Access Floors. Architect s Guide for Detailing & Specifying Access Floor Air Plenums. SustainAbility to the Power of

Size: px
Start display at page:

Download "Access Floors. Architect s Guide for Detailing & Specifying Access Floor Air Plenums. SustainAbility to the Power of"

Transcription

1 Access Floors Architect s Guide for Detailing & Specifying Access Floor Air Plenums SustainAbility to the Power of 1

2 Access floor air plenum integrity begins with proper design and specification. 2

3 Architect s Guide for Detailing & Specifying Access Floor Air Plenums Plenum Integrity is one of the most important aspects of designing, constructing and maintaining an underfloor air delivery (UFAD) system. It is vital that the entire design and construction team does their part to ensure the underfloor plenum is sealed properly. This process starts with the architect. As the architect designing a building with a UFAD system you have the responsibility of providing specifications and details for constructing a plenum with proper sealing and integrity. Every contractor working in the plenum space needs to be aware of their responsibilities and should be equipped with the information they need to successfully complete their work while maintaining plenum integrity. Tate Access Floors is providing the following plenum seal integrity guidelines for consideration. The recommendations contained within this guideline are based on lessons learned through working on a wide range of UFAD projects. To that end, Tate believes a holistic approach to design and construction should be used and recommends regular consultation be held with key individuals on the construction team throughout the entire design process. There are six primary recommendations. An overview and explanation of each recommendations is provided below followed by proposed specification language and construction details. Design: Pre-Bid Meeting: Pre-Construction: Mock-up: Specifications and performance requirements that create awareness and responsibility for plenum sealing integrity should be included in all divisions of the CSI specifications. Drawings detailing the construction requirements for the underfloor air delivery plenum should also be provided. The requirement for pre-bid meetings to inform all subcontractors of the plenum sealing and mock-up construction requirements should be specified. Pre-construction meetings should also be specified to reaffirm the plenum sealing requirements to each sub-contractor division. Specify the construction and testing of a mock-up that includes all actual building conditions relative to the UFAD system. Quality Inspections: Specify the use of a commissioning agent to audit the construction process, perform air leakage testing on the mock-up and final installation, and provide detailed reporting to the GC that ensures the construction of the UFAD system follows the specified requirements. 3

4 Downloadable Specifications & Details Visit Tate s website to download the sealing details and recommended specification language in this guide. The details are available in AutoCAD dwg and PDF file formats. In addition a Microsoft word version of the specifications in this guide can be found in the architectural details under the Product & Spec section of the website CSI Specifications for Consideration The following is Tate s recommended access floor air plenum sealing specification language to insert into the CSI specifications for subcontractors. All of the specifications can be downloaded on-line at DIVISION 01 - GENERAL REQUIREMENT SPECIFICATIONS Pre-Bid & Pre-Construction Meetings: All sub-contractors intending to bid on or awarded work on the project are required to attend pre-bid and pre-construction meetings respectively. The purpose of these meetings is to review all air plenum specifications and details including but not limited to pre-construction mock-ups and plenum sealing requirements. 4

5 Quality Control: All walls passing through the access floor must have gypsum board extending completely to the slab and be sealed at the slab line. All penetrations into cavity walls and slabs for air ducts, plumbing pipes, electrical conduit and voice/data cabling must be completely sealed. All seams and/or holes that have been created for or resulting from the work performed by a specific trade should be properly sealed by that trade and whenever possible performed prior to the installation of the access floor. Quality Control: Special inspections must be conducted by an independent quality auditor or commissioning agent to ensure that plenum sealing work is performed by all subcontractors in compliance with specifications and drawings. Inspections shall occur as work progresses and whenever possible in the presence of a representative from the general contractor. Reports of inspections will be submitted to the general contractor. Plenum Mock-Up & Testing: All subcontractors responsible for constructing or penetrating the underfloor plenum must participate in the construction of an on-site plenum mockup consisting of all planned plenum components, penetrations, seams and openings. The mock-up plenum is to be inspected and tested by an independent commissioning agent for air leakage to verify that it was constructed and sealed in accordance with specifications and drawings including meeting the air leakage requirements. Building Plenum Inspections and Tests: The constructed plenum is to be inspected and tested by an independent commissioning agent for air leakage to verify that it was constructed and sealed in accordance with specifications and drawings including meeting the air leakage requirements. Air Leakage Requirements: Total air leakage from the plenum should be no more than 10% of the design airflow for category 1* leakage, and 10% of the design airflow for category 2 leakage when tested at the typical static pressure range of Pascals. Note:There are two basic categories of UFAD air leakage. Category 1 leakage occurs outside of the intended occupied zone. Category 2 leakage is plenum air that leaks into the occupied zone through spaces other than the designed air distribution devices such as diffusers. Category 2 leakage is unique to UFAD systems because all of this leakage goes into the occupied space whereas in a traditional ducted overhead system, all leakage and short-circuited air enters the return plenum and will not reach the intended zone. *The allowable Category 1 leakage number used to commission UFAD systems is higher than overhead distribution. This higher number is used because the entire HVAC system from supply point to diffuser is being tested in a UFAD system. By comparison overhead systems typically only test the trunk or high and medium pressure ducts. The test being performed on a UFAD system would be the equivelant to using the following equation on an overhead system: Leakage = supply duct + VAV box + low pressure duct + flex duct + diffuser & flex connection. 5

6 DIVISION 03 - CONCRETE SPECIFICATION - Cast in Place Concrete The concrete contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take the necessary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanliness. Any penetrations or holes in the underfloor plenum resulting from the work performed by the division 3 contractors not intended for service utility distribution are required to be properly sealed to prevent air leakage. DIVISION 05 - METAL STAIRS SPECIFICATION The metal stair contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take the necessary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanliness. Any penetrations or holes in the underfloor plenum created for or resulting from the work performed by the division 5 contractors are required to be properly sealed to prevent air leakage. DIVISION 09 - FINISHES (WALLS) SPECIFICATION The wall contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take the necessary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanliness. Any penetrations or holes in the underfloor plenum created for or resulting from the work performed by the wall contractors are required to be properly sealed to prevent air leakage. DIVISION 09 - FINISHES (ACCESS FLOORING) SPECIFICATION The access floor contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take the necessary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanliness. Any penetrations or holes in the underfloor plenum created for or resulting from the work performed by the access flooring contractors are required to be properly sealed to prevent air leakage. DIVISION 09 - FINISHES (TILE CARPETING) SPECIFICATION The carpeting contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take the necessary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanliness. Any penetrations or holes in the underfloor plenum created for or resulting from the work performed by the carpeting contractors are required to be properly sealed to prevent air leakage. 6

