMENT

OFFSHORE FIELD DEVELOPMENT OFFSHORE FIELD DEVELOPMENT OPTIONS & STRATEGY By: Nguyen Ngoc Hoan M.Sc of Petroleum Engineering Hoannn@pidc.com.vn PRESENTATION CONTENT Field Development Consideration Field Development Options & Strategy

More information

Offshore platform/facility provider

Offshore platform/facility provider Engineering and technologies Your field development provider able to deliver all types of offshore fixed and floating facilities through our integrated network of regional locations Infrastructure to the

More information

Hurricanes and the Offshore oil and Natural Gas Industry

Hurricanes and the Offshore oil and Natural Gas Industry Every year, hurricanes of varying strength lay siege to America s coasts. The images of wind-battered buildings and flooded lands are well-known - 2004 and 2005 were particularly destructive seasons. The

More information

HPHT CAPPING STACKS AND NEW TECHNOLOGY FOR SUBSEA WELL CONTROL. December 3, 2014 Presenter: Mike Cargol

HPHT CAPPING STACKS AND NEW TECHNOLOGY FOR SUBSEA WELL CONTROL. December 3, 2014 Presenter: Mike Cargol HPHT CAPPING STACKS AND NEW TECHNOLOGY FOR SUBSEA WELL CONTROL December 3, 2014 Presenter: Mike Cargol Agenda Development Update HPHT Capping Stack Mudline Closure Device Divert and Flow System Well Kill

More information

Conceptual benefits with a cylindrical hull for FPSO, FLNG, drilling and floating powerplant applications

Conceptual benefits with a cylindrical hull for FPSO, FLNG, drilling and floating powerplant applications 21st FPSO Research Forum April 23, 2008, Trondheim, Norway Conceptual benefits with a cylindrical hull for FPSO, FLNG, drilling and floating powerplant applications Fredrik Major, VP Bus. Dev/ R&D, Sevan

More information

Engineering and technologies Floating LNG

Engineering and technologies Floating LNG Engineering and technologies Floating LNG Major contracts confirm Technip's leadership Technip at a glance Technip is a world leader in project management, engineering and construction for the oil and

More information

Subsea Market Review. Subsea 2011 February 9 10, 2011. 2011 Quest Offshore Resources, Inc. 1

Subsea Market Review. Subsea 2011 February 9 10, 2011. 2011 Quest Offshore Resources, Inc. 1 Subsea Market Review Subsea 211 February 9 1, 211 211 Quest Offshore Resources, Inc. 1 Presentation Summary Quest Offshore Recent activity and trends Forecast activity Contractor s perspective 211 Quest

More information

Kodiak Deepwater Project Challenges and Solutions

Kodiak Deepwater Project Challenges and Solutions Kodiak Deepwater Project Challenges and Solutions Marine Technology Society September 24, 2015 Deep Gulf Energy II, LLC Overview of Deep Gulf Energy Companies Deep Gulf Energy Background Exploration and

More information

Opportunities and challenges for global deepwater players

Opportunities and challenges for global deepwater players Content 66/67 Opportunities and challenges for global deepwater players An industry on the seach for new growth areas Rodolfo Guzman, Paola Carvajal, Ben Thuriaux-Alemán With fewer remaining easy-to-access

More information

13. FPSO Operational Problems Don Smith, OGP

13. FPSO Operational Problems Don Smith, OGP OGP Marine Risks Workshop Proceedings 13. FPSO Operational Problems Don Smith, OGP FPSO Operational Problems Don Smith OGP Analysis of Accident Statistics for Floating Monohull and Fixed Installations

More information

Ceiba Field Early Production System. Cameron MOSAIC Systems

Ceiba Field Early Production System. Cameron MOSAIC Systems MOSAIC Certified Ceiba Field Early Production System Cameron MOSAIC Systems for the Ceiba Field Early Production System The Ceiba Field Early Production System Nigeria 0 100 KM Niger Delta C B D E Malabo

More information

A Cost- Effective Computational Tool for Offshore Floater Design

A Cost- Effective Computational Tool for Offshore Floater Design Introduction A Cost- Effective Computational Tool for Offshore Floater Design Jang Whan Kim, Hyunchul Jang & Jim O Sullivan Technip Offshore floating platforms are complex engineering systems with numerous