7 DIVISION 14 - CONVEYING EQUIPMENT SPECIFICATION The conveying equipment contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take the necessary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanliness. Any penetrations or holes in the underfloor plenum created for or resulting from the work performed by the division 14 contractors are required to be properly sealed to prevent air leakage. DIVISION 22 - PLUMBING SPECIFICATION The plumbing contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take the necessary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanliness. Any penetrations or holes in the underfloor plenum created for or resulting from the work performed by the division 22 plumbing contractors are required to be properly sealed to prevent air leakage. DIVISION 23 - HEATING VENTILATION AND AIR CONDITIONING SPECIFICATION The HVAC contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take the necessary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanliness. Any penetrations or holes in the underfloor plenum created for or resulting from the work performed by the division 23 HVAC contractors are required to be properly sealed to prevent air leakage. DIVISION 26 - ELECTRICAL SPECIFICATION The electrical contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take the necessary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanliness. Any penetrations or holes in the underfloor plenum created for or resulting from the work performed by the division 26 electrical contractors are required to be properly sealed to prevent air leakage. DIVISION 27 - COMMUNICATIONS SPECIFICATION The communications contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take the necessary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanliness. Any penetrations or holes in the underfloor plenum created for or resulting from the work performed by the division 26 communications contractors are required to be properly sealed to prevent air leakage. 7

8 Construction Details for Consideration The following are typical sealing details that should be considered to ensure UFAD plenum integrity. All of the details can be downloaded on-line at: Underfloor Air Sealing Locations PLAN VIEW WITHOUT ACCESS FLOOR DETAIL G TELCOM ELECTRICAL DETAIL I & K DETAIL E DETAIL D DETAIL F 8

9 DETAIL A MECHANICAL DETAIL B MENS JANITOR WOMENS KITCHEN DETAIL C ELECTRICAL DETAIL L & M TELCOM DETAIL N 9

10 Base Building Core & Shell Sealing Details A) PERIMETER SEAM ALONG SLAB AND EXTERIOR WALL INTERIOR WALL ASSEMBLY CURTAIN WALL SEAL AT SLAB LINE B) ENCLOSED COLUMN SEAM AT SLAB LINE STRUCTURAL COLUMN WALL ASSEMBLY (TYP) SEAL AT SLAB LINE C) DRYWALL PARTITION CONDITION SCHEDULED GWB SEAL AT SLAB LINE 10

11 D) BASE OF STAIRS ON BUILDING SLAB STAIR TREAD (TYP) SEAL SEAM BETWEEN STAIR AND CURB OR OTHER SUPPORT SEAL AT SLAB LINE CONCRETE CURB OR STRUCTURAL STEEL WITH FULL ENCLOSURE E) TOP OF STAIR INTERFACE WITH CONCRETE CURB OR STRUCTURAL STEEL WITH FULL ENCLOSURE SEAL AT SLAB LINE STAIR TREAD (TYP) F) ELEVATOR SHAFT TOP OF BELOW STAIR INTERFACE ACCESS WITH CONCRETE FLOOR DECK LINE ELEVATOR DOORS CONCRETE CURB OR STRUCTURAL STEEL WITH FULL ENCLOSURE ELEVATOR THRESHOLD SEAL AROUND FULL ENCLOSURE 11

12 G) EXPANSION JOINT IN EXPANSION JOINT SEAL JOINT EXPANSION JOINT IN HVAC System Sealing Details H) OPENING IN SLAB FOR VERTICAL DUCTS VERTICAL DUCT SEAL SPACE AROUND DUCT I) OPENING IN PLENUM WALLS FOR DUCTS DUCT THROUGH WALL SEAL SPACE AROUND DUCT 12

13 Plumbing Sealing Details J) PIPE PENETRATION THROUGH SEAL AROUND PIPE PIPE PENETRATION THROUGH K) PIPE PENETRATION THROUGH PLENUM WALLS SEAL AROUND PIPE PIPE O.D. WALL ASSEMBLY 13

14 Electrical System Sealing Details l) CONDUIT THROUGH PLENUM WALLS SEAL AROUND CONDUIT CONDUIT (AND CABLE BUNDLE) O.D. WALL ASSEMBLY CONDUIT M) OPEN ENDS OF CONDUIT IN THE CONDUIT PLENUM THROUGH SPACE PLENUM WALL OUTLET WALL ASSEMBLY CONDUIT SEAL OPENING AT CONDUIT PENETRATION SEAL OPEN END OF CONDUIT IN PLENUM THERMOSTAT WALL ASSEMBLY CONDUIT SEAL OPENING AT CONDUIT PENETRATION SEAL OPEN END OF CONDUIT IN PLENUM 14

15 Voice/Data System Sealing Details N) CABLE PENETRATIONS THROUGH PLENUM WALL WITH CABLE SLEEVE SEAL AROUND CABLE SLEEVE CABLE SLEEVE O.D. SEAL AROUND CABLES INSIDE SLEEVE WALL ASSEMBLY CAPPED ENDS OF UNUSED CABLE SLEEVE (TYP) CABLE BUNDLE CABLE PENETRATIONS THROUGH PLENUM WALL WITH CABLE SLEEVES 15

16 Access Floor Air Sealing Locations PLAN VIEW WITH ACCESS FLOOR INSTALLED DETAIL 1 & 3 DETAIL 12 DETAIL 4 & 5 TELCOM ELECTRICAL DETAIL 9 & 10 6 RAISED PODIUM DETAIL 8 16

17 DETAIL 2 DETAIL 13 DETAIL 6 & 7 MECHANICAL MENS JANITOR KITCHEN WOMENS ELECTRICAL TELCOM DETAIL 14 17

18 Access Floor Sealing Details 1) PLENUM DIVIDERS PANEL FASTENED TO PEDESTAL HEAD WITH COMBO CORNERLOCK SCREW ACCESS FLOOR PANEL ATTACH PLENUM CHANNEL WITH STRINGER SCREWS FIELD APPLIED GASKET TAPE JOINTS WITH METAL FOIL TAPE 2.4m LONG GALVANIZED STEEL HAT CHANNEL FASTEN WITH TEK SCREWS 26 GA. X 1.8m STEEL BOTTOM ANGLE CUT AS REQUIRED SO THAT IT DOES NOT EXTEND ABOVE HAT CHANNEL FIELD APPLIED TATE PLENUM GASKET P/N TAPE JOINTS WITH METAL FOIL TAPE WHERE BOTTOM ANGLE SECTIONS MEET AND WHERE HAT CHANNEL SECTIONS MEET TAPE JOINTS WITH METAL FOIL TAPE WHERE HAT CHANNEL AND BOTTOM ANGLE MEET BOTTOM ANGLE SET IN FIELD APPLIED CONTINUOUS ADHESIVE BEAD 2) AIR HIGHWAYS FIELD APPLIED GASKET AT HAT CHANNEL AND STRINGERS (TYP) ACCESS FLOOR PANELS STRINGERS (TYP) PEDESTAL (TYP) HAT CHANNEL METAL FOIL TAPE AT JOINTS 18

19 3) PENETRATIONS THROUGH PLENUM DIVIDERS PLENUM DIVIDER ASSEMBLY CABLE SLEEVE (FIRESTOP OR PUTTY INSIDE OF SLEEVE) SEAL TO FILL GAP (TYP) WATER PIPE(S) CONDUIT METAL FOIL TAPE AT JOINTS 4) PERIMETER SEAM WITHOUT WALL BASE PENETRATIONS THROUGH PLENUM DIVIDER WALL EXTENDS TO SUBFLOOR ACCESS FLOOR PANEL SEAL AT FLOOR/WALL LINE CUT PANELS TO WITHIN 1.6MM OF WALL SEAL AT SLAB LINE 5) PERIMETER SEAM WITH WALL BASE ACCESS FLOOR PERIMETER SEAL WITHOUT WALL BASE CUT CARPET TO WALL AND ADHERE TO ACCESS FLOOR WITH RELEASABLE ADHESIVE ACCESS FLOOR PANEL WALL EXTENDS TO SUBFLOOR WALL BASE (WHERE USED) CUT PANELS TO WITHIN 1.6MM OF WALL SEAL AT SLAB LINE ACCESS FLOOR PERIMETER SEAL WITH WALL BASE 19

20 6) PERIMETER SEAM AT NON-SMOOTH WALLS & COLUMNS NON-SMOOTH WALL OR COLUMN CAULK & FASTEN METAL ANGLE TO WALL CUT CARPET TO WALL AND ADD OPTIONAL WALL BASE CONCORE OR ALL STEEL FLOOR PANEL 7) ACCESS FLOOR SEAL AT FASCIA / EXPOSED EDGE WHERE GAPS OCCUR BETWEEN THE EDGE OF THE ACCESS FLOOR AND FASCIA, APPLY DUCT OR METAL TAPE TO SEAL JOINT PRIOR TO APPLICATION OF CARPET. FIRE RATED CAULK OR SEALANT TRIM ANGLE GUARDRAIL POST ATTACH TRIM ANGLE OVER CARPET AND FASCIA PLATE CUT CARPET TO FASCIA PLACE AND ADHERE TO ACCESS FLOOR WITH RELEASABLE ADHESIVE ACCESS FLOOR PANEL FASCIA PLATE (cut to meet edge of access floor) BOTTOM ANGLE 8) PERIMETER SEAM AT ELEVATOR SHAFT Access Floor Seal At Fascia / Exposed Edge 1.6MM 20

21 9) PERIMETER SEAM AT TOP OF STAIR LANDING CONCRETE CURB OR STRUCTURAL STEEL WITH FULL ENCLOSURE SEAL AROUND ENCLOSURE CUT PANELS TO WITHIN 1.6MM OF CURB STAIR TREAD (TYP) ACCESS FLOOR PERIMETER SEAL AT TOP OF STAIR 10) PERIMETER SEAM AT BASE OF STAIR LANDING STAIR TREAD (TYP) SEAL SEAM AROUND ENCLOSURE CUT PANEL TO WITHIN 1.6MM OF STAIR CONCRETE CURB OR STRUCTURAL STEEL WITH FULL ENCLOSURE ACCESS FLOOR PERIMETER SEAL AT BASE OF STAIR 11) PENETRATION IN WALL THROUGH ACCESS FLOOR 21

22 FOAM GASKET ATTACHED 12) PERIMETER SEAM AT FIRE BARRIER BELOW DOOR THRESHOLD OPTION 1: ATTACH THRESHOLD WITH GASKET ON UNDERSIDE CONCORE OR ALL STEEL ACCESS FLOOR PANEL OPTION 2: APPLY SEALANT OR ATTACH GASKET TO BARRIER TO SEAL JOINTS PERIMETER PEDESTAL SUPPORT SHEETROCK FACED FIRE BARRIER SEAL AT SLAB LINE Access Floor Seal At Fire Barrier Below Door Threshold 13 PERIMETER SEAM AT CURB WHERE FLOOR COVERING IS CONTINUOUS CARPET TILE ADHERED TO ACCESS FLOOR AND CURB ACCESS FLOOR PANEL CUT PANELS TO WITHIN 1.6MM OF WALL. FOAM GASKET ATTACHED TO CURB TO SEAL JOINT ACCESS FLOOR SEAL AT CURB CONTINUOUS FLOOR COVERING FROM ACCESS FLOOR TO CURB 14) PERIMETER SEAM AT CURB WHERE FLOOR COVERING IS NOT CONTINUOUS OTHER COVERING ADHERED TO CURB TRANSITION STRIP OR THRESHOLD CARPET TILE ADHERED TO ACCESS FLOOR ACCESS FLOOR PANEL CUT PANELS TO WITHIN 1.6MM OF WALL. IF GAP 22

23 15) CABLE CUTOUTS & GROMMETS PLAN VIEW GROMMET WITH LID PLAN VIEW FOAM PLENUM SEAL CUTOUT TRIM MOLDING SECTION THROUGH CUTOUT FOAM PLENUM SEAL LID IS 2 PART TWIST COVER FULLY CLOSED POSITION TO PREVENT AIR LEAKAGE FOAM PLENUM SEALS: THESE ARE PROVIDED BY THE ACCESS FLOOR MANUFACTURER AND ARE RECOMMENDED TO SEAL CABLE OPENINGS CABLE CUTOUT & SEAL ASSEMBLY 16) POWER, VOICE/DATA DISTRIBUTION BOXES IN ACCESS FLOOR PANELS SEAL UNUSED DUPLEX OPENINGS ATTACH BLANK INTERFACE PLATES TO UNUSED OPENINGS POWER, VOICE, AND DATA DISTRIBUTION BOX 17) PIPE PENETRATION THROUGH ACCESS FLOOR SEAL AROUND PIPE 23

24 Tate Access Floors Pty. Ltd. 28 Biloela Street, Villawood NSW 2163 Tel: Fax: tatetasman.com.au kingspan.com Corporate Headquarters: 7510 Montevideo Road, Jessup, MD Tate Hotline: Tel: Fax: Production Facilities: 7510 Montevideo Road, Jessup, MD Springvale Road, Red Lion, PA tateinc.com kingspan.com Tate Access Floors, Inc. components are proudly made in the U.S.A. A member of MEMBER Tate Building Technology Platform, ConCore, GrateAire, PosiLock, PosiTile, PVD Servicenter, Floating Floors, Integral Trim, SustainAbility and AirArrest are registered trademarks of Tate Access Floors, Inc. DirectAire TM, SmartAire TM and PowerAire TM are trademarks of Tate Access Floors, Inc Tate Access Floors, Inc. Revised 2010 Version /10

Tate s Wire & Cable Solution

Tate s Wire & Cable Solution Access Floors Tate s Wire & Cable Solution A Flexible & Sustainable Management System Access Flooring to the Power of Your company will discover complete flexibility and reconfiguration capability 2 Creating

More information

Raised Floor Data Centers Prepared for the Future

Raised Floor Data Centers Prepared for the Future Raised Floor Data Centers Prepared for the Future Raised Floors Protect My Investment by Providing a Foundation for Current and Future Technologies. Creating the Future Proof Data Center Environment The

More information

Data Center Optimization Services. Maximize Your Data Center

Data Center Optimization Services. Maximize Your Data Center Data Center Optimization Services Maximize Your Data Center Energy savings was definitely the key driver in my decision to use the SmartAire dampers and DirectAire panels. - Larry Hood Senior Construction

More information

HVAC INSTALLATION. Success with 2015 IECC Northeast & Mid-Atlantic. Checklist for Builders & Trades

HVAC INSTALLATION. Success with 2015 IECC Northeast & Mid-Atlantic. Checklist for Builders & Trades Success with 2015 IECC Northeast & Mid-Atlantic Checklist for Builders & Trades COPYRIGHT 2015 ADVANCED ENERGY. ALL RIGHTS RESERVED TEMPLATE 2015.1.0 PAGE 1 CHECKLIST: JOB READY 1. 2. 3. 4. 5. 6. 7. 8.