More information

Oil and Gas Offshore. www.shell.com/us/alaska

Oil and Gas Offshore. www.shell.com/us/alaska 3 C H A P T E R T h r e e : Oil and Gas Offshore Production www.shell.com/us/alaska Planning Piltun-Astokhskoye B a fixed production platform 7.5 miles off Sakhalin Island in 105 waters (2007). When exploration

More information

Safe Offloading from Floating LNG Platforms (SAFE OFFLOAD) R. V. Ahilan Noble Denton Europe

Safe Offloading from Floating LNG Platforms (SAFE OFFLOAD) R. V. Ahilan Noble Denton Europe Safe Offloading from Floating LNG Platforms (SAFE OFFLOAD) R. V. Ahilan Noble Denton Europe Overview Background Project Objective Partners Work Scope Key Developments Deliverables Schedule Additional Participation

More information

M. Kevin McEvoy. CREDIT SUISSE 2013 Energy Summit February 5, 2013 Vail, CO. Oceaneering International, Inc. Safe Harbor Statement

M. Kevin McEvoy. CREDIT SUISSE 2013 Energy Summit February 5, 2013 Vail, CO. Oceaneering International, Inc. Safe Harbor Statement CREDIT SUISSE 2013 Energy Summit February 5, 2013 Vail, CO M. Kevin McEvoy President and CEO Oceaneering International, Inc. Safe Harbor Statement Statements we make in this presentation that express a

More information

AN INNOVATIVE SOLUTION FOR FIXED OFFSHORE LNG REGASIFICATION TERMINALS

AN INNOVATIVE SOLUTION FOR FIXED OFFSHORE LNG REGASIFICATION TERMINALS AN INNOVATIVE SOLUTION FOR FIXED OFFSHORE LNG REGASIFICATION TERMINALS Augusto Bulte Project Manager Foster Wheeler C/Gabriel García Márquez 2 Las Rozas 28232 Madrid (Spain) ABSTRACT Several developments

More information

SWIMMER. An innovative Subsea Intervention System for Deep Offshore Fields. Jean-Jacques QUESNEL CYBERNETIX S.A. Oil&Gas Division

SWIMMER. An innovative Subsea Intervention System for Deep Offshore Fields. Jean-Jacques QUESNEL CYBERNETIX S.A. Oil&Gas Division SWIMMER An innovative Subsea Intervention System for Deep Offshore Fields Jean-Jacques QUESNEL CYBERNETIX S.A. Oil&Gas Division 1 The next generation of Challenges 2 Asset Integrity Monitoring New Challenges

More information

How To Build A Kingkong Production System

How To Build A Kingkong Production System MOSAIC Certified Mariner Energy, Inc./Agip Petroleum King Kong Development Cameron MOSAIC Systems for the King Kong Field Development King Kong Development The King Kong Deepwater Gulf of Mexico Development

More information

MEK4450. Templates & Manifolds. 29 August 2012. 05 Templates and Manifolds. This module will cover:

MEK4450. Templates & Manifolds. 29 August 2012. 05 Templates and Manifolds. This module will cover: 29 MEK4450 05 Templates and Manifolds Templates & Manifolds This module will cover: Applicable Codes and Standards Templates - Purpose of a template Manifolds - Purpose of a manifold Foundations 2 1 29

More information

MUX Control of subsea BOP without an Umbilical

MUX Control of subsea BOP without an Umbilical MUX Control of subsea BOP without an Umbilical Acoustic-based MUX for BOP control The challenges of subsea acoustics Benefits Objectives Example Design strategies Qualification Conclusions Subsea acoustics

More information

An Approach To Oil Spill Containment For Floating Drilling Operations In Canadian Beaufort Sea Pack Ice Conditions

An Approach To Oil Spill Containment For Floating Drilling Operations In Canadian Beaufort Sea Pack Ice Conditions For Floating Drilling Operations In Canadian Beaufort Sea Pack Ice Conditions Canada - US Northern Oil and Gas Research Forum Calgary, Alberta December 2 nd, 2010 An Overview An Overview Of Same Season

More information

THE BALTIC SEA OFFSHORE PROJECTS

THE BALTIC SEA OFFSHORE PROJECTS OFFSHORE PROJECTS OFFSHORE PROJECTS 3 OFFSHORE PROJECTS The start of LUKOIL's offshore operations dates back to 1999, when the Company started exploratory drilling with its in-house ASTRA selfelevating