More information

HVAC INSTALLATION SUCCESS WITH 2012 IECC DELAWARE. for Builders & Trades. Recommended Practices for Optimized Energy Savings

HVAC INSTALLATION SUCCESS WITH 2012 IECC DELAWARE. for Builders & Trades. Recommended Practices for Optimized Energy Savings SUCCESS WITH 2012 IECC DELAWARE Recommended Practices for Optimized Energy Savings for Builders & Trades COPYRIGHT 2015 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION 2015.1.0 CHECKLIST: JOB READY 1. 2.

More information

PANELIZED HOME INSTALLATION GUIDELINE

PANELIZED HOME INSTALLATION GUIDELINE PANELIZED HOME INSTALLATION GUIDELINE A typical home package will be constructed of Snap-N-Lock Insulated Panels clad with steel skins. 4" panels will be used for the walls, and 6" panels for the roof.

More information

6 Reasons to Specify Air-Sealing Grommets in the Design of a New Data Center

6 Reasons to Specify Air-Sealing Grommets in the Design of a New Data Center 6 Reasons to Specify Air-Sealing Grommets in the Design of a New Data Center Ken Brill, Lars Strong and Scott Alwine July 1, 2013 The use of raised-floor grommets to prevent bypass air from escaping the

More information

State of Connecticut Department of Public Health RADON PROGRAM

State of Connecticut Department of Public Health RADON PROGRAM State of Connecticut Department of Public Health RADON PROGRAM Scope The Connecticut Department of Public Health (DPH) Radon Program is providing this information for contractors who decide to build radon

More information

APPLICANT: ORANGE COUNTY, NEW YORK

APPLICANT: ORANGE COUNTY, NEW YORK Figure 1 Div 1 3 rd Flr Leakage in County Executives Office Figure 2 Div 1 3 rd Flr Location 067 approximately 2 SF of visible mold growth above entrance to Room 341 Figure 3 Div 1 3 rd Flr Location 067

More information

Home Energy Evaluation Report for Fritz Kreiss and Catherine McQueen

Home Energy Evaluation Report for Fritz Kreiss and Catherine McQueen Home Energy Evaluation Report for Fritz Kreiss and Catherine McQueen May 2008 Wisconsin Area PO BOX 115 Lake Geneva, WI 53147 CELL (414) 550-4765 Home Performance with ENERGY STAR Evaluation Report Customer

More information

SPACE TYPE: AUTOMATED DATA PROCESSING CENTER (ADP) (MAINFRAME)

SPACE TYPE: AUTOMATED DATA PROCESSING CENTER (ADP) (MAINFRAME) SPACE TYPE: AUTOMATED DATA PROCESSING CENTER (ADP) (MAINFRAME) Construction Criteria The unit costs for ADP Mainframe space types are based on the construction quality and design features in the following

More information

Comment Form on Proposed Gut Rehabilitation Alternatives

Comment Form on Proposed Gut Rehabilitation Alternatives Comment Form on Gut Rehabilitation Alternatives Name: Organization: Email: Instructions Submission: Please submit this form to energystarhomes@energystar.gov by October 10 th, 2012 with the subject line

More information

Duct Construction Standards. Code Reference: 2013 Title 24, Part 6 Standards 150.0(m)1. UL Ratings

Duct Construction Standards. Code Reference: 2013 Title 24, Part 6 Standards 150.0(m)1. UL Ratings DUCTS - CONSTRUCTION DO YOU HAVE A PHOTO OF THIS? PLEASE SEND IT TO US! installation.feedback@ energycodeace.com R-H-DS1 Duct Construction Standards All air-distribution system ducts and plenums shall

More information

Excerpts from the Canadian National Building Code (NBC)

Excerpts from the Canadian National Building Code (NBC) Excerpts from the Canadian National Building Code (NBC) Reproduced here with Permission of the Copyright Owner, the National Research Council of Canada, Institute for Research in Construction. For more

More information

Installation Details. D1 General D2 Walls D3 Ceilings D4 Reference. D Installation Details

Installation Details. D1 General D2 Walls D3 Ceilings D4 Reference. D Installation Details D Installation Details D1 General D2 Walls D3 Ceilings D4 Reference D Installation Details D Contents D1 General Installation and Fastening Sequence for Steel Studs D1.1 Fastener Selection D1.3 D2 Walls

More information

Whitley Manufacturing Co., Inc. 201 W. First Street S. Whitley, IN 46787 Phone (260) 723-5131 Sales Fax (260) 723-6396 whitley@whitleyman.

Whitley Manufacturing Co., Inc. 201 W. First Street S. Whitley, IN 46787 Phone (260) 723-5131 Sales Fax (260) 723-6396 whitley@whitleyman. Building Type Building Code Whitley Classroom Buildings BOCA, UBC, SBCCI, NEC, ADA Structural Support Outrigger construction standard, Whitley model classrooms. Main support beams to be 12 11.8# per lineal

More information

HVAC Air Duct Leakage. Eli P. Howard, III Group Director Technical Resources SMACNA

HVAC Air Duct Leakage. Eli P. Howard, III Group Director Technical Resources SMACNA HVAC Air Duct Leakage Eli P. Howard, III Group Director Technical Resources SMACNA Key Variables that Affect the Amount of Leakage Static Pressure Amount of Duct Openings in the Duct Surface Seams, Joints,

More information

Window Installation Instructions

Window Installation Instructions Caution The correct installation methods of windows in full frame or insert applications is critical towards achieving the tested performance of the window and longterm enjoyment and energy savings for

More information

INSTALLATION OF A BAY WINDOW

INSTALLATION OF A BAY WINDOW INSTALLATION OF A BAY WINDOW Installation of a Bay Window These instructions relate to the replacement of an existing bay window or replacement of a straight window with a new bay window, in an opening

More information

WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME

WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME 1 THE BUILDING PROCESS The focus of Woodland Homes building department is Quality, Service and Predictability. Through

More information

plumbing products guide

plumbing products guide plumbing products guide radiator pipe guide & seals A significant development in the drive to reduce air leakage and heat loss. Installations such as that shown are all too common. The detail is poorly

More information

Sun Windows General Information Sun New Construction Window Installation Instructions

Sun Windows General Information Sun New Construction Window Installation Instructions Sun Windows General Information Section 1 G F H H H A. Apply Weather Resistive Barrier B. Apply Sill Flashing Tape C. Place Waterproof Sill Shims D. Caulk Back of Nail Fin Sides & Top, Set Window, Fasten

More information

How To Prevent Water Damage To A Home

How To Prevent Water Damage To A Home Having inspected about 800 homes in the last four years, I have seen a lot of problems with many homes. Most of these problems are minor; however, there are some problems that are quite serious. One of

More information

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT

More information

The better way to build TM. Installation Manual. FOUNDATION SIPs & FROST WALLS SIPs

The better way to build TM. Installation Manual. FOUNDATION SIPs & FROST WALLS SIPs The better way to build TM Installation Manual FOUNDATION SIPs & FROST WALLS SIPs February 2016 PWF FOUNDATION & FROST WALL SIPs Installation Manual Table of Contents Topics General Requirements...................................

More information

Guide Specifications for Maple Flooring Systems

Guide Specifications for Maple Flooring Systems Guide Specifications for Maple Flooring Systems MFMA Guide Specification for Resilient Pre-Engineered Fixed Panel System Purpose This Guide Specification is designed to assist in the production of actual

More information

The better way to build TM. Installation Manual. EXTERIOR WALL SIPs

The better way to build TM. Installation Manual. EXTERIOR WALL SIPs The better way to build TM Installation Manual EXTERIOR WALL SIPs July 2015 EXTERIOR WALL SIPs Installation Manual Table of Contents Topics General Requirements................................... 3 Materials..............................................

More information

Air-Conditioning, Heating, and Refrigeration Institute. Sheet Metal and Air-Conditioning Contractors National Association

Air-Conditioning, Heating, and Refrigeration Institute. Sheet Metal and Air-Conditioning Contractors National Association Air-Conditioning, Heating, and Refrigeration Institute Sheet Metal and Air-Conditioning Contractors National Association GUIDELINE B-1997 ACKNOWLEDGEMENT These guidelines for Roof Mounted Outdoor Air-

More information

Fire Barriers & Fire Stopping

Fire Barriers & Fire Stopping Presented by: Bill Lauzon, PE Lauzon Life Safety Consulting, LLC 262-945-4567 Lauzon.lsc@gmail.com Web: Lauzon-LSC.com Environmental Part 2 Life Safety Code Chapter 8 Fire Barriers & Fire Stopping 1 Fire

More information

ACOUSTIC ISOLATION DETAILS

ACOUSTIC ISOLATION DETAILS ACOUSTIC ISOLATION DETAILS Icelandic National Concert and Conference Center Reykjavík, Iceland January 5, 2007 Artec Report No. 7742 Artec Project No. 3760 Distribution: Stefán Hermannsson East Harbour

More information

Mark Cramer Inspection Services, Inc.

Mark Cramer Inspection Services, Inc. Mark Cramer Inspection Services, Inc. 492 Twentieth Avenue, Indian Rocks Beach, FL 34635-2970 (727) 595-4211 Fax (727) 596-7583 Certified Member #12085 American Society of Home Inspectors Construction

More information

Installation Instructions

Installation Instructions Installation Instructions One-Piece Deep Wall Sleeve For Use with Packaged Terminal Units Please read these instructions completely before attempting installation. NOTE: Ensure that the unit is only installed

More information

WASHROOM UPGRADE SIR CHARLES TUPPER BUILDING 2250 RIVERSIDE DRIVE, OTTAWA, ON SIR CHARLES TUPPER BUILDING A0.0 COVER SHEET / DRAWING LIST

WASHROOM UPGRADE SIR CHARLES TUPPER BUILDING 2250 RIVERSIDE DRIVE, OTTAWA, ON SIR CHARLES TUPPER BUILDING A0.0 COVER SHEET / DRAWING LIST 0 RIVERSIDE DRIVE, OTTAWA, ON A0.0 COVER SHEET / DRAWING LIST A0. LEGEND AND GENERAL NOTES A0. GENERAL NOTES A0. GENERAL NOTES A0. TYPICAL WASHROOM WALL/SINK SECTION A0. DETAIL - CONTROL JOINT A0. DETAIL

More information

Services Enclosures and Protected Shafts - Maintaining Compartmentation

Services Enclosures and Protected Shafts - Maintaining Compartmentation Introduction When a fire resisting element is used to provide fire compartmentation, every opening that allows services to pass through the element must be adequately protected by sealing, or fire stopping

More information

ENERGY STAR Qualified New Homes Thermal Enclosure Checklist. Water Management Checklist. Eli Caudill

ENERGY STAR Qualified New Homes Thermal Enclosure Checklist. Water Management Checklist. Eli Caudill ENERGY STAR Qualified New Homes Thermal Enclosure Checklist & Water Management Checklist Eli Caudill ENERGY STAR Version 3 Tighter Standards Whole Home Approach Better, More Sustainable Construction Surpasses

More information

Challenges and Failures in Green Building Design Using Under-Floor Air Distribution. Ken Urbanek, PE, HBDP, LEED AP Director of Engineering

Challenges and Failures in Green Building Design Using Under-Floor Air Distribution. Ken Urbanek, PE, HBDP, LEED AP Director of Engineering Challenges and Failures in Green Building Design Using Under-Floor Air Distribution Ken Urbanek, PE, HBDP, LEED AP Director of Engineering Agenda UFAD Overview Challenges / Failures Steps for a Successful

More information

2015 1322) SIGNIFICANT CHANGES INCLUDING CODE COMMENTARY

2015 1322) SIGNIFICANT CHANGES INCLUDING CODE COMMENTARY MINNESOTA ENERGY CODE COMPLIANCE COLLABORATIVE 2015 Minnesota Residential Energy Code (MR 1322) SIGNIFICANT CHANGES INCLUDING CODE COMMENTARY (July 15, 2015 Update) Note: The following information contains

More information

Roof Inspection. Summary Report

Roof Inspection. Summary Report www.real-estate-inspections.com Roof Inspection Summary Report Subject Property Prepared for: File Number: Client in Detroit 05-15-RF-004 Inspector: Craig Milliken, PE # 32779 CPM Real Estate Inspections,

More information

VA25014B0516 VA CINCINNATI PROJECT NO. 539-328 INPATIENT BED TOWER ADDITION (4 TH AND 5 TH FLOORS) SECTION 09 29 00 GYPSUM BOARD

VA25014B0516 VA CINCINNATI PROJECT NO. 539-328 INPATIENT BED TOWER ADDITION (4 TH AND 5 TH FLOORS) SECTION 09 29 00 GYPSUM BOARD SECTION 09 29 00 GYPSUM BOARD PART 1 - GENERAL 1.1 DESCRIPTION This section specifies installation and finishing of gypsum board, vapor retarder and air and moisture barrrier. 1.2 RELATED WORK A. Installation

More information

SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS. System 402 Flush-Glazed Screw Spline Storefront

SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS. System 402 Flush-Glazed Screw Spline Storefront PART 1 GENERAL 1.01 Work Included SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS System 402 Flush-Glazed Screw Spline Storefront A. Furnish and install aluminum architectural storefront system

More information

Foundation. Foundation

Foundation. Foundation Moisture Aside from structural concerns, the most important consideration for foundation design is moisture. No client wants a wet basement. No client wants a damp basement. No client wants mold in their

More information

FAQs. 19. Does the sub floor need to be level before I install my new direct-to-stud bathtub or shower base?