More information

Using the Proxy NPV Model for Value-Based Strategic Decisions

Using the Proxy NPV Model for Value-Based Strategic Decisions Using the Proxy NPV Model for Value-Based Strategic Decisions January 2011 Westney Consulting Group, Inc. www.westney.com The Importance of Value-Based Development Decisions The Influence Curve has long

More information

DELIVERY THROUGH TECHNOLOGY Parque das Conchas Project

DELIVERY THROUGH TECHNOLOGY Parque das Conchas Project DELIVERY THROUGH TECHNOLOGY Parque das Conchas Project Use this area for cover image (height 6.5cm, width 8cm) Marco Brummelhuis Development VP Upstream Brazil 11 May 2010 1 Disclaimer statement This presentation

More information

creating progress for the future

creating progress for the future CREATING PROGRESS OFFSHORE creating progress for the future CREATING PROGRESS SCANAOFFSHORE Scana Offshore group of companies will be present at the OTD in Stavanger, October 23-24 2013. The companies

More information

A DEEPER LOOK AT MODULARIZATION IN FACILITIES CONSTRUCTION. Stephen Whitfield Oil and Gas Facilities Staff Writer

A DEEPER LOOK AT MODULARIZATION IN FACILITIES CONSTRUCTION. Stephen Whitfield Oil and Gas Facilities Staff Writer A DEEPER LOOK AT MODULARIZATION IN FACILITIES CONSTRUCTION Stephen Whitfield Oil and Gas Facilities Staff Writer The Eagle Louisiana, a modular capture vessel (MCV), docked at the Marine Well Containment

More information

AOG 2015 Acoustic System to Monitor Wellhead Fatigue in Real-time. March 12 th 2015. www.pulse-monitoring.com

AOG 2015 Acoustic System to Monitor Wellhead Fatigue in Real-time. March 12 th 2015. www.pulse-monitoring.com AOG 2015 Acoustic System to Monitor Wellhead Fatigue in Real-time March 12 th 2015 Agenda Monitoring method currently used Online monitoring New generation wireless monitoring Benefits of active monitoring

More information

DET NORSKE VERITAS TM

DET NORSKE VERITAS TM DET NORSKE VERITAS TM APPENDIX B HAZID REPORT NO./DNV REG NO.: 2013-4091 / 17TLT29-5 REV 1, 11.06.2013 DET NORSKE VERITAS Table of Contents Page 1 BACKGROUND AND SCOPE OF WORK... 2 2 METHODOLOGY... 4 3

More information

Languages: : French (Mother tongue), English (Fluent), Portuguese (Basic Level)

Languages: : French (Mother tongue), English (Fluent), Portuguese (Basic Level) curriculum vitae Name: : Jeremy de BARBARIN Position: : Engineering Manager Date/Place of Birth: : 14 th of June 1973 in Marseille (France) Nationality: : French Languages: : French (Mother tongue), English

More information

Master Class. Electrical and Instrumentation (E &I) Engineering for Oil and Gas Facilities

Master Class. Electrical and Instrumentation (E &I) Engineering for Oil and Gas Facilities Master Class Electrical and Instrumentation (E &I) Engineering for Oil and Gas Facilities What you will learn: Skills and competencies in E&I oil and gas engineering Knowledge of the latest technologies

More information

Electric heat tracing

Electric heat tracing PIPELINE DESIGN Figure 1. Shorter, more complex piping at a process plant. Electric heat tracing Neil Malone, Heat Trace, UK, discusses electric heat tracing of long pipelines. In considering electric

More information

API Std 53 - Blowout Prevention Equipment Systems for Drilling Wells Last update: August 12, 2015

API Std 53 - Blowout Prevention Equipment Systems for Drilling Wells Last update: August 12, 2015 6.1.2.12 53-03-15 Referring to Section 6.1.2.12, can a surface BOP stack arrangement with one annular, one blind shear ram, and two pipe rams, with the fifth device being optional, be considered a Class

More information

Introduction to Subsea Production System

Introduction to Subsea Production System Introduction to Subsea Production System 04 Xmas Tree Systems Bjørn Søgård Xmas Tree Systems This module will cover: Main codes for XT equipment XT Principles and functions Typical schematic Main types

More information

Subsea School The training program

Subsea School The training program Subsea School The training program Table of Contents Welcome to the FMC Subsea School... 3 Training Schedules and Participation... 4 SS Subsea Technology Introduction... 5 MPS - Subsea Structures... 6

More information

Subsea Standard & Rules What is Subsea?

Subsea Standard & Rules What is Subsea? Subsea Standard & Rules What is Subsea? MEK4450 Standards and Rules Bjørn Søgård, Anders Husby Goals General knowledge of subsea development and production systems Understand the building blocks forming

More information

Rockwell Automation in Oil & Gas

Rockwell Automation in Oil & Gas Rockwell Automation in Oil & Gas November 14, 2013 Rev 5058-CO900E Copyright 2013 Rockwell Automation, Inc. All Rights Reserved. Copyright 2013 Rockwell Automation, Inc. All Rights Reserved. 2 2013 Oil

More information

Technip Presentation. Knut Bø, Nyttårsoil Seminar, Orkanger 14. januar 2009

Technip Presentation. Knut Bø, Nyttårsoil Seminar, Orkanger 14. januar 2009 Technip Presentation Knut Bø, Nyttårsoil Seminar, Orkanger 14. januar 2009 Contents I. II. III. IV Technip at a glance Market Position & Trends Financial Performance Strategy Going Forward V. 2 I. Technip

More information

Guidelines for FEASIBILITY STUDY

Guidelines for FEASIBILITY STUDY Guidelines for FEASIBILITY STUDY INTRODUCTION This document describes the best practices to be followed during the preparation of a Feasibility Study for the Facilities Development of an upstream asset.

More information

Design methodology and numerical analysis of a cable ferry

Design methodology and numerical analysis of a cable ferry Design methodology and numerical analysis of a cable ferry SNAME Annual Meeting; Nov 6-8, 2013, Bellevue, WA Paper #T35 Author name(s): Dean M. Steinke (M)1, Ryan S. Nicoll1 (V), Tony Thompson2 (M), Bruce

More information

Asset Management Conformity Assessment Fitness for Service QHSE. Oil & Gas Services and Tools. For the benefit of business and people

Asset Management Conformity Assessment Fitness for Service QHSE. Oil & Gas Services and Tools. For the benefit of business and people Asset Management Conformity Assessment Fitness for Service QHSE Oil & Gas Services and Tools For the benefit of business and people Services along the whole life of Facilities Bureau Veritas services can

More information

Example. Fluid Power. Circuits

Example. Fluid Power. Circuits Example Fluid Power Circuits To Enhance Symbol Reading Skills To Work On Circuit Reading Skills With Answers HI LO Pump Circuit 18 A1 B1 17 16 15 13 Set 14 2,000 PSI PG2 Set 500 PSI 12 11 7 8 10 PG1 9

More information

VEHICLE SERVICE DISPENSING SYSTEMS

VEHICLE SERVICE DISPENSING SYSTEMS VEHICLE SERVICE DISPENSING SYSTEMS Lincoln s LFC Family of Fluid Inventory Control and Management Systems Finally a complete offering of systems to meet the varying needs of vehicle service centers! Each

More information

A Job Safety Execution Plan is required. mixtures of the above called, natural gas liquids (NGL's) refined products and their components

A Job Safety Execution Plan is required. mixtures of the above called, natural gas liquids (NGL's) refined products and their components TITLE Pipelines and Terminals Manual/Volume 3 - SECTION 02: SUBJECT 20: PURPOSE AND SCOPE During the normal lifetime of a pipeline it becomes necessary to add or remove piping, modify existing piping or

More information

Piers, Wharves & Docks

Piers, Wharves & Docks Piers, Wharves & Docks Exposures and Concerns By: Christopher L. Pesce May 10, 2011 Piers, Wharves & Docks Statistics Why underwriters love to write docks Estimated industry losses for 2010: $30,000,000

More information

DELTA HOUSE PROJECT APPROVED; ARCLIGHT TO PROVIDE FINANCING. Covington, LA: December 13, 2012 - LLOG Exploration Company,

DELTA HOUSE PROJECT APPROVED; ARCLIGHT TO PROVIDE FINANCING. Covington, LA: December 13, 2012 - LLOG Exploration Company, 1001 Ochsner Boulevard, Suite 200 Covington, LA 70433 Phone (985) 801-4300 Fax (985) 801-4796 Press Release Contact: Public Relations Email: pr@llog.com FOR IMMEDIATE RELEASE December 13, 2012 DELTA HOUSE