FAQs. 19. Does the sub floor need to be level before I install my new direct-to-stud bathtub or shower base? 1. Where is the serial number of my tub located? 2. What can I use to clean my tub or shower? 3. What is an Above Floor Rough-in? 4. Can I replace my towel bar? 5. What are grommets? 6. Why do some bathing

More information

WORK SUMMARY April 17, 2015

WORK SUMMARY April 17, 2015 1 A Roof Damaged condenser fins at CU-1, CU-1A, and CU-2A. Rake all condenser fins at CU-1, CU-1A, and CU-2A. 66 3 units 2 A Roof Unacceptable/damaged paint finish at sheet metal parapet Sand/re-paint

More information

SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request

SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request SECTION 00 0110 PROCUREMENT AND CONTRACTING REQUIREMENTS 1.1 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS A. 00 0101 - Project Title Page B. 00 0105 - Certifications Page C. 00 0110 - Table

More information

GreenGuard Housewrap Installation Guide

GreenGuard Housewrap Installation Guide 000768PACBPHW_Flashing Bro 5/23/03 2:52 PM Page 1 For the most current product information, go to www.green-guard.com. Pactiv Building Products believes the information and recommendations herein to be

More information

MRI RF SHIELDING DESIGN

MRI RF SHIELDING DESIGN MRI RF SHIELDING DESIGN Nelco s MRI RF Shielding is specifically designed for the MRI industry. Our engineers have developed a shielded enclosure made entirely of nonmagnetic materials that is unsurpassed

More information

Uniform Construction Code (UCC) Manufactured Homes. Modular Homes. Building Permit Application Package

Uniform Construction Code (UCC) Manufactured Homes. Modular Homes. Building Permit Application Package Uniform Construction Code (UCC) Manufactured Homes (Single-Wide, Double-Wide) Modular Homes Building Permit Application Package Per the Uniform Construction Code (UCC) all structures must be built per

More information

ILLUSION FRAMELESS SHOWER ENCLOSURE INSTALLATION INSTRUCTIONS

ILLUSION FRAMELESS SHOWER ENCLOSURE INSTALLATION INSTRUCTIONS PREPARATION Approximate Installation Time: Tools Required for Installation: 60 minutes Hacksaw Electric Drill 3/16 Masonry Bit Pencil/Felt tip pen Safety Glasses Measuring Tape Masking Tape Standard Screw

More information

Electrical Wiring Technical Bulletin

Electrical Wiring Technical Bulletin Electrical Wiring Technical Bulletin Overview In general, SIP construction is easier and more cost effective when things are planned and thought out before the panels are manufactured. This process will

More information

SPACE TYPE: LABORATORY (WET) FOR CHEMISTRY AND BIOLOGY

SPACE TYPE: LABORATORY (WET) FOR CHEMISTRY AND BIOLOGY SPACE TYPE: LABORATORY (WET) FOR CHEMISTRY AND BIOLOGY Construction Criteria The unit costs for (Wet) space types are based on the construction quality and design features in the following table. This

More information

Lightweight Partition Design for Residential and Commercial Buildings

Lightweight Partition Design for Residential and Commercial Buildings Lightweight Partition Design for Residential and Commercial Buildings Stanley D. Gatland II, CertainTeed Corporation, Valley Forge, Pennsylvania Guidelines are presented for the design and proper installation

More information

UNDERFLOOR AIR DISTRIBUTION

UNDERFLOOR AIR DISTRIBUTION FINAL REPORT NCEMBT-080801 UNDERFLOOR AIR DISTRIBUTION AN EXPERIMENTAL COMPARISON OF AIR DIFFUSION PERFORMANCE BETWEEN UNDERFLOOR AIR DISTRIBUTION AND CONVENTIONAL OVERHEAD AIR DISTRIBUTION SYSTEMS AUGUST

More information

Structure Survey Findings:

Structure Survey Findings: Structure Survey Findings: Visible portions of the following were observed: foundations; structure to walls, columns, floors, roofs, overhang posts, and columns; attached or firmly abutting decks, balconies,

More information

2014 British Columbia Building Code Changes

2014 British Columbia Building Code Changes District of Houston 250-845-2238 2014 British Columbia Building Code Changes A District of Houston interpretation of the 2014 Building Code Changes for 9.36 & 9.32 The following changes reflect the most

More information

Schluter -KERDI-BOARD Substrate, building panel, bonded waterproofing

Schluter -KERDI-BOARD Substrate, building panel, bonded waterproofing Schluter -KERDI-BOARD Substrate, building panel, bonded waterproofing Schluter -KERDI-BOARD The universal substrate for tiles Flat. Level. Plumb. Square. No matter the quality, cost, or extravagance of

More information

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components Infrastructure Facility Condition Summary Weighted Avg Condition Score Facility Components Systems Surveyor/ Date Done Comments G Sitework.9 Site Improvements Parking Pedestrian Paving Site Development

More information

SECTION 08332 COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here)

SECTION 08332 COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here) SECTION 08332 COILING COUNTER DOORS Display hidden notes to specifier. (Don't know how? Click Here) PART 1 GENERAL 1.1 SECTION INCLUDES A. Coiling Metal Counter Doors. B. Coiling Counter Fire Doors. 1.2

More information

Envelope INSULATION BATT (2) Avoid Using Batt Insulation With Metal Framing. Pressure or Friction Fit

Envelope INSULATION BATT (2) Avoid Using Batt Insulation With Metal Framing. Pressure or Friction Fit R-H-DI1 INSULATION BATT NR-E-IB1 Avoid Using Batt Insulation With Metal Framing Batt insulation should not be used with metal framing systems. Although it is common to see fiberglass batt insulation installed

More information

Gramercy Place Condo Association, Inc.

Gramercy Place Condo Association, Inc. Gramercy Place Condo Association, Inc. UNIT MODIFICATION REQUEST Date of Application: Name of Owner (s): Telephone: (Home) (Cell) E-Mail: Anticipated start date: Anticipated ending date: Permission is

More information

Galina Stankevica. Master of Science in Engineering and ICT

Galina Stankevica. Master of Science in Engineering and ICT Commissioning of the HVAC-plant in a large office building designed with an underfloor ventilation system including input into what should be emphasized when evaluating the total system is to be done.

More information

Acoustical Design Guidelines for HVAC Systems in Schools

Acoustical Design Guidelines for HVAC Systems in Schools Acoustical Design Guidelines for HVAC Systems in Schools Seminar 9, ASHRAE Summer Meeting Albuquerque, New Mexico Sponsor: TC 2.6 Sound and Vibration Robert M. Lilkendey Associate Principal Consultant

More information

REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N

REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N PLAN REVIEW FOR: PROJECT NAME: OWNER: ARCH/DESIGNER: ADDRESS: Ph/Fx: Plans Dated: E-mail: Sealed By: Estimated Project Cost - $ REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N

More information

This handout is a guide only and does not contain all of the requirements of the Minnesota State Building Code or city ordinances.