More information

Glossary CALM. Our Activities

Glossary CALM. Our Activities Glossary CALM Our Activities 100 Year Storm Normally all offshore systems are designed to withstand the 100 year storm i.e. the storm that happens once every hundred years at the location where the system

More information

FILLING AND PURGING THE SYSTEM

FILLING AND PURGING THE SYSTEM FILLING INSTRUCTIONS FOR WATER HEATER OR CONDENSING BOILER (City Water) Safety tip: Before beginning, turn off power to boiler and circulator. FILLING AND PURGING Step 1: Close Return Manifold Isolation

More information

A Leader In Maritime Technology

A Leader In Maritime Technology A Leader In Maritime Technology Sea Launch Odyssey Table of Contents Overview 1 LNG Carriers 4 Floating Units 6 Offshore Platforms 8 Floating Production Units 11 Octabuoy Production Platforms 12 Floating

More information

Goliat Produced Water Management

Goliat Produced Water Management Goliat Produced Water Management Hans Tore Nordbø, Process Engineer, Eni Norge AS Tekna Produced Water Management, 21.01.10-22.01.10, Clarion Hotel Stavanger www.eninorge.no PL229 Goliat location, ownership

More information

Facilities Flexibras Tubos Flexíveis Ltda

Facilities Flexibras Tubos Flexíveis Ltda Facilities Flexibras Tubos Flexíveis Ltda A world-class facility for the highest quality flexible pipe to the Brazilian market Technip at a glance Technip is a world leader in project management, engineering

More information

Bundle Pipeline Systems & Shell FRAM Development Iain Watson & Peter Walker

Bundle Pipeline Systems & Shell FRAM Development Iain Watson & Peter Walker Bundle Pipeline Systems & Shell FRAM Development Iain Watson & Peter Walker March 21 st, 2012 27.1.11 Page 1 Agenda Bundle Technologies Advantages of Bundle Systems Shell Fram Bundle FEED 27.1.11 Page

More information

Worldwide Technip in Norway

Worldwide Technip in Norway Worldwide Technip in Norway The leading subsea EPCI and Facilities Contractor for the Norwegian Continental Shelf Technip at a glance Technip is a world leader in project management, engineering and construction

More information

Technip in Norway. 1 Technip in Norway

Technip in Norway. 1 Technip in Norway Technip in Norway 1 Technip in Norway Norway : Part of our North Sea Canada Region Aberdeen Oslo St. Johns Regional Headquarters Satellite operating centers Spoolbase Manufacturing plant (umbilical) 2

More information

DIESEL FUEL CONDITIONING

DIESEL FUEL CONDITIONING COD FILTRATION DIESEL FUEL CONDITIONING REMOVE WATER & PARTICLES TO EXTEND FUEL INJECTOR LIFE & INCREASE COMBUSTION ENGINE FUEL EFFICIENCY Remove free water to saturation point with high single pass efficiency

More information

Improving UPTIME for Drilling Rigs

Improving UPTIME for Drilling Rigs Improving UPTIME for Drilling Rigs Why Modular Control Systems Make Sense Margaret Buckley, DTC International, March 2013 IADC Reliability In general, reliability (systemic def.) is the ability of a person

More information

Subsea Power Grid The key enabler for increased oil recovery IOR

Subsea Power Grid The key enabler for increased oil recovery IOR Subsea Power Grid The key enabler for increased oil recovery IOR Jan Erik Lystad CEO Power Electronic Centre Subsea Technology Centre Orkangerkonferansen 30. mai 2013 Siemens Oil & Gas Drilling Solutions

More information

Competitive Edge through System Engineering

Competitive Edge through System Engineering Competitive Edge through System Engineering KBD Forum 6-7 March 2013 Tore Halvorsen FMC Technologies 0 Floating Production Partial Subsea Processing Subsea Systems today: the enabler for deepwater developments

More information

PETROBRAS BUSINESS PLAN LUCAS TAVARES DE MELLO INVESTOR RELATIONS MANAGER APRIL, 2010

PETROBRAS BUSINESS PLAN LUCAS TAVARES DE MELLO INVESTOR RELATIONS MANAGER APRIL, 2010 PETROBRAS BUSINESS PLAN LUCAS TAVARES DE MELLO INVESTOR RELATIONS MANAGER APRIL, 1 DISCLAIMER The presentation may contain forecasts about future events. Such forecasts merely reflect the expectations

More information

NOTICE INVITING EXPRESSION OF INTEREST FOR FORMING AN ALLIANCE WITH COMPANY OWNING, OPERATING & EXPERIENCED IN CONVERTING/ BUILDING FPSO

NOTICE INVITING EXPRESSION OF INTEREST FOR FORMING AN ALLIANCE WITH COMPANY OWNING, OPERATING & EXPERIENCED IN CONVERTING/ BUILDING FPSO EOI No. T&OS/BD&A/FPSO/NB/01 NOTICE INVITING EXPRESSION OF INTEREST FOR FORMING AN ALLIANCE WITH COMPANY OWNING, OPERATING & EXPERIENCED IN CONVERTING/ BUILDING FPSO The Shipping Corporation of India Ltd.

More information

Platform Technologies for Offshore Renewable Energy Conversion Diego Vannucci, RINA

Platform Technologies for Offshore Renewable Energy Conversion Diego Vannucci, RINA Platform Technologies for Offshore Renewable Energy Conversion Diego Vannucci, RINA Objectives DON T RE-INVENT THE WHEEL! Oil & Gas Industry has been developing offshore technology for 100 years., is there

More information

TANKER - SHORE SAFETY CHECK-LIST

TANKER - SHORE SAFETY CHECK-LIST TANKE - SHOE SAFETY CHECK-LIST Part A - Bulk Liquid General - Physical Checks Bulk Liquid - General Tanker Terminal Code emarks 1 There is safe access between the tanker and shore. L1 The fendering arrangements

More information

Building an LNG driven vessel. LNG developments at Meyer Werft Viking Grace 18_09_2013

Building an LNG driven vessel. LNG developments at Meyer Werft Viking Grace 18_09_2013 1 Building an LNG driven vessel LNG developments at Meyer Werft Viking Grace 18_09_2013 Berufsbildung 13.09.2013 2 Meyer Werft Papenburg MEYER WERFT is a company with tradition, which started operations

More information

Assessment of Hydrocarbon Explosion and Fire Risks. Professor Jeom Paik. The LRET Research Collegium Southampton, 11 July 2 September 2011

Assessment of Hydrocarbon Explosion and Fire Risks. Professor Jeom Paik. The LRET Research Collegium Southampton, 11 July 2 September 2011 Assessment of Hydrocarbon Explosion and Fire Risks by Professor Jeom Paik The LRET Research Collegium Southampton, 11 July 2 September 2011 1 Assessment of Hydrocarbon Explosion and Fire Risks in Offshore

More information

Offshore Oil and Gas. Experience and Capabilities

Offshore Oil and Gas. Experience and Capabilities Offshore Oil and Gas Experience and Capabilities ABS GROUP OVERVIEW As an independent, global provider of safety, risk and integrity management services, ABS Group offers objective, accurate advice based

More information

26.3.3 The Ship/Shore Safety Check-List

26.3.3 The Ship/Shore Safety Check-List International Safety Guide for Oil Tankers and Terminal Fifth Edition 2006-12-05 26.3.3 The Ship/Shore Safety Check-List Ship's Name Berth Date of Arrival Port Time of Arrival Part `A' - Bulk Liquid General

More information

Subsea processing. Oslo 8. September 2011 Håvard Eidsmoen, Statoil 2011-08-11

Subsea processing. Oslo 8. September 2011 Håvard Eidsmoen, Statoil 2011-08-11 Subsea processing Oslo 8. September 2011 Håvard Eidsmoen, Statoil Content Introduction/Motivation Why subsea processing? Overview of technologies, applications and examples Boosting Separation Compression

More information

TECHNIP AT A GLANCE 2014

TECHNIP AT A GLANCE 2014 TECHNIP AT A GLANCE 2014 Unique range of activities A world leader in project management, engineering and construction for the energy industry S U B S E A OFFSHORE Subsea infrastructures, from deep to

More information

12/08/2015. Introduction to Subsea Production Systems. Module structure. 08 Production Control Systems. August 2015

12/08/2015. Introduction to Subsea Production Systems. Module structure. 08 Production Control Systems. August 2015 OIL & GAS Introduction to Subsea Production Systems 08 Production Control Systems August 2015 DNV GL 2013 2015 August 2015 SAFER, SMARTER, GREENER Module structure Section 1 Introduction to control systems

More information

New generation of modern LNG carriers with type C cargo tanks and LNG propulsion system