This handout is a guide only and does not contain all of the requirements of the Minnesota State Building Code or city ordinances. Basement Finishing Guide Community Development Department Building Inspections Division 5200 85 th Avenue North / Brooklyn Park, MN 55443 Phone: (763) 488-6379 / Fax: (763) 493-8171 6/15 www.brooklynpark.org

More information

FIRESTOPPING & SMOKE SEALS

FIRESTOPPING & SMOKE SEALS SPECIFICATION SECTION 07 84 00 FIRESTOPPING & SMOKE SEALS 1 GENERAL 1.1 SECTION INCLUDES 1.1.1 Comply with Division 1, General Requirements and Documents referred to therein. 1.1.2 It is the intent of

More information

CENTER FOR ENVIRONMENTAL HEALTH Emergency Response/Indoor Air Quality Program

CENTER FOR ENVIRONMENTAL HEALTH Emergency Response/Indoor Air Quality Program CENTER FOR ENVIRONMENTAL HEALTH Emergency Response/Indoor Air Quality Program Guidance Concerning Remediation and Prevention of Mold Growth and Water Damage in Public Schools/Buildings to Maintain Air

More information

Standards. www.nordx.com 5 ANSI/TIA/EIA-569-A (CSA T530)

Standards. www.nordx.com 5 ANSI/TIA/EIA-569-A (CSA T530) The primary focus of this standard is to provide design specifications and guidance for all building facilities relating to telecommunications cabling systems and components. This standard identifies and

More information

LIFE SAFETY UPDATE. FULL SPRINKLERING OF ALL NURSING FACILITIES ADDITIONAL CLARIFICATIONS Prepared by Eric Rosenbaum, P.E. Hughes Associates, Inc.

LIFE SAFETY UPDATE. FULL SPRINKLERING OF ALL NURSING FACILITIES ADDITIONAL CLARIFICATIONS Prepared by Eric Rosenbaum, P.E. Hughes Associates, Inc. LIFE SAFETY UPDATE FULL SPRINKLERING OF ALL NURSING FACILITIES ADDITIONAL CLARIFICATIONS Prepared by Eric Rosenbaum, P.E. Hughes Associates, Inc. The purpose of this update is as follows: Remind all state

More information

Avoiding Air Barrier Pitfalls

Avoiding Air Barrier Pitfalls Avoiding Air Barrier Pitfalls Design & Durability November 2013 Air barriers, when correctly installed, help buildings achieve high levels of energy efficiency by decreasing heat loss. For example, great

More information

IECC Compliance Guide for Homes in Virginia

IECC Compliance Guide for Homes in Virginia IECC Compliance Guide for Homes in Virginia Amended Version of 2012 International Energy Conservation Code July 14, 2014 Climate Zone Since the entire state of Virginia falls in the IECC Climate Zone 4,

More information

800 Communications Circuits

800 Communications Circuits ARTICLE 800 Communications Circuits INTRODUCTION TO ARTICLE 800 COMMUNICATIONS CIRCUITS This article has its roots in telephone technology. Consequently, it addresses telephone and related systems that

More information

OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003

OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003 OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003 No. Discipline Sent to Name Item Date Noted Date Resolved How item was resolved Electrical Contractor

More information

SECTION 11 78 13 MORTUARY REFRIGERATORS

SECTION 11 78 13 MORTUARY REFRIGERATORS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 11 78 13 MORTUARY REFRIGERATORS SPEC WRITER NOTE: Delete between //---// if not applicable to project. Also delete any other item or paragraph not applicable in

More information

The Source of Firestop Expertise SM

The Source of Firestop Expertise SM The Source of Firestop Expertise SM Inspector Pocket Guide The following information is intended to provide construction and code enforcement professionals with basic checkpoints to ensure that the required

More information

Issue of the Guidelines on Prevention of Water Seepage in New Buildings

Issue of the Guidelines on Prevention of Water Seepage in New Buildings graphic: Buildings Department Your REF 來 函 檔 號 :. OUR REF 本 處 檔 號 :.BD GR/1-55/173 FAX 圖 文 傳 真 :..28400451 TEL 電 話 :..2626 1717 www.info.gov.hk/bd To : All Authorized Persons 7 March 2005 Registered Structural

More information

AIR LEAKAGE TEST REPORT EPA REGION 8 HEADQUARTERS, DENVER, CO

AIR LEAKAGE TEST REPORT EPA REGION 8 HEADQUARTERS, DENVER, CO AIR LEAKAGE TEST REPORT EPA REGION 8 HEADQUARTERS, DENVER, CO Fred Bauman, Tom Webster, and Darryl Dickerhoff Center for the Built Environment (CBE) University of California, Berkeley August 2008 ACKNOWLEDGMENTS

More information

Hamilton-Wentworth Catholic District School Board Event Listing By Ascending Event Year

Hamilton-Wentworth Catholic District School Board Event Listing By Ascending Event Year Hamilton-Wentworth Catholic District School Board Event Listing By Ascending Event Year Printed On: 2003/04/03 St Patrick CES, 7932 Study [03.3-050 Plumbing Piping Systems] Study condition, remaining service

More information

SUMMARY OF WORK FOR GENERAL CONTRACTOR

SUMMARY OF WORK FOR GENERAL CONTRACTOR SUMMARY OF WORK FOR GENERAL CONTRACTOR 1. General scope of work A. The work at 163 Seabrook consists of: 1. Finish the kitchen and 1 st floor hallway area 2. Finish 1 st floor bathroom and laundry area

More information

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage Property Address: Company Name: Contractor Name: Contractor Address: City: State: Zip: License Number: Phone Number

More information

Inspecting to a higher standard.

Inspecting to a higher standard. Inspecting to a higher standard. Rob Hopkin Silver Spring, MD 20902 Monday, June 2, 2014 ProTec Inspection Services Inc. 19736 Selby Ave Poolesville, MD 20837 301-972-8531 www.protec-inspections.com rob@protec-inspections.com

More information

Residential Decks. Planning and Development Services Department

Residential Decks. Planning and Development Services Department Building Safety Division 8500 Santa Fe Drive Overland Park, KS 66212 (913) 895-6225 Fax (913) 895-5016 Email: permitservices@opkansas.org Planning and Development Services Department Residential Decks

More information

PERFORMANCE TEST REPORT. Rendered to: BAMCO INC. PRODUCT TYPE: ACM Wall Panel Systems

PERFORMANCE TEST REPORT. Rendered to: BAMCO INC. PRODUCT TYPE: ACM Wall Panel Systems PERFORMANCE TEST REPORT Rendered to: BAMCO INC. PRODUCT TYPE: ACM Wall Panel Systems Summary of Results Title Test Specimen #1 Test Specimen #2 Air Infiltration

More information

Cooktop Low-Profile Ventilation Hoods

Cooktop Low-Profile Ventilation Hoods INSTALLATION GUIDE Cooktop Low-Profile Ventilation Hoods Contents Wolf Cooktop Low-Profile Ventilation Hoods........ 3 Cooktop Low-Profile Hood Specifications.......... 4 Cooktop Low-Profile Hood Installation............