New generation of modern LNG carriers with type C cargo tanks and LNG propulsion system Gastech London 2012 New generation of modern LNG carriers with type C cargo tanks and LNG propulsion system Björn Munko Content Introduction Vessels Delivered/Under Construction Gas Plant Design New Designs

More information

Subsea Engineering Days 2015

Subsea Engineering Days 2015 Subsea Engineering Days 2015 London 20-22 October 2015 Value propositions and contact information 4 Subsea (Only for Premier Oil, Genesis & BP) Nils Gunnar Viko - Vice President, Flexible Pipe Technology

More information

Maritime Human Resources Solutions Seminar. Robert Cadigan President & CEO Newfoundland & Labrador Oil & Gas Industries Association

Maritime Human Resources Solutions Seminar. Robert Cadigan President & CEO Newfoundland & Labrador Oil & Gas Industries Association Maritime Human Resources Solutions Seminar Robert Cadigan President & CEO Newfoundland & Labrador Oil & Gas Industries Association About NOIA NOIA s mission is to promote development of East Coast Canada

More information

Det norske oljeselskap - Our first diving operation. Annual Conference The Norwegian Oil and Gas Association Stavanger, Norway 13.03.

Det norske oljeselskap - Our first diving operation. Annual Conference The Norwegian Oil and Gas Association Stavanger, Norway 13.03. Det norske oljeselskap - Our first diving operation Annual Conference The Norwegian Oil and Gas Association Stavanger, Norway 13.03.13 Diving Operations our starting point Det norske started out with a

More information

Press release. SBM Offshore Q1 Trading Update 16 May 2012. Highlights First Quarter 2012. Post Period Highlights

Press release. SBM Offshore Q1 Trading Update 16 May 2012. Highlights First Quarter 2012. Post Period Highlights Press release SBM Offshore Q1 Trading Update 16 May 2012 Highlights First Quarter 2012 Turnover of US$ 763 million, 12% above Q1 prior year Total order portfolio of US$ 16.7 billion US$ 0.5 billion order

More information

and to mutually agree mitigation measures to reduce identified concerns and risks to acceptable levels.

and to mutually agree mitigation measures to reduce identified concerns and risks to acceptable levels. PTC ID: 88 Connecting Offshore Platforms to a Subsea Cable System Jerry Brown, Ocean Specialists Inc. Technical Manager Subsea. Introduction Bandwidth hungry applications for process controls and business

More information

A View from the (Deepwater) Horizon: Regulatory and Statutory Developments Affecting Offshore Drilling and. Spill Liability.

A View from the (Deepwater) Horizon: Regulatory and Statutory Developments Affecting Offshore Drilling and. Spill Liability. A View from the (Deepwater) Horizon: Regulatory and Statutory Developments Affecting Offshore Drilling and Spill Liability Gerald D. Higdon 600 Travis, Suite 2800 Houston, TX 77002 713-238-3709 jhigdon@lockelord.com

More information

GE Oil & Gas DPS. ESRA Norge Seminar Tilgjengelighet/Pålitelighet/RAMS. litelighet/rams. Reliability & Technical Risk Management et

GE Oil & Gas DPS. ESRA Norge Seminar Tilgjengelighet/Pålitelighet/RAMS. litelighet/rams. Reliability & Technical Risk Management et GE Oil & Gas DPS ESRA Norge Seminar Tilgjengelighet/Pålitelighet/RAMS litelighet/rams Reliability & Technical Risk Management et verktøy for å levere pålitelige p undervannssystemer Endre Willmann - Technical

More information

Section 9315. Operations Section Organizational Guidance

Section 9315. Operations Section Organizational Guidance Section 9315 Operations Section Organizational Guidance T able of Contents Section Page 9315 Operations Section Organizational Guidance... 9315-1 9315.1 Minor Inland Spill Scenario... 9315-1 9315.2 Minor

More information

Certification of Materials and Components

Certification of Materials and Components OIL & GAS Certification of Materials and Components Standardisation of the industry s approach to quality control and assurance processes Martin Fowlie 12th February 2015 1 DNV GL 2013 12th February 2015

More information

Maersk Oil UK Environmental Performance Report 2013. An ongoing commitment to continual improvement, legal compliance and prevention of pollution

Maersk Oil UK Environmental Performance Report 2013. An ongoing commitment to continual improvement, legal compliance and prevention of pollution Maersk Oil UK Environmental Performance Report 213 An ongoing commitment to continual improvement, legal compliance and prevention of pollution Maersk Oil North Sea UK Limited Health, Safety & Environment