More information

This permit does not include replacement or upgrading of the existing electrical panel or service (a separate electrical permit must be obtained).

This permit does not include replacement or upgrading of the existing electrical panel or service (a separate electrical permit must be obtained). CITY OF MILPITAS Building & Safety Department 455 E. Calaveras Blvd. Milpitas, CA 95035 408-586-3240 www.ci.milpitas.ca.gov RESIDENTIAL AIR CONDITIONING, REPLACEMENT 1. PERMIT INFORMATION: The replacement

More information

first look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel

first look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel first look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel What is GigaCrete GigaCrete is a family of products based on low carbon footprint Green ceramic binders

More information

Packaged Terminal Air Conditioner Wall Sleeve Installation

Packaged Terminal Air Conditioner Wall Sleeve Installation Installation & Maintenance Data IM 1196 Group: PTAC Part Number: 910141799 Date: October 2013 Packaged Terminal Air Conditioner Installation x 42" PGAN with Top-Mounted Hydronic Heat Note: Installation

More information

ROOFS, SNOW AND ICE DAMS

ROOFS, SNOW AND ICE DAMS ROOFS, SNOW AND ICE DAMS The Problem Ice dams are a common roof performance problem in cold climate buildings. Simply put, they are ridges of ice and icicles caused by melt water from further up the roof

More information

Installation Guide. Bath and Wall Surrounds SERIES 7104 1021861-2-B

Installation Guide. Bath and Wall Surrounds SERIES 7104 1021861-2-B Installation Guide and Wall Surrounds SERIES 7104 1021861-2-B Thank You For Choosing Sterling We appreciate your commitment to Sterling value. Please take a few minutes to review this manual before you

More information

Project: PSFA PROJECT NO: P14-023 - Parkview Early Literacy Center Expansion and Modernization - Roswell Independent School District and NM PSFA

Project: PSFA PROJECT NO: P14-023 - Parkview Early Literacy Center Expansion and Modernization - Roswell Independent School District and NM PSFA August 24, 2015 Addendum No. 1: Project: PSFA PROJECT NO: P14-023 - Parkview Early Literacy Center Expansion and Modernization - Roswell Independent School District and NM PSFA To All Bidders: The following

More information

UB1 AIR CONDITIONING UNIT INSTALLATION INSTRUCTIONS

UB1 AIR CONDITIONING UNIT INSTALLATION INSTRUCTIONS UB1 AIR CONDITIONING UNIT INSTALLATION INSTRUCTIONS INSTALLATION INSTRUCTIONS: Carefully read these instructions before installing your new air-conditioner. AUSTRALIAN AUTOMOTIVE AIR AL00500054E 1 Table

More information

WINDOW INSTALLATION GUIDE FOR NEW CONSTRUCTION - WOOD FRAMING

WINDOW INSTALLATION GUIDE FOR NEW CONSTRUCTION - WOOD FRAMING WINDOW INSTALLATION GUIDE FOR NEW CONSTRUCTION - WOOD FRAMING IMPORTANT NOTICES AND INFORMATION Read these instructions in their entirety prior to installing windows. Any local building code requirements

More information

Building Code Clarifications - 7. Fire Resistance

Building Code Clarifications - 7. Fire Resistance Building Code Clarifications - 7. Fire Resistance 7.1 (15-12-030) Use of combustibles in Type III construction roof assemblies Code Section (15-12-030) Use of Combustibles was revised on May 17, 2000,

More information

#1) BEFORE Purchasing Land Here Is A Checklist Of Things You Should Check

#1) BEFORE Purchasing Land Here Is A Checklist Of Things You Should Check #1) BEFORE Purchasing Land Here Is A Checklist Of Things You Should Check Zoning laws Deed restrictions on home size, foundation style, roof pitch, etc. Suitability (slope, wetland issues, etc.) Accessibility

More information

Energy Company Obligation (ECO): Technical Monitoring Questions

Energy Company Obligation (ECO): Technical Monitoring Questions Energy Company Obligation (ECO) Technical Monitoring Questions v1 30/05/2013 Energy Company Obligation (ECO): Technical Monitoring Questions Under ECO suppliers are required to instruct suitably qualified

More information

Schlüter -KERDI-BOARD Substrate, structural panel, bonded waterproofing

Schlüter -KERDI-BOARD Substrate, structural panel, bonded waterproofing Substrate, structural panel, bonded waterproofing The universal substrate for tiles Perfect covering No matter whether you work with mosaics or large format tiles, an absolutely level substrate with straight

More information

Fig. 2 WALL-TO-WALL PANEL CONNECTIONS CORNER WALL CONNECTION

Fig. 2 WALL-TO-WALL PANEL CONNECTIONS CORNER WALL CONNECTION SIPS SCREWS WITH MINIMUM 1" PENETRATION IN WOOD MEMBER IN SIP WALL PANEL CONNECTED TO @ 24" O.C. MAXIMUM OUTSIDE SKIN EACH SIDE OF FRAMING TYP. AS RECOMMENDED BY FOAM CORE AS EACH SIDE OF FRAMING TYP.

More information

DETAILED INSTALLATION GUIDE

DETAILED INSTALLATION GUIDE DETAILED INSTALLATION GUIDE Warning: Risk of Electrical Shock, Fire or Personal Injury Once Installed and your wiring is run through your SMARTWALL system there is risk of electrical shock, fire or personal

More information

Saint Cloud Business Center

Saint Cloud Business Center Saint Cloud Business Center 14 7th Avenue North Saint Cloud, MN 56303 For Sale Located on 7th Avenue in the heart of downtown across from the Court House Square. A large professional reception area with

More information

Leaky Homes Financial Assistance Package (FAP) Repair plan example

Leaky Homes Financial Assistance Package (FAP) Repair plan example LEAKY HOMES FINANCIAL ASSISTANCE PACKAGE FACT SHEET Repair Plan Example - June 2014 Page 1 Leaky Homes Financial Assistance Package (FAP) Repair plan example Introduction This repair plan example is intended

More information

The WANZ Guide to Window Installation

The WANZ Guide to Window Installation The WANZ Guide to Window Installation as described in E2/AS1 Amendment 5 Ver. 1.1 Page 2 of 74 Contents Overview Page 5 Objective Page 5 Scope Page 5 Opening Preparation Page 7 Step P1 Preliminary Check

More information

City of St. Charles Basement Finish or Remodel

City of St. Charles Basement Finish or Remodel City of St. Charles Basement Finish or Remodel Building & Code Enforcement Division 2 East Main Street St. Charles IL 60174 630.377.4406 (Office) 630.443.4638 (Fax) http://www.stcharlesil.gov Please direct

More information