More information

The Competitive Edge. The Foundation For Competing

The Competitive Edge. The Foundation For Competing Passion - Creativity - Innovation - Initiative - Intellect - Dedication - Compliance - The Competitive Edge The Foundation For Competing Statoil s Subsea Technology Strategy, with selected technology challenges

More information

Technip Offshore Finland

Technip Offshore Finland Facilities Technip Offshore Finland Construction yard Technip Profile A world leader in engineering, project management and technologies, serving the oil & gas industry for more than 50 years A regular

More information

Carbon Capture & Storage Reliable cost effective CO 2 shipping through statistical modelling

Carbon Capture & Storage Reliable cost effective CO 2 shipping through statistical modelling Carbon Capture & Storage Reliable cost effective CO 2 shipping through statistical modelling The Hague November 1st, 2011 Cees van der Ben Note This document and all information contained herein are the

More information

2nd quarter results 2011 12 August 2011

2nd quarter results 2011 12 August 2011 part of Aker 2nd quarter results 2 12 August 2 2 Aker Solutions Agenda Topic Introduction Financials Speaker Øyvind Eriksen, Executive Chairman Leif Borge, President & CFO Q&A session Front page photo:

More information

Design Concepts for. IMO type C cargo tanks. Dr. K.D. Gerdsmeyer. Carriers & Carriers & Offshore Units

Design Concepts for. IMO type C cargo tanks. Dr. K.D. Gerdsmeyer. Carriers & Carriers & Offshore Units Design Concepts for LNG FSRU/FPSO with IMO type C cargo tanks Dr. K.D. Gerdsmeyer Carriers & Carriers & Offshore Units Design Concepts for LNG FSRU/FPSO with IMO type C cargo tanks Content: TGE s experience

More information

Case Study of Emergency Disconnect Sequence in the Gulf of Mexico

Case Study of Emergency Disconnect Sequence in the Gulf of Mexico Case Study of Emergency Disconnect Sequence in the Gulf of Mexico Trent Fleece Subsea BOP Operations Team Lead May 8, 2015 Case Study of Emergency Disconnect Sequence in Gulf of Mexico Industry Standards

More information

Darchem Thermal Protection

Darchem Thermal Protection Darchem Thermal Protection Engineered Materials Thermal and Fire Protection for life www.darchem.co.uk Introduction to Darchem Thermal Protection Darchem Thermal Protection is world renowned for the design,

More information

Study of the Stability of Turret moored Floating Body

Study of the Stability of Turret moored Floating Body 1 Study of the Stability of Turret moored Floating Body Seok Kyu, Cho, Hong Gun, Sung, Sa Young Hong, Yun Ho, Kim, MOERI/KIOST Hang Shoon, Choi, Seoul National Univ. ABSTRACT Turret moored floating platforms,

More information

Oslo, 29 August 2007. Pareto Securities Oil and Offshore Conference Arne Austreid, President and CEO

Oslo, 29 August 2007. Pareto Securities Oil and Offshore Conference Arne Austreid, President and CEO Oslo, 29 August 2007 Pareto Securities Oil and Offshore Conference Arne Austreid, President and CEO 2 Disclaimer All statements in this presentation other than statements of historical fact are forward-looking

More information

LEISTRITZ PUMPEN GMBH. Leistritz Screw Pumps & Systems. Cargo and Liquid Handling

LEISTRITZ PUMPEN GMBH. Leistritz Screw Pumps & Systems. Cargo and Liquid Handling LEISTRITZ PUMPEN GMBH Leistritz Screw Pumps & Systems Cargo and Liquid Handling Leistritz Screw Pumps and Systems Leistritz Pumpen GmbH Leistritz Pumpen GmbH with its headquarters in Nuremberg/Germany

More information

PRODUCTION OPTIMIZATION CONSULTING SERVICES. Delivering comprehensive optimization solutions from a single well to a full field PRODUCTION

PRODUCTION OPTIMIZATION CONSULTING SERVICES. Delivering comprehensive optimization solutions from a single well to a full field PRODUCTION PRODUCTION PRODUCTION OPTIMIZATION CONSULTING SERVICES Delivering comprehensive optimization solutions from a single well to a full field DRILLING & FORMATION EVALUATION WELL CONSTRUCTION COMPLETION &

More information